SlideShare a Scribd company logo
1 of 15
Download to read offline
2
Introduction & Boiler Description
• HPCL had installed and commissioned two
high pressure boilers for GFEC in 2009,
namely SG-10 & SG-11.
• 140 TPH at 40 Kg/cm2g design steam
generation capacity.
• Bi-drum, natural circulation, dual fuel fired ‘D’
type boiler.
• Inverted loop, single pass, single super-heater.
• Super-heater metallurgy T11 alloy with 136
tubes of 2” Nominal dia.
• Three burners positioned one below another
vertically on furnace wall.
3
• Superheater is of inverted loop, single pass design with 136
Nos. of 2” OD T11 material tubes arranged as shown in
diagram below.
Superheater Design
4
• Both SG10 and SG11 boiler had series of superheater
tube ruptures since commissioning in 2009.
• SG10 had 7 and SG11 had 5 instances of premature tube
leak in superheater. Detailed study concluded failure due
to overheating.
• The leak occurred within 3 to 100 days after
commissioning.
• Nature of failures: Short term overheating leading to fish-
mouth rupture.
Failure history of the boiler
5
• Super-heater tube skin temperature was running very
high upto 550-600°C since commissioning against OEM
provided limit of 469°C.
• Steam outlet temperature was also running high upto
380°C against limit of 365°C.
• Boiler load was limited to 60% of MCR (about 80 TPH)
due to high Super-Heater metal temperatures. Still
failures occurred at 50 TPH, 65 TPH and 80 TPH steam
load.
Failure history of the boiler
6
Fish Mouth Rapture in Super Heater tube
7
Metallographic Analysis
• Substantial amount of black thick oxide layer in laminated
formation.
• No steam side deposits were observed.
• 300-500 micron of magnetite layer was observed.
• Microstructure analysis suggested long term temperature
exposure to more than 727 °C.
• Burner operating philosophy and other operational
measures had no impact on failure reduction
Root Cause Failure Analysis
8
Thermo-hydrolic analysis carried out under consultancy of
boiler expert Shri. V. Ganpathi.
 The superheater design pressure drop was too low 0.2-3.0 psi
at full boiler load against recommended values of 30-35 psi
which was causing overheating of superheater tubes.
 Very low pressure drop at start up conditions caused
stagnation of steam flow in hotter and longer tubes facing flue
gases from furnace.
 Lower design steam velocities are found inadequate to provide
heat sinking at higher steam loads in view of increased heat
flux and radiation.
Thermo-hydrolic analysis
9
 Superheater was not preceded by enough screen tube
rows which normally prevents superheater from hot flue
gases by soaking up radiation and equalizing the flue
gas flow across the superheater cavity.
 Due to location of the superheater and single pass
design, the superheater tubes were exposed to high
radiant heat particularly at higher loads.
 Compromised design of superheater, lead to failures at
lower as well as higher loads.
Thermo-hydrolic analysis
10
• Reduction in number of superheater tubes were carried
out as shown in following diagram.
• Total 7 rows (56 tubes) were removed out of originally
provided 17 rows (136 tubes).
Modifications
Original Arrangement
Modified Arrangement
11
• Super heater design was changed from single stage to
double stage and attemperator has been attached
intermediate header to control the steam temperature in
desired limits.
• Super heater metallurgy was T11 & this was upgraded to
T22.
Design Modifications
12
Modifications in Design
13
Improved performance & reliability post-modifications
Parameters Before modification After modification Remarks
Load Avg 75.00 75.00
Stack Temp (Avg) 188.00 164.19 -23.81 degC
O2 (%) (Avg) 6.00 3.50 -2.5%
Air flow TPH (Avg) 113.00 96.58
Efficiency (Avg) 90.43 91.51 +1.1%
TST (Avg) 494.00 445.00 -50 degC
SH outlet temp (Avg) 384.73 355.70
SH pressure drop (Avg) 1.63 2.37
Failure frequency due to
overheating 3 to 100 days NIL
14
Major changes in Original Design
Parameters Original design Modified design
Number of superheater tubes per pass 136 80
MCR, TPH 140 140
Steam drum pressure, Kg/cm2g at MCR 46.4 46.4
Superheater outlet pressure, Kg/cm2g at MCR 42.9 39.6
Superheater pressure drop, Kg/cm2g at MCR 3.5 6.7
Superheater outlet temperature at MCR 380-400 335-355
Superheater steam velocity, m/s at MCR 18 32.6
Superheater steam mass flux, Kg/m2/s at MCR 289.5 492
Expected Superheater TST Max, DegC at MCR >700 490
Failure frequency due to overheating 3 to 100 days NIL
15

More Related Content

What's hot

Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesManohar Tatwawadi
 
Improve plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlImprove plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlHossam Zein
 
Boiler auxillaries in a coal fired power plant
Boiler auxillaries in a coal fired power plantBoiler auxillaries in a coal fired power plant
Boiler auxillaries in a coal fired power plantBoben Anto Chemmannoor
 
Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerVENUS ENERGY AUDIT SYSTEM
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesBoben Anto Chemmannoor
 
Energy audit of Condenser and CW System
Energy audit of Condenser and CW SystemEnergy audit of Condenser and CW System
Energy audit of Condenser and CW SystemManohar Tatwawadi
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heaterSHIVAJI CHOUDHURY
 
A complete presentation on Boiler.
A complete presentation on Boiler.A complete presentation on Boiler.
A complete presentation on Boiler.Anuj Maurya
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheaterHOANG VAN DUC
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plantsSHIVAJI CHOUDHURY
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plantSHIVAJI CHOUDHURY
 
The Coal mill performance monitoring
The Coal mill performance monitoringThe Coal mill performance monitoring
The Coal mill performance monitoringManohar Tatwawadi
 

What's hot (20)

Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Boiler turbe failores
Boiler turbe failoresBoiler turbe failores
Boiler turbe failores
 
Air heater
Air heaterAir heater
Air heater
 
Improve plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlImprove plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater control
 
Boiler Introduction
Boiler IntroductionBoiler Introduction
Boiler Introduction
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
 
Boiler auxillaries in a coal fired power plant
Boiler auxillaries in a coal fired power plantBoiler auxillaries in a coal fired power plant
Boiler auxillaries in a coal fired power plant
 
Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boiler
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Energy audit of Condenser and CW System
Energy audit of Condenser and CW SystemEnergy audit of Condenser and CW System
Energy audit of Condenser and CW System
 
Condenser performance test
Condenser performance testCondenser performance test
Condenser performance test
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
A complete presentation on Boiler.
A complete presentation on Boiler.A complete presentation on Boiler.
A complete presentation on Boiler.
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheater
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
The Coal mill performance monitoring
The Coal mill performance monitoringThe Coal mill performance monitoring
The Coal mill performance monitoring
 
Stator water system chemistry
Stator water system chemistryStator water system chemistry
Stator water system chemistry
 

Viewers also liked

DESIGN OF AIR PRE HEATER AND ECONOMIZER
DESIGN OF AIR PRE HEATER AND ECONOMIZERDESIGN OF AIR PRE HEATER AND ECONOMIZER
DESIGN OF AIR PRE HEATER AND ECONOMIZERGopi Chand
 
Economiser & air preheater
Economiser & air preheaterEconomiser & air preheater
Economiser & air preheaterdishti7
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to BoilersSATYAKAM MOHAPATRA
 

Viewers also liked (20)

Superheater & reheater
Superheater & reheaterSuperheater & reheater
Superheater & reheater
 
DESIGN OF AIR PRE HEATER AND ECONOMIZER
DESIGN OF AIR PRE HEATER AND ECONOMIZERDESIGN OF AIR PRE HEATER AND ECONOMIZER
DESIGN OF AIR PRE HEATER AND ECONOMIZER
 
Economiser & air preheater
Economiser & air preheaterEconomiser & air preheater
Economiser & air preheater
 
Superhtr
SuperhtrSuperhtr
Superhtr
 
Boiler Maintenance & Safety
Boiler Maintenance & SafetyBoiler Maintenance & Safety
Boiler Maintenance & Safety
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
 
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired BoilerOnline Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
 
Case Studies on CFBC Boilers
Case Studies on CFBC BoilersCase Studies on CFBC Boilers
Case Studies on CFBC Boilers
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
 
Boiler Water Treatment for LP,MP and HP Boiler
Boiler Water Treatment for LP,MP and HP BoilerBoiler Water Treatment for LP,MP and HP Boiler
Boiler Water Treatment for LP,MP and HP Boiler
 
Efficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHREfficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHR
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to Boilers
 
Efficient Steam Systems -
Efficient Steam Systems -Efficient Steam Systems -
Efficient Steam Systems -
 
Boiler Water Treatment -
Boiler Water Treatment - Boiler Water Treatment -
Boiler Water Treatment -
 
Safe Operation and Explosions in Boilers
Safe Operation and Explosions in BoilersSafe Operation and Explosions in Boilers
Safe Operation and Explosions in Boilers
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
CFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired BoilerCFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired Boiler
 
Presentation on cooling tower
Presentation on cooling towerPresentation on cooling tower
Presentation on cooling tower
 
Boiler Presentation
Boiler PresentationBoiler Presentation
Boiler Presentation
 

Similar to Boiler Superheater Design Modification

Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC RamagunadamAbhinay Angari
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperiencePooja Agarwal
 
Aiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumAiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumSatria Sakata
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptxrajneeshjauhari2
 
Remaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodRemaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodBarhm Mohamad
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Raghab Gorain
 
Experiments and simulations on heat exchangers in thermoelectric generator f...
Experiments and simulations on heat exchangers in thermoelectric generator f...Experiments and simulations on heat exchangers in thermoelectric generator f...
Experiments and simulations on heat exchangers in thermoelectric generator f...Akhil R
 
U8 Superheater Damage_Nov06.ppt
U8 Superheater Damage_Nov06.pptU8 Superheater Damage_Nov06.ppt
U8 Superheater Damage_Nov06.pptandrizakaria1
 
Optimizing ground heat exchanger length with GeoperformX pipe
Optimizing ground heat exchanger length with  GeoperformX pipeOptimizing ground heat exchanger length with  GeoperformX pipe
Optimizing ground heat exchanger length with GeoperformX pipeJasmin Raymond
 
Est group harbin urea conference 2014 pap paper v1 english
Est group harbin urea conference 2014 pap paper v1 englishEst group harbin urea conference 2014 pap paper v1 english
Est group harbin urea conference 2014 pap paper v1 englishJim Novak (吉因龙)
 
Methane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesMethane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesGerard B. Hawkins
 
Steam Reforming - Practical Operations
Steam Reforming - Practical OperationsSteam Reforming - Practical Operations
Steam Reforming - Practical OperationsGerard B. Hawkins
 
Project-Induction.pptx
Project-Induction.pptxProject-Induction.pptx
Project-Induction.pptxjaegar .
 
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1Sanju Jacob
 
Heat loss in bare and lagged pipes
Heat loss in bare and lagged pipesHeat loss in bare and lagged pipes
Heat loss in bare and lagged pipesNicely Jane Eleccion
 
Adoption of supercritical technology (1)
Adoption of supercritical technology (1)Adoption of supercritical technology (1)
Adoption of supercritical technology (1)HARSHIT GUPTA
 
BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfPrasadKandukuri4
 

Similar to Boiler Superheater Design Modification (20)

02 Boiler Construction.ppt
02 Boiler Construction.ppt02 Boiler Construction.ppt
02 Boiler Construction.ppt
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field Experience
 
BOILER C.PPT
BOILER  C.PPTBOILER  C.PPT
BOILER C.PPT
 
Aiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumAiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agrium
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
 
Remaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodRemaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element method
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
 
Experiments and simulations on heat exchangers in thermoelectric generator f...
Experiments and simulations on heat exchangers in thermoelectric generator f...Experiments and simulations on heat exchangers in thermoelectric generator f...
Experiments and simulations on heat exchangers in thermoelectric generator f...
 
U8 Superheater Damage_Nov06.ppt
U8 Superheater Damage_Nov06.pptU8 Superheater Damage_Nov06.ppt
U8 Superheater Damage_Nov06.ppt
 
Optimizing ground heat exchanger length with GeoperformX pipe
Optimizing ground heat exchanger length with  GeoperformX pipeOptimizing ground heat exchanger length with  GeoperformX pipe
Optimizing ground heat exchanger length with GeoperformX pipe
 
Est group harbin urea conference 2014 pap paper v1 english
Est group harbin urea conference 2014 pap paper v1 englishEst group harbin urea conference 2014 pap paper v1 english
Est group harbin urea conference 2014 pap paper v1 english
 
Methane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesMethane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube Studies
 
Steam Reforming - Practical Operations
Steam Reforming - Practical OperationsSteam Reforming - Practical Operations
Steam Reforming - Practical Operations
 
Project-Induction.pptx
Project-Induction.pptxProject-Induction.pptx
Project-Induction.pptx
 
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
REDESIGN OF SHELL AND TUBE HEAT EXCHANGER 1
 
Heat loss in bare and lagged pipes
Heat loss in bare and lagged pipesHeat loss in bare and lagged pipes
Heat loss in bare and lagged pipes
 
Indigenization of Russian Make WHR by Vizag Steel
Indigenization of Russian Make WHR by Vizag SteelIndigenization of Russian Make WHR by Vizag Steel
Indigenization of Russian Make WHR by Vizag Steel
 
Adoption of supercritical technology (1)
Adoption of supercritical technology (1)Adoption of supercritical technology (1)
Adoption of supercritical technology (1)
 
BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdf
 

Recently uploaded

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 

Recently uploaded (20)

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 

Boiler Superheater Design Modification

  • 1.
  • 2. 2 Introduction & Boiler Description • HPCL had installed and commissioned two high pressure boilers for GFEC in 2009, namely SG-10 & SG-11. • 140 TPH at 40 Kg/cm2g design steam generation capacity. • Bi-drum, natural circulation, dual fuel fired ‘D’ type boiler. • Inverted loop, single pass, single super-heater. • Super-heater metallurgy T11 alloy with 136 tubes of 2” Nominal dia. • Three burners positioned one below another vertically on furnace wall.
  • 3. 3 • Superheater is of inverted loop, single pass design with 136 Nos. of 2” OD T11 material tubes arranged as shown in diagram below. Superheater Design
  • 4. 4 • Both SG10 and SG11 boiler had series of superheater tube ruptures since commissioning in 2009. • SG10 had 7 and SG11 had 5 instances of premature tube leak in superheater. Detailed study concluded failure due to overheating. • The leak occurred within 3 to 100 days after commissioning. • Nature of failures: Short term overheating leading to fish- mouth rupture. Failure history of the boiler
  • 5. 5 • Super-heater tube skin temperature was running very high upto 550-600°C since commissioning against OEM provided limit of 469°C. • Steam outlet temperature was also running high upto 380°C against limit of 365°C. • Boiler load was limited to 60% of MCR (about 80 TPH) due to high Super-Heater metal temperatures. Still failures occurred at 50 TPH, 65 TPH and 80 TPH steam load. Failure history of the boiler
  • 6. 6 Fish Mouth Rapture in Super Heater tube
  • 7. 7 Metallographic Analysis • Substantial amount of black thick oxide layer in laminated formation. • No steam side deposits were observed. • 300-500 micron of magnetite layer was observed. • Microstructure analysis suggested long term temperature exposure to more than 727 °C. • Burner operating philosophy and other operational measures had no impact on failure reduction Root Cause Failure Analysis
  • 8. 8 Thermo-hydrolic analysis carried out under consultancy of boiler expert Shri. V. Ganpathi.  The superheater design pressure drop was too low 0.2-3.0 psi at full boiler load against recommended values of 30-35 psi which was causing overheating of superheater tubes.  Very low pressure drop at start up conditions caused stagnation of steam flow in hotter and longer tubes facing flue gases from furnace.  Lower design steam velocities are found inadequate to provide heat sinking at higher steam loads in view of increased heat flux and radiation. Thermo-hydrolic analysis
  • 9. 9  Superheater was not preceded by enough screen tube rows which normally prevents superheater from hot flue gases by soaking up radiation and equalizing the flue gas flow across the superheater cavity.  Due to location of the superheater and single pass design, the superheater tubes were exposed to high radiant heat particularly at higher loads.  Compromised design of superheater, lead to failures at lower as well as higher loads. Thermo-hydrolic analysis
  • 10. 10 • Reduction in number of superheater tubes were carried out as shown in following diagram. • Total 7 rows (56 tubes) were removed out of originally provided 17 rows (136 tubes). Modifications Original Arrangement Modified Arrangement
  • 11. 11 • Super heater design was changed from single stage to double stage and attemperator has been attached intermediate header to control the steam temperature in desired limits. • Super heater metallurgy was T11 & this was upgraded to T22. Design Modifications
  • 13. 13 Improved performance & reliability post-modifications Parameters Before modification After modification Remarks Load Avg 75.00 75.00 Stack Temp (Avg) 188.00 164.19 -23.81 degC O2 (%) (Avg) 6.00 3.50 -2.5% Air flow TPH (Avg) 113.00 96.58 Efficiency (Avg) 90.43 91.51 +1.1% TST (Avg) 494.00 445.00 -50 degC SH outlet temp (Avg) 384.73 355.70 SH pressure drop (Avg) 1.63 2.37 Failure frequency due to overheating 3 to 100 days NIL
  • 14. 14 Major changes in Original Design Parameters Original design Modified design Number of superheater tubes per pass 136 80 MCR, TPH 140 140 Steam drum pressure, Kg/cm2g at MCR 46.4 46.4 Superheater outlet pressure, Kg/cm2g at MCR 42.9 39.6 Superheater pressure drop, Kg/cm2g at MCR 3.5 6.7 Superheater outlet temperature at MCR 380-400 335-355 Superheater steam velocity, m/s at MCR 18 32.6 Superheater steam mass flux, Kg/m2/s at MCR 289.5 492 Expected Superheater TST Max, DegC at MCR >700 490 Failure frequency due to overheating 3 to 100 days NIL
  • 15. 15