The document provides information on the commissioning process for a boiler. It involves several key steps: air leakage and hydro testing, ensuring boiler auxiliaries are ready, gas distribution testing, light up of the boiler, alkali boil-out and passivation to clean the boiler, steam blowing of piping, safety valve testing, and finally coal firing. The commissioning aims to make the boiler and its systems available for safe, smooth, and reliable operation after erection is completed.