SlideShare a Scribd company logo
1
OPERATION ASPECTS
&
BOILER EMERGENCIES
2
IMPORTANT PARAMETERS IN AFBC BOILER
1. Bed Height / F.D. Air Pressure
2. Primary Air Pressure
3. Bed Temperature / Furnace Temperature
4. Fuel Size
5. Bed Material Size & Specifications
6. Air & Fuel Ratio
3
1. BED HEIGHT / FD AIR PRESSURE
• Static height for AFBC boiler is to be maintained
250 to 300mm during initial light up of boiler.
• Expand bed height for AFBC boiler is to be
maintained 500 to 600 mmwc.
• FD air discharge pressure is to be maintained 600 to
650mmwc
• Wind box or air box pressure is to be maintained 500
to 600mmwc
High W.B. pressure increases the erosion of bed coils
& low WBP affect fluidization.
4
2. PRIMARY AIR PRESSURE
 P.A. fan air header pressure for AFBC boiler
is to be maintained 1000 to 1150 mmwc.
 Diff. of Primary Air Pressure & F.D. Wind Box
pressure is to be maintained approximately 500
mmwc.
High P.A. Pressure increases the high bed coil
erosion and carryover.
Low P.A. pressure cause the blockage of P.A.
lines and puffing in boiler and also increases
chances of clinkerization.
5
3. BED TEMP. / FURNACE TEMPERATURE
• Depends upon the type of fuel & firing method.
• For (Indian Coal) bed temp. in FBC/AFBC/CFBC is to
be maintained 850o
C to 900o
C.
• For Imported Coal bed temp. in FBC/AFBC/CFBC is
to be maintained bed 875o
C to 925o
C.
• For lignite bed temp. in FBC/AFBC/CFBC is to be
maintained 800o
C to 850o
C.
• For Petcock bed temp. in FBC/AFBC/CFBC is to be
maintained 875o
C to 950o
C.
6
• For Rice husk and other Bio-mass fuel bed
temperature in FBC/AFBC/CFBC is to be
maintained 850o
C to 900o
C.
• For Stoker firing furnace temperature is
maintained around 1100o
C to 1200o
C.
• For Pulverized Fuel firing furnace temperature is
maintained 1100o
C to 1300o
C.
• For oil & gas fuel firing furnace temperature is
1100o
C to 1500o
C.
3. BED TEMP. / FURNACE TEMPERATURE
7
4.FUEL SIZE
For FBC / AFBC / CFBC Boiler
Size : 0 to 8 mm,
less then 1mm not allowed more then 20%
Distribution : 1 to 5mm – 70%
5 to 8mm – 20%
0 to 1mm – 10%
Lower the size of coal higher the un-burnt in fly ash.
Higher the size of coal higher the erosion of bed coils
and blockage of fuel air pipe & clinkerization in Boiler.
8
For Stoker fired Boiler
Size : 5 to 25mm,
less then 5mm not allowed more then 5%
Distribution : 5mm to 15mm – 25 %
15mm to 25mm – 75%
0 to 5mm – 05%
Lower the size of coal higher unburnt in fly
ash & carryover through Boiler.
9
For Pulverized Fired Boiler
Raw Coal Feeder Inlet – 0 to 25mm( higher size will
be effected by pulverizer (Pulverizer Inlet)
performance and more rejection )
Pulverized Coal Size – 70% through 200 mesh
Size Distribution : 150 – 200 - 60%
100 – 150 - 30%
75 - 100 - 10%
Higher the size of pulverized coal below 100 mesh
results unburnt in bottom ash.
10
5. BED MATERIAL SIZE & SPECIFICATIONS
Bed Material Size :-
Size:0.85mm o 2.36mm (not below 0.85mm)
Distribution : 0.85 mm to 1.0mm –10%
1.0 mm to 1.5mm – 50%
1.5 to 2.36 mm – 40%
11
Bed Material Specifications :
Crushed Fire Bricks Castable IS8 grade Bricks or
River Silica Sand
Fusion Temperature : 1300 Deg. C.
Shape : Spherical Angular
Bulk Density : 1050 Kg/m3
Silica (SiO2) : 68 %
Al203 : 28 %
Fe203 : 1.05%
PiO2 : 1.67%
MnO : Trace
CaO : 0.54%
MgO : 0.23%
P2O5 : 0.08%
A2O : 0.22%
K2O : 0.45%
12
6. AIR & FUEL RATIO
Typical excess air to achieve highest efficiency for
different fuels are:
• Power plant boilers normally run about 10 to 20 %
• Fuel Oil Fired boilers may run as low as 5 to 15%.
• Natural gasfired boilers may run as low as 5 to 10%
• Pulverized coalfired boilers may run with 15 to 20%
• Gas turbines run very lean with up to 300%
13
COMPARISON OF FLUIDISED BED BOILER
WITH SPREADER STOKER & PF
CHARACTERISTICS FLUIDESED BED SPREADER
STOKER
PF
Fuel quality (Ash, Calorific value.
Volatile matter, Size
distribution)
Has no effect on
operation
Output affected
by coal quality
Output
affected by
coal quality
Maintenance
No moving
parts; less
maintenance
Moving grate in
high temp. zone;
required frequent
maintenance
Frequent
maintenance
due to
pulverizer
Efficiency (for typical Indian Coal
with 45% ash) About 86% Around 76% 86 – 87 %
Efficiency at low load
Better Poor Less
Soot Blowers Not required Necessary Necessary
NOx Formation Low High High
14
EMERGENCY CONDITIONS
15
Various Emergency Conditions:
Drum level low and low-low
Drum level high and high high
Furnace Draft high and high high
Bed Temperature High
Bed Temperature Low
Water wall / screen tube / evaporator tube
failure
Super heater tube failure
High super heater temperature
Low Super heater temperature
Flame Failure
Furnace Explosion
Boiler pressure high
Coal feeder failure
PAH / SAH tube failure
Boiler feed pump failure
Fan Failure
16
DRUM LEVEL LOW AND LOW-LOW:
(A) CAUSE :
1. Failure of boiler feed pump.
2. Failure of drum level controller.
3. Inadvertent opening of C.B.D.
4. Extraordinary change in load. (Sudden reduction in
load)
5. Water tube failure.
17
DRUM LEVEL LOW AND LOW-LOW:
(B) EFFECT : Boiler may damage badly.
(C) ACTION :
• Run the boiler if drum level is within safe limit (Lo
alarm and lo-lo alarm came). If it goes beyond safe
limit allow boiler to trip.
• Attempt to control with feed valve.
• If feed valve is stuck up open parallel line valve or
bypass valve.
• Take care while increasing feed flow that running
B.F.P. do not trip on feed flow high.
• If low level is due to tripping of feed pump start
stand by pump, if it is on manual.
• If water level is below safe level, allow to trip the
boiler on drum level lo-lo to protect the boiler drum
and tubes.
18
(A) CAUSE:
1. Failure of drum level controller.
2. Extra ordinary increase in load
3. Sudden increase in firing rate.
DRUM LEVEL HIGH AND HIGH HIGH:
19
(B) EFFECT:
 Water may enter turbine and serious damages to turbine may occur.
 Joint valve on main steam pipe work leaks.
 Carry over with sharp fall in super heater temperature
(C) ACTION :
1. Run the boiler if drum level is within safe limit (drum level high and
high high alarm came). If goes beyond limit allow boiler to trip.
• Attempt to control with feed valve.
• If feed valve is stuck up close isolating valve.
• Attempt to control drum level by opening C.B.D.
• Close Economizer inlet valve and allow feed pump to run in
recirculation.
• If above measures fail trip the feed pump.
2. If level is due to sudden rise in load. If high level rises above normal
level allow boiler to trip on drum level high high.
• If main steam temperature drop takes place open steam pipe drains.
• Trip the turbine / prime mover when steam
temperature falls.
DRUM LEVEL HIGH AND HIGH HIGH:
20
(A) CAUSE :
1. Due to faulty operation of fan control.
2. Disturbed combustion
3. Un-controlled fuel entry
FURNACE PRESSURE HIGH & HIGH HIGH:
21
(B) EFFECT:
– Boiler may damage due to high furnace pressure.
– Weak parts of furnace (ductings and enclosures)
may explode due to high furnace pressure.
(C) ACTION :
– If it is due to faulty operation of I.D./P.A./S.A. fan
control, take it on manual and maintain the
furnace in suction.
– If furnace pressure has increased beyond limit
allow boiler to trip on furnace draught high high.
FURNACE PRESSURE HIGH & HIGH HIGH:-
22
(A) CAUSE :
1. High CV and low ash coal used.
2. Low P.A. flow / S.A. flow
3. Sudden change in load
4. Faulty bed temp thermocouple
5. Ash recirculating system trouble
BED TEMPERATURE HIGH IN FBC BOILER
23
(B) EFFECT :
 Chances of clinker formation
 Chances of refractory failure
 Chances of screen tube failure
(C) ACTION :
 Control bed temp by recirculation ash through
recirculation feeder.
 Start sand feeder if bed height permits.
 Increase P.A. flow up and increase S.A. flow.
 Reduce the load by cutting coal feeder.
 Coal feeders trip, if temp rises above limit and allow
boiler to trip, if temp exceeds beyond safe limit to save
bed from clinkerisation.
 Check the bed temp thermocouple.
BED TEMPERATURE HIGH IN FBC BOILER
24
(A) CAUSE :
1. High PA with respect to load / high SA flow
w.r.t. load.
2. Low CV high ash coal used.
3. Coal interruption or coal feeder trips or
overfeeding of coal into furnace.
4. Recirculation ash feeder speed may increase.
5. Faulty bed temp. thermocouple.
6. Water tube / screen tube / evaporator tube
failure.
BED TEMPERATURE LOW IN FBC BOILER
25
(B) EFFECT :
 Boiler steam flow will reduce.
 Super heater temp drops.
 Furnace draft will fluctuate.
(C) ACTION :
 Reduce P.A. Fan flow, if excessive / reduce S.A.
flow, if excessive.
 Reduce speed of recirculation ash feeder.
 Stop bed material supply, if running.
 Check bed temp thermocouple.
 Check any leakage sound from furnace.
 Check coal feeder and coal supply.
BED TEMPERATURE LOW IN FBC BOILER
26
(A) CAUSE :
1. Starved water wall.
2. Block tube, eroded tube, pitted tube, salt
deposits.
3. Circulation affected due to open low point
drains.
WATER WALL/ SCREEN/ EVAPORATOR TUBE
FAILURE:
27
(B) EFFECT :
 Hissing steam leakage noise from boiler.
 Unstable flame fluctuating draught.
 Bed temperature drops sharply.
 High feed water flow for given steam generation /
increase in make up water.
 Increase in I.D. Fan loading.
 Below screen temperature drops sharply.
 Flue gas outlet temperature decreased.
WATER WALL/ SCREEN/ EVAPORATOR TUBE
FAILURE:
28
(C) ACTION :
 Every shift check low point drain valve are fully
closed.
 Every shift check the furnace listen furnace to detect
steam noise.
 At first diagnostics of tube failure, start load
reduction; trip out unit before damage become
serious. Quicker shutdown reduces extensive
damage.
 Try to locate tube at low level.
 Don’t allow the drum level to go beyond a danger
level.
 Start another BFP, if drum level is not maintained by
running BFP.
WATER WALL/ SCREEN/ EVAPORATOR TUBE
FAILURE:
29
(A) CAUSE :
1. Sustaining high metal temp due to water wall
slagging or inadequate steam flow and high gas
temp during hot start.
2. Erosion on tubes due to high excess air.
3. Blocked tubes.
4. Starvation of tubes.
5. Salt deposition due to high water level in drum.
Poor quality of spray water.
SUPER HEATER TUBE FAILURE:
30
(B) EFFECT :
• Hissing noise notices.
• Flue gas temp drops.
• High feed water consumption compared to steam
flow.
• Over loading on I.D. Fan.
• Erosion of other tubes and damages to other SAH
tubes.
(C) ACTION :
1. As soon as leakages noticed start reducing the load
and trip the boiler.
2. Listen the SH region for steam leakage.
3. Try to locate leakage through manholes before the
boiler is depressurized.
SUPER HEATER TUBE FAILURE:
31
(A) CAUSE :
1. High excess air.
2. Low feed water temp HP Heater not in service at
constant firing / load.
3. Sudden increase in firing rate to increase steam
pressure.
4. In adequate spray.
5. Lodging of soot on the water walls considerably.
HIGH SUPER HEATER TEMPERATURE:
32
(B) EFFECT :
Rise in (+ve) positive turbine expansion.
– Creep rate increase in tube metal, turbine parts,
steam piping.
(C) ACTION :
1. Check feed water temp. If HP heaters are available,
put in service and if not reduce the load.
2. Slow down firing rate.
3. Reduce excess air, if more.
4. Check Spray control
HIGH SUPER HEATER TEMPERATURE:
33
(A) CAUSE :
1. Dirty super heater
2. Inadequate air flow.
3. High Spray
4. Too high feed water temp.
5. Sharp increase in load and pressure drop.
6. High Drum level.
LOW SUPER HEATER TEMPERATURE:
34
(B) EFFECT :-
1. Turbine expansion may be negative.
2. May induce thermal stresses in S.H.
(C) ACTION :-
1. Check air flow – increase, if necessary.
2. Reduce spray, if more.
3. Check feed water temp.
4. Avoid sharp rise in load to boiler pressure drop.
5. If, it is due to high drum level – allow unit to trip and
open main steam drains.
LOW SUPER HEATER TEMPERATURE:
35
(A) CAUSE :
1. Dirty Oil / Gas Burner
2. Faulty Flame Scanner
3. Failure of Blower
4. Furnace Pressure High
5. Low Combustion Air
FLAME FAILURE:
36
(B) EFFECT :
 Boiler will trip on flame failure
 Chances of furnace explosion, if unburnt oil / gas /
coal mixture entered in furnace.
 Boiler steam pressure may fall down.
 Super Heater Steam Temp. drop sharply.
 Variation observed in drum level (drum level low).
FLAME FAILURE:
37
(C) ACTION :
 Purge the boiler before putting burner back and
purge burner as per cycle time given by supplier.
 Check the flame scanner and clean the photocell, if
found dirty.
 Check the sparking circuit and high voltage
transformer supply.
 Check spark plug, if found dirty, clean it and set the
gap.
 Clean the burner tip, if nozzles (holes) are found
chocked.
 Check the air blower and maintain air fuel ratio.
 Check the explosion doors, close it if opened.
FLAME FAILURE:
38
(A) CAUSE :
1. Accumulation of unburnt fuel during lit up / start
up of boiler.
2. Improper burning.
3. Inadequate air.
4. Secondary combustion.
(B) EFFECT : Furnace explosion can cause extensive
damage.
(C) ACTION :
1. Always purge the boiler with 40% full load air for
about five minutes. No cut short in purging
allowed.
2. Adjust fuel air ratio.
FURNACE EXPLOSION:
39
(A) CAUSE :
1. Sudden drop in load / steam flow.
2. Un-controlled fuel entry.
3. Turbine / prime mover trips.
BOILER PRESSURE HIGH:
40
(B) EFFECT :-
 Disturbance in drum water level.
 Safety valves may life if pressure rise is up to that
extent.
 Boiler may trip on high pressure.
(C) ACTION :-
 Open start up vent valve.
 Control fuel input and drum level.
 Check coal feeder feeding rate.
 Adjust the load on unit, if it has dropped.
 If TG / prime mover has tripped first, allow boiler
to trip but safety valve may lift.
BOILER PRESSURE HIGH:
41
(A) CAUSE :
1. Electrical supply failed
2. V.F.D. fault
3. Bed temperature high
4. Furnace draft high
5. Furnace draft low
6. Drum level high
7. Drum level low
COAL FEEDER FAILURE:
42
(B) EFFECT :
 Boiler pressure may fall down
 SH steam temp fall sharply
 Bed temp. will decrease
 Variation in furnace pressure (LOW)
 Variation in drum level (Low)
COAL FEEDER FAILURE:
43
(C) ACTION :
 Control boiler pressure by reducing load on
turbine / prime mover or process.
 Control super heater steam temp by closing spray
valve.
 Reduce PA / SA flow to control bed temp.
 Control furnace draft and drum level.
 Check electrical fault or emergency stop push button
& restart coal feeder.
 Check VFD fault, if any.
 Restart coal feeder after checking cause of failure.
COAL FEEDER FAILURE:
44
(A) CAUSE : Erosion & Corrosion of tube.
(B) EFFECT :
 Flue gas temp after APH will fall down.
 Increases in O2 percentage at ESP inlet.
 PA / SA Fan overloaded.
 Bed temp may be increased.
(C) ACTION :
 Control flue gas temp by passes PAH.
 Reduce coal feeding to maintain O2 percentage.
 Control bed temp.
 If leakage of tubes are more stop the boiler
and plug / replaced.
PAH/ SAH TUBE FAILURE:
45
(A) CAUSE :
1. Motor protection relay operates
2. Lube oil temperature high
3. Discharge flow high
4. Motor bearing temperature high
5. Deaerator level low
6. BFP suction pressure low
BOILER FEED PUMP FAILURE:
46
(B) EFFECT :
 If standby pump is available, it will start on auto or
start it manually.
 If standby pump does not start on auto & manual,
drum level may go very low, which may trip the
boiler.
BOILER FEED PUMP FAILURE:
47
(C) ACTION :
 Start the stand by pump, if it does not start on auto.
Adjust the load to maintain the drum level as well as
to prevent the tripping of this pump on high feed
water flow.
 See the proper operation of recirculation valve and
C.W. Valve.
 Analyze and rectify the fault in the main feed pump.
Put it on auto.
 Restore the bus supply, if it has lost and make the
pump available.
 Check the deaerator level and if it falls below safe
limit, stop the feed pump, immediately.
 Check the BFP suction strainer and clean it, if found
chocked.
BOILER FEED PUMP FAILURE:
48
(A) CAUSE :-
1. Electrical motor protection
2. Fan bearing temp becomes high high
3. Motor bearing temp becomes very high
4. Drive fault (MCC fault)
5. Boiler trip
LOSS OF FANS:
(1) ID FAN FAILURE
49
(B) EFFECT :
1. Furnace may get pressurized
2. Boiler will trip on boiler furnace pressure high.
(C) ACTION :
1. Check emergency or field stop.
2. Rectify electrical fault, if any.
3. Check cause for boiler trip & normalize it.
4. Check fan / motor-bearing temp.
5. Restart I.D. Fan after checking cause of tripping
and taking corrective actions.
LOSS OF FANS:
(1) ID FAN FAILURE
50
(A) CAUSE :
1. Electrical motor protection.
2. Fan bearing temp. becomes high high.
3. Motor bearing temp. becomes very high.
4. MCC fault.
5. Boiler trip.
6. Run feed back off.
7. ID Fan trip.
8. SA trip.
(1) PA FAN FAILURE
LOSS OF FANS:
51
(B) EFFECT :
 Boiler will trip on
a. Furnace draft low
b. P.A. flow low.
(C) ACTION :
1. Rectify electrical fault, if any.
2. Check cause for boiler trip and normalize it.
3. Check fan / motor-bearing temp.
4. Restart the P.A. Fan after checking the cause of
tripping and taking corrective actions.
(1) PA FAN FAILURE
LOSS OF FANS:
52
(A) CAUSE :
1. Electrical motor protection.
2. Fan bearing temp becomes high high.
3. Motor bearing temp becomes very high.
4. MCC fault.
5. Boiler trip.
6. Run feed back off.
7. I.D. Fan trip.
(1) SA FAN FAILURE
LOSS OF FANS:
53
(B) EFFECT : Boiler will trip on low furnace draft.
(C) ACTIONS :
 Rectify electrical fault, if any.
 Check cause for boiler, trip & normalize it.
 Check fan / motor-bearing temp.
 Restart the S.A. Fan after checking the cause of
tripping and taking corrective actions.
(1) SA FAN FAILURE
LOSS OF FANS:
54
T H A N K
Y O U

More Related Content

What's hot

Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
Manohar Tatwawadi
 
210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance
Manohar Tatwawadi
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
Vaibhav Paydelwar
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
Manohar Tatwawadi
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
VEERABHADRA SWAMY
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its Internals
Ashrant Dass
 
AFBC BOILERS PERFORMANCE IMPROVEMENT
AFBC BOILERS PERFORMANCE IMPROVEMENTAFBC BOILERS PERFORMANCE IMPROVEMENT
AFBC BOILERS PERFORMANCE IMPROVEMENT
Manohar Tatwawadi
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
Ashvani Shukla
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
Vundavilli Gautham
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
Nitin Patel
 
Principle of operation bowl mill
Principle of operation bowl millPrinciple of operation bowl mill
Principle of operation bowl millDevidutta Panda
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
Manohar Tatwawadi
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and FillShad Edwards
 
A complete presentation on Boiler.
A complete presentation on Boiler.A complete presentation on Boiler.
A complete presentation on Boiler.
Anuj Maurya
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
Manohar Tatwawadi
 
Fireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a BoilerFireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a BoilerZalak Shah
 
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power PlantWater steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
Hareesh VS
 

What's hot (20)

Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its Internals
 
AFBC BOILERS PERFORMANCE IMPROVEMENT
AFBC BOILERS PERFORMANCE IMPROVEMENTAFBC BOILERS PERFORMANCE IMPROVEMENT
AFBC BOILERS PERFORMANCE IMPROVEMENT
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
Principle of operation bowl mill
Principle of operation bowl millPrinciple of operation bowl mill
Principle of operation bowl mill
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
 
Boiler turbe failores
Boiler turbe failoresBoiler turbe failores
Boiler turbe failores
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and Fill
 
Dry heat losses in boiler
Dry heat losses in boilerDry heat losses in boiler
Dry heat losses in boiler
 
A complete presentation on Boiler.
A complete presentation on Boiler.A complete presentation on Boiler.
A complete presentation on Boiler.
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Fireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a BoilerFireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a Boiler
 
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power PlantWater steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
 

Viewers also liked

Boiler operation
Boiler operationBoiler operation
Boiler operation
Sakshi Vashist
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
National Productivity Council, Hyderabad, India
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam Generators
Hrishikesh Devan
 
Low Pressure Boiler Start-up Procedure
Low Pressure Boiler Start-up ProcedureLow Pressure Boiler Start-up Procedure
Low Pressure Boiler Start-up Procedure
Anwar Farid Bin Shahudin
 
Boiler Presentation
Boiler PresentationBoiler Presentation
Boiler Presentation
anshsmartstud
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
mitravanu mishra
 
Safe Operation and Explosions in Boilers
Safe Operation and Explosions in BoilersSafe Operation and Explosions in Boilers
Safe Operation and Explosions in Boilers
National Productivity Council, Hyderabad, India
 
Boiler(Introduction,classification and it's types) by sujan kharel
Boiler(Introduction,classification and it's types) by sujan kharelBoiler(Introduction,classification and it's types) by sujan kharel
Boiler(Introduction,classification and it's types) by sujan kharel
ansaluniversity3
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedvtsiri
 
Boiler Introduction
Boiler IntroductionBoiler Introduction
Boiler Introduction
controlsystemworld
 
Boiler operation engineers_rules_20111
Boiler operation engineers_rules_20111Boiler operation engineers_rules_20111
Boiler operation engineers_rules_20111
muhilcumaran
 
Low & Medium Pressure Boiler Water Trouble Shooting Guide
Low & Medium Pressure Boiler Water Trouble Shooting GuideLow & Medium Pressure Boiler Water Trouble Shooting Guide
Low & Medium Pressure Boiler Water Trouble Shooting Guide
Hemish Kapadia
 
Power Plant Chemistry FEED WATER TREATMENT
Power Plant Chemistry FEED WATER TREATMENTPower Plant Chemistry FEED WATER TREATMENT
Power Plant Chemistry FEED WATER TREATMENTDilip Kumar
 
Improving steam boiler operating efficiency
Improving steam boiler operating efficiencyImproving steam boiler operating efficiency
Improving steam boiler operating efficiency
Naqqash Sajid
 
Boiler Water Treatment -
Boiler Water Treatment - Boiler Water Treatment -
Water and fire tube boilers
Water and fire tube boilersWater and fire tube boilers
Water and fire tube boilers
Tariq Jamshaid
 

Viewers also liked (20)

Boiler operation
Boiler operationBoiler operation
Boiler operation
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Boiler operation (2)
Boiler operation (2)Boiler operation (2)
Boiler operation (2)
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam Generators
 
Low Pressure Boiler Start-up Procedure
Low Pressure Boiler Start-up ProcedureLow Pressure Boiler Start-up Procedure
Low Pressure Boiler Start-up Procedure
 
Boiler Presentation
Boiler PresentationBoiler Presentation
Boiler Presentation
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
Safe Operation and Explosions in Boilers
Safe Operation and Explosions in BoilersSafe Operation and Explosions in Boilers
Safe Operation and Explosions in Boilers
 
Boiler(Introduction,classification and it's types) by sujan kharel
Boiler(Introduction,classification and it's types) by sujan kharelBoiler(Introduction,classification and it's types) by sujan kharel
Boiler(Introduction,classification and it's types) by sujan kharel
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridged
 
Boiler Introduction
Boiler IntroductionBoiler Introduction
Boiler Introduction
 
Boiler operation engineers_rules_20111
Boiler operation engineers_rules_20111Boiler operation engineers_rules_20111
Boiler operation engineers_rules_20111
 
Presentation On Boiler Analysis
Presentation On Boiler AnalysisPresentation On Boiler Analysis
Presentation On Boiler Analysis
 
Boiler feedwater
Boiler feedwaterBoiler feedwater
Boiler feedwater
 
Water treatment of steam boilers
Water treatment of steam boilersWater treatment of steam boilers
Water treatment of steam boilers
 
Low & Medium Pressure Boiler Water Trouble Shooting Guide
Low & Medium Pressure Boiler Water Trouble Shooting GuideLow & Medium Pressure Boiler Water Trouble Shooting Guide
Low & Medium Pressure Boiler Water Trouble Shooting Guide
 
Power Plant Chemistry FEED WATER TREATMENT
Power Plant Chemistry FEED WATER TREATMENTPower Plant Chemistry FEED WATER TREATMENT
Power Plant Chemistry FEED WATER TREATMENT
 
Improving steam boiler operating efficiency
Improving steam boiler operating efficiencyImproving steam boiler operating efficiency
Improving steam boiler operating efficiency
 
Boiler Water Treatment -
Boiler Water Treatment - Boiler Water Treatment -
Boiler Water Treatment -
 
Water and fire tube boilers
Water and fire tube boilersWater and fire tube boilers
Water and fire tube boilers
 

Similar to Boiler Operation

BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdf
PrasadKandukuri4
 
Steam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfSteam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdf
GaluhAjeng26
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetRohit Meena
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
drazil
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
Rohit Meena
 
steam boilers.pptx
steam boilers.pptxsteam boilers.pptx
steam boilers.pptx
yogesh padwal
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plantSHIVAJI CHOUDHURY
 
Power plant engineering
Power plant engineeringPower plant engineering
Power plant engineering
nareshmeb
 
Ch.2
Ch.2Ch.2
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
Gerard B. Hawkins
 
sugar mill ss.pptx
sugar mill ss.pptxsugar mill ss.pptx
sugar mill ss.pptx
TANISH SHARMA
 
Factors Affecting Boiler Performance
Factors Affecting Boiler PerformanceFactors Affecting Boiler Performance
Factors Affecting Boiler Performance
Manohar Tatwawadi
 
Unit II boiloers and its mountings
Unit II boiloers and its mountingsUnit II boiloers and its mountings
Unit II boiloers and its mountings
Prashant Kumar
 
Unit-II- Steam Generators.pptx
Unit-II- Steam Generators.pptxUnit-II- Steam Generators.pptx
Unit-II- Steam Generators.pptx
ssuser8147f6
 
Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02
akjshare
 
Boiler accessories
Boiler accessoriesBoiler accessories
Boiler accessories
rudrik joshi
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)
sneh patel
 
Guide to Furnace Sootblowing
Guide to Furnace SootblowingGuide to Furnace Sootblowing
Guide to Furnace SootblowingRichard Smith
 
boilers
boilersboilers
boilers
Saurabh Kumar
 
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCOAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
CHANDRA KUMAR S
 

Similar to Boiler Operation (20)

BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdf
 
Steam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfSteam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdf
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 
steam boilers.pptx
steam boilers.pptxsteam boilers.pptx
steam boilers.pptx
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Power plant engineering
Power plant engineeringPower plant engineering
Power plant engineering
 
Ch.2
Ch.2Ch.2
Ch.2
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
 
sugar mill ss.pptx
sugar mill ss.pptxsugar mill ss.pptx
sugar mill ss.pptx
 
Factors Affecting Boiler Performance
Factors Affecting Boiler PerformanceFactors Affecting Boiler Performance
Factors Affecting Boiler Performance
 
Unit II boiloers and its mountings
Unit II boiloers and its mountingsUnit II boiloers and its mountings
Unit II boiloers and its mountings
 
Unit-II- Steam Generators.pptx
Unit-II- Steam Generators.pptxUnit-II- Steam Generators.pptx
Unit-II- Steam Generators.pptx
 
Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02
 
Boiler accessories
Boiler accessoriesBoiler accessories
Boiler accessories
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)
 
Guide to Furnace Sootblowing
Guide to Furnace SootblowingGuide to Furnace Sootblowing
Guide to Furnace Sootblowing
 
boilers
boilersboilers
boilers
 
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCOAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
 

Recently uploaded

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 

Recently uploaded (20)

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 

Boiler Operation

  • 2. 2 IMPORTANT PARAMETERS IN AFBC BOILER 1. Bed Height / F.D. Air Pressure 2. Primary Air Pressure 3. Bed Temperature / Furnace Temperature 4. Fuel Size 5. Bed Material Size & Specifications 6. Air & Fuel Ratio
  • 3. 3 1. BED HEIGHT / FD AIR PRESSURE • Static height for AFBC boiler is to be maintained 250 to 300mm during initial light up of boiler. • Expand bed height for AFBC boiler is to be maintained 500 to 600 mmwc. • FD air discharge pressure is to be maintained 600 to 650mmwc • Wind box or air box pressure is to be maintained 500 to 600mmwc High W.B. pressure increases the erosion of bed coils & low WBP affect fluidization.
  • 4. 4 2. PRIMARY AIR PRESSURE  P.A. fan air header pressure for AFBC boiler is to be maintained 1000 to 1150 mmwc.  Diff. of Primary Air Pressure & F.D. Wind Box pressure is to be maintained approximately 500 mmwc. High P.A. Pressure increases the high bed coil erosion and carryover. Low P.A. pressure cause the blockage of P.A. lines and puffing in boiler and also increases chances of clinkerization.
  • 5. 5 3. BED TEMP. / FURNACE TEMPERATURE • Depends upon the type of fuel & firing method. • For (Indian Coal) bed temp. in FBC/AFBC/CFBC is to be maintained 850o C to 900o C. • For Imported Coal bed temp. in FBC/AFBC/CFBC is to be maintained bed 875o C to 925o C. • For lignite bed temp. in FBC/AFBC/CFBC is to be maintained 800o C to 850o C. • For Petcock bed temp. in FBC/AFBC/CFBC is to be maintained 875o C to 950o C.
  • 6. 6 • For Rice husk and other Bio-mass fuel bed temperature in FBC/AFBC/CFBC is to be maintained 850o C to 900o C. • For Stoker firing furnace temperature is maintained around 1100o C to 1200o C. • For Pulverized Fuel firing furnace temperature is maintained 1100o C to 1300o C. • For oil & gas fuel firing furnace temperature is 1100o C to 1500o C. 3. BED TEMP. / FURNACE TEMPERATURE
  • 7. 7 4.FUEL SIZE For FBC / AFBC / CFBC Boiler Size : 0 to 8 mm, less then 1mm not allowed more then 20% Distribution : 1 to 5mm – 70% 5 to 8mm – 20% 0 to 1mm – 10% Lower the size of coal higher the un-burnt in fly ash. Higher the size of coal higher the erosion of bed coils and blockage of fuel air pipe & clinkerization in Boiler.
  • 8. 8 For Stoker fired Boiler Size : 5 to 25mm, less then 5mm not allowed more then 5% Distribution : 5mm to 15mm – 25 % 15mm to 25mm – 75% 0 to 5mm – 05% Lower the size of coal higher unburnt in fly ash & carryover through Boiler.
  • 9. 9 For Pulverized Fired Boiler Raw Coal Feeder Inlet – 0 to 25mm( higher size will be effected by pulverizer (Pulverizer Inlet) performance and more rejection ) Pulverized Coal Size – 70% through 200 mesh Size Distribution : 150 – 200 - 60% 100 – 150 - 30% 75 - 100 - 10% Higher the size of pulverized coal below 100 mesh results unburnt in bottom ash.
  • 10. 10 5. BED MATERIAL SIZE & SPECIFICATIONS Bed Material Size :- Size:0.85mm o 2.36mm (not below 0.85mm) Distribution : 0.85 mm to 1.0mm –10% 1.0 mm to 1.5mm – 50% 1.5 to 2.36 mm – 40%
  • 11. 11 Bed Material Specifications : Crushed Fire Bricks Castable IS8 grade Bricks or River Silica Sand Fusion Temperature : 1300 Deg. C. Shape : Spherical Angular Bulk Density : 1050 Kg/m3 Silica (SiO2) : 68 % Al203 : 28 % Fe203 : 1.05% PiO2 : 1.67% MnO : Trace CaO : 0.54% MgO : 0.23% P2O5 : 0.08% A2O : 0.22% K2O : 0.45%
  • 12. 12 6. AIR & FUEL RATIO Typical excess air to achieve highest efficiency for different fuels are: • Power plant boilers normally run about 10 to 20 % • Fuel Oil Fired boilers may run as low as 5 to 15%. • Natural gasfired boilers may run as low as 5 to 10% • Pulverized coalfired boilers may run with 15 to 20% • Gas turbines run very lean with up to 300%
  • 13. 13 COMPARISON OF FLUIDISED BED BOILER WITH SPREADER STOKER & PF CHARACTERISTICS FLUIDESED BED SPREADER STOKER PF Fuel quality (Ash, Calorific value. Volatile matter, Size distribution) Has no effect on operation Output affected by coal quality Output affected by coal quality Maintenance No moving parts; less maintenance Moving grate in high temp. zone; required frequent maintenance Frequent maintenance due to pulverizer Efficiency (for typical Indian Coal with 45% ash) About 86% Around 76% 86 – 87 % Efficiency at low load Better Poor Less Soot Blowers Not required Necessary Necessary NOx Formation Low High High
  • 15. 15 Various Emergency Conditions: Drum level low and low-low Drum level high and high high Furnace Draft high and high high Bed Temperature High Bed Temperature Low Water wall / screen tube / evaporator tube failure Super heater tube failure High super heater temperature Low Super heater temperature Flame Failure Furnace Explosion Boiler pressure high Coal feeder failure PAH / SAH tube failure Boiler feed pump failure Fan Failure
  • 16. 16 DRUM LEVEL LOW AND LOW-LOW: (A) CAUSE : 1. Failure of boiler feed pump. 2. Failure of drum level controller. 3. Inadvertent opening of C.B.D. 4. Extraordinary change in load. (Sudden reduction in load) 5. Water tube failure.
  • 17. 17 DRUM LEVEL LOW AND LOW-LOW: (B) EFFECT : Boiler may damage badly. (C) ACTION : • Run the boiler if drum level is within safe limit (Lo alarm and lo-lo alarm came). If it goes beyond safe limit allow boiler to trip. • Attempt to control with feed valve. • If feed valve is stuck up open parallel line valve or bypass valve. • Take care while increasing feed flow that running B.F.P. do not trip on feed flow high. • If low level is due to tripping of feed pump start stand by pump, if it is on manual. • If water level is below safe level, allow to trip the boiler on drum level lo-lo to protect the boiler drum and tubes.
  • 18. 18 (A) CAUSE: 1. Failure of drum level controller. 2. Extra ordinary increase in load 3. Sudden increase in firing rate. DRUM LEVEL HIGH AND HIGH HIGH:
  • 19. 19 (B) EFFECT:  Water may enter turbine and serious damages to turbine may occur.  Joint valve on main steam pipe work leaks.  Carry over with sharp fall in super heater temperature (C) ACTION : 1. Run the boiler if drum level is within safe limit (drum level high and high high alarm came). If goes beyond limit allow boiler to trip. • Attempt to control with feed valve. • If feed valve is stuck up close isolating valve. • Attempt to control drum level by opening C.B.D. • Close Economizer inlet valve and allow feed pump to run in recirculation. • If above measures fail trip the feed pump. 2. If level is due to sudden rise in load. If high level rises above normal level allow boiler to trip on drum level high high. • If main steam temperature drop takes place open steam pipe drains. • Trip the turbine / prime mover when steam temperature falls. DRUM LEVEL HIGH AND HIGH HIGH:
  • 20. 20 (A) CAUSE : 1. Due to faulty operation of fan control. 2. Disturbed combustion 3. Un-controlled fuel entry FURNACE PRESSURE HIGH & HIGH HIGH:
  • 21. 21 (B) EFFECT: – Boiler may damage due to high furnace pressure. – Weak parts of furnace (ductings and enclosures) may explode due to high furnace pressure. (C) ACTION : – If it is due to faulty operation of I.D./P.A./S.A. fan control, take it on manual and maintain the furnace in suction. – If furnace pressure has increased beyond limit allow boiler to trip on furnace draught high high. FURNACE PRESSURE HIGH & HIGH HIGH:-
  • 22. 22 (A) CAUSE : 1. High CV and low ash coal used. 2. Low P.A. flow / S.A. flow 3. Sudden change in load 4. Faulty bed temp thermocouple 5. Ash recirculating system trouble BED TEMPERATURE HIGH IN FBC BOILER
  • 23. 23 (B) EFFECT :  Chances of clinker formation  Chances of refractory failure  Chances of screen tube failure (C) ACTION :  Control bed temp by recirculation ash through recirculation feeder.  Start sand feeder if bed height permits.  Increase P.A. flow up and increase S.A. flow.  Reduce the load by cutting coal feeder.  Coal feeders trip, if temp rises above limit and allow boiler to trip, if temp exceeds beyond safe limit to save bed from clinkerisation.  Check the bed temp thermocouple. BED TEMPERATURE HIGH IN FBC BOILER
  • 24. 24 (A) CAUSE : 1. High PA with respect to load / high SA flow w.r.t. load. 2. Low CV high ash coal used. 3. Coal interruption or coal feeder trips or overfeeding of coal into furnace. 4. Recirculation ash feeder speed may increase. 5. Faulty bed temp. thermocouple. 6. Water tube / screen tube / evaporator tube failure. BED TEMPERATURE LOW IN FBC BOILER
  • 25. 25 (B) EFFECT :  Boiler steam flow will reduce.  Super heater temp drops.  Furnace draft will fluctuate. (C) ACTION :  Reduce P.A. Fan flow, if excessive / reduce S.A. flow, if excessive.  Reduce speed of recirculation ash feeder.  Stop bed material supply, if running.  Check bed temp thermocouple.  Check any leakage sound from furnace.  Check coal feeder and coal supply. BED TEMPERATURE LOW IN FBC BOILER
  • 26. 26 (A) CAUSE : 1. Starved water wall. 2. Block tube, eroded tube, pitted tube, salt deposits. 3. Circulation affected due to open low point drains. WATER WALL/ SCREEN/ EVAPORATOR TUBE FAILURE:
  • 27. 27 (B) EFFECT :  Hissing steam leakage noise from boiler.  Unstable flame fluctuating draught.  Bed temperature drops sharply.  High feed water flow for given steam generation / increase in make up water.  Increase in I.D. Fan loading.  Below screen temperature drops sharply.  Flue gas outlet temperature decreased. WATER WALL/ SCREEN/ EVAPORATOR TUBE FAILURE:
  • 28. 28 (C) ACTION :  Every shift check low point drain valve are fully closed.  Every shift check the furnace listen furnace to detect steam noise.  At first diagnostics of tube failure, start load reduction; trip out unit before damage become serious. Quicker shutdown reduces extensive damage.  Try to locate tube at low level.  Don’t allow the drum level to go beyond a danger level.  Start another BFP, if drum level is not maintained by running BFP. WATER WALL/ SCREEN/ EVAPORATOR TUBE FAILURE:
  • 29. 29 (A) CAUSE : 1. Sustaining high metal temp due to water wall slagging or inadequate steam flow and high gas temp during hot start. 2. Erosion on tubes due to high excess air. 3. Blocked tubes. 4. Starvation of tubes. 5. Salt deposition due to high water level in drum. Poor quality of spray water. SUPER HEATER TUBE FAILURE:
  • 30. 30 (B) EFFECT : • Hissing noise notices. • Flue gas temp drops. • High feed water consumption compared to steam flow. • Over loading on I.D. Fan. • Erosion of other tubes and damages to other SAH tubes. (C) ACTION : 1. As soon as leakages noticed start reducing the load and trip the boiler. 2. Listen the SH region for steam leakage. 3. Try to locate leakage through manholes before the boiler is depressurized. SUPER HEATER TUBE FAILURE:
  • 31. 31 (A) CAUSE : 1. High excess air. 2. Low feed water temp HP Heater not in service at constant firing / load. 3. Sudden increase in firing rate to increase steam pressure. 4. In adequate spray. 5. Lodging of soot on the water walls considerably. HIGH SUPER HEATER TEMPERATURE:
  • 32. 32 (B) EFFECT : Rise in (+ve) positive turbine expansion. – Creep rate increase in tube metal, turbine parts, steam piping. (C) ACTION : 1. Check feed water temp. If HP heaters are available, put in service and if not reduce the load. 2. Slow down firing rate. 3. Reduce excess air, if more. 4. Check Spray control HIGH SUPER HEATER TEMPERATURE:
  • 33. 33 (A) CAUSE : 1. Dirty super heater 2. Inadequate air flow. 3. High Spray 4. Too high feed water temp. 5. Sharp increase in load and pressure drop. 6. High Drum level. LOW SUPER HEATER TEMPERATURE:
  • 34. 34 (B) EFFECT :- 1. Turbine expansion may be negative. 2. May induce thermal stresses in S.H. (C) ACTION :- 1. Check air flow – increase, if necessary. 2. Reduce spray, if more. 3. Check feed water temp. 4. Avoid sharp rise in load to boiler pressure drop. 5. If, it is due to high drum level – allow unit to trip and open main steam drains. LOW SUPER HEATER TEMPERATURE:
  • 35. 35 (A) CAUSE : 1. Dirty Oil / Gas Burner 2. Faulty Flame Scanner 3. Failure of Blower 4. Furnace Pressure High 5. Low Combustion Air FLAME FAILURE:
  • 36. 36 (B) EFFECT :  Boiler will trip on flame failure  Chances of furnace explosion, if unburnt oil / gas / coal mixture entered in furnace.  Boiler steam pressure may fall down.  Super Heater Steam Temp. drop sharply.  Variation observed in drum level (drum level low). FLAME FAILURE:
  • 37. 37 (C) ACTION :  Purge the boiler before putting burner back and purge burner as per cycle time given by supplier.  Check the flame scanner and clean the photocell, if found dirty.  Check the sparking circuit and high voltage transformer supply.  Check spark plug, if found dirty, clean it and set the gap.  Clean the burner tip, if nozzles (holes) are found chocked.  Check the air blower and maintain air fuel ratio.  Check the explosion doors, close it if opened. FLAME FAILURE:
  • 38. 38 (A) CAUSE : 1. Accumulation of unburnt fuel during lit up / start up of boiler. 2. Improper burning. 3. Inadequate air. 4. Secondary combustion. (B) EFFECT : Furnace explosion can cause extensive damage. (C) ACTION : 1. Always purge the boiler with 40% full load air for about five minutes. No cut short in purging allowed. 2. Adjust fuel air ratio. FURNACE EXPLOSION:
  • 39. 39 (A) CAUSE : 1. Sudden drop in load / steam flow. 2. Un-controlled fuel entry. 3. Turbine / prime mover trips. BOILER PRESSURE HIGH:
  • 40. 40 (B) EFFECT :-  Disturbance in drum water level.  Safety valves may life if pressure rise is up to that extent.  Boiler may trip on high pressure. (C) ACTION :-  Open start up vent valve.  Control fuel input and drum level.  Check coal feeder feeding rate.  Adjust the load on unit, if it has dropped.  If TG / prime mover has tripped first, allow boiler to trip but safety valve may lift. BOILER PRESSURE HIGH:
  • 41. 41 (A) CAUSE : 1. Electrical supply failed 2. V.F.D. fault 3. Bed temperature high 4. Furnace draft high 5. Furnace draft low 6. Drum level high 7. Drum level low COAL FEEDER FAILURE:
  • 42. 42 (B) EFFECT :  Boiler pressure may fall down  SH steam temp fall sharply  Bed temp. will decrease  Variation in furnace pressure (LOW)  Variation in drum level (Low) COAL FEEDER FAILURE:
  • 43. 43 (C) ACTION :  Control boiler pressure by reducing load on turbine / prime mover or process.  Control super heater steam temp by closing spray valve.  Reduce PA / SA flow to control bed temp.  Control furnace draft and drum level.  Check electrical fault or emergency stop push button & restart coal feeder.  Check VFD fault, if any.  Restart coal feeder after checking cause of failure. COAL FEEDER FAILURE:
  • 44. 44 (A) CAUSE : Erosion & Corrosion of tube. (B) EFFECT :  Flue gas temp after APH will fall down.  Increases in O2 percentage at ESP inlet.  PA / SA Fan overloaded.  Bed temp may be increased. (C) ACTION :  Control flue gas temp by passes PAH.  Reduce coal feeding to maintain O2 percentage.  Control bed temp.  If leakage of tubes are more stop the boiler and plug / replaced. PAH/ SAH TUBE FAILURE:
  • 45. 45 (A) CAUSE : 1. Motor protection relay operates 2. Lube oil temperature high 3. Discharge flow high 4. Motor bearing temperature high 5. Deaerator level low 6. BFP suction pressure low BOILER FEED PUMP FAILURE:
  • 46. 46 (B) EFFECT :  If standby pump is available, it will start on auto or start it manually.  If standby pump does not start on auto & manual, drum level may go very low, which may trip the boiler. BOILER FEED PUMP FAILURE:
  • 47. 47 (C) ACTION :  Start the stand by pump, if it does not start on auto. Adjust the load to maintain the drum level as well as to prevent the tripping of this pump on high feed water flow.  See the proper operation of recirculation valve and C.W. Valve.  Analyze and rectify the fault in the main feed pump. Put it on auto.  Restore the bus supply, if it has lost and make the pump available.  Check the deaerator level and if it falls below safe limit, stop the feed pump, immediately.  Check the BFP suction strainer and clean it, if found chocked. BOILER FEED PUMP FAILURE:
  • 48. 48 (A) CAUSE :- 1. Electrical motor protection 2. Fan bearing temp becomes high high 3. Motor bearing temp becomes very high 4. Drive fault (MCC fault) 5. Boiler trip LOSS OF FANS: (1) ID FAN FAILURE
  • 49. 49 (B) EFFECT : 1. Furnace may get pressurized 2. Boiler will trip on boiler furnace pressure high. (C) ACTION : 1. Check emergency or field stop. 2. Rectify electrical fault, if any. 3. Check cause for boiler trip & normalize it. 4. Check fan / motor-bearing temp. 5. Restart I.D. Fan after checking cause of tripping and taking corrective actions. LOSS OF FANS: (1) ID FAN FAILURE
  • 50. 50 (A) CAUSE : 1. Electrical motor protection. 2. Fan bearing temp. becomes high high. 3. Motor bearing temp. becomes very high. 4. MCC fault. 5. Boiler trip. 6. Run feed back off. 7. ID Fan trip. 8. SA trip. (1) PA FAN FAILURE LOSS OF FANS:
  • 51. 51 (B) EFFECT :  Boiler will trip on a. Furnace draft low b. P.A. flow low. (C) ACTION : 1. Rectify electrical fault, if any. 2. Check cause for boiler trip and normalize it. 3. Check fan / motor-bearing temp. 4. Restart the P.A. Fan after checking the cause of tripping and taking corrective actions. (1) PA FAN FAILURE LOSS OF FANS:
  • 52. 52 (A) CAUSE : 1. Electrical motor protection. 2. Fan bearing temp becomes high high. 3. Motor bearing temp becomes very high. 4. MCC fault. 5. Boiler trip. 6. Run feed back off. 7. I.D. Fan trip. (1) SA FAN FAILURE LOSS OF FANS:
  • 53. 53 (B) EFFECT : Boiler will trip on low furnace draft. (C) ACTIONS :  Rectify electrical fault, if any.  Check cause for boiler, trip & normalize it.  Check fan / motor-bearing temp.  Restart the S.A. Fan after checking the cause of tripping and taking corrective actions. (1) SA FAN FAILURE LOSS OF FANS:
  • 54. 54 T H A N K Y O U