SlideShare a Scribd company logo
Burj Khalifa
Report by Rishabh Lala
Well Known Facts
• Specialty : Tallest Building
• Height : 828 meters
• Floors : 162 Floors
• Time : 6 Years
• Completed in: 2010
• Steel : 30 K Tons
• Concrete : 250 K CUM
Well Known Facts
• Accommodation :35 K People
• Elevators : 57
• Escalators : 8
• Elevators Speed : 35 km/h
• Biggest Elevator : 46 People at Once
• Service Elevator : Worlds Tallest
• Water Heating : Solar = 32 K KWH
• Refuge Rooms : one in 30 Floors
Structural Facts
• Designer : SOM Group
• Buttressed Core : Hexagonal Hub
• Concrete : C60-C80, with Fly Ash
• Y Shaped Plan : To reduce wind effect
• Each Wing has : High performance Walls
: and Perimeter Columns
: with Central (Hexagon) Core
• Result : Extremely stiff tower
Typical Floor Plan
Structural Facts
• Confuse the Wind : Vortices never organize
• Reason : At Each Setback, building
• : Building Width Changes
• Hexagonal :
• Wing Walls : Act as webs and flanges
• Hammerhead Walls : of a Beam
• Wall Concrete : C60 –C80
• Optimization : Virtual Work and Lagrange
: Multiplier Methodology
• Setback
Structural Facts
• Differential Column Shortening : Least Affected
• 5 Outrigger Truss Sets : Ensure stress Distribution
• Tower Top : Structural Steel Spire
• Analysis (Gravity, Wind, P Delta): Etabs version 8.4
• 3 D Model : RCC Walls, Slabs, Beams, raft,
Piles, and the spire steel system
• Shells and Nodes : 73500 Shells, and 75 K nodes
• Natural Period (I,II and V) : 11.3 s, 10.2 s, 4.3 s
• Zone (as per DM ) : UBC 97 Zone 2a with Z = 0.15
• Soil Profile : Sc
Mode 1 : 11.3 Seconds Mode 2 : 10.2 Seconds
Mode 5 : 4.3 Seconds
Foundation
• Foundation : Pile Supported Raft
• Raft : 12 feet or 3.7 m thick
• 4 Pours (Parts) : 3 wings and 1 core
• Concrete : C50 (50 MPa)
• Type : Self Consolidating
• Fly ash : 40% with W/C =0.34
• Test Cubes : 3.7 m thick
• Purpose : Thermal Check
• Piles : 194 Bored Cast in- Situ
• Mega Raft Cubes
Piles
• Diameter : 1.5 Meter
• Length : 43 Meter
• Design Capacity : 3000 Tonnes
• Pile Load Test : 6,000 Tonnes
• Cube Strength : C60 (60 MPa)
• Friction Piles Support: Cemented Calcisiltite
• Skin Friction : 250 to 350 tons/sq feet
Wind Engineering
• Wind Tunnel
• Studies Conducted by RWDI
• Vortex Shedding
• High-frequency-force-balance tunnel tests
• 6 Wind Directions
• Aero-Elastic Models were Initiated by the End
Construction Sequence
• Conventional Approach
• But as Building height increases: The results will
diverge from actual behavior
• Time Dependent Approach: Creep, Shrinkage,
Sequential Loading
• Burj Khalifa : 15 Separate FEM
• Time Steps : 50 Years After Construction
 Actual Concrete Behaviour
•  MIDAS Gen 2010
Compensation Method
• Horizontal
• Vertical
Issues
• Rock at 50 m was fragile and
saturated with Ground Water
• Solution:
• 194 Piles Constructed
• Viscous Polymer Slurry
• Owner:
• Project Manager:
•
• Architect/Structural
Engineers/:
• Adopting Architect &
Engineer/Field
Supervision:
• Independent
Verification and Testing
Agency:
• General Contractor:
• Foundation Contractor:
• Emaar Properties
PJSC
• Turner Construction
International
• Skidmore, Owings &
Merrill LLP
• Hyder Consulting Ltd.
• GHD Global Pty. Ltd.
• Samsung/BeSix/Arabtec
• NASA Multiplex

More Related Content

What's hot

Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
Zabihullah Nasiri
 
Rigid frame systems
Rigid frame systemsRigid frame systems
Rigid frame systems
Muftah Aljoat
 
Burj khalifa , its engineering as well as architectural features and facts.
Burj khalifa , its engineering as well as architectural features and facts.Burj khalifa , its engineering as well as architectural features and facts.
Burj khalifa , its engineering as well as architectural features and facts.
Rohit Arora
 
Composite structure of concrete and steel.
Composite structure of concrete and steel.Composite structure of concrete and steel.
Composite structure of concrete and steel.
Suhailkhan204
 
Turning torso
Turning torsoTurning torso
Turning torso
Miral Hadakia
 
Structural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildingsStructural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildings
Manoj Kumar
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
Akshay Revekar
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifa
SUNILPRASAD68
 
High-rise Presentation
High-rise PresentationHigh-rise Presentation
High-rise Presentation
Kaiserin Tania
 
High Rise Building Research Document
High Rise Building Research DocumentHigh Rise Building Research Document
High Rise Building Research Document
Nicholas Socrates
 
Burj khalifa-mode of construction
Burj khalifa-mode of constructionBurj khalifa-mode of construction
Burj khalifa-mode of construction
Joji Mathew
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
Prasad Thanthratey
 
Burj al Arab Constuction
Burj al Arab ConstuctionBurj al Arab Constuction
Highrise structure
Highrise structureHighrise structure
Highrise structure
Bee Key Verma
 
Diagrid structural system
Diagrid structural systemDiagrid structural system
Diagrid structural system
vivek bhathee
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
Anjneya Srivastava
 
Pre engineered building ppt rit
Pre engineered building ppt ritPre engineered building ppt rit
Pre engineered building ppt rit
Shubham Parab
 
Basic design criteria for high rise buildings
Basic design criteria for high rise buildings Basic design criteria for high rise buildings
Basic design criteria for high rise buildings
Parent Construction & Consultancy Ltd.
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
Meer Musabber ali (joyous)
 
Types roof trusses
Types roof trussesTypes roof trusses
Types roof trusses
AnsherinaDelMundo
 

What's hot (20)

Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
Rigid frame systems
Rigid frame systemsRigid frame systems
Rigid frame systems
 
Burj khalifa , its engineering as well as architectural features and facts.
Burj khalifa , its engineering as well as architectural features and facts.Burj khalifa , its engineering as well as architectural features and facts.
Burj khalifa , its engineering as well as architectural features and facts.
 
Composite structure of concrete and steel.
Composite structure of concrete and steel.Composite structure of concrete and steel.
Composite structure of concrete and steel.
 
Turning torso
Turning torsoTurning torso
Turning torso
 
Structural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildingsStructural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildings
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifa
 
High-rise Presentation
High-rise PresentationHigh-rise Presentation
High-rise Presentation
 
High Rise Building Research Document
High Rise Building Research DocumentHigh Rise Building Research Document
High Rise Building Research Document
 
Burj khalifa-mode of construction
Burj khalifa-mode of constructionBurj khalifa-mode of construction
Burj khalifa-mode of construction
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
Burj al Arab Constuction
Burj al Arab ConstuctionBurj al Arab Constuction
Burj al Arab Constuction
 
Highrise structure
Highrise structureHighrise structure
Highrise structure
 
Diagrid structural system
Diagrid structural systemDiagrid structural system
Diagrid structural system
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
 
Pre engineered building ppt rit
Pre engineered building ppt ritPre engineered building ppt rit
Pre engineered building ppt rit
 
Basic design criteria for high rise buildings
Basic design criteria for high rise buildings Basic design criteria for high rise buildings
Basic design criteria for high rise buildings
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
Types roof trusses
Types roof trussesTypes roof trusses
Types roof trusses
 

Viewers also liked

ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
atchitect and design
 
high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)
suraj kumar
 
Bridge Construction & Its Types
Bridge Construction & Its TypesBridge Construction & Its Types
Bridge Construction & Its Types
Zakaria Yahya
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges
David Collings
 
Golden gate bridge construction
Golden gate bridge constructionGolden gate bridge construction
Golden gate bridge construction
Nouman Tahir
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
David H Moloney
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
University of Tikrit
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
MAHAVIR MEENA
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slides
Waqas Javaid
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge constructionsymphonyjo
 
Bridge
Bridge Bridge
Bridge illpa
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
Robin Nirwal
 

Viewers also liked (12)

ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)
 
Bridge Construction & Its Types
Bridge Construction & Its TypesBridge Construction & Its Types
Bridge Construction & Its Types
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges
 
Golden gate bridge construction
Golden gate bridge constructionGolden gate bridge construction
Golden gate bridge construction
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slides
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge construction
 
Bridge
Bridge Bridge
Bridge
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 

Similar to Burj khalifa

Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
Rajesh Prasad
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
HetviPatel58
 
Offshore Drilling rigs (6) i
Offshore Drilling rigs (6) iOffshore Drilling rigs (6) i
Offshore Drilling rigs (6) i
Solomon Okoro
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the world
ADARSH _
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and CaissonsRizwan Samor
 
Tokyo skytree
Tokyo skytreeTokyo skytree
Tokyo skytree
FirshaSaleem
 
ANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptx
AnshuBarmase
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
KriShna Sharma
 
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
pulakrajpadhai
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Rajesh Prasad
 
Extending service life of existing bridges
Extending service life of existing bridgesExtending service life of existing bridges
Extending service life of existing bridges
Eva Lantsoght
 
Burj khalifa Dubai
Burj khalifa DubaiBurj khalifa Dubai
Burj khalifa Dubai
abhaykumar619
 
FYP presentation, structure task
FYP presentation, structure taskFYP presentation, structure task
FYP presentation, structure task
ali_alajmi_squ
 
Beijing National Stadium (China)
Beijing National Stadium (China)Beijing National Stadium (China)
Beijing National Stadium (China)
sultanimulk796
 
Pm burj case
Pm burj casePm burj case
Pm burj case
Pooja Mishra
 
Burj al-arab
Burj al-arabBurj al-arab
Burj al-arab
Souvik Mondal
 
Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operation
Safdar Ali
 

Similar to Burj khalifa (20)

Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
Offshore Drilling rigs (6) i
Offshore Drilling rigs (6) iOffshore Drilling rigs (6) i
Offshore Drilling rigs (6) i
 
Tunnel PDF.pdf
Tunnel PDF.pdfTunnel PDF.pdf
Tunnel PDF.pdf
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the world
 
burjjjj new
burjjjj newburjjjj new
burjjjj new
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
Tokyo skytree
Tokyo skytreeTokyo skytree
Tokyo skytree
 
ANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptx
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
 
Extending service life of existing bridges
Extending service life of existing bridgesExtending service life of existing bridges
Extending service life of existing bridges
 
Burj khalifa Dubai
Burj khalifa DubaiBurj khalifa Dubai
Burj khalifa Dubai
 
FYP presentation, structure task
FYP presentation, structure taskFYP presentation, structure task
FYP presentation, structure task
 
Beijing National Stadium (China)
Beijing National Stadium (China)Beijing National Stadium (China)
Beijing National Stadium (China)
 
Pm burj case
Pm burj casePm burj case
Pm burj case
 
Tokyo Sky Tree
Tokyo Sky TreeTokyo Sky Tree
Tokyo Sky Tree
 
Burj al-arab
Burj al-arabBurj al-arab
Burj al-arab
 
Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operation
 

More from Rishabh Lala

Earth resistant design philosophy
Earth resistant design philosophyEarth resistant design philosophy
Earth resistant design philosophy
Rishabh Lala
 
Software analysis concepts
Software analysis conceptsSoftware analysis concepts
Software analysis concepts
Rishabh Lala
 
Clay Fly Ash Bricks
Clay Fly Ash BricksClay Fly Ash Bricks
Clay Fly Ash Bricks
Rishabh Lala
 
Listening skills in technical education
Listening skills in technical educationListening skills in technical education
Listening skills in technical education
Rishabh Lala
 
Corrosion of re bars
Corrosion of re barsCorrosion of re bars
Corrosion of re bars
Rishabh Lala
 
Internship Report
Internship ReportInternship Report
Internship Report
Rishabh Lala
 
Axis vm presentation
Axis vm presentationAxis vm presentation
Axis vm presentation
Rishabh Lala
 
Properties of Fresh and Hardened Concrete
Properties of Fresh and Hardened ConcreteProperties of Fresh and Hardened Concrete
Properties of Fresh and Hardened Concrete
Rishabh Lala
 
Concrete- Classification,Properties and Testing
Concrete- Classification,Properties and TestingConcrete- Classification,Properties and Testing
Concrete- Classification,Properties and Testing
Rishabh Lala
 
Special Types of Concrete
Special Types of ConcreteSpecial Types of Concrete
Special Types of Concrete
Rishabh Lala
 
Managerial roles and skills and Management as Profession
Managerial roles and skills and Management as ProfessionManagerial roles and skills and Management as Profession
Managerial roles and skills and Management as Profession
Rishabh Lala
 

More from Rishabh Lala (12)

Earth resistant design philosophy
Earth resistant design philosophyEarth resistant design philosophy
Earth resistant design philosophy
 
Software analysis concepts
Software analysis conceptsSoftware analysis concepts
Software analysis concepts
 
Clay Fly Ash Bricks
Clay Fly Ash BricksClay Fly Ash Bricks
Clay Fly Ash Bricks
 
Listening skills in technical education
Listening skills in technical educationListening skills in technical education
Listening skills in technical education
 
Corrosion of re bars
Corrosion of re barsCorrosion of re bars
Corrosion of re bars
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Axis vm presentation
Axis vm presentationAxis vm presentation
Axis vm presentation
 
Properties of Fresh and Hardened Concrete
Properties of Fresh and Hardened ConcreteProperties of Fresh and Hardened Concrete
Properties of Fresh and Hardened Concrete
 
Unit one
Unit oneUnit one
Unit one
 
Concrete- Classification,Properties and Testing
Concrete- Classification,Properties and TestingConcrete- Classification,Properties and Testing
Concrete- Classification,Properties and Testing
 
Special Types of Concrete
Special Types of ConcreteSpecial Types of Concrete
Special Types of Concrete
 
Managerial roles and skills and Management as Profession
Managerial roles and skills and Management as ProfessionManagerial roles and skills and Management as Profession
Managerial roles and skills and Management as Profession
 

Recently uploaded

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
iemerc2024
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
nikitacareer3
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 

Recently uploaded (20)

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 

Burj khalifa

  • 1. Burj Khalifa Report by Rishabh Lala
  • 2. Well Known Facts • Specialty : Tallest Building • Height : 828 meters • Floors : 162 Floors • Time : 6 Years • Completed in: 2010 • Steel : 30 K Tons • Concrete : 250 K CUM
  • 3. Well Known Facts • Accommodation :35 K People • Elevators : 57 • Escalators : 8 • Elevators Speed : 35 km/h • Biggest Elevator : 46 People at Once • Service Elevator : Worlds Tallest • Water Heating : Solar = 32 K KWH • Refuge Rooms : one in 30 Floors
  • 4. Structural Facts • Designer : SOM Group • Buttressed Core : Hexagonal Hub • Concrete : C60-C80, with Fly Ash • Y Shaped Plan : To reduce wind effect • Each Wing has : High performance Walls : and Perimeter Columns : with Central (Hexagon) Core • Result : Extremely stiff tower
  • 6. Structural Facts • Confuse the Wind : Vortices never organize • Reason : At Each Setback, building • : Building Width Changes • Hexagonal : • Wing Walls : Act as webs and flanges • Hammerhead Walls : of a Beam • Wall Concrete : C60 –C80 • Optimization : Virtual Work and Lagrange : Multiplier Methodology
  • 8. Structural Facts • Differential Column Shortening : Least Affected • 5 Outrigger Truss Sets : Ensure stress Distribution • Tower Top : Structural Steel Spire • Analysis (Gravity, Wind, P Delta): Etabs version 8.4 • 3 D Model : RCC Walls, Slabs, Beams, raft, Piles, and the spire steel system • Shells and Nodes : 73500 Shells, and 75 K nodes • Natural Period (I,II and V) : 11.3 s, 10.2 s, 4.3 s • Zone (as per DM ) : UBC 97 Zone 2a with Z = 0.15 • Soil Profile : Sc
  • 9. Mode 1 : 11.3 Seconds Mode 2 : 10.2 Seconds Mode 5 : 4.3 Seconds
  • 10. Foundation • Foundation : Pile Supported Raft • Raft : 12 feet or 3.7 m thick • 4 Pours (Parts) : 3 wings and 1 core • Concrete : C50 (50 MPa) • Type : Self Consolidating • Fly ash : 40% with W/C =0.34 • Test Cubes : 3.7 m thick • Purpose : Thermal Check • Piles : 194 Bored Cast in- Situ
  • 11. • Mega Raft Cubes
  • 12. Piles • Diameter : 1.5 Meter • Length : 43 Meter • Design Capacity : 3000 Tonnes • Pile Load Test : 6,000 Tonnes • Cube Strength : C60 (60 MPa) • Friction Piles Support: Cemented Calcisiltite • Skin Friction : 250 to 350 tons/sq feet
  • 13. Wind Engineering • Wind Tunnel • Studies Conducted by RWDI
  • 14. • Vortex Shedding • High-frequency-force-balance tunnel tests
  • 15. • 6 Wind Directions • Aero-Elastic Models were Initiated by the End
  • 16. Construction Sequence • Conventional Approach • But as Building height increases: The results will diverge from actual behavior • Time Dependent Approach: Creep, Shrinkage, Sequential Loading • Burj Khalifa : 15 Separate FEM • Time Steps : 50 Years After Construction  Actual Concrete Behaviour •  MIDAS Gen 2010
  • 18. Issues • Rock at 50 m was fragile and saturated with Ground Water • Solution: • 194 Piles Constructed • Viscous Polymer Slurry
  • 19. • Owner: • Project Manager: • • Architect/Structural Engineers/: • Adopting Architect & Engineer/Field Supervision: • Independent Verification and Testing Agency: • General Contractor: • Foundation Contractor: • Emaar Properties PJSC • Turner Construction International • Skidmore, Owings & Merrill LLP • Hyder Consulting Ltd. • GHD Global Pty. Ltd. • Samsung/BeSix/Arabtec • NASA Multiplex

Editor's Notes

  1. C-60 and C-80 are in ___ Codes having ____ Strength Water Heating : 378 Panels with 2.7 sqmeter area each
  2. Buttressed Core : greater building height : also called Hexagonal Hub REFUGE ROOMS : RESIST HEAT UPTO 2 HOURS, MADE OF RCC, AND FIRE PROOF SHEETS, TO ENSURE EVACUATION IN CASE OF ANOTHER 9/11- TOTAL 9
  3. Wind: Vortices never get formed as wind encounters different shape at every tier Wall Concrete : C80 for Lower Floors
  4. Walls and Column sizes are kept such that self weight gravity “stresses” on them are equal This reduces differential settlement Outrigger Truss : allows all elements to participate in lateral load resisting ensuring highest efficiency Spire is made of 4000 tons of structural steel, which also houses communication equipments Although, Burj Khalifa is tallest because of this spire only, it was originally designed to resist gravity, wind, seismic and fatique in accordance with AISC Load Specifications for structural steel Building 1999. Although, Gravity Loading(seismic) was not the design criteria. Several Tests were conducted to ensure that there wont be any liquefaction phenomena in soil
  5. First two modes were Purely Translational Modes And the fifth mode was the first torsional mode having 4.3 seconds
  6. Giant test cubes
  7. Induced Vortex Shedding Was Estimated by Wind Tunnel Test RWDI – Rowan Williams Davis Incorporation
  8. High Frequency Force Balance Technique was employed, to get the tentative shape of the tower for analysis Then final shape of the tower was decided, based on the relative stiffness of all the floors
  9. An aero-elastic model has same flexibility as that of the original building, in terms of stiffness, mass and damping. This was done to analyze the effects of several higher modes of vibration and it was found that the motions are within ISO Limits, and secondary damping is not needed.
  10. Conventional Approach is : Considering the building as linearly elastic model and all forces are applied at once as summation of forces
  11. Vertically: Modest increase in the floor to floor height so that it attains its actual height after time dependent effects Horizontal : Recentring : to correct “Gravity induced Side Sway like – differential foundation settlement, creep, shrinkage shifting”
  12. Piles Constructed to avoid Sinking Viscous Polymer Slurry to fill up the holes: when concrete was poured in, the slurry was displaced
  13. Agencie Involved in the project