2. 1. Introduction
2. Longitudinal Span Configuration
3. Construction Sequence
4. Cross Section
5. Support Conditions
6. Sub-Structure and Foundation
7. Prestressing Details
8. Design Check
9. Pre-Camber
10. Modelling & Other Suggestions
midas
Civil
3. Technical
Lecture
by AECOM
Introduction
• Cantilever construction method
1) Very ancient technique
2) Structure is built component by component above
ground level.
3) More recently: Construction of Cable Stayed Bridge
s, Extra-dosed Bridges etc.
4) Prestressed Concrete Bridges
• Cast in situ Segments or Pre-cast segments
• Integral with Pier or On Bearings
• 60m – 300m span
5. Technical
Lecture
by AECOM
• Typical 3 Span system
– Mid Span: L
– End Spans: 0.6L to 0.7L (to control uplift in bearing)
L
0.6 L to 0.7L
0.6 L to 0.7L
• Typical 4 or more Span (varying) system
0.6 L1 to 0.7L1 L1 (L1 + L2)/2 0.6 L2 to 0.7L2
Longitudinal Span Configuration
6. Technical
Lecture
by AECOM
• No such luxury in today’s congested urban area
I. 34 + 60 + 34 m
II. 60 + 60 m
III. 37 + 70 + 67 + 55 + 34m
Longitudinal Span Configuration
7. Technical
Lecture
by AECOM
A. Pier head : On ground supported staging
B. Most of Segments:
Erect/cast using Segment Lifter/Form Traveller
Cantilevered out from preceding segment.
Prestressing tendons running one of the cantilever to the other are str
essed.
Symmetrical construction to minimize unbalanced moment on sub-str
ucture and foundation: Balanced Cantilever
Cast portion (beyond 0.5 x L) of both End-spans Ground Supported st
aging.
Cast Stitch segments
• Stitch in the End – span
• Stitch in the Mid-span
• Levels of the Cantilever arms being stitched should be matched
C. Segmentation: 2.5m to 4m or even 5m
– Construction Cycle
– Capacity of Form Traveller/Segment Lifter
Construction Sequence
9. Technical
Lecture
by AECOM
Casting of Stitch at Mid-
span using suspender.
Balanced Cantilever Bridge :
Delhi Metro Phase III
(34 + 60 + 34m)
Construction Sequence
10. Technical
Lecture
by AECOM
L
H1 H2
• Highway Bridges
– Depth at Face of Pier, H1 : L/15 – L/18 (roughly)
– Depth at Mid-Span, H2 : L/30 – L/35 (roughly)
• Highway vs Railway Bridge
– 34+60+34m span CLC Load Metro Highway
DL 463 463
SIDL 240 85
LL 262 134
Shear Force at Pier Face (ton)
Cross Section
11. Technical
Lecture
by AECOM
• Depth may vary
– Parabolic
– Cubically: need to check for insufficient depth around L/4
– Linearly varying depth
• Local thickening of soffit is required.
Cross Section
12. Technical
Lecture
by AECOM
• Box Girder – On simple bearing
– Stability check during construction
– Minimal secondary effect of Creep, Shrinkage and Prestressing
• Box Girder Integral with Intermediate Piers
– Check pier for un-balanced moment during construction.
– Pronounced secondary effect.
Support Conditions
13. Technical
Lecture
by AECOM
• Flexibility
– High time period (lesser seismic force)
– Lower force due to secondary effects of creep, shrinkage and Pr
estressingTendons
– Twin Piers
𝐹 =
3𝐸𝐼
𝐿
δ
Sub-Structure and Foundation
14. Technical
Lecture
by AECOM
• Cantilever Tendons
– For holding the segments added during cantilever construction
– To take up the negative moment due to SW of Segments, SIDL and/or
Live Load
– At least 1 pair of tendon is anchored per segment.
• Continuity Tendons:
– To take up the force due to effects after the cantilever have been stitched.
Prestressing Details
15. Technical
Lecture
by AECOM
• Top Tendons
– Try to keep the web clear of the
Tendons
• Bottom Tendons
– Keep the webs clear of the tendons
as much as possible
– Keep tendons nearer to the webs as
much as possible
– Enough prestressingfor sections at
mid-span to hog.
– Blister Blocks for anchoring of tendons
Prestressing Details
16. Technical
Lecture
by AECOM
• Why Construction Stage Analysis
Bending Moment Diagram due to SW: Simultaneous Analysis
Bending Moment Diagram due to SW: Sequential Analysis
Analysis
17. Technical
Lecture
by AECOM
– Time Dependent Effects of Creep and Shrinkage
• No secondary effect of Creep and Shrinkage before stitching
Structure before casting of stitch segment
Deformation due
to Shrinkage.
Residual Shrinkage Strain:
i) After 3 days – 4.3 x 10-4
ii) After 14 days – 2.5 x 10-4
• Why Construction Stage Analysis
Analysis
18. Technical
Lecture
by AECOM
– Time Dependent Effects of Creep and Shrinkage
• Different age of concrete at different loading
• Modulus of Elasticity increases with time
• Why Construction Stage Analysis
Analysis
19. Technical
Lecture
by AECOM
• Sub-structure & Foundation
– Regular Checks for Foundation & Piers
– Secondary effects of CR, SH & PS should be considered
– Check during construction (stability or adequacy)
i) Imbalance of 1 segment
ii) Accidental Fall of Empty Form Traveller
Imbalance of 1 Segment
Fall of empty FT
Design Check
20. Technical
Lecture
by AECOM
• Super Structure
– Check during construction (ULS & SLS)
• Maximum Compression at each stage
– Maximum compression: 0.48fck (IRC 112-2011)
• Maximum Tension at each stage
– Minimum compression of 0.2fck - Precast segments (temporary Prestressing)
– Maximum tension of 1 MPa – Cast in situ segments.
• Loads
– SW of Segments
– Form Traveller (usually half the weight of heaviest segment) + Shutter
– Weight of Green Concrete
– Construction Live Load
– Wind / EQ (cantilever)
Design Check
22. Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
23. Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
24. Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
25. Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
26. Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
27. Technical
Lecture
by AECOM
• Super Structure
– Check during Service (0 - Design life)
• Loads
– Regular Loads (SW, SIDL, LL)
– Prestressing
» Losses up to design life should be considered
» Secondary effects are usually significant
– CR & SH: Secondary effects are significant.
– Temperature Variation
• SLS Checks
– Maximum Compression
» Maximum compression: 0.48fck (IRC 112-2011)
– Maximum Tension
Design Check
28. Technical
Lecture
by AECOM
• Super Structure
– Check during Service (0 - Design life)
• ULS Checks
– Moment at the intermediate support
» Hogging for Normal Case
» Reversible in Seismic case
– Shear Check
» Varying depth: Should be checked at regular interval
• Critical at locations with kink
Design Check
29. Technical
Lecture
by AECOM
• Super Structure
– Check during Service (0 - Design life)
• ULS Checks
– Shear Check
» Vertical component of Prestressing: reduces shear
» Resal Effect: Part of Shear is balanced by the component of Nor
mal force in the soffit slab.
Design Check
31. Technical
Lecture
by AECOM
• Why pre-camber
– Under permanent loads the deck should have achiev
ed the desired level.
• Desired Level at what time
– Concrete continues to sag/hog because of creep
– Achieving desired level at the end of design life: not
logical
Pre-Camber
32. Technical
Lecture
by AECOM
• For very wide or very deep section
– Line Beam modelling: up to 20% error
• Shear Lag effect
• Difference in rates of shrinkage and drying creep because of different thicknesses
of slabs.
• 3D model always yields larger deflections and larger Prestress losses
Ref: Excessive Long-Time Deflections of Prestressed Box Girders. I: Record-Span Br
idge in Palau and Other Paradigms - Zdeněk P. Bažant, Qiang Yu and Guang-Hua Li
• Modelling of Piles
• Give concrete more time to gain strength before prestressing
Modelling &other Suggestions