SlideShare a Scribd company logo
1 of 33
Download to read offline
2016 MIDAS Technical Chat
Practical Design of
Balanced Cantilever
Bridges
midas
Civil
Piyush Santhalia
ProjectEngineer, AECOM
1. Introduction
2. Longitudinal Span Configuration
3. Construction Sequence
4. Cross Section
5. Support Conditions
6. Sub-Structure and Foundation
7. Prestressing Details
8. Design Check
9. Pre-Camber
10. Modelling & Other Suggestions
midas
Civil
Technical
Lecture
by AECOM
Introduction
• Cantilever construction method
1) Very ancient technique
2) Structure is built component by component above
ground level.
3) More recently: Construction of Cable Stayed Bridge
s, Extra-dosed Bridges etc.
4) Prestressed Concrete Bridges
• Cast in situ Segments or Pre-cast segments
• Integral with Pier or On Bearings
• 60m – 300m span
Technical
Lecture
by AECOM
Balanced Cantilever Bridge
- Delhi Metro Phase III
- Cast-in-Situ Segments
- Integral with Pier
Introduction
Technical
Lecture
by AECOM
• Typical 3 Span system
– Mid Span: L
– End Spans: 0.6L to 0.7L (to control uplift in bearing)
L
0.6 L to 0.7L
0.6 L to 0.7L
• Typical 4 or more Span (varying) system
0.6 L1 to 0.7L1 L1 (L1 + L2)/2 0.6 L2 to 0.7L2
Longitudinal Span Configuration
Technical
Lecture
by AECOM
• No such luxury in today’s congested urban area
I. 34 + 60 + 34 m
II. 60 + 60 m
III. 37 + 70 + 67 + 55 + 34m
Longitudinal Span Configuration
Technical
Lecture
by AECOM
A. Pier head : On ground supported staging
B. Most of Segments:
 Erect/cast using Segment Lifter/Form Traveller
 Cantilevered out from preceding segment.
 Prestressing tendons running one of the cantilever to the other are str
essed.
 Symmetrical construction to minimize unbalanced moment on sub-str
ucture and foundation: Balanced Cantilever
 Cast portion (beyond 0.5 x L) of both End-spans Ground Supported st
aging.
 Cast Stitch segments
• Stitch in the End – span
• Stitch in the Mid-span
• Levels of the Cantilever arms being stitched should be matched
C. Segmentation: 2.5m to 4m or even 5m
– Construction Cycle
– Capacity of Form Traveller/Segment Lifter
Construction Sequence
Technical
Lecture
by AECOM
Balanced Cantilever Bridge :
Delhi Metro Phase III, 60 + 60m span
Construction Sequence
Technical
Lecture
by AECOM
Casting of Stitch at Mid-
span using suspender.
Balanced Cantilever Bridge :
Delhi Metro Phase III
(34 + 60 + 34m)
Construction Sequence
Technical
Lecture
by AECOM
L
H1 H2
• Highway Bridges
– Depth at Face of Pier, H1 : L/15 – L/18 (roughly)
– Depth at Mid-Span, H2 : L/30 – L/35 (roughly)
• Highway vs Railway Bridge
– 34+60+34m span CLC Load Metro Highway
DL 463 463
SIDL 240 85
LL 262 134
Shear Force at Pier Face (ton)
Cross Section
Technical
Lecture
by AECOM
• Depth may vary
– Parabolic
– Cubically: need to check for insufficient depth around L/4
– Linearly varying depth
• Local thickening of soffit is required.
Cross Section
Technical
Lecture
by AECOM
• Box Girder – On simple bearing
– Stability check during construction
– Minimal secondary effect of Creep, Shrinkage and Prestressing
• Box Girder Integral with Intermediate Piers
– Check pier for un-balanced moment during construction.
– Pronounced secondary effect.
Support Conditions
Technical
Lecture
by AECOM
• Flexibility
– High time period (lesser seismic force)
– Lower force due to secondary effects of creep, shrinkage and Pr
estressingTendons
– Twin Piers
𝐹 =
3𝐸𝐼
𝐿
δ
Sub-Structure and Foundation
Technical
Lecture
by AECOM
• Cantilever Tendons
– For holding the segments added during cantilever construction
– To take up the negative moment due to SW of Segments, SIDL and/or
Live Load
– At least 1 pair of tendon is anchored per segment.
• Continuity Tendons:
– To take up the force due to effects after the cantilever have been stitched.
Prestressing Details
Technical
Lecture
by AECOM
• Top Tendons
– Try to keep the web clear of the
Tendons
• Bottom Tendons
– Keep the webs clear of the tendons
as much as possible
– Keep tendons nearer to the webs as
much as possible
– Enough prestressingfor sections at
mid-span to hog.
– Blister Blocks for anchoring of tendons
Prestressing Details
Technical
Lecture
by AECOM
• Why Construction Stage Analysis
Bending Moment Diagram due to SW: Simultaneous Analysis
Bending Moment Diagram due to SW: Sequential Analysis
Analysis
Technical
Lecture
by AECOM
– Time Dependent Effects of Creep and Shrinkage
• No secondary effect of Creep and Shrinkage before stitching
Structure before casting of stitch segment
Deformation due
to Shrinkage.
Residual Shrinkage Strain:
i) After 3 days – 4.3 x 10-4
ii) After 14 days – 2.5 x 10-4
• Why Construction Stage Analysis
Analysis
Technical
Lecture
by AECOM
– Time Dependent Effects of Creep and Shrinkage
• Different age of concrete at different loading
• Modulus of Elasticity increases with time
• Why Construction Stage Analysis
Analysis
Technical
Lecture
by AECOM
• Sub-structure & Foundation
– Regular Checks for Foundation & Piers
– Secondary effects of CR, SH & PS should be considered
– Check during construction (stability or adequacy)
i) Imbalance of 1 segment
ii) Accidental Fall of Empty Form Traveller
Imbalance of 1 Segment
Fall of empty FT
Design Check
Technical
Lecture
by AECOM
• Super Structure
– Check during construction (ULS & SLS)
• Maximum Compression at each stage
– Maximum compression: 0.48fck (IRC 112-2011)
• Maximum Tension at each stage
– Minimum compression of 0.2fck - Precast segments (temporary Prestressing)
– Maximum tension of 1 MPa – Cast in situ segments.
• Loads
– SW of Segments
– Form Traveller (usually half the weight of heaviest segment) + Shutter
– Weight of Green Concrete
– Construction Live Load
– Wind / EQ (cantilever)
Design Check
Technical
Lecture
by AECOM
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Design Check
Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
Technical
Lecture
by AECOM
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Design Check
Technical
Lecture
by AECOM
• Super Structure
– Check during Service (0 - Design life)
• Loads
– Regular Loads (SW, SIDL, LL)
– Prestressing
» Losses up to design life should be considered
» Secondary effects are usually significant
– CR & SH: Secondary effects are significant.
– Temperature Variation
• SLS Checks
– Maximum Compression
» Maximum compression: 0.48fck (IRC 112-2011)
– Maximum Tension
Design Check
Technical
Lecture
by AECOM
• Super Structure
– Check during Service (0 - Design life)
• ULS Checks
– Moment at the intermediate support
» Hogging for Normal Case
» Reversible in Seismic case
– Shear Check
» Varying depth: Should be checked at regular interval
• Critical at locations with kink
Design Check
Technical
Lecture
by AECOM
• Super Structure
– Check during Service (0 - Design life)
• ULS Checks
– Shear Check
» Vertical component of Prestressing: reduces shear
» Resal Effect: Part of Shear is balanced by the component of Nor
mal force in the soffit slab.
Design Check
Technical
Lecture
by AECOM
Pre-Camber
Technical
Lecture
by AECOM
• Why pre-camber
– Under permanent loads the deck should have achiev
ed the desired level.
• Desired Level at what time
– Concrete continues to sag/hog because of creep
– Achieving desired level at the end of design life: not
logical
Pre-Camber
Technical
Lecture
by AECOM
• For very wide or very deep section
– Line Beam modelling: up to 20% error
• Shear Lag effect
• Difference in rates of shrinkage and drying creep because of different thicknesses
of slabs.
• 3D model always yields larger deflections and larger Prestress losses
Ref: Excessive Long-Time Deflections of Prestressed Box Girders. I: Record-Span Br
idge in Palau and Other Paradigms - Zdeněk P. Bažant, Qiang Yu and Guang-Hua Li
• Modelling of Piles
• Give concrete more time to gain strength before prestressing
Modelling &other Suggestions
2016 MIDAS Technical Chat
Practical Design of
Balanced Cantilever Bridges
midas
Civil
Piyush Santhalia
Project Engineer, AECOM
THANK YOU
Happy Designing

More Related Content

Similar to 02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf

ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
Basic R C C structurs
Basic R C C structursBasic R C C structurs
Basic R C C structursDrDinakarP
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)dgonano
 
MULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKINGMULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKINGManoj Navneeth
 
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE  CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE AIT Solutions
 
Analysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexAnalysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexDhananjay Singh
 
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...Specialized Carriers & Rigging Association
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignDr Mazin Alhamrany
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMFaridGeonova
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersjose bonifacio de souza leite cuadros
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...Rajesh Prasad
 
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed AnwarCost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed AnwarAIT Solutions
 
reinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptreinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptsatheeskumarv2
 
reinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptreinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptAbhishek Paswan
 

Similar to 02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf (20)

ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Basic R C C structurs
Basic R C C structursBasic R C C structurs
Basic R C C structurs
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
MULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKINGMULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKING
 
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE  CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
 
Analysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexAnalysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complex
 
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
My Work
My WorkMy Work
My Work
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
Wilshire Grand Redevelopment Project
Wilshire Grand Redevelopment ProjectWilshire Grand Redevelopment Project
Wilshire Grand Redevelopment Project
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
 
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed AnwarCost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
 
Tony
TonyTony
Tony
 
reinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptreinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.ppt
 
reinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptreinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.ppt
 

Recently uploaded

Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Recently uploaded (20)

Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf

  • 1. 2016 MIDAS Technical Chat Practical Design of Balanced Cantilever Bridges midas Civil Piyush Santhalia ProjectEngineer, AECOM
  • 2. 1. Introduction 2. Longitudinal Span Configuration 3. Construction Sequence 4. Cross Section 5. Support Conditions 6. Sub-Structure and Foundation 7. Prestressing Details 8. Design Check 9. Pre-Camber 10. Modelling & Other Suggestions midas Civil
  • 3. Technical Lecture by AECOM Introduction • Cantilever construction method 1) Very ancient technique 2) Structure is built component by component above ground level. 3) More recently: Construction of Cable Stayed Bridge s, Extra-dosed Bridges etc. 4) Prestressed Concrete Bridges • Cast in situ Segments or Pre-cast segments • Integral with Pier or On Bearings • 60m – 300m span
  • 4. Technical Lecture by AECOM Balanced Cantilever Bridge - Delhi Metro Phase III - Cast-in-Situ Segments - Integral with Pier Introduction
  • 5. Technical Lecture by AECOM • Typical 3 Span system – Mid Span: L – End Spans: 0.6L to 0.7L (to control uplift in bearing) L 0.6 L to 0.7L 0.6 L to 0.7L • Typical 4 or more Span (varying) system 0.6 L1 to 0.7L1 L1 (L1 + L2)/2 0.6 L2 to 0.7L2 Longitudinal Span Configuration
  • 6. Technical Lecture by AECOM • No such luxury in today’s congested urban area I. 34 + 60 + 34 m II. 60 + 60 m III. 37 + 70 + 67 + 55 + 34m Longitudinal Span Configuration
  • 7. Technical Lecture by AECOM A. Pier head : On ground supported staging B. Most of Segments:  Erect/cast using Segment Lifter/Form Traveller  Cantilevered out from preceding segment.  Prestressing tendons running one of the cantilever to the other are str essed.  Symmetrical construction to minimize unbalanced moment on sub-str ucture and foundation: Balanced Cantilever  Cast portion (beyond 0.5 x L) of both End-spans Ground Supported st aging.  Cast Stitch segments • Stitch in the End – span • Stitch in the Mid-span • Levels of the Cantilever arms being stitched should be matched C. Segmentation: 2.5m to 4m or even 5m – Construction Cycle – Capacity of Form Traveller/Segment Lifter Construction Sequence
  • 8. Technical Lecture by AECOM Balanced Cantilever Bridge : Delhi Metro Phase III, 60 + 60m span Construction Sequence
  • 9. Technical Lecture by AECOM Casting of Stitch at Mid- span using suspender. Balanced Cantilever Bridge : Delhi Metro Phase III (34 + 60 + 34m) Construction Sequence
  • 10. Technical Lecture by AECOM L H1 H2 • Highway Bridges – Depth at Face of Pier, H1 : L/15 – L/18 (roughly) – Depth at Mid-Span, H2 : L/30 – L/35 (roughly) • Highway vs Railway Bridge – 34+60+34m span CLC Load Metro Highway DL 463 463 SIDL 240 85 LL 262 134 Shear Force at Pier Face (ton) Cross Section
  • 11. Technical Lecture by AECOM • Depth may vary – Parabolic – Cubically: need to check for insufficient depth around L/4 – Linearly varying depth • Local thickening of soffit is required. Cross Section
  • 12. Technical Lecture by AECOM • Box Girder – On simple bearing – Stability check during construction – Minimal secondary effect of Creep, Shrinkage and Prestressing • Box Girder Integral with Intermediate Piers – Check pier for un-balanced moment during construction. – Pronounced secondary effect. Support Conditions
  • 13. Technical Lecture by AECOM • Flexibility – High time period (lesser seismic force) – Lower force due to secondary effects of creep, shrinkage and Pr estressingTendons – Twin Piers 𝐹 = 3𝐸𝐼 𝐿 δ Sub-Structure and Foundation
  • 14. Technical Lecture by AECOM • Cantilever Tendons – For holding the segments added during cantilever construction – To take up the negative moment due to SW of Segments, SIDL and/or Live Load – At least 1 pair of tendon is anchored per segment. • Continuity Tendons: – To take up the force due to effects after the cantilever have been stitched. Prestressing Details
  • 15. Technical Lecture by AECOM • Top Tendons – Try to keep the web clear of the Tendons • Bottom Tendons – Keep the webs clear of the tendons as much as possible – Keep tendons nearer to the webs as much as possible – Enough prestressingfor sections at mid-span to hog. – Blister Blocks for anchoring of tendons Prestressing Details
  • 16. Technical Lecture by AECOM • Why Construction Stage Analysis Bending Moment Diagram due to SW: Simultaneous Analysis Bending Moment Diagram due to SW: Sequential Analysis Analysis
  • 17. Technical Lecture by AECOM – Time Dependent Effects of Creep and Shrinkage • No secondary effect of Creep and Shrinkage before stitching Structure before casting of stitch segment Deformation due to Shrinkage. Residual Shrinkage Strain: i) After 3 days – 4.3 x 10-4 ii) After 14 days – 2.5 x 10-4 • Why Construction Stage Analysis Analysis
  • 18. Technical Lecture by AECOM – Time Dependent Effects of Creep and Shrinkage • Different age of concrete at different loading • Modulus of Elasticity increases with time • Why Construction Stage Analysis Analysis
  • 19. Technical Lecture by AECOM • Sub-structure & Foundation – Regular Checks for Foundation & Piers – Secondary effects of CR, SH & PS should be considered – Check during construction (stability or adequacy) i) Imbalance of 1 segment ii) Accidental Fall of Empty Form Traveller Imbalance of 1 Segment Fall of empty FT Design Check
  • 20. Technical Lecture by AECOM • Super Structure – Check during construction (ULS & SLS) • Maximum Compression at each stage – Maximum compression: 0.48fck (IRC 112-2011) • Maximum Tension at each stage – Minimum compression of 0.2fck - Precast segments (temporary Prestressing) – Maximum tension of 1 MPa – Cast in situ segments. • Loads – SW of Segments – Form Traveller (usually half the weight of heaviest segment) + Shutter – Weight of Green Concrete – Construction Live Load – Wind / EQ (cantilever) Design Check
  • 21. Technical Lecture by AECOM Stress check during Construction: 37 + 70 + 67 + 55 + 34m Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Design Check
  • 22. Technical Lecture by AECOM Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m Design Check
  • 23. Technical Lecture by AECOM Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m Design Check
  • 24. Technical Lecture by AECOM Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m Design Check
  • 25. Technical Lecture by AECOM Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m Design Check
  • 26. Technical Lecture by AECOM Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m Design Check
  • 27. Technical Lecture by AECOM • Super Structure – Check during Service (0 - Design life) • Loads – Regular Loads (SW, SIDL, LL) – Prestressing » Losses up to design life should be considered » Secondary effects are usually significant – CR & SH: Secondary effects are significant. – Temperature Variation • SLS Checks – Maximum Compression » Maximum compression: 0.48fck (IRC 112-2011) – Maximum Tension Design Check
  • 28. Technical Lecture by AECOM • Super Structure – Check during Service (0 - Design life) • ULS Checks – Moment at the intermediate support » Hogging for Normal Case » Reversible in Seismic case – Shear Check » Varying depth: Should be checked at regular interval • Critical at locations with kink Design Check
  • 29. Technical Lecture by AECOM • Super Structure – Check during Service (0 - Design life) • ULS Checks – Shear Check » Vertical component of Prestressing: reduces shear » Resal Effect: Part of Shear is balanced by the component of Nor mal force in the soffit slab. Design Check
  • 31. Technical Lecture by AECOM • Why pre-camber – Under permanent loads the deck should have achiev ed the desired level. • Desired Level at what time – Concrete continues to sag/hog because of creep – Achieving desired level at the end of design life: not logical Pre-Camber
  • 32. Technical Lecture by AECOM • For very wide or very deep section – Line Beam modelling: up to 20% error • Shear Lag effect • Difference in rates of shrinkage and drying creep because of different thicknesses of slabs. • 3D model always yields larger deflections and larger Prestress losses Ref: Excessive Long-Time Deflections of Prestressed Box Girders. I: Record-Span Br idge in Palau and Other Paradigms - Zdeněk P. Bažant, Qiang Yu and Guang-Hua Li • Modelling of Piles • Give concrete more time to gain strength before prestressing Modelling &other Suggestions
  • 33. 2016 MIDAS Technical Chat Practical Design of Balanced Cantilever Bridges midas Civil Piyush Santhalia Project Engineer, AECOM THANK YOU Happy Designing