SlideShare a Scribd company logo
Page 1
ASSIGNMENT NO. 2
SURVEYING
PROBLEMS ON CHAIN
To solve such problem
1) Lo = (
𝒍 𝟏
𝒍 𝟎
)
𝟐
Lo
2) Ao = (
𝒍 𝟏
𝒍 𝟎
)
𝟐
Ao
TYPE I) To calculate true distance
1. A 20 m chain was tested before the commencement of the day’s work and found to be correct.
After chaining 840 m the chain was found to be 0.08 m too long. At the end day’s work, after
chaining a total distance of 1376 m the chain was found to be 0.12 m too long. What was true
distance chained?
2. The distance between two points, measured with 20 m chain, was recorded as 327 m. It was
afterwards found that the chain was 3 cm too long. What was the true distance between the
points?
3. The distance between two stations was 1200 m when measured with a 20 m chain. The same
distance when measured with 30 m chain was found to be 1195 m. If the 20 m chain was 0.05 m
too long, what was the error in the 30 m chain?
TYPE II) To calculate true distance
1. The distance measured between two points by a 20m chain was 1340 m and when measured by a
30 m chain was 1345 m. If the 30 m chain was one link too short; find out if the 20m chain was
of correct length or not. If not find the error in it.
2. The lengths of 20 m and 30 m chains were tested and found to be correct at the beginning of
work. The distance between two points measured by 20 m chain was 1340 m and when measured
by 30 m chain was 1345 m. 30 m chain was tested again and found to be 20 cm too short.
Page 2
Calculate average chain length and final chain length of 20 m chain at the end of measurement.
(09 Mks)
3. A 30 m chain was found to be 15.24 cm too long after chaining 1524 m. The same chain was
found to be 30.48 cm too long after chaining a total distance of 3048 m. Find the correct length
of the total distance assuming chain was correct at the commencement of chaining.
4. A line was measured by 20 m chain which was accurate before starting the day’s work. After
chaining 900 m, the chain was found to be 6 cm too long. After chaining of 1575 m, the chain
was found to be 14 cm too long. Find the true distance of the line.
5. A 30 m chain (150 links) was found to be one link too short. The area measured with this chain
also plotted to scale 1 cm = 8 m and was found to be 32.659 cm2. The map was found to have
shrunk so that a line originally 10 cm long was only 9.8 cm. Find true area of the field. (09)
TYPE III) To calculate true area
1. A chain was tested before start and found to be 30 m. At the end of work it was checked again
and found to be 30.10 m. Area of plan drawn to a scale 1: 1000 was 160 sq. m. Find the true
area in hectres. (06 Mks)
2. A chain was tested before starting a survey of field and was found to be exactly 30 m. At the end
of the survey it was tested again and was found to measure 30.16 m. The area of plan drawn to a
scale of 1 cm = 60 m was 92.50 cm2. Find the true area of field. (Nov. 2011) 08 Mks
3. An old map was drawn with a scale of 1cm = 10 m, the field was surveyed with a 30 m chain
which was actually 0.05 m short. An original length of 10 cm has now shrunk to 9.5 cm on
drawing. The plan area measured with a planimeter is 95 cm2. Calculate the actual area of the
land.
4. A chain was tested before starting a survey of field and was found to be exactly 20 m. At the end
of the survey it was tested again and was found to measure 20.20 m. The area of plan drawn to a
scale of 1 cm = 80 m was 100 cm2. Find the true area of field.
5. A 30 m chain (150 links) was found to be one link too short. The area measured with this chain
also plotted to scale 1 cm = 8 m and was found to be 32.659 cm2. The map was found to have
shrunk so that a line originally 10 cm long was only 9.8 cm. Find true area of the field.
(09 marks)
6. An old map was drawn with a scale of 1cm = 8 m, but now the paper is found to have shrunk. A
line originally 200 mm long now measures 190 mm only. The area of a plot now measures 100.5
Page 3
cm2. There was also a note that the 30 m chain was 100 mm too short. Find the true area of the
plot.
7. A rectangular field was measured with a 30 m chain. Its length was found to be 3000 m and its
breadth 2500 m. before starting the work the chain was compared with a standard rope and was
found to be short by 5 cm. At the end of the work, the chain was found to be longer than the
standard length by 30 cm. What is the actual area of the field?
8. A 20 m chain was tested before the commencement of the day’s work and found to be correct.
After chaining 840 m the chain was found to be 0.08 m too long. At the end of the day’s work,
after chaining a total distance of 1376 m the chain was found to be 0.12m too long. What was the
true distance chained?
9. A chain was tested before starting a survey of field and was found to be exactly 30 m. At the end
of the survey it was tested again and was found to measure 30.16 m. The area of the plane drawn
to a scale of 1 cm = 60 m was 92.5 cm2. Find the area of the field.
10. A plan of an old survey plotted to a scale of 1 cm = 10 m was found to have shrunk so that a line
originally measuring 25 cm long was found to measure 24.4 cm. If the area of the plan measured
now is 122 cm2, determine the true area of the survey. Calculate shrinkage factor.
11. A old map was plotted to a scale of 40 m to 1cm.Over the years, this map has been shrinking,
and a line originally 20 cm long is only 19.5 cm long at present. Again the 20m chain was 5 cm
too long. If the present area of the map measured by planimeter is 125.50 cm2, find the true area
of land surveyed. ( 9)
12. The old map was drawn to a scale of 1cm = 8 m, but now the paper is found to have shrunk. A
line originally 200 mm long now measures 190mm only. The area of a plot now measures 100.5
cm2. There was also a note that the 30m chain used was 100 mm too short. Find the true area of
the plot.
13. A 20 m chain was tested before the commencement of the day's work and found to be correct.
After chaining 840 m the chain was found to be 0.08 m too long. At the end of day's work, after
chaining a total distance of 1376 m the chain was found to be 0.12 m too long. What was true
distance chained?
14. A chain was tested before start and found to be 30 m. At the end of work it was checked again
and found to be 30.20 m. The area of plan drawn to a scale of 1: 1000 was 200 sq. m. Find the
true area on field in hectares.
15. The area of a plan of an old map plotted to a scale of 1 m = 10 m. Measures 100 sq. m. The plan
is found to have shrunk so that the line originally 10 cm long now measures 9.7 cm, Further the
Page 4
20 m chain used was 8 cm too short. Find the true area of the survey.
16. A chain was tested before start and found to be 30 m. At the end of work it was checked again
and found to be 30.10 m. The area of plan drawn to a scale 1: 1000 was 160 sq .m. Find the true
area in hectres.
17. The old map was drawn to a scale of 1 em = 8 m, but now the paper is found to have shrunk. A
line originally 200 mm long now measures 190 mm only. The area of a plot now measures 100.5
cm-. There was also a note that the 30 m chain used was 100 mm too short. Find the true area of
the plot. (9)
18. A chain was tested before start and found to be 30 m. At the end of work it was checked again
and found to be 30.10 m. The area of plan drawn to a scale 1 : 1000 was 160 sq .m. Find the true
area in hectres.
19. The lengths of 20 m and 30 m chains were tested and found to be correct at the beginning of
work. The distance between two points measured by 20 m chain was 1340 m and when measured
by 30 m chain was 1345 m. 30 m chain was tested again and found to be 20 cm too short.
Calculate average chain length and final chain length of 20 m chain at the end of measurement.
20. The lengths of 20 m and 30 m chains were tested and found to be correct at the beginning of
work. The distance between two points measured by 20 m chain was 1340 m and when measured
by 30 m chain was 1345 m. 30 m chain was tested again and found to be 20 cm too short.
Calculate average chain length and final chain length of 20 m chain at the end of measurement.
21. Distance ABC was measured with a 30 m chain, tested and found to be correct in the
beginning of the work. After measuring AB = 1.2 kms, chain was found to be 10 cm
too long. Chaining was continued till total distance of 2.0 kms up to point C. At the
end of the work chain was found to be 20 cm too long. Find correct distance ABC.

More Related Content

What's hot

Angle determination - Report
Angle determination - ReportAngle determination - Report
Angle determination - Report
Sarchia Khursheed
 
Method Of Chaining On Sloping Ground
Method Of Chaining On Sloping GroundMethod Of Chaining On Sloping Ground
Method Of Chaining On Sloping Ground
university of agriculture
 
Introduction to surveying, ranging and chaining
Introduction to surveying, ranging and chainingIntroduction to surveying, ranging and chaining
Introduction to surveying, ranging and chaining
Shital Navghare
 
Suveying Chain Method
Suveying Chain MethodSuveying Chain Method
Suveying Chain Method
stooty s
 
S2 3.1 tape and offset surveying
S2 3.1 tape and offset surveyingS2 3.1 tape and offset surveying
S2 3.1 tape and offset surveying
Est
 
Types of obstacles in chain surveying
Types of obstacles in chain surveyingTypes of obstacles in chain surveying
Types of obstacles in chain surveying
kazi abir
 
Tacheometric surveying - Assignment
Tacheometric surveying - AssignmentTacheometric surveying - Assignment
Tacheometric surveying - Assignment
Vijay Parmar
 
Chain survey
Chain surveyChain survey
Chain survey
MD Sakib Hasan
 
Surveying - Module I - Introduction to surveying
Surveying - Module I - Introduction to surveying Surveying - Module I - Introduction to surveying
Surveying - Module I - Introduction to surveying
SHAMJITH KM
 
2.2 linear measurement
2.2 linear measurement2.2 linear measurement
2.2 linear measurement
Digvijaysinh Gohil
 
Chain surveying.1
Chain surveying.1Chain surveying.1
Chain surveying.1
Decentumang
 
Module-I SURVEYING-I [BTCVC304]
Module-I SURVEYING-I [BTCVC304]Module-I SURVEYING-I [BTCVC304]
Module-I SURVEYING-I [BTCVC304]
Dr. BASWESHWAR JIRWANKAR
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
Rakesh Verma
 
11.4 circumference and arc length
11.4 circumference and arc length11.4 circumference and arc length
11.4 circumference and arc length
Jessica Garcia
 
Chain surveying and offset
Chain surveying and offsetChain surveying and offset
Chain surveying and offset
Mir Zafarullah
 
Chain surveying
Chain surveyingChain surveying
Chain surveying
JNTUK
 
B.sc. agri i foswce unit 1 surveying
B.sc. agri i foswce unit 1 surveyingB.sc. agri i foswce unit 1 surveying
B.sc. agri i foswce unit 1 surveying
Rai University
 
Surveying and scale_Surveying, Civil Engineering
Surveying and scale_Surveying, Civil EngineeringSurveying and scale_Surveying, Civil Engineering
Surveying and scale_Surveying, Civil Engineering
A Makwana
 
Fieldwork 2
Fieldwork 2 Fieldwork 2
Fieldwork 2
JamesMoy7
 
Unit 1
Unit 1Unit 1

What's hot (20)

Angle determination - Report
Angle determination - ReportAngle determination - Report
Angle determination - Report
 
Method Of Chaining On Sloping Ground
Method Of Chaining On Sloping GroundMethod Of Chaining On Sloping Ground
Method Of Chaining On Sloping Ground
 
Introduction to surveying, ranging and chaining
Introduction to surveying, ranging and chainingIntroduction to surveying, ranging and chaining
Introduction to surveying, ranging and chaining
 
Suveying Chain Method
Suveying Chain MethodSuveying Chain Method
Suveying Chain Method
 
S2 3.1 tape and offset surveying
S2 3.1 tape and offset surveyingS2 3.1 tape and offset surveying
S2 3.1 tape and offset surveying
 
Types of obstacles in chain surveying
Types of obstacles in chain surveyingTypes of obstacles in chain surveying
Types of obstacles in chain surveying
 
Tacheometric surveying - Assignment
Tacheometric surveying - AssignmentTacheometric surveying - Assignment
Tacheometric surveying - Assignment
 
Chain survey
Chain surveyChain survey
Chain survey
 
Surveying - Module I - Introduction to surveying
Surveying - Module I - Introduction to surveying Surveying - Module I - Introduction to surveying
Surveying - Module I - Introduction to surveying
 
2.2 linear measurement
2.2 linear measurement2.2 linear measurement
2.2 linear measurement
 
Chain surveying.1
Chain surveying.1Chain surveying.1
Chain surveying.1
 
Module-I SURVEYING-I [BTCVC304]
Module-I SURVEYING-I [BTCVC304]Module-I SURVEYING-I [BTCVC304]
Module-I SURVEYING-I [BTCVC304]
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
11.4 circumference and arc length
11.4 circumference and arc length11.4 circumference and arc length
11.4 circumference and arc length
 
Chain surveying and offset
Chain surveying and offsetChain surveying and offset
Chain surveying and offset
 
Chain surveying
Chain surveyingChain surveying
Chain surveying
 
B.sc. agri i foswce unit 1 surveying
B.sc. agri i foswce unit 1 surveyingB.sc. agri i foswce unit 1 surveying
B.sc. agri i foswce unit 1 surveying
 
Surveying and scale_Surveying, Civil Engineering
Surveying and scale_Surveying, Civil EngineeringSurveying and scale_Surveying, Civil Engineering
Surveying and scale_Surveying, Civil Engineering
 
Fieldwork 2
Fieldwork 2 Fieldwork 2
Fieldwork 2
 
Unit 1
Unit 1Unit 1
Unit 1
 

Viewers also liked

Surveying assignment solutions 22.2.2015
Surveying assignment solutions 22.2.2015Surveying assignment solutions 22.2.2015
Surveying assignment solutions 22.2.2015
V Vinayaka Ram
 
Surveying assignment
Surveying assignmentSurveying assignment
Surveying assignment
zubda sajda
 
Basic Civil Engineering MCQ
Basic Civil Engineering MCQBasic Civil Engineering MCQ
Basic Civil Engineering MCQ
Pralhad Kore
 
Levelling
LevellingLevelling
Contouring
ContouringContouring
Contouring
GAURAV. H .TANDON
 
Top 52 civil engineer interview questions and answers pdf
Top 52 civil engineer interview questions and answers pdfTop 52 civil engineer interview questions and answers pdf
Top 52 civil engineer interview questions and answers pdf
HarrisonFord888
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
Salauddin Rubel
 

Viewers also liked (7)

Surveying assignment solutions 22.2.2015
Surveying assignment solutions 22.2.2015Surveying assignment solutions 22.2.2015
Surveying assignment solutions 22.2.2015
 
Surveying assignment
Surveying assignmentSurveying assignment
Surveying assignment
 
Basic Civil Engineering MCQ
Basic Civil Engineering MCQBasic Civil Engineering MCQ
Basic Civil Engineering MCQ
 
Levelling
LevellingLevelling
Levelling
 
Contouring
ContouringContouring
Contouring
 
Top 52 civil engineer interview questions and answers pdf
Top 52 civil engineer interview questions and answers pdfTop 52 civil engineer interview questions and answers pdf
Top 52 civil engineer interview questions and answers pdf
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 

Similar to SURVEYING

Chap1.44
Chap1.44Chap1.44
Pendulum~
Pendulum~Pendulum~
Pendulum~
muhammadriyadh17
 
Pendulum~
Pendulum~Pendulum~
1 ESO - Unit 10 - Exercises 1.10.2 - Plane Figures.
1 ESO - Unit 10 - Exercises 1.10.2 - Plane Figures.1 ESO - Unit 10 - Exercises 1.10.2 - Plane Figures.
1 ESO - Unit 10 - Exercises 1.10.2 - Plane Figures.
Gogely The Great
 
MTAP 2017 PERIMETER AND AREA.pptx
MTAP 2017 PERIMETER AND AREA.pptxMTAP 2017 PERIMETER AND AREA.pptx
MTAP 2017 PERIMETER AND AREA.pptx
LeonardoBrunoJr
 
Survey Problem.
Survey Problem.Survey Problem.
Survey Problem.
Ghulam Mehdi
 
Linear measurement
Linear measurement Linear measurement
Linear measurement
RAMPRASAD KUMAWAT
 
Pendulum ssi
Pendulum ssiPendulum ssi
Pendulum ssi
muhd faiz
 

Similar to SURVEYING (8)

Chap1.44
Chap1.44Chap1.44
Chap1.44
 
Pendulum~
Pendulum~Pendulum~
Pendulum~
 
Pendulum~
Pendulum~Pendulum~
Pendulum~
 
1 ESO - Unit 10 - Exercises 1.10.2 - Plane Figures.
1 ESO - Unit 10 - Exercises 1.10.2 - Plane Figures.1 ESO - Unit 10 - Exercises 1.10.2 - Plane Figures.
1 ESO - Unit 10 - Exercises 1.10.2 - Plane Figures.
 
MTAP 2017 PERIMETER AND AREA.pptx
MTAP 2017 PERIMETER AND AREA.pptxMTAP 2017 PERIMETER AND AREA.pptx
MTAP 2017 PERIMETER AND AREA.pptx
 
Survey Problem.
Survey Problem.Survey Problem.
Survey Problem.
 
Linear measurement
Linear measurement Linear measurement
Linear measurement
 
Pendulum ssi
Pendulum ssiPendulum ssi
Pendulum ssi
 

More from Pralhad Kore

Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
Pralhad Kore
 
Chapter wise question papers_bce
Chapter wise question papers_bceChapter wise question papers_bce
Chapter wise question papers_bce
Pralhad Kore
 
Design of staircase_practical_example
Design of staircase_practical_exampleDesign of staircase_practical_example
Design of staircase_practical_example
Pralhad Kore
 
Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"
Pralhad Kore
 
Guidelines_for_building_design
Guidelines_for_building_designGuidelines_for_building_design
Guidelines_for_building_design
Pralhad Kore
 
Strength of materials_I
Strength of materials_IStrength of materials_I
Strength of materials_I
Pralhad Kore
 
Presentation_on_Cellwise_Braced_frames
Presentation_on_Cellwise_Braced_framesPresentation_on_Cellwise_Braced_frames
Presentation_on_Cellwise_Braced_frames
Pralhad Kore
 
Study of MORT_&_H
Study of MORT_&_HStudy of MORT_&_H
Study of MORT_&_H
Pralhad Kore
 
List of various_IRCs_&_sps
List of various_IRCs_&_spsList of various_IRCs_&_sps
List of various_IRCs_&_sps
Pralhad Kore
 
Analysis of multi storey building frames subjected to gravity and seismic loa...
Analysis of multi storey building frames subjected to gravity and seismic loa...Analysis of multi storey building frames subjected to gravity and seismic loa...
Analysis of multi storey building frames subjected to gravity and seismic loa...
Pralhad Kore
 
Seismic response of _reinforced_concrete_concentrically_a_braced_frames
Seismic  response  of _reinforced_concrete_concentrically_a_braced_framesSeismic  response  of _reinforced_concrete_concentrically_a_braced_frames
Seismic response of _reinforced_concrete_concentrically_a_braced_frames
Pralhad Kore
 
Use of mechanical_splices_for_reinforcing_steel
Use of mechanical_splices_for_reinforcing_steelUse of mechanical_splices_for_reinforcing_steel
Use of mechanical_splices_for_reinforcing_steel
Pralhad Kore
 
Guide lines bridge_design
Guide lines bridge_designGuide lines bridge_design
Guide lines bridge_design
Pralhad Kore
 
Dissertation report
Dissertation reportDissertation report
Dissertation report
Pralhad Kore
 
Seismic response of cellwise braced reinforced concrete frames
Seismic response of cellwise braced reinforced concrete framesSeismic response of cellwise braced reinforced concrete frames
Seismic response of cellwise braced reinforced concrete frames
Pralhad Kore
 
Water Management
Water ManagementWater Management
Water Management
Pralhad Kore
 
Basic Loads Cases
Basic Loads CasesBasic Loads Cases
Basic Loads Cases
Pralhad Kore
 
Earthquake analysis by Response Spectrum Method
Earthquake analysis by Response Spectrum MethodEarthquake analysis by Response Spectrum Method
Earthquake analysis by Response Spectrum Method
Pralhad Kore
 
Earthquake analysis by psudeo static method
Earthquake analysis by psudeo static methodEarthquake analysis by psudeo static method
Earthquake analysis by psudeo static method
Pralhad Kore
 
PROBLEMS ON BEARINGS
PROBLEMS ON BEARINGSPROBLEMS ON BEARINGS
PROBLEMS ON BEARINGS
Pralhad Kore
 

More from Pralhad Kore (20)

Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
Chapter wise question papers_bce
Chapter wise question papers_bceChapter wise question papers_bce
Chapter wise question papers_bce
 
Design of staircase_practical_example
Design of staircase_practical_exampleDesign of staircase_practical_example
Design of staircase_practical_example
 
Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"
 
Guidelines_for_building_design
Guidelines_for_building_designGuidelines_for_building_design
Guidelines_for_building_design
 
Strength of materials_I
Strength of materials_IStrength of materials_I
Strength of materials_I
 
Presentation_on_Cellwise_Braced_frames
Presentation_on_Cellwise_Braced_framesPresentation_on_Cellwise_Braced_frames
Presentation_on_Cellwise_Braced_frames
 
Study of MORT_&_H
Study of MORT_&_HStudy of MORT_&_H
Study of MORT_&_H
 
List of various_IRCs_&_sps
List of various_IRCs_&_spsList of various_IRCs_&_sps
List of various_IRCs_&_sps
 
Analysis of multi storey building frames subjected to gravity and seismic loa...
Analysis of multi storey building frames subjected to gravity and seismic loa...Analysis of multi storey building frames subjected to gravity and seismic loa...
Analysis of multi storey building frames subjected to gravity and seismic loa...
 
Seismic response of _reinforced_concrete_concentrically_a_braced_frames
Seismic  response  of _reinforced_concrete_concentrically_a_braced_framesSeismic  response  of _reinforced_concrete_concentrically_a_braced_frames
Seismic response of _reinforced_concrete_concentrically_a_braced_frames
 
Use of mechanical_splices_for_reinforcing_steel
Use of mechanical_splices_for_reinforcing_steelUse of mechanical_splices_for_reinforcing_steel
Use of mechanical_splices_for_reinforcing_steel
 
Guide lines bridge_design
Guide lines bridge_designGuide lines bridge_design
Guide lines bridge_design
 
Dissertation report
Dissertation reportDissertation report
Dissertation report
 
Seismic response of cellwise braced reinforced concrete frames
Seismic response of cellwise braced reinforced concrete framesSeismic response of cellwise braced reinforced concrete frames
Seismic response of cellwise braced reinforced concrete frames
 
Water Management
Water ManagementWater Management
Water Management
 
Basic Loads Cases
Basic Loads CasesBasic Loads Cases
Basic Loads Cases
 
Earthquake analysis by Response Spectrum Method
Earthquake analysis by Response Spectrum MethodEarthquake analysis by Response Spectrum Method
Earthquake analysis by Response Spectrum Method
 
Earthquake analysis by psudeo static method
Earthquake analysis by psudeo static methodEarthquake analysis by psudeo static method
Earthquake analysis by psudeo static method
 
PROBLEMS ON BEARINGS
PROBLEMS ON BEARINGSPROBLEMS ON BEARINGS
PROBLEMS ON BEARINGS
 

Recently uploaded

2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 

Recently uploaded (20)

2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 

SURVEYING

  • 1. Page 1 ASSIGNMENT NO. 2 SURVEYING PROBLEMS ON CHAIN To solve such problem 1) Lo = ( 𝒍 𝟏 𝒍 𝟎 ) 𝟐 Lo 2) Ao = ( 𝒍 𝟏 𝒍 𝟎 ) 𝟐 Ao TYPE I) To calculate true distance 1. A 20 m chain was tested before the commencement of the day’s work and found to be correct. After chaining 840 m the chain was found to be 0.08 m too long. At the end day’s work, after chaining a total distance of 1376 m the chain was found to be 0.12 m too long. What was true distance chained? 2. The distance between two points, measured with 20 m chain, was recorded as 327 m. It was afterwards found that the chain was 3 cm too long. What was the true distance between the points? 3. The distance between two stations was 1200 m when measured with a 20 m chain. The same distance when measured with 30 m chain was found to be 1195 m. If the 20 m chain was 0.05 m too long, what was the error in the 30 m chain? TYPE II) To calculate true distance 1. The distance measured between two points by a 20m chain was 1340 m and when measured by a 30 m chain was 1345 m. If the 30 m chain was one link too short; find out if the 20m chain was of correct length or not. If not find the error in it. 2. The lengths of 20 m and 30 m chains were tested and found to be correct at the beginning of work. The distance between two points measured by 20 m chain was 1340 m and when measured by 30 m chain was 1345 m. 30 m chain was tested again and found to be 20 cm too short.
  • 2. Page 2 Calculate average chain length and final chain length of 20 m chain at the end of measurement. (09 Mks) 3. A 30 m chain was found to be 15.24 cm too long after chaining 1524 m. The same chain was found to be 30.48 cm too long after chaining a total distance of 3048 m. Find the correct length of the total distance assuming chain was correct at the commencement of chaining. 4. A line was measured by 20 m chain which was accurate before starting the day’s work. After chaining 900 m, the chain was found to be 6 cm too long. After chaining of 1575 m, the chain was found to be 14 cm too long. Find the true distance of the line. 5. A 30 m chain (150 links) was found to be one link too short. The area measured with this chain also plotted to scale 1 cm = 8 m and was found to be 32.659 cm2. The map was found to have shrunk so that a line originally 10 cm long was only 9.8 cm. Find true area of the field. (09) TYPE III) To calculate true area 1. A chain was tested before start and found to be 30 m. At the end of work it was checked again and found to be 30.10 m. Area of plan drawn to a scale 1: 1000 was 160 sq. m. Find the true area in hectres. (06 Mks) 2. A chain was tested before starting a survey of field and was found to be exactly 30 m. At the end of the survey it was tested again and was found to measure 30.16 m. The area of plan drawn to a scale of 1 cm = 60 m was 92.50 cm2. Find the true area of field. (Nov. 2011) 08 Mks 3. An old map was drawn with a scale of 1cm = 10 m, the field was surveyed with a 30 m chain which was actually 0.05 m short. An original length of 10 cm has now shrunk to 9.5 cm on drawing. The plan area measured with a planimeter is 95 cm2. Calculate the actual area of the land. 4. A chain was tested before starting a survey of field and was found to be exactly 20 m. At the end of the survey it was tested again and was found to measure 20.20 m. The area of plan drawn to a scale of 1 cm = 80 m was 100 cm2. Find the true area of field. 5. A 30 m chain (150 links) was found to be one link too short. The area measured with this chain also plotted to scale 1 cm = 8 m and was found to be 32.659 cm2. The map was found to have shrunk so that a line originally 10 cm long was only 9.8 cm. Find true area of the field. (09 marks) 6. An old map was drawn with a scale of 1cm = 8 m, but now the paper is found to have shrunk. A line originally 200 mm long now measures 190 mm only. The area of a plot now measures 100.5
  • 3. Page 3 cm2. There was also a note that the 30 m chain was 100 mm too short. Find the true area of the plot. 7. A rectangular field was measured with a 30 m chain. Its length was found to be 3000 m and its breadth 2500 m. before starting the work the chain was compared with a standard rope and was found to be short by 5 cm. At the end of the work, the chain was found to be longer than the standard length by 30 cm. What is the actual area of the field? 8. A 20 m chain was tested before the commencement of the day’s work and found to be correct. After chaining 840 m the chain was found to be 0.08 m too long. At the end of the day’s work, after chaining a total distance of 1376 m the chain was found to be 0.12m too long. What was the true distance chained? 9. A chain was tested before starting a survey of field and was found to be exactly 30 m. At the end of the survey it was tested again and was found to measure 30.16 m. The area of the plane drawn to a scale of 1 cm = 60 m was 92.5 cm2. Find the area of the field. 10. A plan of an old survey plotted to a scale of 1 cm = 10 m was found to have shrunk so that a line originally measuring 25 cm long was found to measure 24.4 cm. If the area of the plan measured now is 122 cm2, determine the true area of the survey. Calculate shrinkage factor. 11. A old map was plotted to a scale of 40 m to 1cm.Over the years, this map has been shrinking, and a line originally 20 cm long is only 19.5 cm long at present. Again the 20m chain was 5 cm too long. If the present area of the map measured by planimeter is 125.50 cm2, find the true area of land surveyed. ( 9) 12. The old map was drawn to a scale of 1cm = 8 m, but now the paper is found to have shrunk. A line originally 200 mm long now measures 190mm only. The area of a plot now measures 100.5 cm2. There was also a note that the 30m chain used was 100 mm too short. Find the true area of the plot. 13. A 20 m chain was tested before the commencement of the day's work and found to be correct. After chaining 840 m the chain was found to be 0.08 m too long. At the end of day's work, after chaining a total distance of 1376 m the chain was found to be 0.12 m too long. What was true distance chained? 14. A chain was tested before start and found to be 30 m. At the end of work it was checked again and found to be 30.20 m. The area of plan drawn to a scale of 1: 1000 was 200 sq. m. Find the true area on field in hectares. 15. The area of a plan of an old map plotted to a scale of 1 m = 10 m. Measures 100 sq. m. The plan is found to have shrunk so that the line originally 10 cm long now measures 9.7 cm, Further the
  • 4. Page 4 20 m chain used was 8 cm too short. Find the true area of the survey. 16. A chain was tested before start and found to be 30 m. At the end of work it was checked again and found to be 30.10 m. The area of plan drawn to a scale 1: 1000 was 160 sq .m. Find the true area in hectres. 17. The old map was drawn to a scale of 1 em = 8 m, but now the paper is found to have shrunk. A line originally 200 mm long now measures 190 mm only. The area of a plot now measures 100.5 cm-. There was also a note that the 30 m chain used was 100 mm too short. Find the true area of the plot. (9) 18. A chain was tested before start and found to be 30 m. At the end of work it was checked again and found to be 30.10 m. The area of plan drawn to a scale 1 : 1000 was 160 sq .m. Find the true area in hectres. 19. The lengths of 20 m and 30 m chains were tested and found to be correct at the beginning of work. The distance between two points measured by 20 m chain was 1340 m and when measured by 30 m chain was 1345 m. 30 m chain was tested again and found to be 20 cm too short. Calculate average chain length and final chain length of 20 m chain at the end of measurement. 20. The lengths of 20 m and 30 m chains were tested and found to be correct at the beginning of work. The distance between two points measured by 20 m chain was 1340 m and when measured by 30 m chain was 1345 m. 30 m chain was tested again and found to be 20 cm too short. Calculate average chain length and final chain length of 20 m chain at the end of measurement. 21. Distance ABC was measured with a 30 m chain, tested and found to be correct in the beginning of the work. After measuring AB = 1.2 kms, chain was found to be 10 cm too long. Chaining was continued till total distance of 2.0 kms up to point C. At the end of the work chain was found to be 20 cm too long. Find correct distance ABC.