PROJECT COST
MANAGEMENT
KNOWLEDGE AREA
COST MANAGEMENT
KNOWLEDGE AREA
OVERVIEW
7.1 Plan Cost management
7.2 Estimate costs
7.3 determine budget
7.4 control costs
COST MANAGEMENT KNOWLEDGE
AREA OVERVIEW
All the processes needed to work
through a project within the confines of
the budget. The cost baseline is created
within this knowledge area’s processes.
7.1 PLAN COST
MANAGEMENT
-PART OF THE PLANNING PROCESS GROUP
This Photo by Unknown Author is licensed under CC BY-SA
PLAN COST MANAGEMENT PROCESS
The process of planning how
managing costs associated with the
project will be planned and
controlled
7.1 PLAN COST
MANAGEMENT
 Part of the Planning Process
Group
 Establishes policies and
procedures for planning,
managing, and controlling
project costs
 OUTPUT:
 Cost Management Plan
COST MANAGEMENT PLAN
GUIDES THE ESTIMATION OF COSTS
AND BUDGET CONSTRUCTION
GUIDES THE PROPER USE OF
SPENDING WITHIN THE PROJECT
INCLUDED IN THE PROJECT
MANAGEMENT PLAN
LIFECYCLE COSTING
The cost of a product’s entire life
expectancy
Life expectancy value of resources
purchased for a project that can be
used in later projects or organizational
activities
VALUE ENGINEERING / ANALYSIS
Lower cost ways to do the same
amount of work
Can be brought on by process
improvements or better resource
purchasing conditions
7.2 ESTIMATE COSTS
-PART OF THE PLANNING PROCESS GROUP
This Photo by Unknown Author is licensed under CC BY-SA
ESTIMATE COST PROCESS
The development of estimates related
to the anticipated costs of project
activities
7.2 ESTIMATE COSTS
 Part of the Planning Process
Group
 Each activity’s cost must be
estimated
 Entire project cost is
estimated
 Products purchased,
wages/labor, contingency
reserves for delay
ESTIMATING COSTS – PROJECT INPUTS
The Scope Baseline
The Cost
Management Plan
Quality
Management Plan
The Project Schedule
Resource
Requirements
Project Risk / Risk
Register
Lessons Learned
Register
Organizational
Process Assets
Enterprise
Environmental
Factors
ESTIMATING COSTS
USING THE WBS
CREATED IN THE
PROJECT SCOPE
MANAGEMENT
KNOWLEDGE
AREA CAN
IMPROVE
ESTIMATIONS
ACTIVITY
ESTIMATIONS
SHOULD INCLUDE
INPUT FROM THE
PERSON DOING
THE WORK
PROJECT
HISTORICAL
INFORMATION /
ORGANIZATIONS
PAST PROJECTS
SHOULD BE USED
FACTORS
IMPACTING
COSTS
High quality / low quality impacts costs
Increased risk factors
Project complexity
General project costs
Training
Project manager costs
Required resources
Other tangible resources
COST TYPES
• Costs that can change with the amount of work output
produced
Variable
Cost
• Costs that do not change as the work output is
increased
Fixed
Costs
• Costs associated with producing project deliverables
Direct
Costs
• Overhead costs that can be accrued by multiple
projects (Program Costs, Organizational Operations)
Indirect
Costs
ESTIMATING COSTS
One-Point Estimation Each estimator submits a cost estimate for the activity
Parametric Estimation
Using historical records to collect average costs for activities
and using that as a basis to estimate current activities
Analogous Estimation
Similar activities are examined for their actual costs and used
to estimate for the current activity
Bottom-up Estimating
Estimations done for each activity or work package,
estimations are combined or rolled up to “Control Accounts” or
group of work packages. Total project costs are found by
combining “Control Accounts”
PERT ANALYSIS
 Three cost estimates are provided for each activity
 Optimistic Estimate (O) – Best case scenario for
activity completion times
 Most Likely Estimate (M) - The most likely
completion time of the activity
 Pessimistic Estimate (P) – Worst case scenario for
activity completion duration
 Using the average of the estimates to estimate the
activity
 Triangular Distribution
 Beta Distribution
 Used for time and cost estimates
ESTIMATION ACCURACY
Rough Order of
magnitude (ROM)
Range of estimates
between -25% and +
75% from actual costs
Budge Estimates
Fall in the Range of -
10% to + 25% from
actual costs
Definitive
Estimates
Range of estimates
between -10% to +10%
from actual costs
7.3 DETERMINE BUDGET
-PART OF THE PLANNING PROCESS GROUP
This Photo by Unknown Author is licensed under CC BY-SA
THE DETERMINE BUDGET PROCESS
Aggregating costs of
activities or work
packages together to
create the project cost
baseline
7.3 DETERMINE BUDGET
Part of the Planning
Process Group
Creates the cost baseline
Activity risks need to be
considered and cost
reserves need to be placed
into the estimates
COST RESERVES
Contingency Reserve
Reserve for handling known risks and is used
as part of the risk management strategy
Management
Cost reserved for unexpected risks or
changes
COST BASELINE
The base estimated costs
of the funds authorized for
spending on the project
Includes all estimated costs
and contingency reserves
but does not include
management reserves
PROJECT
BUDGET
The project cost budget includes
the cost baseline plus the
management reserve
7.4 CONTROL COSTS
-PART OF THE MONITORING & CONTROLLING PROCESS
GROUP
This Photo by Unknown Author is licensed under CC BY-SA
THE CONTROL COSTS PROCESS
The monitoring of the project
expenditures throughout the project
and handling changes to the cost
baseline
7.4 CONTROL COSTS
 Part of the Monitoring &
Controlling Process Group
 Calculating the actual costs spend
and measuring it against the cost
baseline
 Work to prevent changes or
handle changes to the cost if they
do occur
EARNED VALUE
MANAGEMENT
(EVM)
EARNED VALUE MANAGEMENT
Can be used to measure the
performance of the project against the
baselines for scope, schedule, and
costs
This Photo by Unknown Author is licensed under CC BY-NC
EARNED VALUE MANAGEMENT
Planned Value
The planned or estimated value
for planned work
Earned Value (EV)
The value of the work
completed based on the
estimated value
Actual Cost (AC)
The actual cost for the
completed work
CALCULATING PV, EV, AC
PV = % Planned
Complete * Estimated
Total Budget
EV = % Actually
Complete * Estimated
Total Budget
AC = Actual Cost of
the Completed Work
VARIANCES
Schedule Variance (SV) Measures the performance of the schedule
Less than 0 indicates a project behind schedule
Greater than 0 indicates a project ahead of schedule
Cost Variance (CV) Measures the performance of the budget
Less than 0 indicates a project is over budget
Greater than 0 indicates a project that is under budget
Schedule Performance
Index (SPI)
Measure of the efficiency of the project schedule
Greater than 1 indicates a project is ahead of schedule
Less than 1 indicates a project is behind schedule
Cost Performance
Index (CPI)
Measure of the efficiency of the project costs
Greater than 1 indicates a project that is under budget
Less than 1 indicates a project that is over budget
CALCULATING VARIANCE
• SV = EV – PVSchedule Variance (SV)
• CV = EV – ACCost Variance (CV)
• SPI = EV/PVSchedule Performance Index (SPI)
• CPI = EV/ACCost Performance Index (CPI)
EARNED VALUE - FORECASTS
Total budget for all work items in the project to bring them to completion
Budget at
Completion (BAC)
Total estimated costs for completing all project work
Estimate at
Completion (EAC)
Estimate to complete the project from this point forward
Estimate to
Complete (ETC)
The forecasted completion costs of the project
If VAC < 0 Project will be completed over budget
If VAC > 0, Project will be completed under budget
Variance at
Completion (VAC)
Gives an indicator of what efficiency is needed to complete the project in order to make up for past negative
variances with the budget
If TCPI < 0 Project will more easily complete within budget
If TCPI > 0, Project will not be very easy to complete within budget
To Complete
Performance Index
(TCPI)
EARNED VALUE - FORECASTS
Estimate to Complete (ETC)
• ETC is equal to the estimates of the
remaining work items
• OR
• ETC = EAC - AC
Estimate at Completion (EAC)
• EAC = AC + ETC
• If all ETC work will remain within the
budgeted rate:
• EAC = AC + (BAC – EV)
• If the cost performance index is
expected to remain persistent:
• EAC = BAC/CPI
EARNED VALUE - FORECASTS
Variance at Completion (VAC)
• VAC = BAC – EAC
To Complete Performance Index
(TCPI)
• Original budget completion
requirement:
• TCPI = (BAC – EV) / (BAC – AC)
• Accommodating for past variances
• TCPI = (BAC – EV) / (EAC – AC)
SOURCES
A Guide to the Project
Management Body of
Knowledge – PMBOK 6th
Edition
https://www.pmi.org/
Joshua Render
https://agile-mercurial.com

More Related Content

What's hot

Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge AreaJoshua Render
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementMohamed Loey
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management OverviewDavidMcLachlan1
 
Project Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessRuffin Veal and Associates, Inc.
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Agus Suhanto
 
Presentation project management
Presentation project managementPresentation project management
Presentation project managementFlobz Caloy
 
Programme management and project evaluation
Programme management and project evaluationProgramme management and project evaluation
Programme management and project evaluationtumetr1
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 

What's hot (20)

Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge Area
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
Project management professional (pmi) study guide
Project management professional (pmi) study guideProject management professional (pmi) study guide
Project management professional (pmi) study guide
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management Overview
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
 
Project Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition Success
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Pmp integration management
Pmp integration managementPmp integration management
Pmp integration management
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6
 
Presentation project management
Presentation project managementPresentation project management
Presentation project management
 
Programme management and project evaluation
Programme management and project evaluationProgramme management and project evaluation
Programme management and project evaluation
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 

Similar to Project Management: Cost Management Knowledge Area

2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfMadhusha15
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseVladimir Vujovic
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfalvieramada23
 

Similar to Project Management: Cost Management Knowledge Area (20)

2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
Project cost control
Project cost controlProject cost control
Project cost control
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
 

More from Joshua Render

Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Joshua Render
 
Alderfer's ERG theory of motivation
Alderfer's ERG theory of motivationAlderfer's ERG theory of motivation
Alderfer's ERG theory of motivationJoshua Render
 
MacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZMacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZJoshua Render
 
Big Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelBig Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelJoshua Render
 
Drexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelDrexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelJoshua Render
 
7 Core Concepts of Lean
7 Core Concepts of Lean7 Core Concepts of Lean
7 Core Concepts of LeanJoshua Render
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)Joshua Render
 
Guide to User Story Creation
Guide to User Story CreationGuide to User Story Creation
Guide to User Story CreationJoshua Render
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management ProcessesJoshua Render
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaJoshua Render
 
Communication Management Knowledge Area
Communication Management Knowledge AreaCommunication Management Knowledge Area
Communication Management Knowledge AreaJoshua Render
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge AreaJoshua Render
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge AreaJoshua Render
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
What is Osmotic Communication?
What is Osmotic Communication?What is Osmotic Communication?
What is Osmotic Communication?Joshua Render
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge AreaJoshua Render
 
PMI-ACP Domain 1 Agile Principles and Mindset
PMI-ACP Domain 1 Agile Principles and MindsetPMI-ACP Domain 1 Agile Principles and Mindset
PMI-ACP Domain 1 Agile Principles and MindsetJoshua Render
 

More from Joshua Render (20)

Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?
 
Alderfer's ERG theory of motivation
Alderfer's ERG theory of motivationAlderfer's ERG theory of motivation
Alderfer's ERG theory of motivation
 
MacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZMacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory Z
 
Big Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelBig Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor Model
 
Drexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelDrexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance Model
 
What is Kanban?
What is Kanban?What is Kanban?
What is Kanban?
 
7 Core Concepts of Lean
7 Core Concepts of Lean7 Core Concepts of Lean
7 Core Concepts of Lean
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Guide to User Story Creation
Guide to User Story CreationGuide to User Story Creation
Guide to User Story Creation
 
Tuckman's Model
Tuckman's ModelTuckman's Model
Tuckman's Model
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge Area
 
Communication Management Knowledge Area
Communication Management Knowledge AreaCommunication Management Knowledge Area
Communication Management Knowledge Area
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge Area
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge Area
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
What is Osmotic Communication?
What is Osmotic Communication?What is Osmotic Communication?
What is Osmotic Communication?
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 
PMI-ACP Domain 1 Agile Principles and Mindset
PMI-ACP Domain 1 Agile Principles and MindsetPMI-ACP Domain 1 Agile Principles and Mindset
PMI-ACP Domain 1 Agile Principles and Mindset
 
DSDM certifications
DSDM certificationsDSDM certifications
DSDM certifications
 

Recently uploaded

PitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsPitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsAlejandro Cremades
 
Unveiling the Dynamic Gemini_ Personality Traits and Sign Dates.pptx
Unveiling the Dynamic Gemini_ Personality Traits and Sign Dates.pptxUnveiling the Dynamic Gemini_ Personality Traits and Sign Dates.pptx
Unveiling the Dynamic Gemini_ Personality Traits and Sign Dates.pptxmy Pandit
 
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...Björn Rohles
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesHaseebBashir5
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsStefan Wolpers
 
zidauu _business communication.pptx /pdf
zidauu _business  communication.pptx /pdfzidauu _business  communication.pptx /pdf
zidauu _business communication.pptx /pdfzukhrafshabbir
 
Hyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseHyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseirhcs
 
Stages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerStages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerAlejandro Cremades
 
Constitution of Company Article of Association
Constitution of Company Article of AssociationConstitution of Company Article of Association
Constitution of Company Article of Associationseri bangash
 
Unleash Data Power with EnFuse Solutions' Comprehensive Data Management Servi...
Unleash Data Power with EnFuse Solutions' Comprehensive Data Management Servi...Unleash Data Power with EnFuse Solutions' Comprehensive Data Management Servi...
Unleash Data Power with EnFuse Solutions' Comprehensive Data Management Servi...Rahul Bedi
 
Powers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdfPowers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdflinciy03
 
How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?Alejandro Cremades
 
A Brief Introduction About Jacob Badgett
A Brief Introduction About Jacob BadgettA Brief Introduction About Jacob Badgett
A Brief Introduction About Jacob BadgettJacobBadgett
 
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra
 
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdfبروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdfomnme1
 
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot ReportFuture of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot ReportDubai Multi Commodity Centre
 
Raising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE VenturesRaising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE VenturesAlejandro Cremades
 
Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.smalmahmud11
 
Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Alejandro Cremades
 
How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future worldChris Skinner
 

Recently uploaded (20)

PitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsPitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for Startups
 
Unveiling the Dynamic Gemini_ Personality Traits and Sign Dates.pptx
Unveiling the Dynamic Gemini_ Personality Traits and Sign Dates.pptxUnveiling the Dynamic Gemini_ Personality Traits and Sign Dates.pptx
Unveiling the Dynamic Gemini_ Personality Traits and Sign Dates.pptx
 
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
Meaningful Technology for Humans: How Strategy Helps to Deliver Real Value fo...
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO Services
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & Transformations
 
zidauu _business communication.pptx /pdf
zidauu _business  communication.pptx /pdfzidauu _business  communication.pptx /pdf
zidauu _business communication.pptx /pdf
 
Hyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseHyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings release
 
Stages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerStages of Startup Funding - An Explainer
Stages of Startup Funding - An Explainer
 
Constitution of Company Article of Association
Constitution of Company Article of AssociationConstitution of Company Article of Association
Constitution of Company Article of Association
 
Unleash Data Power with EnFuse Solutions' Comprehensive Data Management Servi...
Unleash Data Power with EnFuse Solutions' Comprehensive Data Management Servi...Unleash Data Power with EnFuse Solutions' Comprehensive Data Management Servi...
Unleash Data Power with EnFuse Solutions' Comprehensive Data Management Servi...
 
Powers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdfPowers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdf
 
How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?
 
A Brief Introduction About Jacob Badgett
A Brief Introduction About Jacob BadgettA Brief Introduction About Jacob Badgett
A Brief Introduction About Jacob Badgett
 
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
 
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdfبروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
بروفايل شركة ميار الخليج للاستشارات الهندسية.pdf
 
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot ReportFuture of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
 
Raising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE VenturesRaising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE Ventures
 
Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.
 
Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)
 
How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future world
 

Project Management: Cost Management Knowledge Area

  • 2. COST MANAGEMENT KNOWLEDGE AREA OVERVIEW 7.1 Plan Cost management 7.2 Estimate costs 7.3 determine budget 7.4 control costs
  • 3. COST MANAGEMENT KNOWLEDGE AREA OVERVIEW All the processes needed to work through a project within the confines of the budget. The cost baseline is created within this knowledge area’s processes.
  • 4. 7.1 PLAN COST MANAGEMENT -PART OF THE PLANNING PROCESS GROUP This Photo by Unknown Author is licensed under CC BY-SA
  • 5. PLAN COST MANAGEMENT PROCESS The process of planning how managing costs associated with the project will be planned and controlled
  • 6. 7.1 PLAN COST MANAGEMENT  Part of the Planning Process Group  Establishes policies and procedures for planning, managing, and controlling project costs  OUTPUT:  Cost Management Plan
  • 7. COST MANAGEMENT PLAN GUIDES THE ESTIMATION OF COSTS AND BUDGET CONSTRUCTION GUIDES THE PROPER USE OF SPENDING WITHIN THE PROJECT INCLUDED IN THE PROJECT MANAGEMENT PLAN
  • 8. LIFECYCLE COSTING The cost of a product’s entire life expectancy Life expectancy value of resources purchased for a project that can be used in later projects or organizational activities
  • 9. VALUE ENGINEERING / ANALYSIS Lower cost ways to do the same amount of work Can be brought on by process improvements or better resource purchasing conditions
  • 10. 7.2 ESTIMATE COSTS -PART OF THE PLANNING PROCESS GROUP This Photo by Unknown Author is licensed under CC BY-SA
  • 11. ESTIMATE COST PROCESS The development of estimates related to the anticipated costs of project activities
  • 12. 7.2 ESTIMATE COSTS  Part of the Planning Process Group  Each activity’s cost must be estimated  Entire project cost is estimated  Products purchased, wages/labor, contingency reserves for delay
  • 13. ESTIMATING COSTS – PROJECT INPUTS The Scope Baseline The Cost Management Plan Quality Management Plan The Project Schedule Resource Requirements Project Risk / Risk Register Lessons Learned Register Organizational Process Assets Enterprise Environmental Factors
  • 14. ESTIMATING COSTS USING THE WBS CREATED IN THE PROJECT SCOPE MANAGEMENT KNOWLEDGE AREA CAN IMPROVE ESTIMATIONS ACTIVITY ESTIMATIONS SHOULD INCLUDE INPUT FROM THE PERSON DOING THE WORK PROJECT HISTORICAL INFORMATION / ORGANIZATIONS PAST PROJECTS SHOULD BE USED
  • 15. FACTORS IMPACTING COSTS High quality / low quality impacts costs Increased risk factors Project complexity General project costs Training Project manager costs Required resources Other tangible resources
  • 16. COST TYPES • Costs that can change with the amount of work output produced Variable Cost • Costs that do not change as the work output is increased Fixed Costs • Costs associated with producing project deliverables Direct Costs • Overhead costs that can be accrued by multiple projects (Program Costs, Organizational Operations) Indirect Costs
  • 17. ESTIMATING COSTS One-Point Estimation Each estimator submits a cost estimate for the activity Parametric Estimation Using historical records to collect average costs for activities and using that as a basis to estimate current activities Analogous Estimation Similar activities are examined for their actual costs and used to estimate for the current activity Bottom-up Estimating Estimations done for each activity or work package, estimations are combined or rolled up to “Control Accounts” or group of work packages. Total project costs are found by combining “Control Accounts”
  • 18. PERT ANALYSIS  Three cost estimates are provided for each activity  Optimistic Estimate (O) – Best case scenario for activity completion times  Most Likely Estimate (M) - The most likely completion time of the activity  Pessimistic Estimate (P) – Worst case scenario for activity completion duration  Using the average of the estimates to estimate the activity  Triangular Distribution  Beta Distribution  Used for time and cost estimates
  • 19. ESTIMATION ACCURACY Rough Order of magnitude (ROM) Range of estimates between -25% and + 75% from actual costs Budge Estimates Fall in the Range of - 10% to + 25% from actual costs Definitive Estimates Range of estimates between -10% to +10% from actual costs
  • 20. 7.3 DETERMINE BUDGET -PART OF THE PLANNING PROCESS GROUP This Photo by Unknown Author is licensed under CC BY-SA
  • 21. THE DETERMINE BUDGET PROCESS Aggregating costs of activities or work packages together to create the project cost baseline
  • 22. 7.3 DETERMINE BUDGET Part of the Planning Process Group Creates the cost baseline Activity risks need to be considered and cost reserves need to be placed into the estimates
  • 23. COST RESERVES Contingency Reserve Reserve for handling known risks and is used as part of the risk management strategy Management Cost reserved for unexpected risks or changes
  • 24. COST BASELINE The base estimated costs of the funds authorized for spending on the project Includes all estimated costs and contingency reserves but does not include management reserves
  • 25. PROJECT BUDGET The project cost budget includes the cost baseline plus the management reserve
  • 26. 7.4 CONTROL COSTS -PART OF THE MONITORING & CONTROLLING PROCESS GROUP This Photo by Unknown Author is licensed under CC BY-SA
  • 27. THE CONTROL COSTS PROCESS The monitoring of the project expenditures throughout the project and handling changes to the cost baseline
  • 28. 7.4 CONTROL COSTS  Part of the Monitoring & Controlling Process Group  Calculating the actual costs spend and measuring it against the cost baseline  Work to prevent changes or handle changes to the cost if they do occur
  • 30. EARNED VALUE MANAGEMENT Can be used to measure the performance of the project against the baselines for scope, schedule, and costs This Photo by Unknown Author is licensed under CC BY-NC
  • 31. EARNED VALUE MANAGEMENT Planned Value The planned or estimated value for planned work Earned Value (EV) The value of the work completed based on the estimated value Actual Cost (AC) The actual cost for the completed work
  • 32. CALCULATING PV, EV, AC PV = % Planned Complete * Estimated Total Budget EV = % Actually Complete * Estimated Total Budget AC = Actual Cost of the Completed Work
  • 33. VARIANCES Schedule Variance (SV) Measures the performance of the schedule Less than 0 indicates a project behind schedule Greater than 0 indicates a project ahead of schedule Cost Variance (CV) Measures the performance of the budget Less than 0 indicates a project is over budget Greater than 0 indicates a project that is under budget Schedule Performance Index (SPI) Measure of the efficiency of the project schedule Greater than 1 indicates a project is ahead of schedule Less than 1 indicates a project is behind schedule Cost Performance Index (CPI) Measure of the efficiency of the project costs Greater than 1 indicates a project that is under budget Less than 1 indicates a project that is over budget
  • 34. CALCULATING VARIANCE • SV = EV – PVSchedule Variance (SV) • CV = EV – ACCost Variance (CV) • SPI = EV/PVSchedule Performance Index (SPI) • CPI = EV/ACCost Performance Index (CPI)
  • 35. EARNED VALUE - FORECASTS Total budget for all work items in the project to bring them to completion Budget at Completion (BAC) Total estimated costs for completing all project work Estimate at Completion (EAC) Estimate to complete the project from this point forward Estimate to Complete (ETC) The forecasted completion costs of the project If VAC < 0 Project will be completed over budget If VAC > 0, Project will be completed under budget Variance at Completion (VAC) Gives an indicator of what efficiency is needed to complete the project in order to make up for past negative variances with the budget If TCPI < 0 Project will more easily complete within budget If TCPI > 0, Project will not be very easy to complete within budget To Complete Performance Index (TCPI)
  • 36. EARNED VALUE - FORECASTS Estimate to Complete (ETC) • ETC is equal to the estimates of the remaining work items • OR • ETC = EAC - AC Estimate at Completion (EAC) • EAC = AC + ETC • If all ETC work will remain within the budgeted rate: • EAC = AC + (BAC – EV) • If the cost performance index is expected to remain persistent: • EAC = BAC/CPI
  • 37. EARNED VALUE - FORECASTS Variance at Completion (VAC) • VAC = BAC – EAC To Complete Performance Index (TCPI) • Original budget completion requirement: • TCPI = (BAC – EV) / (BAC – AC) • Accommodating for past variances • TCPI = (BAC – EV) / (EAC – AC)
  • 38. SOURCES A Guide to the Project Management Body of Knowledge – PMBOK 6th Edition https://www.pmi.org/ Joshua Render https://agile-mercurial.com