7. Project Cost Management
Managing Funds Effectively
Cost Challenges In Construction Industry
Demand Side Challenges : Recession & Falling Demand
Supply Side Challenges : Increasing Cost Of Resources
Increase In Construction Cost In India
Managing Construction Cost Is Critical
For Project Success And Company Profitability
Pareto's Principle - The 80-20 Rule
roughly 80% of the cost management come from effective control of
20% of the causes.
Costs Components Approx %**
Pre-acquisition costs All costs incurred for aquiring land 10-15
Construction Development and construction costs 40-45
Amenities cost 10-15
Administrative & other
Site administration 8-10
Marketing & sales 5-8
Insurance, taxes & regulatory charges 7-10
Allocation of capitalized costs 5-10
**Based on our survey with few builders in Pune for joint venture projects with
land owners
Costing & Quantity Survey
Surveyor plays a critical role in real estate construction project
management by supporting project manager for all commercial activities
as follows:
 Cost planning
 Cost estimating
 Cost control & monitoring budget
 Contracts negotiation
 Procurement advice
 Preparing bill of quantities (BOQ)
 Preparation of payment invoice and certification.
 Assessment of variations
 Contract dispute resolution
 Valuation for insurance purposes
Surveyor also helps project manager for preparing feasibility studies, risk
management , investment appraisal and auditing
Project cost management includes the processes involved in
planning, estimating, budgeting, financing, funding, managing and
controlling costs so that the project can be completed within the
approved budget.
Project Cost Management
Group 7. Project Cost Management
Initiating
Planning
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
Executing
M&C 7.4 Control Costs
Closing
It is the process that establishes the policies, procedures and
documentation for planning, managing, expending and controlling
project costs
7.1 Plan Cost Management
Fixed Cost Vs Variable Cost
Total Cost = Fixed Cost + Unit Cost X Units Used
Direct Costs Vs Indirect Costs
Plan Cost Management
Cost Management Plan : Also includes
 Rules for performance measurement
 Organizational procedures links : The WBS component used for
the project cost accounting is called control account.
 Control Thresholds : Variance thresholds for monitoring cost
performance to indicate an agreed-upon amount of variation
to be allowed before some action needs to be taken. Typically
expressed as percentage deviations from the baseline plan
Cost estimating involves developing an estimate of the costs of all
resources needed to complete the project.
The accuracy of estimates tends to improve as a project moves
though its life cycle.
7.2 Estimate Costs
 Order of magnitude estimates: “Ballpark” estimates without
detailed data, done at the feasibility stage for selecting right
construction project. The range of accuracy is given as -25 to
+75% and would be used for initiating or project approval.
 Budget estimates: Based on slightly better data and used to
establish initial funding during the early stages of planning. This
budget is used for alternative resource analysis and getting
funding approval for the project. The range of accuracy is given
as -10 to +25%.
 Definitive estimates: A bottom-up estimate using estimates of
WBS work packages This estimate would be done in the latter
stages of planning and be used to establish a cost baseline and
monitor spending. It is progressively elaborated. Range of
accuracy is -5 to +10%.
7.2 Estimate Costs
7.2 Estimate Costs
Inputs
1. Cost Management Plan
2. Scope Baseline
3. Project Schedule
4. Risk Register
5. Human Resource
Management Plan
6. EEFs
7. OPAs
T & T
1. Expert Judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimating
6. Reserve Analysis
7. Cost of Quality
8. Vendor bid Analysis
9. Group decision making
techniques
Outputs
1. Activity cost Estimates
2. Basis of Estimates
3. Project Documents Updates
Reserve Analysis
Applied to the base cost to account for uncertainties in quantities,
unit costs work elements or other project requirements during
construction.
requirements for an activity or work item.
 Contingency Reserve
 It used to manage identified risks
 It is estimated based on decision tree method or Expected
Monitory Value (EMV)
 The project manager has authority to use
 Management Reserve
 It is used to manage unidentified risks
 It is calculated as a percentage of the cost, or time of project
 Management approval is required to use management
reserve
The use of either type of reserve is intended to reduce the chance
of a cost overrun
Determine Budget
 For Small construction projects use Small
internal workshops using the Pre-defined Excel
workbook
 For mid size project use Cost Risk Assessment
(CRA) workshops typically held internally
 For large projects / programs / portfolio use
Cost Estimating and Validation Process (CEVP)
workshops which includes external subject
matter experts
Cost budgeting involves aggregating cost estimates for all individual
activities or work packages so that a cost baseline can be
established for measuring performance.
The baseline includes authorized budgets and contingency reserves,
but excludes management reserves.
7.3 Determine Budget
Challenges For Budgeting In Construction Industry
 Budget / costing need to be decided at very early stage of the
project life cycle with very little room to change latter.
 The compilation and uncertainty of project may result in poor
budget reliability
 Working drawing at initial stage might result in unpractical
budget
 It is difficult to control costs especially for contracts and external
workers if basic construction procedures are followed
 The financing structure is unreasonable if it depends on one
financing channel too much which contributes to the rise of costs
 Most builders do not have relevant systems and processes in
place
Cost Aggregation
Cost estimates at lower level are aggregated or “rolled up” at
higher levels (including control accounts) and then finally for
the entire project.
Outputs
 Cost Baseline : The approved version of the time-phased project
budget excluding management reserves. The management reserves
plus the cost baseline give the project budget.
The baseline is often displayed in the form of an S-curve. Large projects
may have multiple cost baselines.
Determine Budget
Effective cost control requires management of the
approved cost performance baseline (often simply called
the cost baseline or approved budget) and any changes to
that baseline.
7.4 Control Costs
Tools &
Technique
1. Earned Value Management
2. Forecasting (EAC)
3. To-complete Performance index (TCPI)
4. Performance Reviews
5. Performance Management software
6. Reserve Analysis
Outputs
1. Change requests
2. Project Management Plan Updates
3. Work Performance Information
Earned Value Management
Term Definition & Equation
Planned
Value (PV)
Also called Budgeted cost of work scheduled (BCWS)
PV or BCWS = Hourly rate * Total hour planned or
scheduled
Earned
value (EV)
Also called budgeted cost of work performed (BCWP)
EV or BCWP = sum of the planned value of work
completed or Baseline cost * % completed actual
Actual cost
(AC)
Also called actual cost of work performed (ACWP)
AC or ACWP = Sum of all costs actually incurred for the
work completed by the specified date
Term Definition & Equation
(BAC) Budget At Completion- The value of total planned
work, the project cost baseline
Cost
varianc
e (CV)
CV = EV – AC
+Ve = under planned cost, Neutral = on planned cost,
-Ve = over planned cost
Schedu
le
varianc
e(SV)
SV = EV – PV
Positive = ahead of schedule, Neutral = On schedule,
Negative = Behind schedule
Varianc
e at
comple
tion
(VAC)
VAC = BAC – EAC
Positive = Under the planned cost, Neutral = On
planned cost, Negative = Over planned cost
Term Definition & Equation
CPI CPI = EV / AC
Greater than 1 – under planned cost, exactly 1 – on
planned cost, less than 1 – over planned cost
SPI SPI = EV / PV
1< ahead of schedule, exactly 1 – on schedule, 1>
behind schedule
Estimate
at
completi
on (EAC)
1. If the CPI is expected to be the same for the
reminder of the project, EAC can be calculated
using EAC = BAC / CPI
2. If the future work will be accomplished at planned
rate, use EAC = AC + (BAC – EV)
3. If initial plan is no longer valid , use EAC = AC +
Bottom-up ETC
4. If both the CPI and SPI influence the remaining
work , use EAC = AC + [(BAC-EV) / (CPI*SPI)]
Term Definition & Equation
Estimate
to
complete
(ETC)
ETC = EAC – AC
To
complete
performa
nce
index
(TCPI)
1. The efficiency that must be maintained in order to
complete on plan TCPI = (BAC-EV) / (BAC-AC)
2. The efficiency that must be maintained in order to
complete at current EAC TCPI = (BAC-EV) / (EAC-
AC)
Greater than 1 – Harder to complete, Exactly 1 –
Same to complete, Lesser than 1 – Easier to
complete
Trainings by Vidya Bhagwat
08 Quality Management : Gateway For Customer
Satisfaction
Next Chapter

More Related Content

What's hot

COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
Chapter 07 project cost management
Chapter 07 project cost managementChapter 07 project cost management
Chapter 07 project cost managementghizlanejabri
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management EssentialsGlen Alleman
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniquesWissem Amara
 
Cost & value management
Cost & value management Cost & value management
Cost & value management kamariya keyur
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costsharwoodr
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 

What's hot (20)

Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Project Control System
Project Control SystemProject Control System
Project Control System
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Chapter 07 project cost management
Chapter 07 project cost managementChapter 07 project cost management
Chapter 07 project cost management
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost Management
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
 
Project controls
Project controlsProject controls
Project controls
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Project Management 12
Project Management 12Project Management 12
Project Management 12
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
Cost & value management
Cost & value management Cost & value management
Cost & value management
 
Cost management
Cost managementCost management
Cost management
 
Cost management
Cost managementCost management
Cost management
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
 
Cost Control Process for Construction
Cost Control Process for ConstructionCost Control Process for Construction
Cost Control Process for Construction
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 

Viewers also liked

Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - PresentationHassan Rizwan
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsAGC of California
 
PM Unit III - Project Cash Flows
PM   Unit III - Project Cash FlowsPM   Unit III - Project Cash Flows
PM Unit III - Project Cash FlowsGhaith Al Darmaki
 
Reconciliation of Cost & Financial Accounts
Reconciliation of Cost & Financial AccountsReconciliation of Cost & Financial Accounts
Reconciliation of Cost & Financial AccountsDhrumil Shah
 
1 project cash flow
1 project cash flow1 project cash flow
1 project cash flowBhumit Patel
 
Cost Control
Cost ControlCost Control
Cost Controlmudduckk
 
Cost management
Cost managementCost management
Cost managementshkadry
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniquesCjkayes CjKayes
 
Introduction to cost accounting
Introduction to cost accountingIntroduction to cost accounting
Introduction to cost accountingrsingh96
 

Viewers also liked (20)

Schedule Control Report-2
Schedule Control Report-2Schedule Control Report-2
Schedule Control Report-2
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Accounting and Finance
Accounting and FinanceAccounting and Finance
Accounting and Finance
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - Presentation
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction Projects
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
PM Unit III - Project Cash Flows
PM   Unit III - Project Cash FlowsPM   Unit III - Project Cash Flows
PM Unit III - Project Cash Flows
 
Reconciliation of Cost & Financial Accounts
Reconciliation of Cost & Financial AccountsReconciliation of Cost & Financial Accounts
Reconciliation of Cost & Financial Accounts
 
1 project cash flow
1 project cash flow1 project cash flow
1 project cash flow
 
COST CONTROL
COST CONTROLCOST CONTROL
COST CONTROL
 
Cost Control
Cost ControlCost Control
Cost Control
 
Cost control
Cost controlCost control
Cost control
 
Cost management
Cost managementCost management
Cost management
 
Spm unit 1
Spm unit 1Spm unit 1
Spm unit 1
 
Estimation of Cash Flow
Estimation of Cash FlowEstimation of Cash Flow
Estimation of Cash Flow
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniques
 
Spm unit 4
Spm unit 4Spm unit 4
Spm unit 4
 
Spm unit2
Spm unit2Spm unit2
Spm unit2
 
Introduction to cost accounting
Introduction to cost accountingIntroduction to cost accounting
Introduction to cost accounting
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 

Similar to 2.07 cost management 1

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfMadhusha15
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdfzohir khellouf
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع Mohamed Dahi
 

Similar to 2.07 cost management 1 (20)

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 

More from reddvise

Rera highlights
Rera highlightsRera highlights
Rera highlightsreddvise
 
Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )reddvise
 
Silent feature regulation bill act 2016
Silent feature regulation bill act 2016Silent feature regulation bill act 2016
Silent feature regulation bill act 2016reddvise
 
Rera highlights
Rera highlightsRera highlights
Rera highlightsreddvise
 
Real estate regulation bill act 2016
Real estate regulation bill act 2016Real estate regulation bill act 2016
Real estate regulation bill act 2016reddvise
 
Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )reddvise
 
Maha rera overview
Maha rera overviewMaha rera overview
Maha rera overviewreddvise
 
Maharashtra rera act 2017
Maharashtra rera act 2017Maharashtra rera act 2017
Maharashtra rera act 2017reddvise
 
Sims real-estate-young-leadership-program-2
Sims real-estate-young-leadership-program-2Sims real-estate-young-leadership-program-2
Sims real-estate-young-leadership-program-2reddvise
 
Iref hl sims final
Iref hl sims finalIref hl sims final
Iref hl sims finalreddvise
 
Sales -introducation
Sales  -introducationSales  -introducation
Sales -introducationreddvise
 
Marketing -introducation
Marketing  -introducationMarketing  -introducation
Marketing -introducationreddvise
 
Real estate sector over view sims edp
Real estate sector over view  sims edpReal estate sector over view  sims edp
Real estate sector over view sims edpreddvise
 
Entrepreneurship matrix blue print 13
Entrepreneurship matrix blue print 13Entrepreneurship matrix blue print 13
Entrepreneurship matrix blue print 13reddvise
 
1 managing real estate
1 managing real estate1 managing real estate
1 managing real estatereddvise
 
Real estate construction profitability analysis iref virupaksh
Real estate construction profitability analysis iref virupakshReal estate construction profitability analysis iref virupaksh
Real estate construction profitability analysis iref virupakshreddvise
 
Edp real estate services business guidelines
Edp  real estate services business guidelinesEdp  real estate services business guidelines
Edp real estate services business guidelinesreddvise
 
Edp sims business development
Edp sims  business developmentEdp sims  business development
Edp sims business developmentreddvise
 
01 managing real estate srevices business edp sims
01 managing real estate srevices business edp sims01 managing real estate srevices business edp sims
01 managing real estate srevices business edp simsreddvise
 
Lead generation and customer targeting with technology
Lead generation and customer targeting with technologyLead generation and customer targeting with technology
Lead generation and customer targeting with technologyreddvise
 

More from reddvise (20)

Rera highlights
Rera highlightsRera highlights
Rera highlights
 
Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )
 
Silent feature regulation bill act 2016
Silent feature regulation bill act 2016Silent feature regulation bill act 2016
Silent feature regulation bill act 2016
 
Rera highlights
Rera highlightsRera highlights
Rera highlights
 
Real estate regulation bill act 2016
Real estate regulation bill act 2016Real estate regulation bill act 2016
Real estate regulation bill act 2016
 
Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )
 
Maha rera overview
Maha rera overviewMaha rera overview
Maha rera overview
 
Maharashtra rera act 2017
Maharashtra rera act 2017Maharashtra rera act 2017
Maharashtra rera act 2017
 
Sims real-estate-young-leadership-program-2
Sims real-estate-young-leadership-program-2Sims real-estate-young-leadership-program-2
Sims real-estate-young-leadership-program-2
 
Iref hl sims final
Iref hl sims finalIref hl sims final
Iref hl sims final
 
Sales -introducation
Sales  -introducationSales  -introducation
Sales -introducation
 
Marketing -introducation
Marketing  -introducationMarketing  -introducation
Marketing -introducation
 
Real estate sector over view sims edp
Real estate sector over view  sims edpReal estate sector over view  sims edp
Real estate sector over view sims edp
 
Entrepreneurship matrix blue print 13
Entrepreneurship matrix blue print 13Entrepreneurship matrix blue print 13
Entrepreneurship matrix blue print 13
 
1 managing real estate
1 managing real estate1 managing real estate
1 managing real estate
 
Real estate construction profitability analysis iref virupaksh
Real estate construction profitability analysis iref virupakshReal estate construction profitability analysis iref virupaksh
Real estate construction profitability analysis iref virupaksh
 
Edp real estate services business guidelines
Edp  real estate services business guidelinesEdp  real estate services business guidelines
Edp real estate services business guidelines
 
Edp sims business development
Edp sims  business developmentEdp sims  business development
Edp sims business development
 
01 managing real estate srevices business edp sims
01 managing real estate srevices business edp sims01 managing real estate srevices business edp sims
01 managing real estate srevices business edp sims
 
Lead generation and customer targeting with technology
Lead generation and customer targeting with technologyLead generation and customer targeting with technology
Lead generation and customer targeting with technology
 

Recently uploaded

Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 

2.07 cost management 1

  • 1. 7. Project Cost Management Managing Funds Effectively
  • 2. Cost Challenges In Construction Industry Demand Side Challenges : Recession & Falling Demand Supply Side Challenges : Increasing Cost Of Resources Increase In Construction Cost In India
  • 3. Managing Construction Cost Is Critical For Project Success And Company Profitability Pareto's Principle - The 80-20 Rule roughly 80% of the cost management come from effective control of 20% of the causes. Costs Components Approx %** Pre-acquisition costs All costs incurred for aquiring land 10-15 Construction Development and construction costs 40-45 Amenities cost 10-15 Administrative & other Site administration 8-10 Marketing & sales 5-8 Insurance, taxes & regulatory charges 7-10 Allocation of capitalized costs 5-10 **Based on our survey with few builders in Pune for joint venture projects with land owners
  • 4. Costing & Quantity Survey Surveyor plays a critical role in real estate construction project management by supporting project manager for all commercial activities as follows:  Cost planning  Cost estimating  Cost control & monitoring budget  Contracts negotiation  Procurement advice  Preparing bill of quantities (BOQ)  Preparation of payment invoice and certification.  Assessment of variations  Contract dispute resolution  Valuation for insurance purposes Surveyor also helps project manager for preparing feasibility studies, risk management , investment appraisal and auditing
  • 5. Project cost management includes the processes involved in planning, estimating, budgeting, financing, funding, managing and controlling costs so that the project can be completed within the approved budget. Project Cost Management Group 7. Project Cost Management Initiating Planning 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget Executing M&C 7.4 Control Costs Closing
  • 6. It is the process that establishes the policies, procedures and documentation for planning, managing, expending and controlling project costs 7.1 Plan Cost Management Fixed Cost Vs Variable Cost Total Cost = Fixed Cost + Unit Cost X Units Used Direct Costs Vs Indirect Costs
  • 7. Plan Cost Management Cost Management Plan : Also includes  Rules for performance measurement  Organizational procedures links : The WBS component used for the project cost accounting is called control account.  Control Thresholds : Variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. Typically expressed as percentage deviations from the baseline plan
  • 8. Cost estimating involves developing an estimate of the costs of all resources needed to complete the project. The accuracy of estimates tends to improve as a project moves though its life cycle. 7.2 Estimate Costs
  • 9.  Order of magnitude estimates: “Ballpark” estimates without detailed data, done at the feasibility stage for selecting right construction project. The range of accuracy is given as -25 to +75% and would be used for initiating or project approval.  Budget estimates: Based on slightly better data and used to establish initial funding during the early stages of planning. This budget is used for alternative resource analysis and getting funding approval for the project. The range of accuracy is given as -10 to +25%.  Definitive estimates: A bottom-up estimate using estimates of WBS work packages This estimate would be done in the latter stages of planning and be used to establish a cost baseline and monitor spending. It is progressively elaborated. Range of accuracy is -5 to +10%. 7.2 Estimate Costs
  • 10. 7.2 Estimate Costs Inputs 1. Cost Management Plan 2. Scope Baseline 3. Project Schedule 4. Risk Register 5. Human Resource Management Plan 6. EEFs 7. OPAs T & T 1. Expert Judgment 2. Analogous estimating 3. Parametric estimating 4. Bottom-up estimating 5. Three-point estimating 6. Reserve Analysis 7. Cost of Quality 8. Vendor bid Analysis 9. Group decision making techniques Outputs 1. Activity cost Estimates 2. Basis of Estimates 3. Project Documents Updates
  • 11.
  • 12. Reserve Analysis Applied to the base cost to account for uncertainties in quantities, unit costs work elements or other project requirements during construction. requirements for an activity or work item.  Contingency Reserve  It used to manage identified risks  It is estimated based on decision tree method or Expected Monitory Value (EMV)  The project manager has authority to use  Management Reserve  It is used to manage unidentified risks  It is calculated as a percentage of the cost, or time of project  Management approval is required to use management reserve The use of either type of reserve is intended to reduce the chance of a cost overrun Determine Budget
  • 13.  For Small construction projects use Small internal workshops using the Pre-defined Excel workbook  For mid size project use Cost Risk Assessment (CRA) workshops typically held internally  For large projects / programs / portfolio use Cost Estimating and Validation Process (CEVP) workshops which includes external subject matter experts
  • 14. Cost budgeting involves aggregating cost estimates for all individual activities or work packages so that a cost baseline can be established for measuring performance. The baseline includes authorized budgets and contingency reserves, but excludes management reserves. 7.3 Determine Budget
  • 15. Challenges For Budgeting In Construction Industry  Budget / costing need to be decided at very early stage of the project life cycle with very little room to change latter.  The compilation and uncertainty of project may result in poor budget reliability  Working drawing at initial stage might result in unpractical budget  It is difficult to control costs especially for contracts and external workers if basic construction procedures are followed  The financing structure is unreasonable if it depends on one financing channel too much which contributes to the rise of costs  Most builders do not have relevant systems and processes in place
  • 16. Cost Aggregation Cost estimates at lower level are aggregated or “rolled up” at higher levels (including control accounts) and then finally for the entire project.
  • 17.
  • 18. Outputs  Cost Baseline : The approved version of the time-phased project budget excluding management reserves. The management reserves plus the cost baseline give the project budget. The baseline is often displayed in the form of an S-curve. Large projects may have multiple cost baselines. Determine Budget
  • 19.
  • 20. Effective cost control requires management of the approved cost performance baseline (often simply called the cost baseline or approved budget) and any changes to that baseline. 7.4 Control Costs Tools & Technique 1. Earned Value Management 2. Forecasting (EAC) 3. To-complete Performance index (TCPI) 4. Performance Reviews 5. Performance Management software 6. Reserve Analysis Outputs 1. Change requests 2. Project Management Plan Updates 3. Work Performance Information
  • 21. Earned Value Management Term Definition & Equation Planned Value (PV) Also called Budgeted cost of work scheduled (BCWS) PV or BCWS = Hourly rate * Total hour planned or scheduled Earned value (EV) Also called budgeted cost of work performed (BCWP) EV or BCWP = sum of the planned value of work completed or Baseline cost * % completed actual Actual cost (AC) Also called actual cost of work performed (ACWP) AC or ACWP = Sum of all costs actually incurred for the work completed by the specified date
  • 22.
  • 23. Term Definition & Equation (BAC) Budget At Completion- The value of total planned work, the project cost baseline Cost varianc e (CV) CV = EV – AC +Ve = under planned cost, Neutral = on planned cost, -Ve = over planned cost Schedu le varianc e(SV) SV = EV – PV Positive = ahead of schedule, Neutral = On schedule, Negative = Behind schedule Varianc e at comple tion (VAC) VAC = BAC – EAC Positive = Under the planned cost, Neutral = On planned cost, Negative = Over planned cost
  • 24. Term Definition & Equation CPI CPI = EV / AC Greater than 1 – under planned cost, exactly 1 – on planned cost, less than 1 – over planned cost SPI SPI = EV / PV 1< ahead of schedule, exactly 1 – on schedule, 1> behind schedule Estimate at completi on (EAC) 1. If the CPI is expected to be the same for the reminder of the project, EAC can be calculated using EAC = BAC / CPI 2. If the future work will be accomplished at planned rate, use EAC = AC + (BAC – EV) 3. If initial plan is no longer valid , use EAC = AC + Bottom-up ETC 4. If both the CPI and SPI influence the remaining work , use EAC = AC + [(BAC-EV) / (CPI*SPI)]
  • 25. Term Definition & Equation Estimate to complete (ETC) ETC = EAC – AC To complete performa nce index (TCPI) 1. The efficiency that must be maintained in order to complete on plan TCPI = (BAC-EV) / (BAC-AC) 2. The efficiency that must be maintained in order to complete at current EAC TCPI = (BAC-EV) / (EAC- AC) Greater than 1 – Harder to complete, Exactly 1 – Same to complete, Lesser than 1 – Easier to complete
  • 26. Trainings by Vidya Bhagwat 08 Quality Management : Gateway For Customer Satisfaction Next Chapter