SlideShare a Scribd company logo
PROJECT MANAGEMENT
 CPM & PERT TECHNIQUES
FLOW OF PRESENTATION




 INTRODUCTION
 NETWORK PLANNING
 ESTIMATING TIME
 CPM
 PERT
Project Management



Project
• A project is an interrelated set of activities that has a definite
   starting and ending point and that results in a unique product
   or service.

Project management
• Project management is a scientific way of planning, implementing,
   monitoring & controlling the various aspects of a project such as time,
   money, materials, manpower & other resources.
Network Planning Methods



    Methods used for network planning are:
       CPM
       PERT

    Managing a project with network planning methods involves four steps:

1.   Describing the Project.
2.   Diagramming the Network.
3.   Estimating time of completion.
4.   Monitoring Project Progress.
Network Diagram



Concepts
• Activity
• Precedence relationship
• Successor
• Event
Guidelines for network diagram




1.   Before an activity can begin, its preceding
     activities must be completed.
2.   Arrows indicate logical precedence.
3.   Flow of the diagram is from left to right.
4.   Arrows should not intersect.
5.   Dangling should be avoided.
APPRAOCHES FOR
                                   NETWORK DIAGRAM



ACTIVITY ON ARC(AOA):
• Uses arcs to represent activities and nodes
  to represent events.
• It is Event Oriented.
                     3



         1     2                    6     7     8




                         4   5
DUMMY ACTIVITY

    AOA approach requires the addition of a                Dummy
    Activity to clarify the precedence relationships     between
    the two activities. It is a zero time activity and
    consumes no resources.

Dummy Activity is used in two situations:
1) When two or more activities start and end at the same
   nodes
                                 1             3



                                           2
2) When two or more activities share the same
   precedence activity but not all the precedence are
   shared.

                 1       3       5

                                           7

                 2       4           6
ACTIVITY ON NODE(AON):


Uses nodes to represent activities and arcs indicate
precedence relationships between       them.
It is Activity Oriented.
ESTIMATING TIME
                                                      OF
                                                  COMPLETION

Planning the schedule of the project

Time estimates include:
1)   Total time for completion.
2)    ES- Earliest start time: the earliest time at which the activity
     can start given that its precedent activities must be completed first.

3)   EF-Earliest finish time: equals to the earliest start time for the activity
     plus the time required to complete the activity.

4)   LF- Latest finish time: the latest time in which the activity can be
     completed without delaying the project.

5)   LS- Latest start time: equal to the latest finish time minus the time
     required to complete the activity.
6)   FORWARD PASS:
     The early start and early finish times are calculated by
     moving forward through the network and considering the
     predecessor activities Considers maximum

7)   BACKWARD PASS:
     The latest start and finish times are calculated by moving backward through the
     network.
     Considers minimum

8)   SLACK TIME:
     Slack time for an activity is the difference between its earliest and latest start
     time or between the earliest and latest finish time.
     Critical path is the path of activities having zero Slack time.
A Simple Project




Activity    Immediate      Expected
           Predecessor       Time
   A            -              5
   B            -             6
   C           A              4
   D          A, B            2
Precedence Diagram
ES      Earliest Starting (time)
EF      Earliest Finishing
LS      Latest Starting
LF      Latest Finishing
Slack   Difference Time
CRITICAL PATH
                                         METHODS(CPM)

HISTORY :
  It was developed by J.E.KELLY of REMINGTON-RAND
  and M.R.WALKER of DU PONT and the emphasis was
  on the trade-off between the cost of project and its overall
  completion time. The first test was made in 1958,when CPM
  was applied to the construction of a new chemical plant.

DEFINITION:
  Critical path is the sequence of activities between a project’s
  start and finish that takes the longest time to complete.
STEPS IN DETERMINING
                                      CRITICAL PATH


• Specify the individual activities.

• Determine the sequence of the activities.

• Draw the network diagram.

• Estimate the activity completion time.

• Identify the critical path.

• Update the CPM diagram.
Activit Preceden Normal time   Normal
y       ce       (week)        Cost (Rs)


A         -            3       300
B         A            3       30
C         A            7       420
D         A            9       720
E         D            5       250
F       B,C,E          6       320
G         F            4       400
H         F           13       780
I         G           10       1000
Total                          4220
4           7




1   2       5   6




        3
                    8
Overhead cost as per the given data- Rs.50
Paths in the network diagram :
A-D-F-G-I = 32
A-D-F-H = 31
A-C-F-H = 29
A-C-F-G-I = 30
A-B-E-F-H = 30
A-B-E-F-G-I = 31
Critical path – A-D-F-G-I = 32
             4             7




  1      2             6
                 5


             3
                           8
TIME ESTIMATES


o Optimistic time (to) – It is the shortest time     in which the
   activity can be completed.
o Most likely time (tm) – It is the probable time
   required to perform the activity.
o Pessimistic time (tp) – It is the longest estimated time
   required to perform an activity.
o Expected time
  te = to + 4tm + tp
                6
STEPS IN PERT

1.   Identify the specific activities.

2.   Determine proper sequence of the activities.

3.   Construct the network diagram.

4.   Estimate the time required for each activity.

5.   Determine the critical path.

6.   Update the PERT chart.
Activity   Descrip Preced    Optimis Most      Pessimi Expecte
           tion    ence      tic time Likely   stic    d time
                                      time     time

A          Initial      -      12       16       26      17
           design
B          Survey      A        6        9       18      10
           market
C          Build       A        8       10       18      11
           prototype
D          Test        C        2        3       4       3
           prototype
E          Redesign    B,D      3        4       11      5
           ing
F          Market      E        6        8       10      8
           testing
G          Set up      F       15       20       25      20
           productio
           n
1   2       4      5      6       7




        3


                 A-B-E-F-G = 60
        A-C-D-E-F-G = 64 (CRITICAL PATH)
Advantages of PERT


• Expected project completion time.

• Probability of completion before a specified date.

• The critical path activities that directly impact the completion
  time.

• The activities that have slack time and that can lend resources
  to critical path activities.

• Activity start and end dates.
LIMITATIONS

• The PERT Formula Requires Too Much Work.
• The network charts tend to be large and unwieldy.
• Calculating the time estimates is very complex for all the
  activities.
• Updating of the project is time consuming and requires high
  costs.
• Emphasis is laid only on time factors and cost factors are
  neglected.
Difference between
                                            CPM & PERT

               CPM                                  PERT
• CPM works with fixed               • PERT works with probabilistic
deterministic time                   time
• CPM is useful for repetitive and   • PERT is useful for non repetitive
non complex projects with a          and complex projects with
certain degree of time estimates.    uncertain time estimates.

• CPM includes time-cost trade off. • PERT is restricted to time
                                     variable.

• CPM- for construction projects.    • PERT- used for R&D programs.
Thank You…

More Related Content

What's hot

Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
Vikram Thadeshvar
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Mr. Ramesh Nayaka
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
Ishan Gandhi
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
student
 
Project planning
Project planning Project planning
Project planning
Dipnarayan Thakur
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
Pulchowk Campus
 
Project organisation structure
Project organisation structureProject organisation structure
Project organisation structure
sachin kumar sharma
 
Project Formulation
Project FormulationProject Formulation
Project Formulation
Simranpreet Singh
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
Venugopal Venkatachalapathy
 
Introduction to Operations Research
Introduction to Operations ResearchIntroduction to Operations Research
Introduction to Operations Research
Victor Seelan
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
hoang tung
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
Ragjni Govindaraju
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 
Project appraisal
Project appraisalProject appraisal
Project appraisal
Rajesh Adatravu
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
Jeff Hilton
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
salsa moyara
 
Payback timevalue of money and iir
Payback timevalue of money and iirPayback timevalue of money and iir
Payback timevalue of money and iir
Subhash Rohit
 
Project life cycle costing
Project life cycle costing Project life cycle costing
Project life cycle costing
Shashikumar_chari
 

What's hot (20)

Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Project planning
Project planning Project planning
Project planning
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Project organisation structure
Project organisation structureProject organisation structure
Project organisation structure
 
Project Formulation
Project FormulationProject Formulation
Project Formulation
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
Introduction to Operations Research
Introduction to Operations ResearchIntroduction to Operations Research
Introduction to Operations Research
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Project appraisal
Project appraisalProject appraisal
Project appraisal
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Payback timevalue of money and iir
Payback timevalue of money and iirPayback timevalue of money and iir
Payback timevalue of money and iir
 
Project life cycle costing
Project life cycle costing Project life cycle costing
Project life cycle costing
 

Viewers also liked

Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
Institute of Rural Management
 
Social Cost Benefi Analysis
Social Cost Benefi AnalysisSocial Cost Benefi Analysis
Social Cost Benefi Analysis
Ankita Bharti
 
Pert cpm
Pert cpmPert cpm
Pert cpm
Jyoti Mamtani
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
Abhishek Pachisia
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniques
Cjkayes CjKayes
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 
Om edit
Om editOm edit
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pert
djoufack
 
Pert & cpm
Pert & cpmPert & cpm
Pert & cpm
Moudud Hasan
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Mohan Kumar G
 
Social Cost Benefit Analysis
Social Cost Benefit AnalysisSocial Cost Benefit Analysis
Social Cost Benefit Analysis
Saurabh Sood
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
J. Scott Christianson
 
Delhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni ChannelDelhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni Channel
DelhiQuery
 
E logistics
E logisticsE logistics
E logistics
Tigani Suliman
 
16319859 Indian Logistics Industry
16319859 Indian Logistics Industry16319859 Indian Logistics Industry
16319859 Indian Logistics Industry
Sunil Singh
 
E logistics
E logisticsE logistics
E logistics
Amit Upadhye
 
Gati : eCommerce and Logistics
Gati : eCommerce and LogisticsGati : eCommerce and Logistics
Gati : eCommerce and Logistics
eTailing India
 
Snapdeal vs amazon
Snapdeal vs amazonSnapdeal vs amazon
Snapdeal vs amazon
Sparsh Bansal
 
Logistics and ecommerce in india and china
Logistics and ecommerce in india and chinaLogistics and ecommerce in india and china
Logistics and ecommerce in india and china
Kaushik Raja
 
E-Logisitics PPT
E-Logisitics PPTE-Logisitics PPT
E-Logisitics PPT
Parixit Dwivedi
 

Viewers also liked (20)

Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Social Cost Benefi Analysis
Social Cost Benefi AnalysisSocial Cost Benefi Analysis
Social Cost Benefi Analysis
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniques
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Om edit
Om editOm edit
Om edit
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pert
 
Pert & cpm
Pert & cpmPert & cpm
Pert & cpm
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
 
Social Cost Benefit Analysis
Social Cost Benefit AnalysisSocial Cost Benefit Analysis
Social Cost Benefit Analysis
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
 
Delhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni ChannelDelhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni Channel
 
E logistics
E logisticsE logistics
E logistics
 
16319859 Indian Logistics Industry
16319859 Indian Logistics Industry16319859 Indian Logistics Industry
16319859 Indian Logistics Industry
 
E logistics
E logisticsE logistics
E logistics
 
Gati : eCommerce and Logistics
Gati : eCommerce and LogisticsGati : eCommerce and Logistics
Gati : eCommerce and Logistics
 
Snapdeal vs amazon
Snapdeal vs amazonSnapdeal vs amazon
Snapdeal vs amazon
 
Logistics and ecommerce in india and china
Logistics and ecommerce in india and chinaLogistics and ecommerce in india and china
Logistics and ecommerce in india and china
 
E-Logisitics PPT
E-Logisitics PPTE-Logisitics PPT
E-Logisitics PPT
 

Similar to Pert & cpm project management

Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
kongara
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
Deepak Paithankar
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
AaliButt1
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
AynetuTerefe2
 
Cpmprt
CpmprtCpmprt
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
IIMSE Edu
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
Dr. Divya Khandelwal
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
Sougata Das
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
JerryHung19
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
Ahmad Basim Hamza
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
albert937613
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
Akihisa Akimoto
 
Project management
Project managementProject management
Project management
Kwesi Kissiedu
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
Shadina Shah
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
DejeneDay
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
sitinorhafizabintiab1
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
MdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
MdSabujHossen2
 

Similar to Pert & cpm project management (20)

Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Project management
Project managementProject management
Project management
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 

Recently uploaded

How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
Lacey Max
 
2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
aragme
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
SEOSMMEARTH
 
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
Stephen Cashman
 
Building Your Employer Brand with Social Media
Building Your Employer Brand with Social MediaBuilding Your Employer Brand with Social Media
Building Your Employer Brand with Social Media
LuanWise
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Neil Horowitz
 
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
46adnanshahzad
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
AnnySerafinaLove
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
Chandresh Chudasama
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
my Pandit
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
ecamare2
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
JeremyPeirce1
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
Adnet Communications
 
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfThe 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
thesiliconleaders
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
NZSG
 
How to Implement a Real Estate CRM Software
How to Implement a Real Estate CRM SoftwareHow to Implement a Real Estate CRM Software
How to Implement a Real Estate CRM Software
SalesTown
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Holger Mueller
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
ssuser567e2d
 

Recently uploaded (20)

How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
 
2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
 
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
 
Building Your Employer Brand with Social Media
Building Your Employer Brand with Social MediaBuilding Your Employer Brand with Social Media
Building Your Employer Brand with Social Media
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
 
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
 
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfThe 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
 
How to Implement a Real Estate CRM Software
How to Implement a Real Estate CRM SoftwareHow to Implement a Real Estate CRM Software
How to Implement a Real Estate CRM Software
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
 

Pert & cpm project management

  • 1. PROJECT MANAGEMENT CPM & PERT TECHNIQUES
  • 2. FLOW OF PRESENTATION  INTRODUCTION  NETWORK PLANNING  ESTIMATING TIME  CPM  PERT
  • 3. Project Management Project • A project is an interrelated set of activities that has a definite starting and ending point and that results in a unique product or service. Project management • Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
  • 4. Network Planning Methods  Methods used for network planning are: CPM PERT  Managing a project with network planning methods involves four steps: 1. Describing the Project. 2. Diagramming the Network. 3. Estimating time of completion. 4. Monitoring Project Progress.
  • 5. Network Diagram Concepts • Activity • Precedence relationship • Successor • Event
  • 6. Guidelines for network diagram 1. Before an activity can begin, its preceding activities must be completed. 2. Arrows indicate logical precedence. 3. Flow of the diagram is from left to right. 4. Arrows should not intersect. 5. Dangling should be avoided.
  • 7. APPRAOCHES FOR NETWORK DIAGRAM ACTIVITY ON ARC(AOA): • Uses arcs to represent activities and nodes to represent events. • It is Event Oriented. 3 1 2 6 7 8 4 5
  • 8. DUMMY ACTIVITY AOA approach requires the addition of a Dummy Activity to clarify the precedence relationships between the two activities. It is a zero time activity and consumes no resources. Dummy Activity is used in two situations: 1) When two or more activities start and end at the same nodes 1 3 2
  • 9. 2) When two or more activities share the same precedence activity but not all the precedence are shared. 1 3 5 7 2 4 6
  • 10. ACTIVITY ON NODE(AON): Uses nodes to represent activities and arcs indicate precedence relationships between them. It is Activity Oriented.
  • 11. ESTIMATING TIME OF COMPLETION Planning the schedule of the project Time estimates include: 1) Total time for completion. 2) ES- Earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first. 3) EF-Earliest finish time: equals to the earliest start time for the activity plus the time required to complete the activity. 4) LF- Latest finish time: the latest time in which the activity can be completed without delaying the project. 5) LS- Latest start time: equal to the latest finish time minus the time required to complete the activity.
  • 12. 6) FORWARD PASS: The early start and early finish times are calculated by moving forward through the network and considering the predecessor activities Considers maximum 7) BACKWARD PASS: The latest start and finish times are calculated by moving backward through the network. Considers minimum 8) SLACK TIME: Slack time for an activity is the difference between its earliest and latest start time or between the earliest and latest finish time. Critical path is the path of activities having zero Slack time.
  • 13. A Simple Project Activity Immediate Expected Predecessor Time A - 5 B - 6 C A 4 D A, B 2
  • 15. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Difference Time
  • 16.
  • 17. CRITICAL PATH METHODS(CPM) HISTORY : It was developed by J.E.KELLY of REMINGTON-RAND and M.R.WALKER of DU PONT and the emphasis was on the trade-off between the cost of project and its overall completion time. The first test was made in 1958,when CPM was applied to the construction of a new chemical plant. DEFINITION: Critical path is the sequence of activities between a project’s start and finish that takes the longest time to complete.
  • 18. STEPS IN DETERMINING CRITICAL PATH • Specify the individual activities. • Determine the sequence of the activities. • Draw the network diagram. • Estimate the activity completion time. • Identify the critical path. • Update the CPM diagram.
  • 19. Activit Preceden Normal time Normal y ce (week) Cost (Rs) A - 3 300 B A 3 30 C A 7 420 D A 9 720 E D 5 250 F B,C,E 6 320 G F 4 400 H F 13 780 I G 10 1000 Total 4220
  • 20. 4 7 1 2 5 6 3 8
  • 21. Overhead cost as per the given data- Rs.50 Paths in the network diagram : A-D-F-G-I = 32 A-D-F-H = 31 A-C-F-H = 29 A-C-F-G-I = 30 A-B-E-F-H = 30 A-B-E-F-G-I = 31
  • 22. Critical path – A-D-F-G-I = 32 4 7 1 2 6 5 3 8
  • 23. TIME ESTIMATES o Optimistic time (to) – It is the shortest time in which the activity can be completed. o Most likely time (tm) – It is the probable time required to perform the activity. o Pessimistic time (tp) – It is the longest estimated time required to perform an activity. o Expected time te = to + 4tm + tp 6
  • 24. STEPS IN PERT 1. Identify the specific activities. 2. Determine proper sequence of the activities. 3. Construct the network diagram. 4. Estimate the time required for each activity. 5. Determine the critical path. 6. Update the PERT chart.
  • 25. Activity Descrip Preced Optimis Most Pessimi Expecte tion ence tic time Likely stic d time time time A Initial - 12 16 26 17 design B Survey A 6 9 18 10 market C Build A 8 10 18 11 prototype D Test C 2 3 4 3 prototype E Redesign B,D 3 4 11 5 ing F Market E 6 8 10 8 testing G Set up F 15 20 25 20 productio n
  • 26. 1 2 4 5 6 7 3 A-B-E-F-G = 60 A-C-D-E-F-G = 64 (CRITICAL PATH)
  • 27. Advantages of PERT • Expected project completion time. • Probability of completion before a specified date. • The critical path activities that directly impact the completion time. • The activities that have slack time and that can lend resources to critical path activities. • Activity start and end dates.
  • 28. LIMITATIONS • The PERT Formula Requires Too Much Work. • The network charts tend to be large and unwieldy. • Calculating the time estimates is very complex for all the activities. • Updating of the project is time consuming and requires high costs. • Emphasis is laid only on time factors and cost factors are neglected.
  • 29. Difference between CPM & PERT CPM PERT • CPM works with fixed • PERT works with probabilistic deterministic time time • CPM is useful for repetitive and • PERT is useful for non repetitive non complex projects with a and complex projects with certain degree of time estimates. uncertain time estimates. • CPM includes time-cost trade off. • PERT is restricted to time variable. • CPM- for construction projects. • PERT- used for R&D programs.