This document provides an overview of network models and summarizes key concepts related to PERT and CPM techniques. Some key points:
- Network models consist of nodes and connecting lines that can be used to model a variety of problems. PERT and CPM are two widely used network techniques.
- PERT was developed for project planning under uncertainty. CPM focuses on tradeoffs between time and cost. Both use the same calculations but differ in time estimation approaches.
- Critical paths identify the minimum time needed to complete a project. Activities on the critical path must be carefully managed to avoid delays. Non-critical activities have slack time and can be delayed without impacting the project completion date.
Enterprise Excellence is Inclusive Excellence.pdfKaiNexus
Enterprise excellence and inclusive excellence are closely linked, and real-world challenges have shown that both are essential to the success of any organization. To achieve enterprise excellence, organizations must focus on improving their operations and processes while creating an inclusive environment that engages everyone. In this interactive session, the facilitator will highlight commonly established business practices and how they limit our ability to engage everyone every day. More importantly, though, participants will likely gain increased awareness of what we can do differently to maximize enterprise excellence through deliberate inclusion.
What is Enterprise Excellence?
Enterprise Excellence is a holistic approach that's aimed at achieving world-class performance across all aspects of the organization.
What might I learn?
A way to engage all in creating Inclusive Excellence. Lessons from the US military and their parallels to the story of Harry Potter. How belt systems and CI teams can destroy inclusive practices. How leadership language invites people to the party. There are three things leaders can do to engage everyone every day: maximizing psychological safety to create environments where folks learn, contribute, and challenge the status quo.
Who might benefit? Anyone and everyone leading folks from the shop floor to top floor.
Dr. William Harvey is a seasoned Operations Leader with extensive experience in chemical processing, manufacturing, and operations management. At Michelman, he currently oversees multiple sites, leading teams in strategic planning and coaching/practicing continuous improvement. William is set to start his eighth year of teaching at the University of Cincinnati where he teaches marketing, finance, and management. William holds various certifications in change management, quality, leadership, operational excellence, team building, and DiSC, among others.
Premium MEAN Stack Development Solutions for Modern BusinessesSynapseIndia
Stay ahead of the curve with our premium MEAN Stack Development Solutions. Our expert developers utilize MongoDB, Express.js, AngularJS, and Node.js to create modern and responsive web applications. Trust us for cutting-edge solutions that drive your business growth and success.
Know more: https://www.synapseindia.com/technology/mean-stack-development-company.html
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxmy Pandit
Explore the world of the Taurus zodiac sign. Learn about their stability, determination, and appreciation for beauty. Discover how Taureans' grounded nature and hardworking mindset define their unique personality.
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...PaulBryant58
This article provides a comprehensive guide on how to
effectively manage the convert Accpac to QuickBooks , with a particular focus on utilizing online accounting services to streamline the process.
What are the main advantages of using HR recruiter services.pdfHumanResourceDimensi1
HR recruiter services offer top talents to companies according to their specific needs. They handle all recruitment tasks from job posting to onboarding and help companies concentrate on their business growth. With their expertise and years of experience, they streamline the hiring process and save time and resources for the company.
Skye Residences | Extended Stay Residences Near Toronto Airportmarketingjdass
Experience unparalleled EXTENDED STAY and comfort at Skye Residences located just minutes from Toronto Airport. Discover sophisticated accommodations tailored for discerning travelers.
Website Link :
https://skyeresidences.com/
https://skyeresidences.com/about-us/
https://skyeresidences.com/gallery/
https://skyeresidences.com/rooms/
https://skyeresidences.com/near-by-attractions/
https://skyeresidences.com/commute/
https://skyeresidences.com/contact/
https://skyeresidences.com/queen-suite-with-sofa-bed/
https://skyeresidences.com/queen-suite-with-sofa-bed-and-balcony/
https://skyeresidences.com/queen-suite-with-sofa-bed-accessible/
https://skyeresidences.com/2-bedroom-deluxe-queen-suite-with-sofa-bed/
https://skyeresidences.com/2-bedroom-deluxe-king-queen-suite-with-sofa-bed/
https://skyeresidences.com/2-bedroom-deluxe-queen-suite-with-sofa-bed-accessible/
#Skye Residences Etobicoke, #Skye Residences Near Toronto Airport, #Skye Residences Toronto, #Skye Hotel Toronto, #Skye Hotel Near Toronto Airport, #Hotel Near Toronto Airport, #Near Toronto Airport Accommodation, #Suites Near Toronto Airport, #Etobicoke Suites Near Airport, #Hotel Near Toronto Pearson International Airport, #Toronto Airport Suite Rentals, #Pearson Airport Hotel Suites
"𝑩𝑬𝑮𝑼𝑵 𝑾𝑰𝑻𝑯 𝑻𝑱 𝑰𝑺 𝑯𝑨𝑳𝑭 𝑫𝑶𝑵𝑬"
𝐓𝐉 𝐂𝐨𝐦𝐬 (𝐓𝐉 𝐂𝐨𝐦𝐦𝐮𝐧𝐢𝐜𝐚𝐭𝐢𝐨𝐧𝐬) is a professional event agency that includes experts in the event-organizing market in Vietnam, Korea, and ASEAN countries. We provide unlimited types of events from Music concerts, Fan meetings, and Culture festivals to Corporate events, Internal company events, Golf tournaments, MICE events, and Exhibitions.
𝐓𝐉 𝐂𝐨𝐦𝐬 provides unlimited package services including such as Event organizing, Event planning, Event production, Manpower, PR marketing, Design 2D/3D, VIP protocols, Interpreter agency, etc.
Sports events - Golf competitions/billiards competitions/company sports events: dynamic and challenging
⭐ 𝐅𝐞𝐚𝐭𝐮𝐫𝐞𝐝 𝐩𝐫𝐨𝐣𝐞𝐜𝐭𝐬:
➢ 2024 BAEKHYUN [Lonsdaleite] IN HO CHI MINH
➢ SUPER JUNIOR-L.S.S. THE SHOW : Th3ee Guys in HO CHI MINH
➢FreenBecky 1st Fan Meeting in Vietnam
➢CHILDREN ART EXHIBITION 2024: BEYOND BARRIERS
➢ WOW K-Music Festival 2023
➢ Winner [CROSS] Tour in HCM
➢ Super Show 9 in HCM with Super Junior
➢ HCMC - Gyeongsangbuk-do Culture and Tourism Festival
➢ Korean Vietnam Partnership - Fair with LG
➢ Korean President visits Samsung Electronics R&D Center
➢ Vietnam Food Expo with Lotte Wellfood
"𝐄𝐯𝐞𝐫𝐲 𝐞𝐯𝐞𝐧𝐭 𝐢𝐬 𝐚 𝐬𝐭𝐨𝐫𝐲, 𝐚 𝐬𝐩𝐞𝐜𝐢𝐚𝐥 𝐣𝐨𝐮𝐫𝐧𝐞𝐲. 𝐖𝐞 𝐚𝐥𝐰𝐚𝐲𝐬 𝐛𝐞𝐥𝐢𝐞𝐯𝐞 𝐭𝐡𝐚𝐭 𝐬𝐡𝐨𝐫𝐭𝐥𝐲 𝐲𝐨𝐮 𝐰𝐢𝐥𝐥 𝐛𝐞 𝐚 𝐩𝐚𝐫𝐭 𝐨𝐟 𝐨𝐮𝐫 𝐬𝐭𝐨𝐫𝐢𝐞𝐬."
3.0 Project 2_ Developing My Brand Identity Kit.pptxtanyjahb
A personal brand exploration presentation summarizes an individual's unique qualities and goals, covering strengths, values, passions, and target audience. It helps individuals understand what makes them stand out, their desired image, and how they aim to achieve it.
Putting the SPARK into Virtual Training.pptxCynthia Clay
This 60-minute webinar, sponsored by Adobe, was delivered for the Training Mag Network. It explored the five elements of SPARK: Storytelling, Purpose, Action, Relationships, and Kudos. Knowing how to tell a well-structured story is key to building long-term memory. Stating a clear purpose that doesn't take away from the discovery learning process is critical. Ensuring that people move from theory to practical application is imperative. Creating strong social learning is the key to commitment and engagement. Validating and affirming participants' comments is the way to create a positive learning environment.
Memorandum Of Association Constitution of Company.pptseri bangash
www.seribangash.com
A Memorandum of Association (MOA) is a legal document that outlines the fundamental principles and objectives upon which a company operates. It serves as the company's charter or constitution and defines the scope of its activities. Here's a detailed note on the MOA:
Contents of Memorandum of Association:
Name Clause: This clause states the name of the company, which should end with words like "Limited" or "Ltd." for a public limited company and "Private Limited" or "Pvt. Ltd." for a private limited company.
https://seribangash.com/article-of-association-is-legal-doc-of-company/
Registered Office Clause: It specifies the location where the company's registered office is situated. This office is where all official communications and notices are sent.
Objective Clause: This clause delineates the main objectives for which the company is formed. It's important to define these objectives clearly, as the company cannot undertake activities beyond those mentioned in this clause.
www.seribangash.com
Liability Clause: It outlines the extent of liability of the company's members. In the case of companies limited by shares, the liability of members is limited to the amount unpaid on their shares. For companies limited by guarantee, members' liability is limited to the amount they undertake to contribute if the company is wound up.
https://seribangash.com/promotors-is-person-conceived-formation-company/
Capital Clause: This clause specifies the authorized capital of the company, i.e., the maximum amount of share capital the company is authorized to issue. It also mentions the division of this capital into shares and their respective nominal value.
Association Clause: It simply states that the subscribers wish to form a company and agree to become members of it, in accordance with the terms of the MOA.
Importance of Memorandum of Association:
Legal Requirement: The MOA is a legal requirement for the formation of a company. It must be filed with the Registrar of Companies during the incorporation process.
Constitutional Document: It serves as the company's constitutional document, defining its scope, powers, and limitations.
Protection of Members: It protects the interests of the company's members by clearly defining the objectives and limiting their liability.
External Communication: It provides clarity to external parties, such as investors, creditors, and regulatory authorities, regarding the company's objectives and powers.
https://seribangash.com/difference-public-and-private-company-law/
Binding Authority: The company and its members are bound by the provisions of the MOA. Any action taken beyond its scope may be considered ultra vires (beyond the powers) of the company and therefore void.
Amendment of MOA:
While the MOA lays down the company's fundamental principles, it is not entirely immutable. It can be amended, but only under specific circumstances and in compliance with legal procedures. Amendments typically require shareholder
Remote sensing and monitoring are changing the mining industry for the better. These are providing innovative solutions to long-standing challenges. Those related to exploration, extraction, and overall environmental management by mining technology companies Odisha. These technologies make use of satellite imaging, aerial photography and sensors to collect data that might be inaccessible or from hazardous locations. With the use of this technology, mining operations are becoming increasingly efficient. Let us gain more insight into the key aspects associated with remote sensing and monitoring when it comes to mining.
Unveiling the Secrets How Does Generative AI Work.pdfSam H
At its core, generative artificial intelligence relies on the concept of generative models, which serve as engines that churn out entirely new data resembling their training data. It is like a sculptor who has studied so many forms found in nature and then uses this knowledge to create sculptures from his imagination that have never been seen before anywhere else. If taken to cyberspace, gans work almost the same way.
2. Introduction
• Network models consists of a set of circles, or nodes, and
lines, which are referred to as either arcs or branches, that
connect some nodes to other nodes
• Networks are important tools of management science
• Not only can networks be used to model a wide variety of
problems, they can often solved more easily than other
models of the same problem, and they present models in a
visual format
2
3. NETWORK TECHNIQUES
PERT CPM
PERT(Program Evaluation and
Review Technique)
- Developed by the US Navy with Booz
Hamilton Lockheed on the Polaris
Missile/Submarine
program 1958
CPM (Critical Path Method)
-Developed by El Du Pont for
Chemical Plant Shutdown
Project- about same time as
PERT
Similarity: Both use same calculations, almost similar
Difference: Main difference is probabilistic and
deterministic in time estimation
3
4. History
PERT was developed by the US Navy for the planning and control
of the Polaris missile program and the emphasis was on completing
the program in the shortest possible time. In addition PERT
had the ability to cope with uncertain activity completion
times (e.g. for a particular activity the most likely completion time
is 4 weeks but it could be anywhere between 3 weeks and 8 weeks).
CPM was developed by Du Pont and the emphasis was on the
trade-off between the cost of the project and its overall
completion time (e.g. for certain activities it may be possible to
decrease their completion times by spending more money - how
does this affect the overall completion time of the project?)
4
5. PERT and CPM
• PERT and CPM are the two most widely used techniques for
planning and coordinating large-scale projects
• By using PERT and CPM, mangers are able to obtain:
1. A graphical display of project activities
2. An estimate of how long the project will take
3. An indication of which activities are the most critical to
timely completion of the project
4. An indication of how long any activity can be delayed with
out lengthening the project
5
6. PERT and CPM
• PERT and CPM are best applied in Project Scheduling
• “A project is a series of activities directed to
accomplishment of a desired objective”
• “Schedule converts action plan into operating time table”
6
7. PERT and CPM
In CPM activities are shown as a network of precedence
relationships using activity-on-node network construction
– Single estimate of activity time
– Deterministic activity times
Used in : Production management - for the jobs
of repetitive in nature where the activity time
estimates can be predicted with considerable
certainty due to the existence of past experience.
7
8. PERT and CPM
In PERT activities are shown as a network of precedence
relationships using activity-on-arrow network construction
– Multiple time estimates
– Probabilistic activity times
Used in : Project management - for non-repetitive
jobs (research and development work), where the time
and cost estimates tend to be quite uncertain. This
technique uses probabilistic time estimates.
8
9. Gantt Chart
• The Gantt Chart is a popular tool for planning and
scheduling simple projects
• It enables managers to initially schedule project
activities and, then, to monitor progress over time by
comparing planned progress to actual progress
• Even though Gantt Chart is simple to use, it may
delay the project completion time as activities could
not start until the preceding activity was completed.
9
10. Originated by H.L.Gantt in 1918
Gantt Chart
Advantages
- Gantt charts are quite commonly used.
- They provide an easy graphical
representation of when activities
(might) take place.
Limitations
- Do not clearly indicate details regarding
the progress of activities
- Do not give a clear indication of
interrelationship between the separate
activities 10
11. • Some objectives of project scheduling include:
– Completing the project as early as possible by determining an
earliest start and finish time for each of the activities
– Determining the likelihood a project will be completed within a
certain time period
– Finding a minimum cost schedule that completes the project by a
certain date
– Finding a minimum time to complete a project within budget
restrictions
– Investigating the results of possible delays in one or more of an
activity’s completion time
– Evaluating the costs and benefits of reducing the time of
performing one or more of the activities
11
12. • Graphical portrayal of activities and event
• Shows dependency relationships between tasks/activities in
a project
• Clearly shows tasks that must precede (precedence) or follow
(succeeding) other tasks in a logical manner
• Clear representation of plan – a powerful tool for planning
and controlling project
Network
12
15. Definition of terms in a network
• Activity : any portions of project (tasks) which required
by project, uses up resource and consumes
time – may involve labor, paper work,
contractual negotiations, machinery operations
• Event : beginning or ending points of one or more
activities, instantaneous point in time, also
called ‘nodes’
• Network : Combination of all project activities and the events
successor
activity
Preceding
Activity
Event
15
16. Emphasis on Logic in Network Construction
• Construction of network should be based on logical or technical
dependencies among activities
• Example - before activity ‘Approve Drawing’ can be started the
activity ‘Prepare Drawing’ must be completed
• Common error – build network on the basis of time logic (a feeling
for proper sequence ) see example below
WRONG X
CORRECT
16
17. Example 1- A simple network
Consider the list of four activities for making a simple product:
Activity Description Immediate
predecessors
A Buy Plastic Body -
B Design Component -
C Make Component B
D Assemble product A,C
Immediate predecessors for a particular activity are the activities
that, when completed, enable the start of the activity in question.
17
18. Network of Four Activities
1 3 4
2
A
B C
D
Arcs indicate project activities
Nodes correspond to the beginning
and ending of activities
The above graphical representation is referred to as the PERT/CPM network
18
19. Sequence of activities
• One can start work on activities A and B anytime, since
neither of these activities depends upon the completion of
prior activities.
• Activity C cannot be started until activity B has been
completed
• Activity D cannot be started until both activities A and
C have been completed.
19
20. Example 2
Develop the network for a project with following activities and
immediate predecessors:
Activity Immediate
predecessors
A -
B -
C B
D A, C
E C
F C
G D,E,F
Class Activity: Try to do network for the first five (A,B,C,D,E) activities
20
21. Network of first five activities
1 3 4
2
A
B
C
D
5
E
We need to introduce
a dummy activity
21
22. •Note how the network correctly identifies D, E, and F as the immediate
predecessors for activity G.
•Dummy activities is used to identify precedence relationships correctly and to
eliminate possible confusion of two or more activities having the same starting and
ending nodes
•Dummy activities have no resources (time, labor, machinery, etc) – purpose is to
preserve logic of the network
Network of all the Seven Activities
1 3 4
2
A
B
C
D
5
E
7
6
F
G
dummy
22
23. Examples of the use of dummy activity
Dummy
RIGHT
1
1
2
Activity c not
required for e
a
b
c
d
e
a
b
c
d
e
WRONG X
RIGHT
Network concurrent activities
1 2 1
2
3
a
WRONG X
a
b
b
WRONG X
RIGHT
23
24. 1 1
2 2
3 3
4
a d
b e
c f
a d
b
e
f
c
WRONG!!! RIGHT!!!
a precedes d
a and b precede e,
b and c precede f (a does not precede f)
24
25. Scheduling with activity time
Activity Immediate Completion
predecessors Time (week)
A - 5
B - 6
C A 4
D A 3
E A 1
F E 4
G D,F 14
H B,C 12
I G,H 2
Total …… 51
This information indicates that the total time required to complete
activities is 51 weeks. However, we can see from the network that
several of the activities can be conducted simultaneously (A and B,
for example). 25
26. Earliest Start (ES) and Earliest Finish time (EF)
• We are interested in the longest path through the network, i.e.,
the critical path.
• Starting at the network’s origin (node 1) and using a starting
time of 0, we compute an earliest start (ES) and earliest
finish (EF) time for each activity in the network.
• The expression EF = ES + t can be used to find the earliest
finish time for a given activity.
• For example, for activity A, ES = 0 and t = 5; thus the earliest
finish time for activity A is
EF = 0 + 5 = 5
26
27. Arc with ES and EF time
1
2
Activity
ES = earliest start time
EF = earliest finish time
t = expected activity
time
27
28. Network with ES & EF time
1
3
4
2
5
7
6
D[5,8]
3
Earliest start time rule:
The earliest start time for an activity leaving a particular node is
equal to the largest of the earliest finish times for all activities
entering the node.
28
29. Activity, Duration, ES, EF, LS, LF
2
3
Activity
ES = earliest start time
EF = earliest finish time
LF = latest finish time
LS = latest start time
29
30. • To find the critical path we need a backward pass calculation.
• Starting at the completion point (node 7) and using a latest
finish time (LF) of 26 for activity I, we trace back through the
network computing a latest start (LS) and latest finish time
for each activity
• The expression LS = LF – t can be used to calculate latest start
time for each activity.
• For example, for activity I, LF = 26 and t = 2, thus the latest start
time for activity I is:
LS = 26 – 2 = 24
Latest Start (LS) and Latest Finish (LF) time
30
31. Network with LS & LF time
1
3
4
2
5
7
6
D[5,8]
3[7,10]
Latest finish time rule:
The latest finish time for an activity entering a particular node is
equal to the smallest of the latest start times for all activities
leaving the node.
31
32. Slack or Free Time or Float
Slack/Free Time/Flot is the length of time an activity can be delayed
without affecting the completion date for the entire project.
For example, slack for C = 3 weeks, i.e Activity C can be delayed up to 3 weeks
(start anywhere between weeks 5 and 8).
ES
5
LS
8
EF
9
LF-EF = 12 –9 =3
LS-ES = 8 – 5 = 3
LF-ES-t = 12-5-4 = 3
LF
12
2
3
32
33. • Activity start time and completion time may be delayed
by deliberate reasons as well as by unforeseen reasons.
• Some of these delays may affect the overall completion
date.
• The effects of these delays can be determined by the slack
time, for each activity.
Summary of Slack Times
Slack time for an activity = LS-ES or LF-EF
33
34. The Critical Path
The activities with 0 slack time form at least one Critical Path of
connected activities, each of which is an immediate predecessor for
another activity on the path from the beginning (time = 0) to the
end (the completion time of the project).
– Critical activities must be rigidly scheduled.
• Any delay in a critical activity will delay the entire project.
– The critical path is the longest in the network
Sum of the completion times of activities on a critical path
=
Project completion time
34
35. Activity schedule for our example
Activity Earliest
start (ES)
Latest
start (LS)
Earliest
finish (EF)
Latest
finish (LF)
Slack
(LS-ES)
Critical
path
A 0 0 5 5 0 Yes
B 0 6 6 12 6
C 5 8 9 12 3
D 5 7 8 10 2
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3
I 24 24 26 26 0 Yes
Last EF= The project duration
35
36. Important Questions
• What is the total time to complete the project?
– 26 weeks if the individual activities are completed on
schedule(Last ES).
• What are the scheduled start and completion times for each
activity?
– ES, EF, LS, LF are given for each activity.
• What activities are critical and must be completed as
scheduled in order to keep the project on time?
– Critical path activities: A, E, F, G, and I.
• How long can non-critical activities be delayed before they
cause a delay in the project’s completion time
– Slack time available for all activities are given. 36
37. Importance of Float (Slack) and Critical Path
1. Slack or Float shows how much allowance each activity
has, i.e how long it can be delayed without affecting
completion date of project
2. Critical path is a sequence of activities from start to
finish with zero slack. Critical activities are activities
on the critical path.
3. Critical path identifies the minimum time to complete
project
4. If any activity on the critical path is shortened or
extended, project time will be shortened or extended
accordingly
37
38. 5. So, a lot of effort should be put in trying to control
activities along this path, so that project can meet due
date. If any activity is lengthened, be aware that project
will not meet deadline and some action needs to be taken.
6. If can spend resources to speed up some activity, do so
only for critical activities.
7. Don’t waste resources on non-critical activity, it will not
shorten the project time.
8. If resources can be saved by lengthening some activities,
do so for non-critical activities, up to limit of float.
9. Total Float belongs to the path
Importance of Float (Slack) and Critical Path
38
39. Example (CPM)
• Assume that ABC Computers manufactures computers.
• It is about to design, manufacture, and market a new
model computer.
• In broad terms, the three major tasks to perform are to:
– Design and manufacture the computer
– Train staff and vendor representatives on the features and
use of the computer
– Advertise the computer
39
40. Activity Description
A Prototype model design
B Purchase of materials
Manufacturing C Manufacture of prototype model
activities D Revision of design
E Initial production run
F Staff training
Training activities G Staff input on prototype models
H Sales training
I Pre-production advertising
Advertising activities campaign
J Post-redesign advertising
campaign
Detailed Activities
40
41. Precedence Relations
Activity Immediate Predecessor's)
Starts
after
Completion
Days
A-Prototype Design NONE 90
B-Purchase Materials A-Prototype Design
Starts
After
15
C-Manufacture Prototypes B-Purchase Materials
Starts
After
5
D-Design Revision
C-Manufacture Prototypes and
G-Staff Input
Starts
After
20
E-Initial Production Run D-Design Revision
Starts
After
21
F-Staff Training A-Prototype Design
Starts
After
25
G-Staff Input
C-Manufacture Prototypes and
F-Staff Training
Starts
After
14
H-Sales Training D-Design Revision
Starts
After
28
I-Pre-Production Advertising A-Prototype Design
Starts
After
30
J-Post Redesign Advertising
D-Design Revsion and
I-Pre-Production Advertising
Starts
After
45
41
43. Earliest Start and Finish Times
• We enter these as (ES,EF) above each node.
H
28
E
21
G
14
J
45
A
90
B
15
D
20
I
30
F
25
C
5
90
90)
(0,
(90,
(90,
(90,105)
15
25
115)
30
120)
(105,
5
110)
(115,
14
129) (129,
20
149) (149,
(149,
21
170)
28
177)
(149,
45
194)
Earliest Project completion time = MAX(EF) = 194
MAX(120,149)
MAX(110,115)
43
47. Possible Delays
• There could be a delay in just one activity.
– Any delay more than the slack time for the activity will delay
the entire project by the difference between the activity delay
and the slack time
• There could be delays in more than one activity.
– If activities are on different paths or on the same path but
separated by a critical activity, each of the delays is evaluated
separately. The project delay = max (these delays –
corresponding slack).
– Activities on the same path which are not separated by a
critical activity share the slack. Both will have the same value
for the slack and any combined delays in these activities that
exceed this common slack results in a project delay equal to
(total activity delay) – (common slack).
– Usually with multiple delays the model is simply re-solved!
47
48. Examples of Activity Delays
• Activity G is delayed 5 days
– G is on the critical path (has 0 slack) so the project will be delayed
5 days.
• Activity E is delayed 15 days
– E has 24 days of slack so the project will not be delayed
• Activity B is delayed 15 days
– B has 5 days of slack so the project will be delayed 10 days
• Activity E is delayed 30 days and Activity I is delayed 30 days
– E and I are on different paths. E has 24 days of slack which could
cause a 30-24 = 6 day delay; I has 29 days of slack which could
cause 30-29 = 1 day delay. The project is delayed by the
MAX(6,1) = 6 days.
48
49. Examples of Activity Delays
• Activity B is delayed 4 days and Activity E is delayed 4 days
– B and E are on the same path but are separated by critical
activities (G and D). This is the same as the case above. B
has 5 days slack so delaying it 4 days would not delay the
project; E has 24 days of slack so a 4 day delay will not
delay the project – Net effect– No delay.
• Activity B is delayed 4 days and Activity C is delayed 4 days
– B and C are on the same path with no critical activity in
between. They share the same 5 days of slack. So sense
both are delayed 4 days for a total of 8 days, the project is
delayed 8 – 5 = 3 days.
49
50. PERT For Dealing With Uncertainty
• So far, times were estimated with relative certainty/confidence
• For many situations, however, this is not possible, e.g Research,
development, new products and projects etc.
• In PERT we use 3 time estimates:
m= most likely time estimate, mode.
a = optimistic time estimate, and
b = pessimistic time estimate
Expected Value (TE) = (a + 4m + b) /6
Variance (V) = ( ( b – a) / 6 ) 2
Std Deviation (δ) = SQRT (V)
50
51. Precedences and Project Activity Times
Immediate Optimistic Most Likely Pessimistic EXP Var S.Dev
Activity Predecessor Time Time Time TE V
a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2
Example (PERT)
51
52. The complete PERT network
2 6
1 3 7
4 5
a
(20,4)
d
(15,25)
e
(10,4)
f
(14,4)
j
(8,4)
i
(18,28.4)
g
(4,0)
h
(11,5.4)
c
(10,4)
b
(20,0)
52
53. Critical Path Analysis (PERT)
Activity LS ES Slacks Critical ?
a 0 0 0 Yes
b 1 0 1
c 4 0 4
d 20 20 0 Yes
e 25 20 5
f 29 20 9
g 21 20 1
h 14 10 4
i 25 24 1
j 35 35 0 Yes
53
54. The complete PERT Network
2 6
1 3 7
4 5
b
(20,0)
d
(15,25)
e
(10,4)
f
(14,4)
j
(8,4)
i
(18,28.4)
g
(4,0)
h
(11,5.4)
c
(10,4)
Critical Time = 43
EF=20 35
43
24
10
20
a
(20,4)
54
55. Assume, the Project Manager promised to complete the project in 50 days.
Question: What are the chances of meeting that deadline? (Determine P)
Calculate Z, where
Z = (D-S) / V
Example,
D = 50 (specified date);
S = 20+15+8 =43 (Scheduled date);
V = (4+25+4) =33 (Variance of the critical path);
Z = (50 – 43) / 5.745
= 1.22 standard deviations.
The probability value of Z = 1.22, is 0.888 (Table value);i.e., the chance of
meeting the deadline is 0.888)
1.22
55
56. Question: What deadline are you 95% sure of meeting? (Determine D)
D = S+ZV……….. (From previous formula)
Z value associated with 0.95 is 1.645 (Table value)
D=S + 5.745 (1.645)
= 43 + 9.45
= 52.45 days
Thus, there is a 95 percent chance of finishing the
project by 52.45 days.
56
57. Comparison Between CPM and PERT
CPM PERT
1 Uses network, calculate float or slack,
identify critical path and activities, guides
to monitor and controlling project
Same as CPM
2 Uses one value of activity time Requires 3 estimates of activity time
Calculates mean and variance of time
3 Used where times can be estimated with
confidence, familiar activities
Used where times cannot be estimated
with confidence.
Unfamiliar or new activities
4 Minimizing cost is more important Meeting time target or estimating percent
completion is more important
5 Example: construction projects, building
one off machines, ships, etc
Example: Involving new activities or
products, research and development etc
57
58. Benefits of CPM / PERT Network
Consistent framework for planning, scheduling,
monitoring, and controlling project.
• Shows interdependence of all tasks, work packages,
and work units.
• Helps proper communications between departments
and functions.
• Determines expected project completion date.
• Identifies so-called critical activities, which can
delay the project completion time.
58
59. • Identified activities with slacks that can be delayed for
specified periods without penalty, or from which resources
may be temporarily borrowed
• Determines the dates on which tasks may be started or
must be started if the project is to stay in schedule.
• Shows which tasks must be coordinated to avoid resource
or timing conflicts.
• Shows which tasks may run in parallel to meet project
completion date
Benefits of CPM / PERT Network