SUBJECT
PROJECT MANAGEMENT & ENGINEERING
ECONOMICS (PMEE)
CONTENTS
CRITICAL PATH METHOD & PROGRAM EVALUATION AND REVIEW
TECHNIQUE
(CPM & PERT )
Compiled By : Deepak Narayan Paithankar
Assistant Professor, Department of Civil Engineering, Sanjivani College of Engineering, Kopargaon.
FLOW OF
PRESENTATION
 INTRODUCTION
 NETWORK PLANNING
 ESTIMATING TIME
 CPM
 PERT
Project
Management
Project
• A project is an interrelated set of activities that has a definite
starting and ending point and that results in a unique product
or service.
Project management
• Project management is a scientific way of planning, implementing,
monitoring & controlling the various aspects of a project such as time,
money, materials, manpower & other resources.
4
Project Managem ent Tools
•
•
•
Older sim pler - Gantt Chart
More m odern – CPM/ PERT
N ewest – Microsoft Project ™
Gantt Chart
Activity
Foundation
Framing
Plumbing
Electrical
Wall Board
Siding
Paint Interior
Paint Exterior
Fixtures
Start 5
Days After Start
10 15 20 25 30 35 40 45 50
5 10 15 20 25 30
Days After Start
Start 35 40 45 50
5
6
Advantages of Gantt
1. Easy to understand
2. Easy to construct
Network Planning
Methods
 Methods used for network planning are:
CPM
PERT
 Managing a project with network planning methods involves four steps:
1.
2.
3.
4.
Describing the Project.
Diagramming the Network.
Estimating time of completion.
Monitoring Project Progress.
Network Diagram
Concepts
• Activity
• Precedence relationship
• Successor
• Event
Guidelines for network diagram
1. Before an activity can begin, its preceding
activities must be completed.
2. Arrows indicate logical precedence.
3. Flow of the diagram is from left to right.
4. Arrows should not intersect.
5. Dangling should be avoided.
APPRAOCHES FOR
NETWORK DIAGRAM
ACTIVITY ON ARC(AOA):
• Uses arcs to represent activities and nodes
to represent events.
• It is Event Oriented.
3
1 876
54
2
DUMMY
ACTIVITY
AOA approach requires the addition of a
Activity to clarify the precedence relationships
the two activities. It is a zero time activity and
consumes no resources.
Dummy
between
Dummy Activity is used in two situations:
1) When two or more activities start and end at the same
nodes
1 3
2
2) When two or more activities share the same
precedence activity but not all the precedence are
shared.
1 3 5
6
7
2 4
Uses nodes to represent activities
precedence relationships between
It is Activity Oriented.
and arcs indicate
them.
ACTIVITY ON
NODE(AON):
ESTIMATING TIME OF
COMPLETION
Planning the schedule of the project
Time estimates include:
1) Total time for completion.
2) ES- Earliest start time: the earliest time at which the activity
can start given that its precedent activities must be completed first.
3) EF-Earliest finish time: equals to the earliest start time for the activity
plus the time required to complete the activity.
4) LF- Latest finish time: the latest time in which the activity can be
completed without delaying the project.
5) LS- Latest start time: equal to the latest finish time minus the time
required to complete the activity.
6) FORWARD PASS:
The early start and early finish times are calculated by
moving forward through the network and considering the
predecessor activities Considers maximum
7) BACKWARD PASS:
The latest start and finish times are calculated by moving backward through the
network.
Considers minimum
8) SLACK TIME:
Slack time for an activity is the difference between its earliest and latest start
time or between the earliest and latest finish time.
Critical path is the path of activities having zero Slack time.
A Simple Project
Activity Immediate
Predecessor
Expected
Time
5
6
4
2
A
B
C
D
-
-
A
A, B
Precedence Diagram
ES
EF
LS
LF
Slack
Earliest Starting (time)
Earliest Finishing
Latest Starting
Latest Finishing
Difference Time
CRITICAL PATH
METHODS(CPM)
HISTORY :
It was developed by J.E.KELLY of REMINGTON-RAND
and M.R.WALKER of DU PONT and the emphasis was
on the trade-off between the cost of project and its overall
completion time. The first test was made in 1958,when CPM
was applied to the construction of a new chemical plant.
DEFINITION:
Critical path is the sequence of activities between a project’s
start and finish that takes the longest time to complete.
STEPS IN
DETERMINING
CRITICAL PATH
• Specify the individual activities.
• Determine the sequence of the activities.
• Draw the network diagram.
• Estimate the activity completion time.
• Identify the critical path.
• Update the CPM diagram.
Activit
y
Preceden
ce
Normal time
(week)
Normal
Cost (Rs)
A - 3 300
B A 3 30
C A 7 420
D A 9 720
E D 5 250
F B,C,E 6 320
G F 4 400
H F 13 780
I G 10 1000
Total 4220
1
3
8
7
65
4
2
Overhead cost as per the given data- Rs.50
Paths in the network diagram :
A-D-F-G-I = 32
A-D-F-H = 31
A-C-F-H = 29
A-C-F-G-I = 30
A-B-E-F-H = 30
A-B-E-F-G-I = 31
Critical path – A-D-F-G-I = 32
1
8
7
6
3
5
4
2
TIME
ESTIMATES
o Optimistic time (to) – It is the shortest time
activity can be completed.
o Most likely time (tm) – It is the probable time
required to perform the activity.
in which the
o Pessimistic time (tp) – It is the longest estimated time
required to perform an activity.
o Expected time
te = to + 4tm + tp
6
STEPS IN
PERT
1. Identify the specific activities.
2. Determine proper sequence of the activities.
3. Construct the network diagram.
4. Estimate the time required for each activity.
5. Determine the critical path.
6. Update the PERT chart.
Activity Descrip
tion
Preced
ence
Optimis
tic time
Most
Likely
time
Pessimi
stic
time
Expecte
d time
A Initial
design
- 12 16 26 17
B Survey
market
A 6 9 18 10
C Build
prototype
A 8 10 18 11
D Test
prototype
C 2 3 4 3
E Redesign
ing
B,D 3 4 11 5
F Market
testing
E 6 8 10 8
G Set up
productio
n
F 15 20 25 20
1 7652
3
A-B-E-F-G = 60
A-C-D-E-F-G = 64 (CRITICAL PATH)
4
Advantages of PERT
• Expected project completion time.
• Probability of completion before a specified date.
• The critical path activities that directly impact the completion
time.
• The activities that have slack time and that can lend resources
to critical path activities.
• Activity start and end dates.
LIMITATIONS
• The PERT Formula Requires Too Much Work.
• The network charts tend to be large and unwieldy.
• Calculating the time estimates is very complex for all the
activities.
• Updating of the project is time consuming and requires high
costs.
• Emphasis is laid only on time factors and cost factors are
neglected.
Difference between
CPM & PERT
Thank
You
…

More Related Content

What's hot

Network analysis by PERT and CPM
Network analysis by PERT and CPMNetwork analysis by PERT and CPM
Network analysis by PERT and CPM
Rajendrakumar Kadi
 
Sewer appurtenances
Sewer appurtenances Sewer appurtenances
Sewer appurtenances
SitalParajuli
 
Trumpet interchange
Trumpet interchange Trumpet interchange
Trumpet interchange
Spice Shuvo
 
MultiModal Transportation in New DElhi
MultiModal Transportation in New DElhiMultiModal Transportation in New DElhi
MultiModal Transportation in New DElhi
Hamza Hashmi
 
Signalling in Railways
Signalling in RailwaysSignalling in Railways
Signalling in Railways
Anupama Jha
 
highway development in india
highway development in indiahighway development in india
highway development in india
Prathi Baa
 
Losses IN Canals
Losses IN CanalsLosses IN Canals
Losses IN Canals
Anand Kumar
 
Traffic regulatory measures subjective assignment 2 - academic writing
Traffic regulatory measures   subjective assignment 2 - academic writingTraffic regulatory measures   subjective assignment 2 - academic writing
Traffic regulatory measures subjective assignment 2 - academic writing
Chockalingam T
 
Critical path method
Critical path methodCritical path method
Critical path method
Dhruv Shah
 
Irrigation Channels
Irrigation ChannelsIrrigation Channels
Irrigation Channels
GAURAV. H .TANDON
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
Pulchowk Campus
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
Hafiz JUNAID
 
Signalling and Interlocking
Signalling and InterlockingSignalling and Interlocking
Signalling and Interlocking
srinivas2036
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time survey
Sai Santosh Yakkali
 
Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
GAURAV. H .TANDON
 
Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
Bibhabasu Mohanty
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
Asif Sultan Razu
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and scheduling
Subash Bhattarai
 
PERT
PERTPERT
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 

What's hot (20)

Network analysis by PERT and CPM
Network analysis by PERT and CPMNetwork analysis by PERT and CPM
Network analysis by PERT and CPM
 
Sewer appurtenances
Sewer appurtenances Sewer appurtenances
Sewer appurtenances
 
Trumpet interchange
Trumpet interchange Trumpet interchange
Trumpet interchange
 
MultiModal Transportation in New DElhi
MultiModal Transportation in New DElhiMultiModal Transportation in New DElhi
MultiModal Transportation in New DElhi
 
Signalling in Railways
Signalling in RailwaysSignalling in Railways
Signalling in Railways
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Losses IN Canals
Losses IN CanalsLosses IN Canals
Losses IN Canals
 
Traffic regulatory measures subjective assignment 2 - academic writing
Traffic regulatory measures   subjective assignment 2 - academic writingTraffic regulatory measures   subjective assignment 2 - academic writing
Traffic regulatory measures subjective assignment 2 - academic writing
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Irrigation Channels
Irrigation ChannelsIrrigation Channels
Irrigation Channels
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Signalling and Interlocking
Signalling and InterlockingSignalling and Interlocking
Signalling and Interlocking
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time survey
 
Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
 
Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and scheduling
 
PERT
PERTPERT
PERT
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 

Similar to Project Management & Engineering Economics

Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
kongara
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
AaliButt1
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
IIMSE Edu
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
Akihisa Akimoto
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
salsa moyara
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
Drprem Jerusha
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
Chandra Shekar Immani
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
Sougata Das
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
ShwetaMahdole
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
Sheetu Goel
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
tanishkagupta907
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
JerryHung19
 

Similar to Project Management & Engineering Economics (20)

Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Project management
Project managementProject management
Project management
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 

Recently uploaded

Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Po-Chuan Chen
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
CarlosHernanMontoyab2
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 

Recently uploaded (20)

Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 

Project Management & Engineering Economics

  • 1. SUBJECT PROJECT MANAGEMENT & ENGINEERING ECONOMICS (PMEE) CONTENTS CRITICAL PATH METHOD & PROGRAM EVALUATION AND REVIEW TECHNIQUE (CPM & PERT ) Compiled By : Deepak Narayan Paithankar Assistant Professor, Department of Civil Engineering, Sanjivani College of Engineering, Kopargaon.
  • 2. FLOW OF PRESENTATION  INTRODUCTION  NETWORK PLANNING  ESTIMATING TIME  CPM  PERT
  • 3. Project Management Project • A project is an interrelated set of activities that has a definite starting and ending point and that results in a unique product or service. Project management • Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
  • 4. 4 Project Managem ent Tools • • • Older sim pler - Gantt Chart More m odern – CPM/ PERT N ewest – Microsoft Project ™
  • 5. Gantt Chart Activity Foundation Framing Plumbing Electrical Wall Board Siding Paint Interior Paint Exterior Fixtures Start 5 Days After Start 10 15 20 25 30 35 40 45 50 5 10 15 20 25 30 Days After Start Start 35 40 45 50 5
  • 6. 6 Advantages of Gantt 1. Easy to understand 2. Easy to construct
  • 7. Network Planning Methods  Methods used for network planning are: CPM PERT  Managing a project with network planning methods involves four steps: 1. 2. 3. 4. Describing the Project. Diagramming the Network. Estimating time of completion. Monitoring Project Progress.
  • 8. Network Diagram Concepts • Activity • Precedence relationship • Successor • Event
  • 9. Guidelines for network diagram 1. Before an activity can begin, its preceding activities must be completed. 2. Arrows indicate logical precedence. 3. Flow of the diagram is from left to right. 4. Arrows should not intersect. 5. Dangling should be avoided.
  • 10. APPRAOCHES FOR NETWORK DIAGRAM ACTIVITY ON ARC(AOA): • Uses arcs to represent activities and nodes to represent events. • It is Event Oriented. 3 1 876 54 2
  • 11. DUMMY ACTIVITY AOA approach requires the addition of a Activity to clarify the precedence relationships the two activities. It is a zero time activity and consumes no resources. Dummy between Dummy Activity is used in two situations: 1) When two or more activities start and end at the same nodes 1 3 2
  • 12. 2) When two or more activities share the same precedence activity but not all the precedence are shared. 1 3 5 6 7 2 4
  • 13. Uses nodes to represent activities precedence relationships between It is Activity Oriented. and arcs indicate them. ACTIVITY ON NODE(AON):
  • 14. ESTIMATING TIME OF COMPLETION Planning the schedule of the project Time estimates include: 1) Total time for completion. 2) ES- Earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first. 3) EF-Earliest finish time: equals to the earliest start time for the activity plus the time required to complete the activity. 4) LF- Latest finish time: the latest time in which the activity can be completed without delaying the project. 5) LS- Latest start time: equal to the latest finish time minus the time required to complete the activity.
  • 15. 6) FORWARD PASS: The early start and early finish times are calculated by moving forward through the network and considering the predecessor activities Considers maximum 7) BACKWARD PASS: The latest start and finish times are calculated by moving backward through the network. Considers minimum 8) SLACK TIME: Slack time for an activity is the difference between its earliest and latest start time or between the earliest and latest finish time. Critical path is the path of activities having zero Slack time.
  • 16. A Simple Project Activity Immediate Predecessor Expected Time 5 6 4 2 A B C D - - A A, B
  • 18. ES EF LS LF Slack Earliest Starting (time) Earliest Finishing Latest Starting Latest Finishing Difference Time
  • 19.
  • 20. CRITICAL PATH METHODS(CPM) HISTORY : It was developed by J.E.KELLY of REMINGTON-RAND and M.R.WALKER of DU PONT and the emphasis was on the trade-off between the cost of project and its overall completion time. The first test was made in 1958,when CPM was applied to the construction of a new chemical plant. DEFINITION: Critical path is the sequence of activities between a project’s start and finish that takes the longest time to complete.
  • 21. STEPS IN DETERMINING CRITICAL PATH • Specify the individual activities. • Determine the sequence of the activities. • Draw the network diagram. • Estimate the activity completion time. • Identify the critical path. • Update the CPM diagram.
  • 22. Activit y Preceden ce Normal time (week) Normal Cost (Rs) A - 3 300 B A 3 30 C A 7 420 D A 9 720 E D 5 250 F B,C,E 6 320 G F 4 400 H F 13 780 I G 10 1000 Total 4220
  • 24. Overhead cost as per the given data- Rs.50 Paths in the network diagram : A-D-F-G-I = 32 A-D-F-H = 31 A-C-F-H = 29 A-C-F-G-I = 30 A-B-E-F-H = 30 A-B-E-F-G-I = 31
  • 25. Critical path – A-D-F-G-I = 32 1 8 7 6 3 5 4 2
  • 26. TIME ESTIMATES o Optimistic time (to) – It is the shortest time activity can be completed. o Most likely time (tm) – It is the probable time required to perform the activity. in which the o Pessimistic time (tp) – It is the longest estimated time required to perform an activity. o Expected time te = to + 4tm + tp 6
  • 27. STEPS IN PERT 1. Identify the specific activities. 2. Determine proper sequence of the activities. 3. Construct the network diagram. 4. Estimate the time required for each activity. 5. Determine the critical path. 6. Update the PERT chart.
  • 28. Activity Descrip tion Preced ence Optimis tic time Most Likely time Pessimi stic time Expecte d time A Initial design - 12 16 26 17 B Survey market A 6 9 18 10 C Build prototype A 8 10 18 11 D Test prototype C 2 3 4 3 E Redesign ing B,D 3 4 11 5 F Market testing E 6 8 10 8 G Set up productio n F 15 20 25 20
  • 29. 1 7652 3 A-B-E-F-G = 60 A-C-D-E-F-G = 64 (CRITICAL PATH) 4
  • 30. Advantages of PERT • Expected project completion time. • Probability of completion before a specified date. • The critical path activities that directly impact the completion time. • The activities that have slack time and that can lend resources to critical path activities. • Activity start and end dates.
  • 31. LIMITATIONS • The PERT Formula Requires Too Much Work. • The network charts tend to be large and unwieldy. • Calculating the time estimates is very complex for all the activities. • Updating of the project is time consuming and requires high costs. • Emphasis is laid only on time factors and cost factors are neglected.