PROJECT MANAGEMENT
CPM & PERT TECHNIQUES
FLOW OF PRESENTATION
 INTRODUCTION
 NETWORK PLANNING
 ESTIMATING TIME
 CPM
 PERT
Project Management
Project
• A project is an interrelated set of activities that has a definite
starting and ending point and that results in a unique product
or service.
Project management
• Project management is a scientific way of planning, implementing,
monitoring & controlling the various aspects of a project such as time,
money, materials, manpower & other resources.
Network Planning Methods
 Methods used for network planning are:
CPM
PERT
 Managing a project with network planning methods involves four steps:
1. Describing the Project.
2. Diagramming the Network.
3. Estimating time of completion.
4. Monitoring Project Progress.
Network Diagram
Concepts
• Activity
• Precedence relationship
• Successor
• Event
Guidelines for network diagram
1. Before an activity can begin, its preceding
activities must be completed.
2. Arrows indicate logical precedence.
3. Flow of the diagram is from left to right.
4. Arrows should not intersect.
5. Dangling should be avoided.
APPRAOCHES FOR
NETWORK DIAGRAM
ACTIVITY ON ARC(AOA):
• Uses arcs to represent activities and nodes
to represent events.
• It is Event Oriented.
1 876
54
3
2
DUMMY ACTIVITY
AOA approach requires the addition of a Dummy
Activity to clarify the precedence relationships between
the two activities. It is a zero time activity and
consumes no resources.
Dummy Activity is used in two situations:
1) When two or more activities start and end at the same
nodes
1 3
2
2) When two or more activities share the same
precedence activity but not all the precedence are
shared.
1 53
6
7
2 4
Uses nodes to represent activities and arcs indicate
precedence relationships between them.
It is Activity Oriented.
ACTIVITY ON NODE(AON):
ESTIMATING TIME
OF
COMPLETION
Planning the schedule of the project
Time estimates include:
1) Total time for completion.
2) ES- Earliest start time: the earliest time at which the activity
can start given that its precedent activities must be completed first.
3) EF-Earliest finish time: equals to the earliest start time for the activity
plus the time required to complete the activity.
4) LF- Latest finish time: the latest time in which the activity can be
completed without delaying the project.
5) LS- Latest start time: equal to the latest finish time minus the time
required to complete the activity.
6) FORWARD PASS:
The early start and early finish times are calculated by
moving forward through the network and considering the
predecessor activities Considers maximum
7) BACKWARD PASS:
The latest start and finish times are calculated by moving backward through the
network.
Considers minimum
8) SLACK TIME:
Slack time for an activity is the difference between its earliest and latest start
time or between the earliest and latest finish time.
Critical path is the path of activities having zero Slack time.
A Simple Project
Activity Immediate
Predecessor
Expected
Time
A - 5
B - 6
C A 4
D A, B 2
Precedence Diagram
ES Earliest Starting (time)
EF Earliest Finishing
LS Latest Starting
LF Latest Finishing
Slack Difference Time
CRITICAL PATH
METHODS(CPM)
HISTORY :
It was developed by J.E.KELLY of REMINGTON-RAND
and M.R.WALKER of DU PONT and the emphasis was
on the trade-off between the cost of project and its overall
completion time. The first test was made in 1958,when CPM
was applied to the construction of a new chemical plant.
DEFINITION:
Critical path is the sequence of activities between a project’s
start and finish that takes the longest time to complete.
STEPS IN DETERMINING
CRITICAL PATH
• Specify the individual activities.
• Determine the sequence of the activities.
• Draw the network diagram.
• Estimate the activity completion time.
• Identify the critical path.
• Update the CPM diagram.
Activit
y
Preceden
ce
Normal time
(week)
Normal
Cost (Rs)
A - 3 300
B A 3 30
C A 7 420
D A 9 720
E D 5 250
F B,C,E 6 320
G F 4 400
H F 13 780
I G 10 1000
Total 4220
1
8
7
6
3
5
4
2
Overhead cost as per the given data- Rs.50
Paths in the network diagram :
A-D-F-G-I = 32
A-D-F-H = 31
A-C-F-H = 29
A-C-F-G-I = 30
A-B-E-F-H = 30
A-B-E-F-G-I = 31
Critical path – A-D-F-G-I = 32
1
8
7
6
3
5
4
2
TIME ESTIMATES
o Optimistic time (to) – It is the shortest time in which the
activity can be completed.
o Most likely time (tm) – It is the probable time
required to perform the activity.
o Pessimistic time (tp) – It is the longest estimated time
required to perform an activity.
o Expected time
te = to + 4tm + tp
6
STEPS IN PERT
1. Identify the specific activities.
2. Determine proper sequence of the activities.
3. Construct the network diagram.
4. Estimate the time required for each activity.
5. Determine the critical path.
6. Update the PERT chart.
Activity Descrip
tion
Preced
ence
Optimis
tic time
Most
Likely
time
Pessimi
stic
time
Expecte
d time
A Initial
design
- 12 16 26 17
B Survey
market
A 6 9 18 10
C Build
prototype
A 8 10 18 11
D Test
prototype
C 2 3 4 3
E Redesign
ing
B,D 3 4 11 5
F Market
testing
E 6 8 10 8
G Set up
productio
n
F 15 20 25 20
1 7652
3
4
A-B-E-F-G = 60
A-C-D-E-F-G = 64 (CRITICAL PATH)
Advantages of PERT
• Expected project completion time.
• Probability of completion before a specified date.
• The critical path activities that directly impact the completion
time.
• The activities that have slack time and that can lend resources
to critical path activities.
• Activity start and end dates.
LIMITATIONS
• The PERT Formula Requires Too Much Work.
• The network charts tend to be large and unwieldy.
• Calculating the time estimates is very complex for all the
activities.
• Updating of the project is time consuming and requires high
costs.
• Emphasis is laid only on time factors and cost factors are
neglected.
Difference between
CPM & PERT
CPM PERT
• CPM works with fixed
deterministic time
• PERT works with probabilistic
time
• CPM is useful for repetitive and
non complex projects with a
certain degree of time estimates.
• PERT is useful for non repetitive
and complex projects with
uncertain time estimates.
• CPM includes time-cost trade off. • PERT is restricted to time
variable.
• CPM- for construction projects. • PERT- used for R&D programs.
Thank You…

More Related Content

What's hot

Project presentation
Project presentationProject presentation
Project presentation
ali ucar
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method
Mkaur01
 
Project networks
Project networksProject networks
Project networks
J. Scott Christianson
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
NR Computer Learning Center
 
Critical path method
Critical path methodCritical path method
Critical path method
Shubhi Verma
 
Network construction
Network construction  Network construction
Network construction
Dr. Mahmoud Al-Naimi
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Alecsis Roe Frasco
 
Critical path method
Critical path methodCritical path method
Critical path method
Dhruv Shah
 
Pert analysis
Pert analysisPert analysis
Pert analysis
Hashamuddin Yaakob
 
05 critical path analysis
05 critical path analysis05 critical path analysis
05 critical path analysisSam Catlin
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
El Moro
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
Akihisa Akimoto
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
hoang tung
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
BLESSY ALOSHIOUS
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
Prasad Thanthratey
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
tutor2u
 

What's hot (19)

Project presentation
Project presentationProject presentation
Project presentation
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method
 
Project networks
Project networksProject networks
Project networks
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Network construction
Network construction  Network construction
Network construction
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
05 critical path analysis
05 critical path analysis05 critical path analysis
05 critical path analysis
 
Project management
Project managementProject management
Project management
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 

Similar to Pertcpm projectmanagement SIDDANNA M BALAPGOL

Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
IIMSE Edu
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
AaliButt1
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
Sougata Das
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
albert937613
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
TecnicoItca
 
project network
project networkproject network
project network
Sougata Das
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
Chandra Shekar Immani
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
ShwetaMahdole
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
MdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
MdSabujHossen2
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
ahsanrabbani
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
Akaresh Jose Kaviyil JY
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
SAJID ALI RUK
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
Shahrukh Vahora
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
tanishkagupta907
 

Similar to Pertcpm projectmanagement SIDDANNA M BALAPGOL (20)

Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
project network
project networkproject network
project network
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
 

More from Siddanna Balapgol

Sitting is killing you siddanna Balapgol
Sitting is killing you siddanna BalapgolSitting is killing you siddanna Balapgol
Sitting is killing you siddanna Balapgol
Siddanna Balapgol
 
Vision life-income-plan-08-01-13
Vision life-income-plan-08-01-13Vision life-income-plan-08-01-13
Vision life-income-plan-08-01-13Siddanna Balapgol
 
Surveyquestionnaireformatforproject SIDDANNA M BALAPGOL
Surveyquestionnaireformatforproject SIDDANNA M BALAPGOLSurveyquestionnaireformatforproject SIDDANNA M BALAPGOL
Surveyquestionnaireformatforproject SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Sample mba final year project
Sample mba final year projectSample mba final year project
Sample mba final year projectSiddanna Balapgol
 
Pride marketing14e basic_SIDDANNA M BALAPGOL
Pride marketing14e basic_SIDDANNA M BALAPGOLPride marketing14e basic_SIDDANNA M BALAPGOL
Pride marketing14e basic_SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Postpurchaseconsumerbehaviour 100318121357-phpapp02
Postpurchaseconsumerbehaviour 100318121357-phpapp02Postpurchaseconsumerbehaviour 100318121357-phpapp02
Postpurchaseconsumerbehaviour 100318121357-phpapp02Siddanna Balapgol
 
Post purchasebehavior-SIDDANNA M BALAPGOL
Post purchasebehavior-SIDDANNA M BALAPGOLPost purchasebehavior-SIDDANNA M BALAPGOL
Post purchasebehavior-SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Optimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOL
Optimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOLOptimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOL
Optimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Optimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOL
Optimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOLOptimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOL
Optimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Microencapsulation SIDDANNA M BALAPGOL
Microencapsulation SIDDANNA M BALAPGOLMicroencapsulation SIDDANNA M BALAPGOL
Microencapsulation SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Lifeinsuranceprojectreport SIDDANNA M BALAPGOL
Lifeinsuranceprojectreport SIDDANNA M BALAPGOLLifeinsuranceprojectreport SIDDANNA M BALAPGOL
Lifeinsuranceprojectreport SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Kotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOLKotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Kotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOLKotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Insuarancesector SIDDANNA M BALAPGOL
Insuarancesector SIDDANNA M BALAPGOLInsuarancesector SIDDANNA M BALAPGOL
Insuarancesector SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Forum the employeeorthecompany SIDDANNA M BALAPGOL
Forum the employeeorthecompany SIDDANNA M BALAPGOLForum the employeeorthecompany SIDDANNA M BALAPGOL
Forum the employeeorthecompany SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Finalcommonwealthscam SIDDANNA M BALAPGOL
Finalcommonwealthscam SIDDANNA M BALAPGOLFinalcommonwealthscam SIDDANNA M BALAPGOL
Finalcommonwealthscam SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Final presentation of scams SIDDANNA M BALAPGOL
Final presentation of scams SIDDANNA M BALAPGOLFinal presentation of scams SIDDANNA M BALAPGOL
Final presentation of scams SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Empower pension-plan-SIDDANNA M BALAPGOL
Empower pension-plan-SIDDANNA M BALAPGOLEmpower pension-plan-SIDDANNA M BALAPGOL
Empower pension-plan-SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Consumersatisfactionordissatisfactionf SIDDANNA M BALAPGOL
Consumersatisfactionordissatisfactionf SIDDANNA M BALAPGOLConsumersatisfactionordissatisfactionf SIDDANNA M BALAPGOL
Consumersatisfactionordissatisfactionf SIDDANNA M BALAPGOL
Siddanna Balapgol
 

More from Siddanna Balapgol (20)

Sitting is killing you siddanna Balapgol
Sitting is killing you siddanna BalapgolSitting is killing you siddanna Balapgol
Sitting is killing you siddanna Balapgol
 
SIDDANNA BALAPGOL
SIDDANNA BALAPGOLSIDDANNA BALAPGOL
SIDDANNA BALAPGOL
 
Vision life-income-plan-08-01-13
Vision life-income-plan-08-01-13Vision life-income-plan-08-01-13
Vision life-income-plan-08-01-13
 
Surveyquestionnaireformatforproject SIDDANNA M BALAPGOL
Surveyquestionnaireformatforproject SIDDANNA M BALAPGOLSurveyquestionnaireformatforproject SIDDANNA M BALAPGOL
Surveyquestionnaireformatforproject SIDDANNA M BALAPGOL
 
Sample mba final year project
Sample mba final year projectSample mba final year project
Sample mba final year project
 
Pride marketing14e basic_SIDDANNA M BALAPGOL
Pride marketing14e basic_SIDDANNA M BALAPGOLPride marketing14e basic_SIDDANNA M BALAPGOL
Pride marketing14e basic_SIDDANNA M BALAPGOL
 
Postpurchaseconsumerbehaviour 100318121357-phpapp02
Postpurchaseconsumerbehaviour 100318121357-phpapp02Postpurchaseconsumerbehaviour 100318121357-phpapp02
Postpurchaseconsumerbehaviour 100318121357-phpapp02
 
Post purchasebehavior-SIDDANNA M BALAPGOL
Post purchasebehavior-SIDDANNA M BALAPGOLPost purchasebehavior-SIDDANNA M BALAPGOL
Post purchasebehavior-SIDDANNA M BALAPGOL
 
Optimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOL
Optimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOLOptimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOL
Optimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOL
 
Optimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOL
Optimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOLOptimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOL
Optimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOL
 
Microencapsulation SIDDANNA M BALAPGOL
Microencapsulation SIDDANNA M BALAPGOLMicroencapsulation SIDDANNA M BALAPGOL
Microencapsulation SIDDANNA M BALAPGOL
 
Lifeinsuranceprojectreport SIDDANNA M BALAPGOL
Lifeinsuranceprojectreport SIDDANNA M BALAPGOLLifeinsuranceprojectreport SIDDANNA M BALAPGOL
Lifeinsuranceprojectreport SIDDANNA M BALAPGOL
 
Kotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOLKotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOL
 
Kotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOLKotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOL
 
Insuarancesector SIDDANNA M BALAPGOL
Insuarancesector SIDDANNA M BALAPGOLInsuarancesector SIDDANNA M BALAPGOL
Insuarancesector SIDDANNA M BALAPGOL
 
Forum the employeeorthecompany SIDDANNA M BALAPGOL
Forum the employeeorthecompany SIDDANNA M BALAPGOLForum the employeeorthecompany SIDDANNA M BALAPGOL
Forum the employeeorthecompany SIDDANNA M BALAPGOL
 
Finalcommonwealthscam SIDDANNA M BALAPGOL
Finalcommonwealthscam SIDDANNA M BALAPGOLFinalcommonwealthscam SIDDANNA M BALAPGOL
Finalcommonwealthscam SIDDANNA M BALAPGOL
 
Final presentation of scams SIDDANNA M BALAPGOL
Final presentation of scams SIDDANNA M BALAPGOLFinal presentation of scams SIDDANNA M BALAPGOL
Final presentation of scams SIDDANNA M BALAPGOL
 
Empower pension-plan-SIDDANNA M BALAPGOL
Empower pension-plan-SIDDANNA M BALAPGOLEmpower pension-plan-SIDDANNA M BALAPGOL
Empower pension-plan-SIDDANNA M BALAPGOL
 
Consumersatisfactionordissatisfactionf SIDDANNA M BALAPGOL
Consumersatisfactionordissatisfactionf SIDDANNA M BALAPGOLConsumersatisfactionordissatisfactionf SIDDANNA M BALAPGOL
Consumersatisfactionordissatisfactionf SIDDANNA M BALAPGOL
 

Recently uploaded

LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
marketing317746
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 

Recently uploaded (20)

LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 

Pertcpm projectmanagement SIDDANNA M BALAPGOL

  • 1. PROJECT MANAGEMENT CPM & PERT TECHNIQUES
  • 2. FLOW OF PRESENTATION  INTRODUCTION  NETWORK PLANNING  ESTIMATING TIME  CPM  PERT
  • 3. Project Management Project • A project is an interrelated set of activities that has a definite starting and ending point and that results in a unique product or service. Project management • Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
  • 4. Network Planning Methods  Methods used for network planning are: CPM PERT  Managing a project with network planning methods involves four steps: 1. Describing the Project. 2. Diagramming the Network. 3. Estimating time of completion. 4. Monitoring Project Progress.
  • 5. Network Diagram Concepts • Activity • Precedence relationship • Successor • Event
  • 6. Guidelines for network diagram 1. Before an activity can begin, its preceding activities must be completed. 2. Arrows indicate logical precedence. 3. Flow of the diagram is from left to right. 4. Arrows should not intersect. 5. Dangling should be avoided.
  • 7. APPRAOCHES FOR NETWORK DIAGRAM ACTIVITY ON ARC(AOA): • Uses arcs to represent activities and nodes to represent events. • It is Event Oriented. 1 876 54 3 2
  • 8. DUMMY ACTIVITY AOA approach requires the addition of a Dummy Activity to clarify the precedence relationships between the two activities. It is a zero time activity and consumes no resources. Dummy Activity is used in two situations: 1) When two or more activities start and end at the same nodes 1 3 2
  • 9. 2) When two or more activities share the same precedence activity but not all the precedence are shared. 1 53 6 7 2 4
  • 10. Uses nodes to represent activities and arcs indicate precedence relationships between them. It is Activity Oriented. ACTIVITY ON NODE(AON):
  • 11. ESTIMATING TIME OF COMPLETION Planning the schedule of the project Time estimates include: 1) Total time for completion. 2) ES- Earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first. 3) EF-Earliest finish time: equals to the earliest start time for the activity plus the time required to complete the activity. 4) LF- Latest finish time: the latest time in which the activity can be completed without delaying the project. 5) LS- Latest start time: equal to the latest finish time minus the time required to complete the activity.
  • 12. 6) FORWARD PASS: The early start and early finish times are calculated by moving forward through the network and considering the predecessor activities Considers maximum 7) BACKWARD PASS: The latest start and finish times are calculated by moving backward through the network. Considers minimum 8) SLACK TIME: Slack time for an activity is the difference between its earliest and latest start time or between the earliest and latest finish time. Critical path is the path of activities having zero Slack time.
  • 13. A Simple Project Activity Immediate Predecessor Expected Time A - 5 B - 6 C A 4 D A, B 2
  • 15. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Difference Time
  • 16.
  • 17. CRITICAL PATH METHODS(CPM) HISTORY : It was developed by J.E.KELLY of REMINGTON-RAND and M.R.WALKER of DU PONT and the emphasis was on the trade-off between the cost of project and its overall completion time. The first test was made in 1958,when CPM was applied to the construction of a new chemical plant. DEFINITION: Critical path is the sequence of activities between a project’s start and finish that takes the longest time to complete.
  • 18. STEPS IN DETERMINING CRITICAL PATH • Specify the individual activities. • Determine the sequence of the activities. • Draw the network diagram. • Estimate the activity completion time. • Identify the critical path. • Update the CPM diagram.
  • 19. Activit y Preceden ce Normal time (week) Normal Cost (Rs) A - 3 300 B A 3 30 C A 7 420 D A 9 720 E D 5 250 F B,C,E 6 320 G F 4 400 H F 13 780 I G 10 1000 Total 4220
  • 21. Overhead cost as per the given data- Rs.50 Paths in the network diagram : A-D-F-G-I = 32 A-D-F-H = 31 A-C-F-H = 29 A-C-F-G-I = 30 A-B-E-F-H = 30 A-B-E-F-G-I = 31
  • 22. Critical path – A-D-F-G-I = 32 1 8 7 6 3 5 4 2
  • 23. TIME ESTIMATES o Optimistic time (to) – It is the shortest time in which the activity can be completed. o Most likely time (tm) – It is the probable time required to perform the activity. o Pessimistic time (tp) – It is the longest estimated time required to perform an activity. o Expected time te = to + 4tm + tp 6
  • 24. STEPS IN PERT 1. Identify the specific activities. 2. Determine proper sequence of the activities. 3. Construct the network diagram. 4. Estimate the time required for each activity. 5. Determine the critical path. 6. Update the PERT chart.
  • 25. Activity Descrip tion Preced ence Optimis tic time Most Likely time Pessimi stic time Expecte d time A Initial design - 12 16 26 17 B Survey market A 6 9 18 10 C Build prototype A 8 10 18 11 D Test prototype C 2 3 4 3 E Redesign ing B,D 3 4 11 5 F Market testing E 6 8 10 8 G Set up productio n F 15 20 25 20
  • 26. 1 7652 3 4 A-B-E-F-G = 60 A-C-D-E-F-G = 64 (CRITICAL PATH)
  • 27. Advantages of PERT • Expected project completion time. • Probability of completion before a specified date. • The critical path activities that directly impact the completion time. • The activities that have slack time and that can lend resources to critical path activities. • Activity start and end dates.
  • 28. LIMITATIONS • The PERT Formula Requires Too Much Work. • The network charts tend to be large and unwieldy. • Calculating the time estimates is very complex for all the activities. • Updating of the project is time consuming and requires high costs. • Emphasis is laid only on time factors and cost factors are neglected.
  • 29. Difference between CPM & PERT CPM PERT • CPM works with fixed deterministic time • PERT works with probabilistic time • CPM is useful for repetitive and non complex projects with a certain degree of time estimates. • PERT is useful for non repetitive and complex projects with uncertain time estimates. • CPM includes time-cost trade off. • PERT is restricted to time variable. • CPM- for construction projects. • PERT- used for R&D programs.