SlideShare a Scribd company logo
1 of 16
Chapter 8
Scheduling
Project Management
A Managerial Approach
Solving the Network
The expected time, TE, Standard deviation
and variance
 TE = (a +4m +b2)/6
 where
 a optimistic time estimate
 b pessimistic time estimate
 m most likely time estimate, the mode
CRITICAL PATH CALCULATIONS
Critical Path: is the path through the network that takes
the longest total time. It therefore determines the earliest
possible time the project can be completed.
Critical path requires more careful monitoring, because if
they are not completed on time, the project will be late –
unless the subsequent activities are completed in less than
the scheduled time.
CRITICAL PATH CALCULATIONS
Critical Activity: An activity that has total float equal to zero. All
Activities on the critical path are known as Critical Activities.
Float/Slack: Float is the time available to retard or advance
the start time of an activity without delaying the completion of
the project.
CRITICAL PATH CALCULATIONS
The critical path calculations include two phases.
Forward Pass
Backward Pass
Forward Pass: The first phase is called the forward pass, where calculations
begin from the “start” node and move to the “end” node. At each node a
number is computed representing the earliest occurrence time of the
corresponding event.
Backward Pass: The second phase, called the backward pass, begins
calculations from the “end” node and moves to the “start” node. The number
computed at each node (shown in triangles Δ) represents the latest
occurrence time of the corresponding event.
Activity Days Precedents
a Schedule of liabilities 3 -
b Mail confirmation 15 a
c Test pension plan 5 a
d Vouch selected liabilities 60 a
e Test accruals 6 d
f Process confirmations 40 b
g Reconcile interest 10 c, e
h Verify debt compliance 7 f
i Investigate balances 6 g
j Review payments 12 h, i
Q#1 Draw the network and calculate the CP, and slack
times of activities
Question #2
A project consists of Six activities: A,B,C,D, E, F. A and B have no
preceding activities, but activity C requires that activity B must be
completed before C can begin. Activity D cannot start until both
activities A and B are complete. Activity F can start any time.
Activity E requires activities A and C to be completed before it can
start. If the activity times are A: 10 days; B: 4 days; C: 8 days; D: 3
days, E = 2 days, and F: 1 day,
 Find out the minimum time possible to complete this project.
 Are there any critical path activities? Which one are those?
Take no more than 20 minutes to solve the above problem. You may consult with
each other.
Gantt Charts
“A manner of illustrating multiple, time based
activities on a horizontal time scale”
 The Gantt chart shows planned and actual progress
for a number of tasks displayed against a horizontal
time scale
 It is an effective and easy-to-read method of
indicating the actual current status for each set of
tasks compared to the planned progress for each
item of the set
 It can be helpful in expediting, sequencing, and
reallocating resources among tasks
 Gantt charts usually do not show technical
dependencies
Chapter 8-14
Gantt Chart
Chapter 8-15
Gantt Charts
 There are several advantages to the use of Gantt
charts:
 Even though they may contain a great deal of
information, they are easily understood
 While they may require frequent updating, they are easy
to maintain
 Gantt charts provide a clear picture of the current state of
a project
 They are easy to construct
Chapter 8-16

More Related Content

What's hot

The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
Nicola2903
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
simu_mihai
 
05 critical path analysis
05 critical path analysis05 critical path analysis
05 critical path analysis
Sam Catlin
 

What's hot (20)

06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Network construction
Network construction  Network construction
Network construction
 
05 critical path analysis
05 critical path analysis05 critical path analysis
05 critical path analysis
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Critical Path Method presentation.
Critical Path Method presentation.Critical Path Method presentation.
Critical Path Method presentation.
 
CPM NETWORK
CPM NETWORKCPM NETWORK
CPM NETWORK
 

Similar to Ch08 pm2ndhalf

Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
Sonali Srivastava
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
annettsparrow
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
hannahpepino1
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 

Similar to Ch08 pm2ndhalf (20)

Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
Cpm pert asgm. prashant
Cpm pert asgm. prashantCpm pert asgm. prashant
Cpm pert asgm. prashant
 
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Ovi project
Ovi  projectOvi  project
Ovi project
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMAR
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 

More from Libra chudry

More from Libra chudry (19)

Final p pt km 16
Final p pt km 16Final p pt km 16
Final p pt km 16
 
Final p pt km 15
Final p pt km 15Final p pt km 15
Final p pt km 15
 
Final p pt km 06
Final p pt km 06Final p pt km 06
Final p pt km 06
 
Final p pt km 01
Final p pt km 01Final p pt km 01
Final p pt km 01
 
Three megatrends
Three megatrendsThree megatrends
Three megatrends
 
Human resource managemen
Human resource managemenHuman resource managemen
Human resource managemen
 
Project auditing
Project auditingProject auditing
Project auditing
 
Ch11(1)
Ch11(1)Ch11(1)
Ch11(1)
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Employee engagement
Employee engagementEmployee engagement
Employee engagement
 
Motivation
MotivationMotivation
Motivation
 
Scheduling
SchedulingScheduling
Scheduling
 
Supplier partnership
Supplier partnershipSupplier partnership
Supplier partnership
 
Hcpm
HcpmHcpm
Hcpm
 
High commitment performance management
High commitment performance managementHigh commitment performance management
High commitment performance management
 
Knowledge management
Knowledge managementKnowledge management
Knowledge management
 
The relationship between interpersonal conflict and workplace bullying
The relationship between interpersonal conflict and workplace bullyingThe relationship between interpersonal conflict and workplace bullying
The relationship between interpersonal conflict and workplace bullying
 
Variables & concepts
Variables & conceptsVariables & concepts
Variables & concepts
 
Budgeting and cost estimation
Budgeting and cost estimationBudgeting and cost estimation
Budgeting and cost estimation
 

Recently uploaded

obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
yulianti213969
 
Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...
DUBAI (+971)581248768 BUY ABORTION PILLS IN ABU dhabi...Qatar
 
Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312
LR1709MUSIC
 
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
bleessingsbender
 

Recently uploaded (20)

Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
 
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxGoal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Top Quality adbb 5cl-a-d-b Best precursor raw material
Top Quality adbb 5cl-a-d-b Best precursor raw materialTop Quality adbb 5cl-a-d-b Best precursor raw material
Top Quality adbb 5cl-a-d-b Best precursor raw material
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
 
Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...
 
Moradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in PenacovaMoradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in Penacova
 
Progress Report - Oracle's OCI Analyst Summit 2024
Progress Report - Oracle's OCI Analyst Summit 2024Progress Report - Oracle's OCI Analyst Summit 2024
Progress Report - Oracle's OCI Analyst Summit 2024
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptxThompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
 
Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312
 
A DAY IN THE LIFE OF A SALESPERSON .pptx
A DAY IN THE LIFE OF A SALESPERSON .pptxA DAY IN THE LIFE OF A SALESPERSON .pptx
A DAY IN THE LIFE OF A SALESPERSON .pptx
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON ESCORTS SERVICE PROVIDE
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON  ESCORTS SERVICE PROVIDEGURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON  ESCORTS SERVICE PROVIDE
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON ESCORTS SERVICE PROVIDE
 
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
 
10 Influential Leaders Defining the Future of Digital Banking in 2024.pdf
10 Influential Leaders Defining the Future of Digital Banking in 2024.pdf10 Influential Leaders Defining the Future of Digital Banking in 2024.pdf
10 Influential Leaders Defining the Future of Digital Banking in 2024.pdf
 
Managerial Accounting 5th Edition by Stacey Whitecotton test bank.docx
Managerial Accounting 5th Edition by Stacey Whitecotton test bank.docxManagerial Accounting 5th Edition by Stacey Whitecotton test bank.docx
Managerial Accounting 5th Edition by Stacey Whitecotton test bank.docx
 

Ch08 pm2ndhalf

  • 3.
  • 4. The expected time, TE, Standard deviation and variance  TE = (a +4m +b2)/6  where  a optimistic time estimate  b pessimistic time estimate  m most likely time estimate, the mode
  • 5.
  • 6.
  • 7.
  • 8.
  • 9. CRITICAL PATH CALCULATIONS Critical Path: is the path through the network that takes the longest total time. It therefore determines the earliest possible time the project can be completed. Critical path requires more careful monitoring, because if they are not completed on time, the project will be late – unless the subsequent activities are completed in less than the scheduled time.
  • 10. CRITICAL PATH CALCULATIONS Critical Activity: An activity that has total float equal to zero. All Activities on the critical path are known as Critical Activities. Float/Slack: Float is the time available to retard or advance the start time of an activity without delaying the completion of the project.
  • 11. CRITICAL PATH CALCULATIONS The critical path calculations include two phases. Forward Pass Backward Pass Forward Pass: The first phase is called the forward pass, where calculations begin from the “start” node and move to the “end” node. At each node a number is computed representing the earliest occurrence time of the corresponding event. Backward Pass: The second phase, called the backward pass, begins calculations from the “end” node and moves to the “start” node. The number computed at each node (shown in triangles Δ) represents the latest occurrence time of the corresponding event.
  • 12. Activity Days Precedents a Schedule of liabilities 3 - b Mail confirmation 15 a c Test pension plan 5 a d Vouch selected liabilities 60 a e Test accruals 6 d f Process confirmations 40 b g Reconcile interest 10 c, e h Verify debt compliance 7 f i Investigate balances 6 g j Review payments 12 h, i Q#1 Draw the network and calculate the CP, and slack times of activities
  • 13. Question #2 A project consists of Six activities: A,B,C,D, E, F. A and B have no preceding activities, but activity C requires that activity B must be completed before C can begin. Activity D cannot start until both activities A and B are complete. Activity F can start any time. Activity E requires activities A and C to be completed before it can start. If the activity times are A: 10 days; B: 4 days; C: 8 days; D: 3 days, E = 2 days, and F: 1 day,  Find out the minimum time possible to complete this project.  Are there any critical path activities? Which one are those? Take no more than 20 minutes to solve the above problem. You may consult with each other.
  • 14. Gantt Charts “A manner of illustrating multiple, time based activities on a horizontal time scale”  The Gantt chart shows planned and actual progress for a number of tasks displayed against a horizontal time scale  It is an effective and easy-to-read method of indicating the actual current status for each set of tasks compared to the planned progress for each item of the set  It can be helpful in expediting, sequencing, and reallocating resources among tasks  Gantt charts usually do not show technical dependencies Chapter 8-14
  • 16. Gantt Charts  There are several advantages to the use of Gantt charts:  Even though they may contain a great deal of information, they are easily understood  While they may require frequent updating, they are easy to maintain  Gantt charts provide a clear picture of the current state of a project  They are easy to construct Chapter 8-16