This document discusses project control and different types of control processes. It defines project control as keeping a project on target and as close to plan as possible. The three main types of control processes are cybernetic control, go/no-go control, and post control. Go/no-go controls involve testing if preset conditions have been met, while post controls are applied after a project to improve future performance. Effective control systems should be flexible, cost-effective, useful, timely, and accurate. Formal change control and clear change guidelines are also important aspects of project control.
3. Cost
Difficulties may need more resources
Scope may increase
Bid was be too low
Reporting was poor
Budget was inadequate
Correction not in time
Input price changed
4. Time
Difficulties took long to solve
Initial estimates were optimistic
Sequencing was incorrect
Resources unavailable
Preceding tasks were incomplete
Change orders
Governmental regulations were altered
5. Project Control
“The act of reducing the difference
between plan and reality”
The process of keeping the project on target
and as close to plan as feasibly possible.
Of course, this means you must first have a
plan
It also means you must have a way of
detecting when a project is off the target
6. The Fundamental Purposes of Control
To make the actual meet the plan
The Process
1. Identify key performance areas
2. Set standards
3. Measure performance
4. Compare
5. Take corrective action
7. Physical Asset Control
Control over the use of physical assets
Includes preventive and corrective
maintenance
Must also control inventory
8. Human Resource Control
Want to make sure people are used
wisely
Employees need to be motivated to
perform at their best
Project manager may have to write
performance appraisals
9. Financial Resource Control
Financial resource control is tied in with the
other types of control
Project financial controls are very similar to
general financial control
The project may be answerable to another
firm or division
It is important the project manager manage
financial assets properly
10. Three Types of Control Processes
1. Cybernetic control
2. Go/no-go control
3. Post control
11. Cybernetic Control
A system is constantly monitored
When a deviation is spotted, corrective
action is taken
Cybernetic controls are not common in
projects
12. Go/No-go Controls
Testing to see if some preset condition has
been met
Most of project management is go/no-go
controls
Use cannot be based on the calendar
– Some will take place at milestones
– Other will take place when work packages are
completed
– Still other will be on-going
13. Go/No-go Controls Continued
Data to be collected will match the
critical elements of the project plan
Actual is compared to what was
expected in the plan
Regular reports are given to the project
manager and senior management
14. Phase-Gated Processes
Controls the project at various points
throughout its life cycle
Most commonly used for new
product/service development projects
Project must pass gate to continue
funding
15. Post Control
These are controls that are applied
after-the-fact
Their purpose is mainly for improving
performance on future projects
Often times, a final report is prepared
comparing the plan with reality
Sometimes called “lessons learned”
16. Post Control Report Sections
1. The project objectives
2. Milestones, checkpoints, and budgets
3. The final report on project results
4. Recommendations for performance
and process improvement
17. The Design of Control Systems
Who sets the standards?
Are the standards realistic?
Are the standards clear?
Will they achieve the project goals?
What should be monitored?
How should they be monitored?
Many more…
18. Characteristics of a Good Control
System
Flexible
Cost effective
Useful
Ethical
Timely
Accurate
Simple
Easy to maintain
Can be changed
Fully documented
20. Critical Ratio
Critical ratio = actual progress X budgeted cost
scheduled progress actual cost
Indices and ratios greater than 1.0 are favorable
21. Control as a Function of Management
Control is usually exercised through people
Control is exercised when monitoring face a
problem
The control may come from any level of
management
The goal of the control is to get the project
back on track
22. Balance in a Control System
Too much control dampens innovation
A control system should correct errors
Corrections should be the smallest
needed
It should minimize its impact on people
23. Common Control System
Problems
1. Placing too much weight on easy-to-
measure factors
2. Emphasizing the short-run at the expense
of the long-run
3. Ignoring changes to the environment or
goals
4. Over-control by top management
5. “If it is not measured, it is not important”
24. Control of Creative Activities
Creativity is hard to control
Too much control will suppress
creativity
Three general approaches
1. Progress Review
2. Personnel Reassignment
3. Control of Input Resources
25. Formal Change Control System
Review requests for changes
Identify impacts
Translate impacts to plan
Evaluate cost and benefits
Identify alternative changes
Accept or reject
Communicate
Ensure implementation
Report
26. Change Guidelines
1. All contracts specify how change will
be handled
2. Any change requires a change order
3. Project manager must be consulted
4. Must be approved in writing
5. Master plan should reflect changes