SlideShare a Scribd company logo
1 of 9
Download to read offline
1/9
Civilverse Admin 4 September 2021
Critical Path Explained with 7 Q&As & a Free Excel
Template
civilverse.org/critical-path
Introduction to Critical Path Method-
1. Q1: What is a Critical Path Method?
2. Q2: What is a critical path & how does it affect the project completion?
3. Q3: What terms should I know to understand the critical path method?
4. Q4: How to identify the Critical Path & calculate the project duration?
5. Q5: How to check critical path?
6. Q6: Does critical path change?
7. Q7: What affects the critical path?
8. Free Excel Template to Calculate the Critical Path for Your Project
9. Final Words
2/9
Q1: What is a Critical Path Method?
Critical Path Method (CPM) is a project management technique used for scheduling. It
was developed in the late 1950s by Morgan Walker & E. Kelley Jr. in the USA. It is an
effective technique to identify the activities that directly affect the project duration.
A network diagram is the backbone of CPM. It is made up of activities logically &
sequentially linked to each other. Any two activities are linked by one of the below-given
relationships in a network diagram, therefore it is important to understand these links.
Finish to Start (FS): Anactivitystarts after the preceding activity ends.
Start to Start (SS): Two activities start together.
Finish to Finish (FF): Anactivity ends with another activity at the same time.
Start to Finish (SF): Successor activity ends before the start of preceding activity.
The above-mentioned links rule the project duration calculation and hence are of utmost
importance. A network diagram helps in the easy identification of activities that affect the
project completion most. What are these activities called? Read the next Q&A.
Q2: What is a critical path & how does it affect the project
completion?
A Critical path is the longest chain of activities in a network diagram that is to be done to
complete the project. The activities constituting the critical path are called critical
activities. The duration of critical activities governs the total duration of the project.
The critical path duration is the minimum time required to complete the project. Hence,
the delay in the execution of a critical activity leads to a delay in project completion. Also,
the float or slack for a critical activity is zero.
3/9
Confused about the float? what does that mean? The next section answers your query with
all the related CPM terminology.
Q3: What terms should I know to understand the critical path
method?
Earliest Start Time (EST): The time by which an activity can commence without
affecting its predecessor. It is equal to the earliest finish of predecessor activity.
Earliest Finish Time (EFT): Thesum total of activity duration and earliest finish
time of an activity is the earliest finish time for an activity. EFT represents the time
by which an activity can end at earliest.
Latest Start Time (LST): The LST is the time by which the start of an activity can
be delayed without affecting the succeeding activity.
Latest Finish Time (LFT): It is the most delayed time by which an activity can
end without affecting its successor.
Milestone: It is a task with zero duration and marks the start or end of the project
or an important task.
Dummy Activity: Dummy activity also has zero duration but it is different from
milestone. It is added in a network to show the relationship between activities when
the relationship cannot be shown by arrows. For example, in below network
diagram, a dummy activity is added to show the dependence of activity E on activity
C.
Forward Pass: It is a process of calculating the project completion by adding the
activity durations starting from the first activity to the last in a network diagram.
The ESTs and EFTs for each activity are calculated. The longest path (critical path)
in the network diagram has the shortest duration to complete the project.
Backward Pass: It is a process of back calculating the duration of a project
starting from its end date. The LSTs & LFTs are calculated.
Float: Itis a duration by which an activity can be delayed without affecting the
project completion. The activity float is the difference between EST & LST or EFT &
LFT of an activity. As said earlier, the critical activities have zero float and hence the
EST=LST & EFT=LFT.
Activity Crash: The process ofreducing the activity duration by assigning
additional resources is called activity crash. The cost of crashing an activity
generally higher than the normal execution of an activity. It is generally used to
cover up the delay on critical path.
Q4: How to identify the Critical Path & calculate the project
duration?
We will understand the process with the help of an example. The below table contains a
list of activities to complete the project.
4/9
Nomenclature for Network Diagram
We will follow the below-given nomenclature and format for the network diagram.
Let us create a network diagram and calculate the
EST, EFT, LST & LFT for each activity.
Network Diagram with Activity Duration
After the network diagram, we will do a forward pass with the following steps.
Forward Pass
The starting activity is assumed to start on zero date and it acts as EST for activity A.
The EFT of activity A is calculated by (EST + duration of A).
The EFT of activity A acts as EST for its’ predecessor activity (i.e., activity B).
Process is repeated for each activity.
For activity H, the EST comes from two different activities i.e., E &G. The higher
value of the two is considered.
The EFT of end activity (i.e., activity H) is the project duration (i.e., 19 days for the
given example).
5/9
Forward Pass for Calculation of EST & EFT
Now, we will perform a backward pass.
Backward Pass
The EFT of end activity H is its’ LFT.
The LST of activity H is calculated by deducting the duration from LFT.
The LST of each activity acts as the LFT for its’ predecessor.
For activities having two successors, the LFTs are two. Take the smaller value as the
LFT of that activity.
Backward Pass for Calculation of LST & LFT
Float Calculation
The difference between early and late time is float for that activity.
Float Calculation
Critical Path Determination
6/9
The chain of activities having zero float is the critical path for the project. In the
given example, the critical path is A-B-C-F-G-H.
Q5: How to check critical path?
Now, we have determined the critical path it is important to check if it is the correct one
before reporting it to stakeholders. For checking the authenticity of critical there are two
methods as mentioned in the DCMA 14-point schedule quality metrics. Let us discuss
them.
Critical Path Test
It is a simple test involving a critical activity. Perform this as below mentioned steps.
Choose any one of the critical activities.
Increase the duration of this activity by x number of days.
Recalculate the project duration.
Now, the project duration has also increased by x days. If so, the network diagram is
said to have passed the critical path test.
A failed critical path test indicates the missing relationship between the activities.
Critical Path Length Index
This test checks the likelihood of achieving the targeted completion date. Follow the
below-given steps to check the CPLI.
Calculate the remaining working days on critical path.
Calculate the total float.
Calculate the total remaining days.
Now, add the remaining working days and total float. Divide the obtained sum by
the remaining days. This gives the CPLI.
A CPLI of 1 indicates the project will complete on time. Value lesser than 1 indicates the
delay and the CPLI of greater than 1 show the early completion of the project than the
planned date.
Q6: Does critical path change?
Yes, it does. During the project execution, some tasks may get delayed, expedited or
experience their duration change and hence, their ETs & LTs change. The change in ETs
and LTs result in a change in float and hence the critical path.
Let us understand with the same example as explained earlier. During the 9 day of
project execution (after completion of activity B) following points were observed-
The activity B took 6 days to complete against the original duration of 5 days.
th
7/9
The activity D will take 6 days to complete against the original planned duration of 1
day due to various reasons.
Due to the above changes, the forward and backward passes are to be re-done. Now, ETs
and LTs of the upcoming activities have changed so is their float. Following are the
changes-
Change in Critical Path
The float of activities C, F & G have increase from 0 to 2 thus, are not on critical path
anymore.
The activities D & E have become critical activities as their float of 1 day has reduced
to zero.
Q7: What affects the critical path?
If you have gone through the entire post, you must have figured out some of the factors
affecting the critical path. Here, I have summarised them.
Inter-dependency between the activities.
Duration of an activity. The uncertainty of activity duration leads to the risk of
critical path change. Also, the incorrect estimation of activity duration may generate
misguided metrics. Read these 6 powerful methods to correctly estimate the
activity durations.
Work breakdown structure. The incorrect capturing of the project scope or the
level of decomposition of scope may affect the sequencing and relationship between
the activities thus, affecting the critical path.
Resource assignment to the activity. If the assigned resource is changed or
increased/decreased or there is difference in planned and actual productivity, the
duration of activity changes.
Updating of the project. Inaccurate measurement of works or tasks missed
during the update may lead to change in the critical path.
Free Schedule Excel Template to Calculate the Critical Path for
Your Project
8/9
Download the free excel schedule template for a residential building project. The template
calculates the ETs, LTs and the float for each activity. The critical activities are highlighted
in yellow and the separate column also tells the critical activity status. The expected
completion dates for upcoming and in-progress summary tasks are projected in the actual
finish column.
Excel Template Snapshot
In the in-built Gantt chart, the critical path is highlighted with red bars.
Download the Excel Template for Critical Path Determination
The purpose of this excel is to reinforce the concepts of ET, FT and float calculation. You
can also customise this excel to your needs. However, scheduling software like MS Project
and Primavera will give more accurate results and hence they are preferable.
Final Words
The importance of a critical path is undeniable in project management. Hence, the correct
implementation of the critical path method is necessary to get the correct picture of the
progress. The float consumption of near-critical activities should be well observed and
reported in advance.
The critical path should also be built with uncertainty to accommodate the minor
fluctuations in activity duration. However, the decision for the same should be made in
line with the stakeholder’s expectations.
Due to the vast concepts of the critical path method and multiple implications, only the
basic information has been covered in this article to introduce the concepts to beginners.
Also, the experts can brush up on their basics and provide feedback and expert opinions
in the comments below.
Read more about the project schedule in this beginner’s guide for the project schedule.
Get this another project schedule Gantt template for planned and actual cost, delay
analysis and dashboard.
Correctly estimate the construction labour requirement with this labour planning
template.
9/9

More Related Content

What's hot

Site visit report
Site visit reportSite visit report
Site visit reportJıa Yıı
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS projectSamir Paralikar
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...marcus evans Network
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHICJonathan Donado
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projectsakashpadole
 
Critical path method
Critical path methodCritical path method
Critical path methodNicola2903
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Site organization and networking techniques
Site organization and networking techniquesSite organization and networking techniques
Site organization and networking techniquestivar rose
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control ChecklistAnand Subramaniam
 
Earned value management
Earned value managementEarned value management
Earned value managementAshif AR
 
Recent construction technologies
Recent construction technologiesRecent construction technologies
Recent construction technologiesChandana Yadav
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Chetanraj M
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...Shamil Habet
 

What's hot (20)

Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Site organization and networking techniques
Site organization and networking techniquesSite organization and networking techniques
Site organization and networking techniques
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control Checklist
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Recent construction technologies
Recent construction technologiesRecent construction technologies
Recent construction technologies
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
project management (10).pptx
project management (10).pptxproject management (10).pptx
project management (10).pptx
 

Similar to Critical Path Explained With 7 Q&As and a Free Excel Template

Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxmohammad_bilal
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pertBhim Upadhyaya
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)hannahpepino1
 
Focus on CPM and Resp Matrix
Focus on CPM and Resp MatrixFocus on CPM and Resp Matrix
Focus on CPM and Resp Matrixdmdk12
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLSiddanna Balapgol
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttAbdisalamMohamud5
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 

Similar to Critical Path Explained With 7 Q&As and a Free Excel Template (20)

Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
pert/cpm
pert/cpmpert/cpm
pert/cpm
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pert
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
Focus on CPM and Resp Matrix
Focus on CPM and Resp MatrixFocus on CPM and Resp Matrix
Focus on CPM and Resp Matrix
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
Cpm pert asgm. prashant
Cpm pert asgm. prashantCpm pert asgm. prashant
Cpm pert asgm. prashant
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
 
CPM and PERT
CPM and  PERTCPM and  PERT
CPM and PERT
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþtttttttttttttt
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
Pert 182
Pert 182Pert 182
Pert 182
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 

More from SHAZEBALIKHAN1

5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateSHAZEBALIKHAN1
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction WorksSHAZEBALIKHAN1
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateSHAZEBALIKHAN1
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileSHAZEBALIKHAN1
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteSHAZEBALIKHAN1
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepSHAZEBALIKHAN1
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract ManagementSHAZEBALIKHAN1
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceSHAZEBALIKHAN1
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?SHAZEBALIKHAN1
 

More from SHAZEBALIKHAN1 (20)

5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and Deep
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract Management
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & Performance
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 

Critical Path Explained With 7 Q&As and a Free Excel Template

  • 1. 1/9 Civilverse Admin 4 September 2021 Critical Path Explained with 7 Q&As & a Free Excel Template civilverse.org/critical-path Introduction to Critical Path Method- 1. Q1: What is a Critical Path Method? 2. Q2: What is a critical path & how does it affect the project completion? 3. Q3: What terms should I know to understand the critical path method? 4. Q4: How to identify the Critical Path & calculate the project duration? 5. Q5: How to check critical path? 6. Q6: Does critical path change? 7. Q7: What affects the critical path? 8. Free Excel Template to Calculate the Critical Path for Your Project 9. Final Words
  • 2. 2/9 Q1: What is a Critical Path Method? Critical Path Method (CPM) is a project management technique used for scheduling. It was developed in the late 1950s by Morgan Walker & E. Kelley Jr. in the USA. It is an effective technique to identify the activities that directly affect the project duration. A network diagram is the backbone of CPM. It is made up of activities logically & sequentially linked to each other. Any two activities are linked by one of the below-given relationships in a network diagram, therefore it is important to understand these links. Finish to Start (FS): Anactivitystarts after the preceding activity ends. Start to Start (SS): Two activities start together. Finish to Finish (FF): Anactivity ends with another activity at the same time. Start to Finish (SF): Successor activity ends before the start of preceding activity. The above-mentioned links rule the project duration calculation and hence are of utmost importance. A network diagram helps in the easy identification of activities that affect the project completion most. What are these activities called? Read the next Q&A. Q2: What is a critical path & how does it affect the project completion? A Critical path is the longest chain of activities in a network diagram that is to be done to complete the project. The activities constituting the critical path are called critical activities. The duration of critical activities governs the total duration of the project. The critical path duration is the minimum time required to complete the project. Hence, the delay in the execution of a critical activity leads to a delay in project completion. Also, the float or slack for a critical activity is zero.
  • 3. 3/9 Confused about the float? what does that mean? The next section answers your query with all the related CPM terminology. Q3: What terms should I know to understand the critical path method? Earliest Start Time (EST): The time by which an activity can commence without affecting its predecessor. It is equal to the earliest finish of predecessor activity. Earliest Finish Time (EFT): Thesum total of activity duration and earliest finish time of an activity is the earliest finish time for an activity. EFT represents the time by which an activity can end at earliest. Latest Start Time (LST): The LST is the time by which the start of an activity can be delayed without affecting the succeeding activity. Latest Finish Time (LFT): It is the most delayed time by which an activity can end without affecting its successor. Milestone: It is a task with zero duration and marks the start or end of the project or an important task. Dummy Activity: Dummy activity also has zero duration but it is different from milestone. It is added in a network to show the relationship between activities when the relationship cannot be shown by arrows. For example, in below network diagram, a dummy activity is added to show the dependence of activity E on activity C. Forward Pass: It is a process of calculating the project completion by adding the activity durations starting from the first activity to the last in a network diagram. The ESTs and EFTs for each activity are calculated. The longest path (critical path) in the network diagram has the shortest duration to complete the project. Backward Pass: It is a process of back calculating the duration of a project starting from its end date. The LSTs & LFTs are calculated. Float: Itis a duration by which an activity can be delayed without affecting the project completion. The activity float is the difference between EST & LST or EFT & LFT of an activity. As said earlier, the critical activities have zero float and hence the EST=LST & EFT=LFT. Activity Crash: The process ofreducing the activity duration by assigning additional resources is called activity crash. The cost of crashing an activity generally higher than the normal execution of an activity. It is generally used to cover up the delay on critical path. Q4: How to identify the Critical Path & calculate the project duration? We will understand the process with the help of an example. The below table contains a list of activities to complete the project.
  • 4. 4/9 Nomenclature for Network Diagram We will follow the below-given nomenclature and format for the network diagram. Let us create a network diagram and calculate the EST, EFT, LST & LFT for each activity. Network Diagram with Activity Duration After the network diagram, we will do a forward pass with the following steps. Forward Pass The starting activity is assumed to start on zero date and it acts as EST for activity A. The EFT of activity A is calculated by (EST + duration of A). The EFT of activity A acts as EST for its’ predecessor activity (i.e., activity B). Process is repeated for each activity. For activity H, the EST comes from two different activities i.e., E &G. The higher value of the two is considered. The EFT of end activity (i.e., activity H) is the project duration (i.e., 19 days for the given example).
  • 5. 5/9 Forward Pass for Calculation of EST & EFT Now, we will perform a backward pass. Backward Pass The EFT of end activity H is its’ LFT. The LST of activity H is calculated by deducting the duration from LFT. The LST of each activity acts as the LFT for its’ predecessor. For activities having two successors, the LFTs are two. Take the smaller value as the LFT of that activity. Backward Pass for Calculation of LST & LFT Float Calculation The difference between early and late time is float for that activity. Float Calculation Critical Path Determination
  • 6. 6/9 The chain of activities having zero float is the critical path for the project. In the given example, the critical path is A-B-C-F-G-H. Q5: How to check critical path? Now, we have determined the critical path it is important to check if it is the correct one before reporting it to stakeholders. For checking the authenticity of critical there are two methods as mentioned in the DCMA 14-point schedule quality metrics. Let us discuss them. Critical Path Test It is a simple test involving a critical activity. Perform this as below mentioned steps. Choose any one of the critical activities. Increase the duration of this activity by x number of days. Recalculate the project duration. Now, the project duration has also increased by x days. If so, the network diagram is said to have passed the critical path test. A failed critical path test indicates the missing relationship between the activities. Critical Path Length Index This test checks the likelihood of achieving the targeted completion date. Follow the below-given steps to check the CPLI. Calculate the remaining working days on critical path. Calculate the total float. Calculate the total remaining days. Now, add the remaining working days and total float. Divide the obtained sum by the remaining days. This gives the CPLI. A CPLI of 1 indicates the project will complete on time. Value lesser than 1 indicates the delay and the CPLI of greater than 1 show the early completion of the project than the planned date. Q6: Does critical path change? Yes, it does. During the project execution, some tasks may get delayed, expedited or experience their duration change and hence, their ETs & LTs change. The change in ETs and LTs result in a change in float and hence the critical path. Let us understand with the same example as explained earlier. During the 9 day of project execution (after completion of activity B) following points were observed- The activity B took 6 days to complete against the original duration of 5 days. th
  • 7. 7/9 The activity D will take 6 days to complete against the original planned duration of 1 day due to various reasons. Due to the above changes, the forward and backward passes are to be re-done. Now, ETs and LTs of the upcoming activities have changed so is their float. Following are the changes- Change in Critical Path The float of activities C, F & G have increase from 0 to 2 thus, are not on critical path anymore. The activities D & E have become critical activities as their float of 1 day has reduced to zero. Q7: What affects the critical path? If you have gone through the entire post, you must have figured out some of the factors affecting the critical path. Here, I have summarised them. Inter-dependency between the activities. Duration of an activity. The uncertainty of activity duration leads to the risk of critical path change. Also, the incorrect estimation of activity duration may generate misguided metrics. Read these 6 powerful methods to correctly estimate the activity durations. Work breakdown structure. The incorrect capturing of the project scope or the level of decomposition of scope may affect the sequencing and relationship between the activities thus, affecting the critical path. Resource assignment to the activity. If the assigned resource is changed or increased/decreased or there is difference in planned and actual productivity, the duration of activity changes. Updating of the project. Inaccurate measurement of works or tasks missed during the update may lead to change in the critical path. Free Schedule Excel Template to Calculate the Critical Path for Your Project
  • 8. 8/9 Download the free excel schedule template for a residential building project. The template calculates the ETs, LTs and the float for each activity. The critical activities are highlighted in yellow and the separate column also tells the critical activity status. The expected completion dates for upcoming and in-progress summary tasks are projected in the actual finish column. Excel Template Snapshot In the in-built Gantt chart, the critical path is highlighted with red bars. Download the Excel Template for Critical Path Determination The purpose of this excel is to reinforce the concepts of ET, FT and float calculation. You can also customise this excel to your needs. However, scheduling software like MS Project and Primavera will give more accurate results and hence they are preferable. Final Words The importance of a critical path is undeniable in project management. Hence, the correct implementation of the critical path method is necessary to get the correct picture of the progress. The float consumption of near-critical activities should be well observed and reported in advance. The critical path should also be built with uncertainty to accommodate the minor fluctuations in activity duration. However, the decision for the same should be made in line with the stakeholder’s expectations. Due to the vast concepts of the critical path method and multiple implications, only the basic information has been covered in this article to introduce the concepts to beginners. Also, the experts can brush up on their basics and provide feedback and expert opinions in the comments below. Read more about the project schedule in this beginner’s guide for the project schedule. Get this another project schedule Gantt template for planned and actual cost, delay analysis and dashboard. Correctly estimate the construction labour requirement with this labour planning template.
  • 9. 9/9