SlideShare a Scribd company logo
Chapter six
Network Analysis with
CPM and PERT
By;-Dagnaygebaw Goshme (MSc.)
6.1.Basic concepts on net work
A 'network' is defined as a graphic representation with a
flow of some type in its branches. It represents
nodes and branches.
A node is the intersection of the two branch lines. It is
denoted by a circle.
Each node represents an event, which is a specific
definable accomplishment recognizable at a particular
instant of time.
Each branch represents an activity.
The arrowheads indicate the sequence in which events
must be achieved.
Thus an event is the completion of all the activities leading
into that node and this event must precede the
initiation of the activity leading out of the node.
node Branch node
Example 1: A company is interested in preparing a
budget. The details of the activities and the
departments involved are given in the Table.
The project of budgeting can be displayed in a
network or project graph by an arrow diagram. Jobs
are shown as arrows leading from one node to the
other as in Figure
From the arrow diagram, we infer that:
activity A is the first job.
Jobs B and C start only after A is over.
A is called the predecessor of B and C and
B and C the successors of A.
Rules for Construction of Network
(a) Each activity is represented by one and only one arrow.
 This means that no single activity can be
represented twice in a network.
(b) No two activities can be identified by the same end events.
This means that there should not be loops in the network.
(c)Time follows from left to right.
All the arrows point in one direction.Arrows pointing in
opposite direction must be avoided.
(d) Arrows should not cross each other.
(e) Every node must have at least one activity preceding it and at
least one activity following it, except for the nodes at the very
beginning and at the very end of the network
Dummy Activities
 There is a need for dummy activities when the
project contains groups of two or more jobs which
have common predecessors.
 The time taken for the dummy activities is zero.
 Suppose we have the following project of jobs with
their immediate predecessors.
Activity B is the common immediate predecessor of both D
and E.
A is the immediate predecessor of D alone and C is the
predecessor of E.
Let B lead into two dummy jobs D1 and D2 and let D1 be
an immediate predecessor of D and D2 of E as shown in
Figure
Dummy arrow represents an activity with zero time duration.
It is represented by a dotted line and is introduced in a network
to clarify activity pattern under the following situations.
(i) It is created to make activities with common starting and
finishing events distinguishable.
(ii)To identify and maintain the proper precedence relationship
between activities those are not connected by events.
Consider an example where A and B are parallel (concurrent
activities). C is dependent on A and D is dependent on both A
and B.
Such a situation can be represented easily by use of dummy
activity as shown in Figure
Example 2: A project consists of the following activities
whose precedence relationship is given below. Draw an arrow
diagram to represent the project.
Since B & C are the immediate predecessor of H
CPM(Critical Path Method)
It is also a network technique but it is concerned with
obtaining the trade-off, between cost and
completion date for large projects.
In any project consisting of several activities each
activity can be completed in a normal duration with
normal cost.
If we employ more persons or skilled people or given
overtime to the workers, the activity could be
completed in a reduced duration known as crash
duration.
But this involves an increased cost in the form of
additional resources.
With CPM the amount needed to complete the
various activities is assumed to be known with
certainty.
 So, the direct costs for the activities increase and hence the cost of the
project also increases.
 By reducing the activity duration of some or all possible
completed ahead of the schedule.
 This will naturally reduce the overhead cost for the entire
project.
 On one hand the direct expenses increase, if we shorten the activity
duration, but, the indirect expenses for the project are reduced.
 We have to strike a balance or an optimum time schedule, or
a least cost schedule is to be obtained.This is the purpose of
the Critical Path Method.
 CPM is mostly used in construction projects, or in situations
already handled, so that the details like
the normal completion time,
crash duration and
cost of crashing are already known.
 The critical path method (CPM) aims at:-
 The determination of the time to complete a project
 The important activities on which a manager shall focus
attention.
 From the start event to the end event, the time required to
complete all the activities of the project in the specified sequence
is known as the project completion time.
 A continuous sequence, consisting of nodes and activities
alternatively, beginning with the start event and stopping at the end
event of a network is called a path in the network.
 The path with the largest time is called the critical path and
the activities along this path are called the critical activities
or bottleneck activities.
 The activities are called critical because they cannot be
delayed.
 In CPM, it is assumed that precise time estimate is available
for each activity.
To FindThe Critical Path
 After listing all the activities with their precedence relationship we
project these activities in a project graph represented by arrows or
Activity On Node diagram (AON).
 Now we have to find the minimum time required for completion of
the entire project.
 For this we must find the longest path with the sequence of
connected activities through the network. This is called the critical
path of the network and its length determines the time for
completion of the project.
 The activities in the critical path are so critical that, if they are
delayed, the project completion date cannot be met and the project
finish time will have to be extended.
 We shall now see how to identify the critical path, the critical
activities and the duration of the project.
 The meaning of path and length of a path should first be made clear.
D
We have five activities A, B, C, D and E with the time of
completion of the activities 5, 6, 7, 3 and 6 days respectively.
In this network, there are three ways to get from the
starting point at node 1 and travel through the network to
end at node 4.
These ways are called paths.Thus, a path is defined as "a
set of nodes connected by lines which begin at the initial
node of a network and end at the terminal node".
There are three paths namely, 1-3-4,1-2-3-4 and 1-2-4
where the numbers represent the nodes.
 The length of a path in a network is the total time it takes to
travel along the path.
 This time is calculated by adding the individual times between the
connected nodes on the path.
 A path is called a critical path if it is the longest the path in a
project network.
 We have the times of the three distinct paths has shown below.
 Path Time (days)
1-3-4 5 + 3 = 8 days
1-2-3-4 6 + 7 + 3 = 16
1-2-4 6 + 6 = 12
 The path connecting the nodes 1,2,3 and 4 constitutes the longest
path and hence 1-2-3-4 is the critical path.
 The minimum time to complete the project is the time taken for
the longest path namely 16 days.
 The activities B (1-2), C (2-3) and D(3-4) constitute the critical
activities.
 These jobs are critical in determining the project's duration.
Determine the critical path, the critical activities and the
project completion time.
Consider the paths, beginning with the start node
and stopping with the end node.There are two such
paths for the given project.
A- B- D- F= time of 3 + 5 + 10 + 4 = 22 weeks.
A -C –E- F= time of 3 + 7 + 5 + 4 = 19 weeks.
Compare the times for the two paths. Maximum of
{22,19} = 22.
We see that path I has the maximum time of 22
weeks.Therefore, path I is the critical path.The
critical activities are A, B, D and F.
The project completion time is 22 weeks.
We notice that C and E are non- critical activities.
Find out the completion time and the critical activities for the following
project
we identify 4 paths, beginning with the start node of 1 and terminating at the
end node of 10.They are as follows:
Path I ,A D G K=Time for the path = 8 + 20 + 8 + 6 = 42 units of time
Path II, B E H K=Time for the path = 10 + 16 + 11 + 6 = 43 units of time
Path III, B E I L=Time for the path = 10 + 16 + 14 + 5 = 45 units of time.
Path IV, C F J L=Time for the path = 7 + 25 + 10 + 5 = 47 units of time.
Maximum of {42, 43, 45, 47} = 47 which is a critical path.And critical activities
are C, F, J and L.The non-critical activities are A, B, D, E, G, H, I and K.The
project completion time is 47 units .
PERT "Programme Evaluation and
ReviewTechnique
It was created as a means to plan and accelerate the
development of the Polaris Ballistic Missile.
In USA the defense department developed a nuclear
missile to be launched from beneath the ocean's
surface by a mobile submarine, which would be an
effective deterrent against aggression by an enemy.
This paved way to plan how to design, develop and
plan the different stages in the production of a missile
and how quickly this task could be completed.
A planning and scheduling technique named PERT gave
the answer to these questions.
In any new venture, uncertainties are bound to creep
in.
PERT incorporated these uncertainties into a
model, which provides a reasonable answer to these
uncertainties.
There are certain statistical aspects scheduling large
projects consisting of numerous activities whose
completion times are uncertain and are
independent of one another.
PERT is an event-oriented technique.
By 'event' we mean reaching a certain stage of
completion of the project.
PERT is useful in research and developmental
projects,
Programme Evaluation and Review Technique
(PERT) is a tool that would help a project manager
in project planning and control.
It would enable him in continuously monitoring a
project and taking corrective measures wherever
necessary.
This technique involves statistical methods.
In PERT, we assume that it is not possible to have
precise time estimate for each activity and instead,
probabilistic estimates of time alone are possible.
A multiple time estimate approach is followed here.
In probabilistic time estimate, the following 3 types
of estimate are possible:
1. Pessimistic time estimate ( P t )
2. Optimistic time estimate ( O t )
3. Most likely time estimate ( M t )
The optimistic estimate of time is based on the
assumption that an activity will not involve any
difficulty during execution and it can be completed
within a short period.
On the other hand, a pessimistic estimate is made
on the assumption that there would be unexpected
problems during the execution of an activity and hence
it would consume more time.
The most likely time estimate is made in between
the optimistic and the pessimistic estimates of time.
Thus the three estimates of time have the relationship
to < tm < tp
 Practically speaking, neither the pessimistic nor the
optimistic estimate may hold in reality and it is the most
likely time estimate that is expected to prevail in almost
all cases.
 Therefore, it is preferable to give more weight to the most
likely time estimate.
 We give a weight of 4 to most likely time estimate and a
weight of 1 each to the pessimistic and optimistic time
estimates.
 We arrive at a time estimate ( te) as the weighted average of
these estimates as follows:
Since we have taken 6 units ( 1 for P t , 4 for M t
and 1 for O t ), we divide the sum by 6.
With this time estimate, we can determine the
project completion time as better applicable as
compared to CPM.
Since PERT involves the average of three
estimates of time for each activity, this method is
very practical and the results from PERT will be have
a reasonable amount of reliability.
Measure of Certainty
The 3 estimates of time are such that
to < tm < tp
Therefore the range for the time estimate is tp - to.
The time taken by an activity in a project network follows a
distribution with a standard deviation of one sixth of the
range, approximately.
The certainty of the time estimate of an activity can be
analyzed with the help of the variance.
The greater the variance, the more uncertainty in the
time estimate of an activity.
 Example
Two experts A and B examined an activity and arrived
at the following time estimates.
Experts Time Estimate
to tm tp
A 4 6 8
B 4 7 10
Determine which expert is more certain about his
estimates of time:
Using the single time estimates of the activities, we get the
following network diagram for the project.
There are four such paths for the given project.They are as
follows:
Path I, A B D F H=Time for the path: 4+6+12+21+5 = 48 days.
Path II, A B D G I=Time for the path: 4+6+12+ 6+3 = 31 days.
Path III,A C E F H= Time for the path: 4+10+9+ 21+5 = 49 days.
Path IV, A C E G I= Time for the path: 4+10+9+ 6+3 = 32 days.
1 2
3
4
5
6
7
8
A, 4
 Compare the times for the four paths.
Maximum of {48, 31, 49, 32} = 49.
We see that Path III has the maximum time.
Therefore the critical path is Path III. i.e., 1  2 4
5  6  8
The critical activities are A, C, E, F and H.
The non-critical activities are B, D, G and I.
Project time (Also called project length) = 49 days.
1
6
7
8
2
3
4
5
Path I, A C F I= Time for the path: 6+12+11+4 = 33 weeks.
Path II, A D G I= Time for the path: 6+5+7+ 4= 22 weeks.
Path III, B E H=Time for the path: 5+9+15 = 29 weeks
Compare the times for the three paths.
Maximum of {33, 22, 29} = 33.
It is noticed that Path I has the maximum time.
Therefore the critical path is Path I. i.e., 1  2  3
 5  8
The critical activities are A, C, F and I.
The non-critical activities are B, D, G and H.
Project time = 33 weeks.
Calculation of Standard Deviation and
Variance for the Critical Activities:
Variance of project time (Also calledVariance of project
length) = Sum of the variances for the critical activities =
1+4+1+ 4/9 = 58/9Weeks.
Standard deviation of project time = √Variance = √58/9 =
2.54 weeks.
The following are the suggested applications when
PERT or CPM is found useful.
The construction of a building or of a highway.
Planning and launching a new product.
Scheduling maintenance for a project.
The manufacture and assembly of a large machine tool.
To conduct a music or drama festival.
Preparation of budget for a company.

More Related Content

What's hot

Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
Asif Sultan Razu
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
student
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
Munaf Dayee
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
Prasad Thanthratey
 
Cpmpert
CpmpertCpmpert
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Critical path method
Critical path methodCritical path method
Critical path method
Dushyant Nasit
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Zulfiquer Ahmed Amin
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
Amrit Mty
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
Mayur Rahangdale
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
briankirui9
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
Shashank Kapoor
 
Project networks
Project networksProject networks
Project networks
J. Scott Christianson
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
Ganesh Kandalkar
 
Critical path method
Critical path methodCritical path method
Critical path method
Shubhi Verma
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
ahsanrabbani
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
Jignesh Kariya
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
DavidMcLachlan1
 

What's hot (20)

Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Cpmpert
CpmpertCpmpert
Cpmpert
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Project networks
Project networksProject networks
Project networks
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 

Similar to Unit.6. network analysis with cpm and pert

PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
IrfanPathan88
 
CPM PERT.pptx
CPM PERT.pptxCPM PERT.pptx
CPM PERT.pptx
MumtazAli889808
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
IrtizaMalik
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
SAJID ALI RUK
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 
Lecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdfLecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdf
AbdulMajeetMohamed
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
TecnicoItca
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Cpm pert asgm. prashant
Cpm pert asgm. prashantCpm pert asgm. prashant
Cpm pert asgm. prashant
Prashant Bhadauria
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
DhesinghRajaLekha
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
Pulchowk Campus
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
Sougata Das
 
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docxOperations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
hopeaustin33688
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
Dr.R. SELVAM
 
Basics CPM&PERT.ppt
Basics CPM&PERT.pptBasics CPM&PERT.ppt
Basics CPM&PERT.ppt
ssuserad50d3
 
Network analysis
Network analysisNetwork analysis
Network analysis
Mohit Mahajan
 
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxYagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
jeffevans62972
 

Similar to Unit.6. network analysis with cpm and pert (20)

PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
CPM PERT.pptx
CPM PERT.pptxCPM PERT.pptx
CPM PERT.pptx
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Lecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdfLecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdf
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
Cpm pert asgm. prashant
Cpm pert asgm. prashantCpm pert asgm. prashant
Cpm pert asgm. prashant
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docxOperations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Basics CPM&PERT.ppt
Basics CPM&PERT.pptBasics CPM&PERT.ppt
Basics CPM&PERT.ppt
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxYagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
 

More from DagnaygebawGoshme

Unit.5. transportation and assignment problems
Unit.5. transportation and assignment problemsUnit.5. transportation and assignment problems
Unit.5. transportation and assignment problems
DagnaygebawGoshme
 
Unit.4.integer programming
Unit.4.integer programmingUnit.4.integer programming
Unit.4.integer programming
DagnaygebawGoshme
 
Unit.3. duality and sensetivity analisis
Unit.3. duality and sensetivity analisisUnit.3. duality and sensetivity analisis
Unit.3. duality and sensetivity analisis
DagnaygebawGoshme
 
Unit.2. linear programming
Unit.2. linear programmingUnit.2. linear programming
Unit.2. linear programming
DagnaygebawGoshme
 
Unit.1 . introduction to oprational research
Unit.1 . introduction to oprational researchUnit.1 . introduction to oprational research
Unit.1 . introduction to oprational research
DagnaygebawGoshme
 
linear programming
linear programming linear programming
linear programming
DagnaygebawGoshme
 

More from DagnaygebawGoshme (6)

Unit.5. transportation and assignment problems
Unit.5. transportation and assignment problemsUnit.5. transportation and assignment problems
Unit.5. transportation and assignment problems
 
Unit.4.integer programming
Unit.4.integer programmingUnit.4.integer programming
Unit.4.integer programming
 
Unit.3. duality and sensetivity analisis
Unit.3. duality and sensetivity analisisUnit.3. duality and sensetivity analisis
Unit.3. duality and sensetivity analisis
 
Unit.2. linear programming
Unit.2. linear programmingUnit.2. linear programming
Unit.2. linear programming
 
Unit.1 . introduction to oprational research
Unit.1 . introduction to oprational researchUnit.1 . introduction to oprational research
Unit.1 . introduction to oprational research
 
linear programming
linear programming linear programming
linear programming
 

Recently uploaded

The new type of smart, sustainable entrepreneurship and the next day | Europe...
The new type of smart, sustainable entrepreneurship and the next day | Europe...The new type of smart, sustainable entrepreneurship and the next day | Europe...
The new type of smart, sustainable entrepreneurship and the next day | Europe...
Antonis Zairis
 
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
betoozp
 
Webinar Exploring DORA for Fintechs - Simont Braun
Webinar Exploring DORA for Fintechs - Simont BraunWebinar Exploring DORA for Fintechs - Simont Braun
Webinar Exploring DORA for Fintechs - Simont Braun
FinTech Belgium
 
Introduction to Indian Financial System ()
Introduction to Indian Financial System ()Introduction to Indian Financial System ()
Introduction to Indian Financial System ()
Avanish Goel
 
how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.
DOT TECH
 
how can i use my minded pi coins I need some funds.
how can i use my minded pi coins I need some funds.how can i use my minded pi coins I need some funds.
how can i use my minded pi coins I need some funds.
DOT TECH
 
Chương 6. Ancol - phenol - ether (1).pdf
Chương 6. Ancol - phenol - ether (1).pdfChương 6. Ancol - phenol - ether (1).pdf
Chương 6. Ancol - phenol - ether (1).pdf
va2132004
 
Scope Of Macroeconomics introduction and basic theories
Scope Of Macroeconomics introduction and basic theoriesScope Of Macroeconomics introduction and basic theories
Scope Of Macroeconomics introduction and basic theories
nomankalyar153
 
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Quotidiano Piemontese
 
USDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptxUSDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptx
marketing367770
 
Intro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptxIntro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptx
shetivia
 
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdfWhich Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Kezex (KZX)
 
how to swap pi coins to foreign currency withdrawable.
how to swap pi coins to foreign currency withdrawable.how to swap pi coins to foreign currency withdrawable.
how to swap pi coins to foreign currency withdrawable.
DOT TECH
 
Latino Buying Power - May 2024 Presentation for Latino Caucus
Latino Buying Power - May 2024 Presentation for Latino CaucusLatino Buying Power - May 2024 Presentation for Latino Caucus
Latino Buying Power - May 2024 Presentation for Latino Caucus
Danay Escanaverino
 
how to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchangehow to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchange
DOT TECH
 
how can I sell pi coins after successfully completing KYC
how can I sell pi coins after successfully completing KYChow can I sell pi coins after successfully completing KYC
how can I sell pi coins after successfully completing KYC
DOT TECH
 
NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...
NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...
NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...
Amil baba
 
What website can I sell pi coins securely.
What website can I sell pi coins securely.What website can I sell pi coins securely.
What website can I sell pi coins securely.
DOT TECH
 
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
ydubwyt
 
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit CardPoonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
nickysharmasucks
 

Recently uploaded (20)

The new type of smart, sustainable entrepreneurship and the next day | Europe...
The new type of smart, sustainable entrepreneurship and the next day | Europe...The new type of smart, sustainable entrepreneurship and the next day | Europe...
The new type of smart, sustainable entrepreneurship and the next day | Europe...
 
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
 
Webinar Exploring DORA for Fintechs - Simont Braun
Webinar Exploring DORA for Fintechs - Simont BraunWebinar Exploring DORA for Fintechs - Simont Braun
Webinar Exploring DORA for Fintechs - Simont Braun
 
Introduction to Indian Financial System ()
Introduction to Indian Financial System ()Introduction to Indian Financial System ()
Introduction to Indian Financial System ()
 
how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.
 
how can i use my minded pi coins I need some funds.
how can i use my minded pi coins I need some funds.how can i use my minded pi coins I need some funds.
how can i use my minded pi coins I need some funds.
 
Chương 6. Ancol - phenol - ether (1).pdf
Chương 6. Ancol - phenol - ether (1).pdfChương 6. Ancol - phenol - ether (1).pdf
Chương 6. Ancol - phenol - ether (1).pdf
 
Scope Of Macroeconomics introduction and basic theories
Scope Of Macroeconomics introduction and basic theoriesScope Of Macroeconomics introduction and basic theories
Scope Of Macroeconomics introduction and basic theories
 
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
 
USDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptxUSDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptx
 
Intro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptxIntro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptx
 
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdfWhich Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
 
how to swap pi coins to foreign currency withdrawable.
how to swap pi coins to foreign currency withdrawable.how to swap pi coins to foreign currency withdrawable.
how to swap pi coins to foreign currency withdrawable.
 
Latino Buying Power - May 2024 Presentation for Latino Caucus
Latino Buying Power - May 2024 Presentation for Latino CaucusLatino Buying Power - May 2024 Presentation for Latino Caucus
Latino Buying Power - May 2024 Presentation for Latino Caucus
 
how to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchangehow to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchange
 
how can I sell pi coins after successfully completing KYC
how can I sell pi coins after successfully completing KYChow can I sell pi coins after successfully completing KYC
how can I sell pi coins after successfully completing KYC
 
NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...
NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...
NO1 Uk Rohani Baba In Karachi Bangali Baba Karachi Online Amil Baba WorldWide...
 
What website can I sell pi coins securely.
What website can I sell pi coins securely.What website can I sell pi coins securely.
What website can I sell pi coins securely.
 
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
 
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit CardPoonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
 

Unit.6. network analysis with cpm and pert

  • 1. Chapter six Network Analysis with CPM and PERT By;-Dagnaygebaw Goshme (MSc.)
  • 2. 6.1.Basic concepts on net work A 'network' is defined as a graphic representation with a flow of some type in its branches. It represents nodes and branches. A node is the intersection of the two branch lines. It is denoted by a circle. Each node represents an event, which is a specific definable accomplishment recognizable at a particular instant of time. Each branch represents an activity. The arrowheads indicate the sequence in which events must be achieved. Thus an event is the completion of all the activities leading into that node and this event must precede the initiation of the activity leading out of the node.
  • 4. Example 1: A company is interested in preparing a budget. The details of the activities and the departments involved are given in the Table.
  • 5. The project of budgeting can be displayed in a network or project graph by an arrow diagram. Jobs are shown as arrows leading from one node to the other as in Figure From the arrow diagram, we infer that: activity A is the first job. Jobs B and C start only after A is over. A is called the predecessor of B and C and B and C the successors of A.
  • 6. Rules for Construction of Network (a) Each activity is represented by one and only one arrow.  This means that no single activity can be represented twice in a network. (b) No two activities can be identified by the same end events. This means that there should not be loops in the network. (c)Time follows from left to right. All the arrows point in one direction.Arrows pointing in opposite direction must be avoided. (d) Arrows should not cross each other. (e) Every node must have at least one activity preceding it and at least one activity following it, except for the nodes at the very beginning and at the very end of the network
  • 7. Dummy Activities  There is a need for dummy activities when the project contains groups of two or more jobs which have common predecessors.  The time taken for the dummy activities is zero.  Suppose we have the following project of jobs with their immediate predecessors.
  • 8. Activity B is the common immediate predecessor of both D and E. A is the immediate predecessor of D alone and C is the predecessor of E. Let B lead into two dummy jobs D1 and D2 and let D1 be an immediate predecessor of D and D2 of E as shown in Figure
  • 9. Dummy arrow represents an activity with zero time duration. It is represented by a dotted line and is introduced in a network to clarify activity pattern under the following situations. (i) It is created to make activities with common starting and finishing events distinguishable. (ii)To identify and maintain the proper precedence relationship between activities those are not connected by events. Consider an example where A and B are parallel (concurrent activities). C is dependent on A and D is dependent on both A and B. Such a situation can be represented easily by use of dummy activity as shown in Figure
  • 10. Example 2: A project consists of the following activities whose precedence relationship is given below. Draw an arrow diagram to represent the project.
  • 11. Since B & C are the immediate predecessor of H
  • 12.
  • 13. CPM(Critical Path Method) It is also a network technique but it is concerned with obtaining the trade-off, between cost and completion date for large projects. In any project consisting of several activities each activity can be completed in a normal duration with normal cost. If we employ more persons or skilled people or given overtime to the workers, the activity could be completed in a reduced duration known as crash duration. But this involves an increased cost in the form of additional resources. With CPM the amount needed to complete the various activities is assumed to be known with certainty.
  • 14.  So, the direct costs for the activities increase and hence the cost of the project also increases.  By reducing the activity duration of some or all possible completed ahead of the schedule.  This will naturally reduce the overhead cost for the entire project.  On one hand the direct expenses increase, if we shorten the activity duration, but, the indirect expenses for the project are reduced.  We have to strike a balance or an optimum time schedule, or a least cost schedule is to be obtained.This is the purpose of the Critical Path Method.  CPM is mostly used in construction projects, or in situations already handled, so that the details like the normal completion time, crash duration and cost of crashing are already known.
  • 15.  The critical path method (CPM) aims at:-  The determination of the time to complete a project  The important activities on which a manager shall focus attention.  From the start event to the end event, the time required to complete all the activities of the project in the specified sequence is known as the project completion time.  A continuous sequence, consisting of nodes and activities alternatively, beginning with the start event and stopping at the end event of a network is called a path in the network.  The path with the largest time is called the critical path and the activities along this path are called the critical activities or bottleneck activities.  The activities are called critical because they cannot be delayed.  In CPM, it is assumed that precise time estimate is available for each activity.
  • 16. To FindThe Critical Path  After listing all the activities with their precedence relationship we project these activities in a project graph represented by arrows or Activity On Node diagram (AON).  Now we have to find the minimum time required for completion of the entire project.  For this we must find the longest path with the sequence of connected activities through the network. This is called the critical path of the network and its length determines the time for completion of the project.  The activities in the critical path are so critical that, if they are delayed, the project completion date cannot be met and the project finish time will have to be extended.  We shall now see how to identify the critical path, the critical activities and the duration of the project.  The meaning of path and length of a path should first be made clear.
  • 17. D We have five activities A, B, C, D and E with the time of completion of the activities 5, 6, 7, 3 and 6 days respectively. In this network, there are three ways to get from the starting point at node 1 and travel through the network to end at node 4. These ways are called paths.Thus, a path is defined as "a set of nodes connected by lines which begin at the initial node of a network and end at the terminal node". There are three paths namely, 1-3-4,1-2-3-4 and 1-2-4 where the numbers represent the nodes.
  • 18.  The length of a path in a network is the total time it takes to travel along the path.  This time is calculated by adding the individual times between the connected nodes on the path.  A path is called a critical path if it is the longest the path in a project network.  We have the times of the three distinct paths has shown below.  Path Time (days) 1-3-4 5 + 3 = 8 days 1-2-3-4 6 + 7 + 3 = 16 1-2-4 6 + 6 = 12  The path connecting the nodes 1,2,3 and 4 constitutes the longest path and hence 1-2-3-4 is the critical path.  The minimum time to complete the project is the time taken for the longest path namely 16 days.  The activities B (1-2), C (2-3) and D(3-4) constitute the critical activities.  These jobs are critical in determining the project's duration.
  • 19. Determine the critical path, the critical activities and the project completion time.
  • 20. Consider the paths, beginning with the start node and stopping with the end node.There are two such paths for the given project. A- B- D- F= time of 3 + 5 + 10 + 4 = 22 weeks. A -C –E- F= time of 3 + 7 + 5 + 4 = 19 weeks. Compare the times for the two paths. Maximum of {22,19} = 22. We see that path I has the maximum time of 22 weeks.Therefore, path I is the critical path.The critical activities are A, B, D and F. The project completion time is 22 weeks. We notice that C and E are non- critical activities.
  • 21. Find out the completion time and the critical activities for the following project we identify 4 paths, beginning with the start node of 1 and terminating at the end node of 10.They are as follows: Path I ,A D G K=Time for the path = 8 + 20 + 8 + 6 = 42 units of time Path II, B E H K=Time for the path = 10 + 16 + 11 + 6 = 43 units of time Path III, B E I L=Time for the path = 10 + 16 + 14 + 5 = 45 units of time. Path IV, C F J L=Time for the path = 7 + 25 + 10 + 5 = 47 units of time. Maximum of {42, 43, 45, 47} = 47 which is a critical path.And critical activities are C, F, J and L.The non-critical activities are A, B, D, E, G, H, I and K.The project completion time is 47 units .
  • 22. PERT "Programme Evaluation and ReviewTechnique It was created as a means to plan and accelerate the development of the Polaris Ballistic Missile. In USA the defense department developed a nuclear missile to be launched from beneath the ocean's surface by a mobile submarine, which would be an effective deterrent against aggression by an enemy. This paved way to plan how to design, develop and plan the different stages in the production of a missile and how quickly this task could be completed. A planning and scheduling technique named PERT gave the answer to these questions.
  • 23. In any new venture, uncertainties are bound to creep in. PERT incorporated these uncertainties into a model, which provides a reasonable answer to these uncertainties. There are certain statistical aspects scheduling large projects consisting of numerous activities whose completion times are uncertain and are independent of one another. PERT is an event-oriented technique. By 'event' we mean reaching a certain stage of completion of the project. PERT is useful in research and developmental projects,
  • 24. Programme Evaluation and Review Technique (PERT) is a tool that would help a project manager in project planning and control. It would enable him in continuously monitoring a project and taking corrective measures wherever necessary. This technique involves statistical methods. In PERT, we assume that it is not possible to have precise time estimate for each activity and instead, probabilistic estimates of time alone are possible. A multiple time estimate approach is followed here. In probabilistic time estimate, the following 3 types of estimate are possible:
  • 25. 1. Pessimistic time estimate ( P t ) 2. Optimistic time estimate ( O t ) 3. Most likely time estimate ( M t ) The optimistic estimate of time is based on the assumption that an activity will not involve any difficulty during execution and it can be completed within a short period. On the other hand, a pessimistic estimate is made on the assumption that there would be unexpected problems during the execution of an activity and hence it would consume more time. The most likely time estimate is made in between the optimistic and the pessimistic estimates of time.
  • 26. Thus the three estimates of time have the relationship to < tm < tp  Practically speaking, neither the pessimistic nor the optimistic estimate may hold in reality and it is the most likely time estimate that is expected to prevail in almost all cases.  Therefore, it is preferable to give more weight to the most likely time estimate.  We give a weight of 4 to most likely time estimate and a weight of 1 each to the pessimistic and optimistic time estimates.  We arrive at a time estimate ( te) as the weighted average of these estimates as follows:
  • 27. Since we have taken 6 units ( 1 for P t , 4 for M t and 1 for O t ), we divide the sum by 6. With this time estimate, we can determine the project completion time as better applicable as compared to CPM. Since PERT involves the average of three estimates of time for each activity, this method is very practical and the results from PERT will be have a reasonable amount of reliability.
  • 28. Measure of Certainty The 3 estimates of time are such that to < tm < tp Therefore the range for the time estimate is tp - to. The time taken by an activity in a project network follows a distribution with a standard deviation of one sixth of the range, approximately. The certainty of the time estimate of an activity can be analyzed with the help of the variance. The greater the variance, the more uncertainty in the time estimate of an activity.
  • 29.  Example Two experts A and B examined an activity and arrived at the following time estimates. Experts Time Estimate to tm tp A 4 6 8 B 4 7 10 Determine which expert is more certain about his estimates of time:
  • 30.
  • 31.
  • 32.
  • 33. Using the single time estimates of the activities, we get the following network diagram for the project. There are four such paths for the given project.They are as follows: Path I, A B D F H=Time for the path: 4+6+12+21+5 = 48 days. Path II, A B D G I=Time for the path: 4+6+12+ 6+3 = 31 days. Path III,A C E F H= Time for the path: 4+10+9+ 21+5 = 49 days. Path IV, A C E G I= Time for the path: 4+10+9+ 6+3 = 32 days. 1 2 3 4 5 6 7 8 A, 4
  • 34.  Compare the times for the four paths. Maximum of {48, 31, 49, 32} = 49. We see that Path III has the maximum time. Therefore the critical path is Path III. i.e., 1  2 4 5  6  8 The critical activities are A, C, E, F and H. The non-critical activities are B, D, G and I. Project time (Also called project length) = 49 days.
  • 35.
  • 36. 1 6 7 8 2 3 4 5 Path I, A C F I= Time for the path: 6+12+11+4 = 33 weeks. Path II, A D G I= Time for the path: 6+5+7+ 4= 22 weeks. Path III, B E H=Time for the path: 5+9+15 = 29 weeks
  • 37. Compare the times for the three paths. Maximum of {33, 22, 29} = 33. It is noticed that Path I has the maximum time. Therefore the critical path is Path I. i.e., 1  2  3  5  8 The critical activities are A, C, F and I. The non-critical activities are B, D, G and H. Project time = 33 weeks. Calculation of Standard Deviation and Variance for the Critical Activities:
  • 38. Variance of project time (Also calledVariance of project length) = Sum of the variances for the critical activities = 1+4+1+ 4/9 = 58/9Weeks. Standard deviation of project time = √Variance = √58/9 = 2.54 weeks.
  • 39. The following are the suggested applications when PERT or CPM is found useful. The construction of a building or of a highway. Planning and launching a new product. Scheduling maintenance for a project. The manufacture and assembly of a large machine tool. To conduct a music or drama festival. Preparation of budget for a company.