Critical Path Method
Introduction
Once you have the network diagrams for the activities, as well as the activity duration estimates, you can begin scheduling the project. The critical path method (CPM) is one of the key techniques for developing a project schedule.
In a schedule network diagram, the critical path is the longest full path linking activities that must be performed in sequence. It's important to identify this path, because if one of its activities is delayed, the end date of your project is delayed too.
CPM provides a way to calculate four time boundaries:
· the early start date, which is the earliest possible start date for each activity to begin
· the early finish date, which is the earliest date each activity can end
· the latest start date, which is the latest possible time for each activity to begin
· the latest finish date, which is the latest date each activity can end
CPM involves completing three steps:
1. performing a forward pass through the network diagram
2. performing a backward pass to check your initial results
3. calculating the float for each activity to determine the critical path
The forward pass
The first step in CPM is performing a forward pass through the schedule network diagram so you can establish the early start and finish dates for each activity. This is done so that resources, such as project team members and equipment, can be allocated as soon as possible. Allocating resources assists in determining project expenditure and therefore establishing the project budget.
When performing a forward pass, you begin with the first activity in the network diagram and move forward. You
1. record the earliest date the first activity can start
2. add the duration of this activity to the early start date
3. subtract one day from the result
Some project managers find it useful to record activities' start and finish times in the network diagram. The early start is usually filled in on the top left corner of each activity block, with the early finish date shown in the right corner.
The backward pass
The second step in determining the critical path for a project is to perform a backward pass through the schedule network diagram.
You perform the backward pass to establish the latest start and finish dates for the project to remain on schedule.
In a backward pass, you start at the end of the project and work back, subtracting the estimated duration of each preceding activity.
To begin the backward pass, the late finish date will either be a hard date that's been set or the early finish date of the last activity in the project. An example of a hard date may be a deadline that determines the project's end date.
To calculate the late start date, you
1. subtract the duration of the last activity from its late finish date
2. add one day because the last day of the project is included as a working day
As you work backward through the schedule network diagram, the late finish date will fall on the working day preceding the lat.
Critical Path MethodIntroductionOnce you have the network diag.docx
1. Critical Path Method
Introduction
Once you have the network diagrams for the activities, as well
as the activity duration estimates, you can begin scheduling the
project. The critical path method (CPM) is one of the key
techniques for developing a project schedule.
In a schedule network diagram, the critical path is the longest
full path linking activities that must be performed in sequence.
It's important to identify this path, because if one of its
activities is delayed, the end date of your project is delayed too.
CPM provides a way to calculate four time boundaries:
· the early start date, which is the earliest possible start date for
each activity to begin
· the early finish date, which is the earliest date each activity
can end
· the latest start date, which is the latest possible time for each
activity to begin
· the latest finish date, which is the latest date each activity can
end
CPM involves completing three steps:
1. performing a forward pass through the network diagram
2. performing a backward pass to check your initial results
3. calculating the float for each activity to determine the critical
path
The forward pass
The first step in CPM is performing a forward pass through the
schedule network diagram so you can establish the early start
and finish dates for each activity. This is done so that resources,
such as project team members and equipment, can be allocated
as soon as possible. Allocating resources assists in determining
project expenditure and therefore establishing the project
budget.
When performing a forward pass, you begin with the first
activity in the network diagram and move forward. You
2. 1. record the earliest date the first activity can start
2. add the duration of this activity to the early start date
3. subtract one day from the result
Some project managers find it useful to record activities' start
and finish times in the network diagram. The early start is
usually filled in on the top left corner of each activity block,
with the early finish date shown in the right corner.
The backward pass
The second step in determining the critical path for a project is
to perform a backward pass through the schedule network
diagram.
You perform the backward pass to establish the latest start and
finish dates for the project to remain on schedule.
In a backward pass, you start at the end of the project and work
back, subtracting the estimated duration of each preceding
activity.
To begin the backward pass, the late finish date will either be a
hard date that's been set or the early finish date of the last
activity in the project. An example of a hard date may be a
deadline that determines the project's end date.
To calculate the late start date, you
1. subtract the duration of the last activity from its late finish
date
2. add one day because the last day of the project is included as
a working day
As you work backward through the schedule network diagram,
the late finish date will fall on the working day preceding the
late start date of the last activity.
When activities occur in parallel, the smaller of the late start
values of the activities is used to calculate the late finish date
for the preceding activity.
The late start date should usually be the same as the early start
date for the first activity in a schedule network diagram. Any
other result may indicate that you've made an error, unless there
is a hard end date and you're starting the project in advance to
give yourself an extra buffer.
3. Calculating the float
When there's a difference between the early finish date of an
activity and the early start date of an activity that immediately
follows it, the difference is called slack time, or float. It's the
amount of time that an earlier activity can be delayed without
affecting the completion time of the project.
The final step in the CPM is to find the activities that lie on the
project's critical path by calculating their float. The critical path
is sometimes defined as the longest path through the network
diagram and contains no float.
The easiest way to find the critical path is to find the activities
where the early start date is the same as the late start date. If
the two dates are the same, there's no float available for that
activity, and it must lie on the critical path.
You can also calculate the float for each activity by subtracting
the early start date from the late start date, or by subtracting the
early finish date from the late finish date.
If any of the activities on the critical path aren't completed on
time, all of the activities that follow it will run late too. So it's
important to prevent this, for example by ensuring enough
resources are allocated for completing critical activities.
The critical path is one of the techniques for developing a
project schedule. It identifies the shortest period of time in
which the project can be completed. The critical path method
involves completing three steps. You perform a forward pass
through the network diagram, perform a backward pass to check
your initial results, and then calculate the float for each activity
to determine the critical path.
Course: Developing and Controlling the Project Schedule
Topic: Critical Path Method
Critical Path Calculations
Purpose: Use this job aid as a reference to the calculations used
in the critical path method.
One-to-one dependency between tasks
4. One-to-one dependency between tasks
Forward pass
Early start date + Duration - 1 = Early finish date
The early start date of an activity should fall on the next
working day after the early finish date of the previous activity.
Backward pass
Late finish date - Duration + 1 = Late start date
The late finish date of an activity should fall on the working
day before the late start date of the following activity.
One-to-many dependency between tasks
One-to-many dependency between tasks
Forward pass
Early start date + Duration - 1 = Early finish date
The early start date of the dependent activities should fall on
the next working day after the early finish date of the previous
activity.
Backward pass
Late finish date - Duration + 1 = Late start date
The late finish date of the previous activity should fall on the
working day before the smaller late start date of the succeeding
activity – that is, the working day before the late start date of
the critical path activity.
Many-to-one dependency between tasks
Many-to-one dependency between tasks
Forward pass
Early start date + Duration - 1 = Early finish date
The early start date of the dependent activity will be the
working day after the larger early finish date of the previous
activities.
Backward pass
Late finish date - Duration + 1 = Late start date
The late finish date of the preceding activities will be the
working day before the late start date of the dependent activity.
Course: Developing and Controlling the Project Schedule
5. Topic: Critical Path Method
Microsoft® Project Painting Exercise
Microsoft® Project
· Microsoft® Project (also called “MS-Project”) is one of the
most popular tools for project planning projects today. It is
relatively easy to use and makes it easier to manage projects.
· Microsoft® Project Exercise: The Painting Project
· This is a simple exercise in Microsoft® Project. These
instructions are brief and only cover the basics. The objective of
this exercise is to prepare you for Week 3 Learning Team
assignment. This exercise only covers how to log into
Microsoft® Project, set up a simple schedule, and log out. The
exercise is not concerned with monitoring or controlling the
execution of a plan.
Start Microsoft® Project
To start Microsoft® Project; click through “Start > Programs >
Microsoft Office 2013 > Microsoft Project” Microsoft® Project
should start up, with a blank “Gantt chart” view of a new
project.
Saving Microsoft® Project
It is recommended that you save your project immediately. So
please Save your project now using the following format ‘Last
Name_Paint_Project’. If you last name is Allen, your
Microsoft® Project file name will be ‘Allen_Paint_Project’.
If you are prompted to save the project with a baseline, click
Yes. You may continue to work on the baseline until you have
completed the exercise and turned it in as the final baseline.
Microsoft® Project Settings
6. Before getting into the details of a the Painting Project, it is
beneficial to enter a few Microsoft® Project settings. These
settings are:
· Duration Unit of Measure. The normal default for duration is
the day (day) which consist of 8 hours. There are other unit of
measures that you may decide to use. The most popular are
minute (min), hour (hr), and week (wk). For this exercise we
will use the default setting.
· The working calendar. There is a default Standard Calendar
which consists of a 5-day work week (Monday through Friday)
with Saturday and Sunday set as non-working days. A day is
made up of 8 hours. It is recommended for this exercise that you
leave Microsoft® Project set to the Standard Calendar. If you
want to explore other calendars or how to set up your own
calendar, click as follows “Project > Project Information”. The
following pop up menu will appear with Calendar showing as
‘Standard’.
· Available resources. It is beneficial to set up your known
resources pool at the start of the project. Note. You may change
the resources in the pool at any time, as resources are added to
and subtracted from the project. To set up the resource pool
click as follows “Resource> Resource Sheet”. You’ll get a table
in which you can define the names of resources that you wish to
be available.
Simply type a name in the “Name” field, and use a new line for
each different resource. For the Painting Project, the following
are the resources.
Jackie Smith – Standard Rate $25.00; Overtime Rate $37.00
Tom Busch – Standard Rate $20.00; Overtime Rate $30.00
Alan Jacobs – Standard Rate $15.00; Overtime Rate $22.00
7. Suzie Smith – Standard Rate $15.00; Overtime Rate $22.00
Paint – One time cost of $700
Paint Supplies (paint brushes and tape, drop cloth, etc.) – One
time cost of $450
Enter these in your resource sheet.
· Project start or end date. When you first start developing a
schedule for a project it is useful to set up the project start or
end date. To enter this date, click as follows “Project > Project
Information”. At work you may have a project that will start in
a few weeks so you would use a project start date. If this is the
case you will select ‘Project Start Date’ in the ‘Schedule from:’
field and enter the projected project start date in the ‘Start date’
field as follows:
If you are doing a project for a wedding or an event, the project
would have an end date; the date the event will occur. If this is
the case you will select ‘Project End Date’ in the ‘Schedule
from:’ field and enter the desired project end date in the ‘Finish
date’ field as follows:
For the Paint Project, select Project Start Date and enter June
21, 2014.
· Creating Tasks (aka activities). When you start Microsoft®
Project, by default you’ll see a blank Gantt chart. The first three
columns (on the left) are headed “”, “Task Mode”, “Task Name”
and “Task Duration”. To enter the tasks, work down the third
column, entering Task Name and pressing the Down Arrow key
(↓) at the end of each entry.
Note. Microsoft® Project assigns each task a Task ID or line #
8. and inserted a default duration of 1 day for each task. Do not
worry about this duration at this point in time.
· Creating work packages and subtasks. Just like outlining a
report in Microsoft® Word, or a presentation in Microsoft®
PowerPoint®, you can outline a project’s tasks. There are
several ways of doing this, but here’s just one.
· First (outside of the software), write down your tasks, grouped
under headings that describe their intended effect. These
headings are called “Work packages”. For example, the Paint
Project consist of several work packages:
Painting bedroom and bathroom
· Purchase paint and materials
· Prep rooms for painting
· Paint rooms
· Clean up paint items
· These work packages are then expressed in detail as sets of
subtasks, as follows:
Painting bedroom and bathroom
· Purchase paint and materials
· Drive to paint store
· Select paint and materials
· Purchase paint and materials
· Drive back and put paint and materials at house
· Purchase of paint materials complete
· Prep rooms for painting
· Remove any furniture that is in the way
· Tape off any fixtures that will not be removed; covering so
paint does not get on them
· Place drop cloths in appropriate areas
9. · Inspect to make sure all surfaces not requiring paint are
covered adequately
· Prep rooms for painting complete
· Paint rooms
· Paint bedroom
· Paint bathroom
· Let paint dry
· Paint room complete
· Clean up paint items
· Pick up drop cloths and dispose of them
· Remove tape form any fixtures and dispose of tape
· Place furniture back where required
· Clean up items complete
· To achieve this effect in Microsoft® Project, enter all the
tasks, grouping them together under their work package. Then
use the “Indent” function (the icon) to make the subtasks part of
the work package by moving them to the right. Note how the
task immediately above the indented one changes to work
package, or summary tasks, with a bold font. When you indent a
task, it becomes a subtask of the next “un-indented” task (work
package) above it. You may also “outdent” using the icon.
This indenting to form work packages is extremely useful to
control how projects are displayed. By expanding and
collapsing a Work package, you can show or hide subtasks to
show just the level of detail you want.
You can select multiple tasks (shift-click) before indenting.
· Enter the Paint Project Work Packages and Subtasks. Once
you have entered these items it is recommend that you set
Microsoft Project to Auto-Schedule which allows Microsoft
Project to calculate the task start and end dates for you. To set
each work package and subtask to auto schedule highlight each
10. and then click on Auto Schedule.
When done your Gantt Chart should look as follows:
Linking Tasks
You should understand the concept of linkage or precedence—
which some activities need to finish before others can start (like
putting on socks before putting on shoes before tying laces). It
is easy to create the commonest type of linkage—FS, or Finish-
to-Start—between them. Simply:
· With the left mouse button, select the earlier activity.
· Hold down the ‘Control’ (or ‘Ctrl’) key
· Select the later activity and release the left mouse button and
control key
· Click the ‘Link tasks’ icon (it looks like a chain).
You should see the later activity’s duration bar get pushed to
the right, and its left end will align with the right end of the
earlier one. An arrow will appear showing the link.
General rule
Never link work packages themselves—always expand both
work packages first and specify linkages between specific
activities.
Link the tasks as they could occur, regardless of resources, in
the Paint Project. When complete, your file should look as
follows:
11. Note. Removing any furniture that is in the way does not have
to wait for delivery of paint and paint supplies, but Taping off
any fixtures or placing drop cloths does have to wait, so those
tasks are linked to a purchase of paint and material task.
Assigning Resources to Tasks
Now it is time to use the resources that you set up. To assign a
resource to a task, go to the Gantt Chart and, on the task line
item. click on the resource name column. A pop up menu should
appear with the list of the resources in your resource pool.
Simply select the correct resource and move to the next sub
task. Work packages are not assigned resources. For the Paint
Project, the following resource are to be assigned to each
subtask.
Task Name
Task Resource(s) to be assigned
Drive to paint store
Alan Jacobs
Select paint and materials
Alan Jacobs
Purchase paint and material
Alan Jacobs; Paint; Paint supplies
Drive back and put paint and materials at house
Alan Jacobs
Remove any furniture that is in the way
Tom Busch
Tape off any fixtures that will not be removed
Suzie Smith
Place drop cloths in appropriate areas
Suzie Smith
Inspect to make sure all surfaces are covered adequately
Suzie Smith
Paint bedroom
12. Jackie Smith
Paint bathroom
Jackie Smith
Pick up drop cloths and dispose of them
Suzie Smith
Remove tape from any fixtures and dispose of tape
Suzie Smith
Place furniture back where required
Tom Busch
Assigning Task Duration
Now you can work with our resources to determine the duration
of each of their assigned tasks. Once durations have been agreed
to you will input that into Microsoft Project. To input the
durations, click in the “Duration” box for each task and specify
its duration and time unit (min, hr, day or wk). The agreed to
durations for the Paint Project are as follows:
Task Name
Task Agreed to Duration
Drive to paint store
1 hr
Select paint and materials
6 hr
Purchase paint and material
45 min
Drive back and put paint and materials at house
1 hr
Purchase paint and materials complete
0 day
Remove any furniture that is in the way
2 hr
Tape off any fixtures that will not be removed
6 hr
Place drop cloths in appropriate areas
1 hr
13. Inspect to make sure all surfaces are covered adequately
1 hr
Prep rooms for painting complete
0 day
Paint bedroom
1 day
Paint bathroom
4 hr
Let paint dry
1 day
Paint rooms complete
0 day
Pick up drop cloths and dispose of them
1 hr
Remove tape from any fixtures and dispose of tape
4 hr
Place furniture back where required
1 hr
Clean up paint items complete
0 day
Upon entering these durations, you should see Jackie Smith as
an over-allocated resource.
If Jackie is the only painter available then the resource must be
leveled so that Jackie is not working a 12 hour day and getting
paid overtime. To level resources in Microsoft® Project go to
‘Resource’ tab and click on Level Resource. Then select Jackie
Smith and click on level now.Scheduling a project –
determining duration and the critical path
By default, the Gantt chart shows what is happening in the
project. With the Gantt Chart open, click the Format tab and
notice the Critical Tasks checkbox.
If you check the box, Microsoft® Project will show you the
Critical Path highlighted in red as follows.
14. At this point you have completed the Paint Project Exercise.
Save the file and submit in the Assessments Tab.
Setting Project Baselines
Learning Objective
After completing this topic, you should be able to
· set a baseline in Project 2013
1. Meet your instructor
Narrator: I'm Susan Domina and I've been teaching Microsoft
Project for over 20 years. In this course we're going to explore
many of the tools that Project 2013 offers that help you track
your project's performance, such as baselines and how to enter
progress information for your project tasks.
Narrator: We're also going to explore how to use tools in
Microsoft Project 2013 to analyze your project, such as how to
display critical path information and use the Task Inspector tool
to identify any potential issues such as task deadline misses.
2. Demo: Saving project baselines
Once our project is underway, we'll want to be able to compare
how the project is progressing to how far along we thought we
would be by now, when we initially planned the project. The
good news is that the Project comes with tools to capture a
project's baseline. A baseline represents a snapshot of the work,
cost, and schedule information at the time you save it. The best
time to capture an initial baseline is when the plan is complete
but before actual project work begins. Then you can save
additional baselines called interim plans at different times
throughout the project lifecycle to capture progress. The
purpose of capturing these later baselines is to be able to
compare the progress of our project to the initial plan. Let's
pretend that we think we're done with the planning and we want
to save a project baseline. On the PROJECT tab, in the Schedule
group, I'll click on Set Baseline andSet Baseline. That opens up
15. the Set Baseline dialog box and we're going to leave it at
the Set Baseline: Baseline – an entire project – because we don't
want to just save some of the tasks, we want to save the
information for all of the tasks. And I'll click OK.
Graphic
By default, the Microsoft Project 2013 interface consists of a
Quick Access Toolbar of frequently-use commands, and a
ribbon with tabs such as, TASK, RESOURCE, and PROJECT.
The project plan is displayed below these elements.
In this example, a project plan is open in Gantt Chart view and
on the ribbon, the PROJECT tab is selected.
The PROJECT tab includes the Insert, Apps, Properties, and
Schedule groups. The Schedule group contains the options:
Calculate Project, Set Baseline, and Move Project.
The Set Baseline drop-down menu has two options: Set Baseline
and Clear Baseline.
The Set Baseline dialog box contains the Set baseline and Set
interim plan radio buttons. The Set baseline radio button has an
associated drop-down list box, set to Baseline by default.
There are also radio buttons for applying settings to the entire
project or selected tasks.
Now if something minor changes in the project plan before the
actual work begins, you may want to save over your initial
baseline once you've updated the appropriate information. And
by minor changes I mean maybe a few task start dates have
changed or a task was added or removed. Let me show you how
to save over a previous initial baseline. Again on the PROJECT
tab, in the Schedule group, I'll click on Set Baseline – Set
Baseline. And you can see that it tells us the date of the initial
baseline and we don't need to change anything because we want
to set the baseline for the entire project and overwrite this
16. initial one. And so I'll click OK and it does tell us, "Baseline
has already been used..." on what date and it asks us if we're
sure we want to overwrite this baseline –Yes. Project notes the
last saved date in the Set Baseline dialog box. However, once
work on the project has started and you want to save additional
baselines for comparison, do not save over the initial baseline,
but rather select another from the Set Baseline drop-down list.
Graphic
The instructor reopens the Set Baseline dialog box. Under the
Set baseline radio button option, the drop-down list box reads:
Baseline (last saved 6/7/13).
When the instructor clicks OK, a Microsoft Project dialog box
opens and reads: Baseline has already been used on 6/7/13. Are
you sure you want to overwrite the data in this baseline? The
instructor clicks Yes.
So for that you would go up to project Set Baseline–Set
Baseline and you would drop-down this list and choose
next Baseline 1, then Baseline 2 etc. You may not use them all
but it has an extra ten for you. And I'll just Cancel out here. So
now you know to save an initial baseline after all the planning
but before the project work starts, and then you can save later
baselines to compare to the original one.
Graphic
The instructor reopens the Set Baseline dialog box. She opens
the drop-down list under the Set baseline radio button. It
contains options for setting different baselines, numbered from
Baseline 1 to Baseline 10.
3. Demo: Viewing project baselines
Now that we've saved a baseline, I want to show you what
information was saved. So I want to apply the table that will
show it best to our Gantt Chart view. So I'm going to go up to
this upper left-hand corner, what we call the Select All cell or
00, and I'll right-click and right now its in the Entry table, there
are whole slew of tables, the one I'm interested in isn't listed
here, but we can go to More Tables. And here the complete list
17. of all the tables is listed. And we want the Baseline table which
is a tasktable and click Apply. So when we saved the baseline,
Microsoft Project saved for each task, data for Task Name,
Baseline Duration, Baseline Start, Baseline Finish, Baseline
Work, and Baseline Cost. So when you save a baseline, now you
know what information Project is saving whether you display
this table or not.
Graphic
The Select All shortcut menu includes options such as Calculate
Project, Cost, Entry, Hyperlink, Schedule, Variance, Work, and
More Tables. A check mark is visible next to the Entry option.
Clicking More Tables opens the More Tables dialog box, which
radio buttons to select task or resource tables. A list box
displays the available tables for each option. There are also
buttons for New, Edit, Copy, and Organizer.
The instructor selects the Baseline table and clicks Apply.
There might occasionally be a need to clear the initial baseline
for a project so we can start again. Here's an example: suppose
we completed our plan and it is in the customer review phase
and actual work has not yet started, then something big changes
in the project plan, such as whole new deliverables are added
and/or other deliverables are removed; we need to redo our plan
and capture the updated initial baseline before beginning project
work. Another example of when an initial baseline might need
to be cleared is if you're assigned to do another project that is
similar to this one. Rather than starting from scratch, you'll
copy this file and the dates and such will be different, so you'll
update those for the new project. And then you save the current
file with a new name and you clear the baseline. To clear
baseline, first we go up to the PROJECT tab of the ribbon and
in the Schedule group I'll click on Set Baseline, and from the
list I'll choose Clear Baseline.
Graphic
Selecting Clear Baseline opens the Clear Baseline dialog box. It
18. contains two radio buttons: Clear baseline plan and Clear
interim plan, which each have corresponding drop-down list
boxes. The dialog box also contains radio button options
enabling the settings for an entire project or for selected tasks.
And we do want to clear the baseline for the entire project. And
we only have this first one saved so that's the one we want to
clear and OK. So now in the Baseline table, see how all of the
baseline values have been cleared and all these were filled in.
Typically when we clear a baseline we want to then update any
information as necessary and then reset the project baseline, and
save the project file. So if you do have a need to clear the
baseline you now know when it's appropriate and how to do it.
Graphic
In this case, Clear baseline plan is selected, and the associated
baseline you want to clear was last saved on 6/7/13. The Entire
project radio button is also selected.
Updating Project Progress
Learning Objective
After completing this topic, you should be able to
· update the progress of a task in Project 2013
1. Demo: Updating completion percentages
Capturing the progress of a project is crucial to producing
accurate and useful status reports. The simplest method of
tracking progress is by inputting estimates of the percentage of
work that is complete on each task. First, I prefer to enter
actuals in the Gantt Chart view with the tracking table applied.
So we're already in a Gantt Chart view and if I right-click up in
this Select All area – upper left of the table – I see it's now
currently on the Entry table, and I'm going to choose Tracking.
And if we want to see more columns, we can drag the divider
bar farther to the right. And when I'm close to where I want to
have it positioned, I can then double-click and it will scoot over
to the divider line between that column and the next. And we
can see the Gantt bars. If not, we could have scrolled or used
the Shift+Ctrl+F5 to get there quickly.
Graphic
19. By default, the Microsoft Project 2013 interface consists of a
Quick Access Toolbar of frequently-use commands, and a
ribbon with tabs such as, TASK, RESOURCE, and PROJECT.
The project plan is displayed below these elements.
In this example, a project plan is open in Gantt Chart view and
on the ribbon, the VIEW tab is selected.
The Select All shortcut menu includes the options: Calculate
Project, Cost, Entry, Hyperlink, and More Tables.
The Tracking table is displayed and the columns Actual Start,
Actual Finish, Percentage Complete, Physical Percent
Complete, Actual Duration, Remaining Duration, Actual Cost,
and Actual Work Hours are visible. The divider bar is
separating the Tracking table and the Gantt chart.
Two more adjustments I want to make. One is that you can
change the column width of any of these columns by simply
placing your mouse pointer between that column and the next
column up in the column header. When you get this vertical bar
with double-headed horizontal arrows, you can drag either left
or right. And the final change I want to make, to adjust it the
way I want it, is I want to move Percent Complete to between
Actual Start and Actual Finish. And so I'm going to click on the
column header for Percent Complete and then I let go of my
mouse button and I press and hold again, and drag it to where I
want it. You can see the vertical insertion line between Actual
Start and Actual Finish and that's where I'm going to drop it.
And now we'll enter the Actual Start date of a few of the tasks
that have started and their estimated percent complete. This first
one started on January 6th and I'll press Tab to move over to the
right and it's complete so I'll type in 100%.
Graphic
The instructor types 1/6/14 in the Actual Start column for the
"Identify resource requirements" task. She then types 100 in the
Percent Complete column.
20. And so notice it puts in an Actual Finish date because it knew
the Actual Duration because it assumes the estimate of the
Actual Duration. If it's incorrect then you would type an Actual
Finish date and it would recalculate the Actual Duration. Now
over on the Gantt chart, when I put in 100% complete, notice
the darker blue line appeared and it's in that first bar but not in
any of these other ones yet. And I'll click in the second
one, 1/13/14. This one though is only 75% complete so I'll
type 75, Enter. So it doesn't put in an Actual Finish date
because it's not done yet. And again we can look at the Gantt
bar with the darker line 75% of the way across. And finally the
last one that I'm going to enter for now: it started on January
20th and it is complete.
Graphic
The Actual Finish, Actual Duration, and Actual Work columns
are automatically propagated with the information 1/23/14, 5
days, and 40 hours, respectively.
The instructor types 1/13/14 in the Actual Start column for the
"Advertise position to internal and external candidates" task.
She then types 75 into the Percent Complete column for the
same task. When she presses Enter the Actual Duration,
Remaining Duration and Actual Work columns are
automatically propagated with the information 3.75 days, 1.25
days, and 30 hours respectively.
The instructor then types 1/20/14 into the Actual Start column
for the "Select candidates to interview" task.
And again you can see Microsoft Project populate some of these
other fields. So if we enter 100% complete and there is a task
duration for a task, rather than an estimated task duration, the
Actual Finish date will auto-populate based on the task duration
information. So this is one limitation of the Percent Complete
method for updating project progress. That Project assumes that
whatever duration was initially planned for the task is the actual
duration, but like I said, we can overcome this by then typing an
21. actual finish date. And so quick and easy method of updating
project progress is to enter the start date and the percent
complete.
Graphic
When she types 100 in the Percent Complete column and
presses Enter, the Actual Finish, Actual Duration, and Actual
Work columns are automatically propagated with the
information 1/21/14, 2 days, and 16 hours respectively.
2. Demo: Updating actual and remaining work
Another method of updating project progress is to enter actual
work and remaining work information. This method, unlike just
updating Percent Complete, allows us to see date slippage based
on any increased remaining work estimates. Before we enter
actual work and remaining work information, let's set up how
we want things displayed for what we're going to do. We
already have the Gantt Chart view with the Tracking table
applied. To check, I could just right-click here and see tracking.
And I want the Actual Work column to be between the Actual
Start and Actual Finish columns. So here's the Actual Work
column, I click at the top in the column header to select it and
I'll press and hold and drag it over to where I want it. I'm going
to do the same with moving Percent Complete out of the way –
for the moment – and I also want Remaining Work. Now we
don't have Remaining Work as one of our columns but one thing
you can do is right-click on a column header and choose Insert
Column and you get all the columns for a task table.
Graphic
The instructor positions the Actual Work column between the
Actual Start and Actual Finish columns. She then positions the
Percent Complete column between the Actual Finish and
Physical Percent Complete columns.
To add the Remaining Work column, she right-clicks the Actual
Finish column header selects Insert Column from the shortcut
menu. Other options in the menu include: Hide Column, Text
Styles, Field Settings, and Custom Fields.
22. A new column is inserted next to the Actual Finish column, and
a list menu with different column options opens.
And if I want to get quickly to the R's, I'll type in an "R" and
there is Remaining Work. And again I can adjust any column
widths as necessary by placing my mouse pointer between two
column headers and dragging. That'll change the one on the left.
When we enter a value in the Actual Work column, the value in
the Remaining Work column is going to be automatically
updated to reflect the estimated work hours left on a task. If we
disagree with how many hours are left we can type in our
Remaining Work estimate and the Percent Complete column
also auto-populates. Actual Work and Remaining Work values
are typically in hours units based on the standard calendar. Let
me update a few tasks to show you. First, "Prepare interview
questions." I'll click on the Start Date, it started on January 8th.
I'll enter that and as far as actual work completed so far, I'll
type in a 4.
Graphic
The Remaining Work column is added between Actual Work
and Actual Finish.
So it's subtracted 4 from the 56 that used to be here in
Remaining Work and leaves 52. And again if I estimate that that
is different, that the Remaining Work is different than 52 hours,
I would click here and type whatever number of hours we
thought. And we think it's just 36 hours left. And for "Conduct
interview(s)," we started that task on January 22nd and as for
Actual Work, 10 hours of work has been done on that so far,
again I don't have to type the "H" because the default is hours.
And if we think that 46 hours is remaining then we'll go with
what Microsoft Project calculated, the original 56 minus 10 is
46. And for "Select final candidates based on interview results,"
I'll type in the actual start date 1/15 and so far the Actual Work
on this task is 24 hours.
Graphic
When the Actual Start and Actual Work values are specified for
23. the task, the values in the Remaining Work column is
automatically updated to 52 hours.
The instructor types 1/22/14 in the Actual Start column and 10
in the Actual Work column for the "Conduct interview(s)" task.
The Remaining Work, Percentage Complete, Actual Duration
and Remaining Duration columns are automatically populated
with values.
The instructor then types 1/15/14 in the Actual Start column and
24 in the Actual Work column for the "Select final candidates
based on interview results" task.
And that leaves none left and that's fine. So as I'm updating
these things on the left-hand side, the right-hand side is
updating as well. So the Gantt bars for things that are partially
done are showing a progress bar and you can scroll around to
see the different progress bars. So when you enter the actual
work and estimate the remaining work, you can use this method
of entering project progress.
3. Demo: Rescheduling incomplete work
Based on the Percent Complete or Actual Work and Remaining
Work information, there may be times when we have to
reschedule incomplete work on tasks, in order to update our
project schedule accordingly. One example would be if we're
not able to assign a resource to a particular task that requires a
specific skill; we want to reschedule the incomplete work for a
later time when a particular resource with that skill is available
to finish it. Another example would be if the equipment or
material needed is not going to be available when originally
planned, so we'll reschedule the work for a later date when the
equipment or material is available or delivered. Let me show
you how to reschedule incomplete work on a task. Let's say we
need to reschedule the Remaining Work of task 4 to start again
after January 19th. First we select the row with the task with
incomplete work, that's "Prepare interview questions," and then
24. on the PROJECT tab in the Status group, I'll click on Update
Project.
Graphic
A project is open in Gantt Chart view and the TASK tab is
selected.
The PROJECT tab includes the Status group, with the Update
Project option. There is also a Status Date option set to NA.
Clicking Update Project opens the Update Project dialog box.
And that opens up the Update Project dialog box. We want this
choice, the Reschedule uncompleted work to start after. And I'm
going to type in January 19th, year 14, and we just want to do
the selected tasks. We don't want to do this for the entire
project. So click OK. And if I scroll you can see the task started
earlier and there is a dotted line and then it's rescheduled for
after January 19th. So we have a Split Gantt bar for "Prepare
interview questions" with that dotted line in between. That's
how Project shows that part of the work was done earlier and
then the Remaining Work was rescheduled. We can select
multiple tasks to reschedule, to start after a certain date, or we
can also select to reschedule the entire project through the
Update Project dialog box.
Graphic
The Update Project dialog box contains the Update work as
complete through radio button, with two secondary options: Set
0% – 100% complete and Set 0% or 100% complete only. There
is also a Reschedule uncompleted work to start after radio
button, with an associated drop-down list box. You can also
select whether the changes should be made to the entire project
or selected tasks.
The instructor selects the Reschedule uncompleted work to start
after radio button, with the corresponding date reading: 6/7/13.
She alters the date to 1/19/14.
25. In the Gantt chart, the changes to the schedule are reflected.
So we would do that in the same way if we're going to select
multiple tasks. We would select them on the PROJECT tab in
the Status group; we'd go to Update Project. I'm not going to
actually do it but we could go with our multiple selected tasks,
or we could go with the entire project. Again I'm just going
to Cancel. Sometimes we might want to use the Update
Tasks button rather than the Update Project button, because we
might not need to update the entire project timeline but only the
timeline for specific tasks. To update a task – and I'm going to
select task 9, "Create offer letter," we're going to go to the
TASK tab of the ribbon and in the Schedule group, I'll click on
the drop-down arrow forMark on Track,and I'll choose Update
Tasks. So that opens up the Update Tasks dialog box. And what
we're going to do in here is put in an Actual Start date of
January 6th and a Finish date of January 7th.
Graphic
The TASK tab contains the Schedule group with options such
as, Mark on Track, Respect Links, and Inactivate. The Mark on
Track drop-down menu has the options Mark on Track and
Update Tasks. She selects Update Tasks and the Update Tasks
dialog box opens.
The dialog box contains options for setting task parameters
regarding the name of the task, the percentage complete, and a
range of other task-specific options. There is a Name text box, a
Duration text box, % Complete, Actual duration, and Remaining
duration spin boxes, and Actual and Current section, which
each have Start and Finish fields.
The instructor types 1/6/14 for the Actual Start date and 1/7/14
for the Actual Finish date.
And so we're a little different than our currently scheduled and
I'll click OK. And again if I use theCtrl+Shift+F5 to quickly get
my right-hand Gantt bars to where they're showing the task that
I'm selecting; I can see that it was supposed to just take this one
26. day January 6th – they took us two days to finish it and that's
okay. So that's how Project shows rescheduling work and also
using the Update Tasks dialog box, as well as the Update
Project dialog box. So when circumstances call for you to
reschedule incomplete work or update one or more tasks, now
you know how to do so.
Graphic
When she clicks OK, the changes are implemented to the project
and the correct values are automatically propagated within the
columns corresponding to task 9.
4. Demo: Moving project deadlines
Another way to update a project is to move the whole project
deadline at once using the Project Information dialog box. Let's
see how to do that. First of all it doesn't matter what tasks we
select because we'll be working with the project as a whole, in
the Project Information dialog box. So we'll go up to the
PROJECT tab and in the Properties group, I'll click on Project
Information. And that opens up the Project Information dialog
box for, specifically, this project. And right now we have it set
to be scheduled from the Project Start Date and we had initially
given it the Start Date. So now we're going to drop-down the
list where it says Schedule from and choose Project Finish Date.
And now we no longer have access to change the project Start
dateup here but we do have the ability to change the Finish date.
So I'm going to change the Finish date to March 7th of the same
year and I'll click OK. So when the best way to update the
project is to move the project deadline, you know how to do it
in the Project Information dialog box.
Graphic
A project is open in Gantt Chart view and the PROJECT tab is
selected.
The Properties group contains the options: Project Information,
Custom Fields, Links Between Projects, WBS, and Change
Working Time.
27. The Project Information a dialog box contains the options: Start
date, Finish date, Schedule from, Current date, Status date,
Calendar, and Priority. There is an Enterprise Customer Fields
section.
The Schedule from drop-down list has two options: Project Start
Date and Project Finish Date.
Activity: Perform End-of-phase Progress Updates
Learning Objective
After completing this topic, you should be able to
· update progress and set the baseline at the end of a phase in
Project 2013
Exercise overview
Now we have a few questions.
Supplement
Selecting the link title opens the resource in a new browser
window.
Job Aid
Access the job aid Updating Progress Information to review
ways to update the progress information for a project in Project
2013.
In this exercise, you're required to recognize how to update a
project in Project 2013.
This involves the following tasks:
· updating progress information for the project and
· setting and viewing a project baseline
Updating progress
Question
You want to update the progress information for two tasks in a
project.
What is the most efficient way to do this?
Options:
1. Enter the estimated percentage complete for the tasks
2. Reschedule incomplete work
3. Create a new project baseline
28. 4. Modify the actual work and remaining work values for the
tasks
Answer
Option 1: Correct. If you specify the percentage of work
complete for the relevant tasks, Project 2013 automatically
updates other entries, including actual and remaining work, for
those tasks.
Option 2: Incorrect. Rescheduling incomplete work on a task
moves the task start date, decreasing the record of progress
made as a result.
Option 3: Incorrect. Creating a new project baseline simply
saves the existing project and task information. It doesn't alter
or update the details of individual tasks.
Option 4: Incorrect. Modifying the actual work and remaining
work values is more time-consuming than simply entering the
estimated percentage complete for each task. When you specify
the estimated percentage of completed work, Project 2013
automatically updates the actual and remaining work values.
Correct answer(s):
1. Enter the estimated percentage complete for the tasks
Question
You need to update the progress information for two tasks.
Task 3 is fully complete, and task 4 is half complete. How do
you update the task details?
Options:
1. Type 100 in the % Complete cell for task 3
2. Type 50 in the % Complete cell for task 4
3. Mark task 3 as fully complete
4. Enter the start date and finish dates for task 4
5. Mark task 4 as half complete
6. Enter the start date and finish dates for task 3
Answer
Correct answer(s):
1. Type 100 in the % Complete cell for task 3
2. Type 50 in the % Complete cell for task 4
29. Question
You want to update the actual and remaining work values for a
set of tasks, without having Project automatically update any
other values.
How do you do this?
Options:
1. Manually enter the actual work and remaining work
information for the tasks
2. Access and alter information at the project level
3. Reschedule incomplete work on the tasks
Answer
Option 1: Correct. Manually entering work values in the Actual
Work and Remaining Work columns for specific tasks updates
only those values.
Option 2: Incorrect. You can use the Project Information dialog
box to make changes to the details for an entire project, but not
to alter progress information for specific tasks.
Option 3: Incorrect. Rescheduling incomplete work on tasks
moves their start dates but doesn't change their actual and
remaining work values.
Correct answer(s):
1. Manually enter the actual work and remaining work
information for the tasks
Setting a baseline
Question
You've completed a project phase and want to save the current
project information as a baseline.
You've already clicked the PROJECT tab, what do you do next?
Options:
1. Click Set Baseline
2. Select Baseline
3. Select Baseline 1
4. Select Baseline 2
Answer
30. Correct answer(s):
1. Click Set Baseline
Progress information for tasks has been updated and a new
baseline has been created and viewed in Project 2013.
Comparing Progress against a Baseline
Learning Objective
After completing this topic, you should be able to
· identify performance variances using a Gantt chart in Project
2013
1. Demo: Viewing variances
Variance is the difference between planned values and actual
values, such as cost or time it takes to complete tasks. Variance
is a major concern for every project manager because many
projects have an inflexible project finish date. It's important to
be able to identify slippage, whether it would be date slippage
or effort slippage, so we can have an accurate assessment of the
situation. Then we as project managers can either reschedule
tasks, assign more resources, or re-prioritize project
deliverables to ensure the project still finishes on time overall.
Let's see how to view date variance. On the VIEW tab I want to
get to Gantt chart, so I'll click GanttChart. And I don't want to
see these columns, I want to see the table called Variance, so
I'll right-click in this upper left-hand corner, instead of
the Entry table, I'll click Variance.
Graphic
By default, the Microsoft Project 2013 interface consists of a
Quick Access Toolbar of frequently-use commands, and a
ribbon with tabs such as, TASK, RESOURCE, and PROJECT.
The project plan is displayed below these elements.
In this example, a project plan is open in Resource Sheet view
and on the ribbon, the VIEW tab is selected.
The VIEW tab includes the Task View group with the options
Gantt Chart and Task Usage.
31. In Gantt Chart view, the instructor right-clicks the
Select All cell and two actions are implemented simultaneously.
The cells in the table are selected and a menu opens with the
options: Calculate Project, Cost, Entry, Hyperlink, Schedule,
Summary, Tracking, Usage, Variance, Work, and More Tables.
So you can see the different columns we're seeing now and as
an example, "Identify resource requirements." We thought it
was going to start on the 17th of January, we actually started
nine workdays earlier than that on January 6th. So we have a
negative nine days for the Start Variance and so a negative
number means something happened early. Looking at the Finish,
we finished the same date that we thought we would finish
according to the baseline, so it has a zero days of variance for
the Finish. And another example is "Conduct interview(s)." We
originally thought we were going to start conducting the
interviews on January 9th here in the Baseline Start column. We
didn't actually start them until January 22nd, so that's nine
workdays later. So a positive nine in Start Variance is nine days
late. And likewise we finished nine days late as well. So on any
project that is in progress you'll want to be watching the
variances to see how much tasks are slipping in time and this is
a nice place to do that.
Graphic
The Variance table lists columns such as, Start, Finish, Baseline
Start, Baseline Finish, Start Variance, and Finish Variance.
The "Identify resource requirements" task has a Start Variance
of minus 9 days and a Finish Variance of 0 days. The
corresponding Start and Finish dates are 1/6/14 and 1/23/14
respectively; and the Baseline Start and Baseline Finish dates
are 1/17/14 and 1/23/14 days respectively.
The "Conduct interview(s)" task has a Start Variance of 9 days
and a Finish Variance of the same. The corresponding Start and
Finish dates are 1/22/14 and 1/30/14 respectively; and the
Baseline Start and Baseline Finish dates are 1/9/14 and 1/17/14
32. respectively.
Work variance will show you any differences between the
original planned hours to complete a task and the actual hours it
took to complete it. Let me show you how to view work
variance. First we'll go up to the VIEWtab of the ribbon and I'll
choose Gantt Chart and in this Gantt chart, if you look across
the column headers, we're seeing things about Start and Finish
dates, Baseline Start and Finish dates, and then the variance for
the Start and Finish dates, and that's not what we want to see at
the moment. So in the upper left-hand corner, I'm going to
right-click in that Select All area and instead of seeing
the Variance table I'd like to see the Work table. So now we're
seeing Work, Baseline Work, and Variance for work, among
other columns.
Graphic
The instructor opens the Variance table in Gantt Chart view.
She then changes to the Work table.
When the Work table is implemented, the column headers are
modified to read: Work, Baseline, Variance, Actual, Remaining,
and Percent Work Complete.
I'd like to focus on one example. Here we have "Select final
candidates based on interview results." The baseline for this
task was 16 hours meaning that we estimated it would take 16
hours to do it. However, the actual work was 24 hours so it took
longer than we thought it would. Thus the variance is 8 hours –
the difference between 24 and 16. Since the hours of work on a
project is one of the things that directly impacts the cost of the
project, paying attention not just to date slippage but also to
work variance can be valuable information as we proceed
through our project, so we can try to keep costs under control.
Graphic
The instructor selects task number 6, "Select final candidates
based on interview results". The values for the task according to
the column headers Work, Baseline, Variance, Actual,
Remaining, and Percentage Work Complete read: 24 hours, 16
33. hours, 8 hours, 24 hours, 0 hours, and 100% respectively.
We view cost variance if we want to see changes in the project
cost from the original planned cost, for either tasks or the
project as a whole. To view cost variance we'll go to a Gantt
chart. Up to the VIEW tab of the ribbon, click on the Gantt
Chart and right now if I right-click in the upper left-hand corner
to see what table I'm looking at, it's the Work table but we want
the Cost table. So I'll choose that and you can see the columns
across. Let's use "Identify sponsors and stakeholders" as our
example.
Graphic
In this example, the instructor view a project in Gantt Chart
view, and then used the Select All shortcut menu to change to
the Cost table.
We originally thought this task was going to cost $5,000, we
can see that here in the Baseline column. It actually ended up
costing $6,400 and so that is a variance of $1,400 if you
subtract. And it's the only one with the variance at this point.
So the variance of this task is also the same as the variance of
the summary tasks above. As project managers we need to be
able to find the information in which we are interested among
all the data that's stored in a project file. So when you're trying
to understand how you're doing with costs in your project,
you'll want to know how to view the Cost table to see the Cost
Variances.
Graphic
The Cost table contains the columns: Fixed Cost, Fixed Cost
Accrual, Total Cost, Baseline, Variance, and Actual.
For the selected task, the Baseline column reflects $5000 and
the Fixed Cost and Total Cost columns read $6,400. The
Variance column reads $5,000.
The instructor pronounces the dollar amounts as 64 hundred or
14 hundred; not six thousand-four hundred or a thousand-four
hundred.
34. Displaying Critical Path Information
Learning Objective
After completing this topic, you should be able to
· view a critical path in Project 2013
1. Demo: Viewing critical paths
A project's critical path is the series of sequential tasks that
must be completed on schedule for a project to finish on time.
We might want to view the critical path information for our
project when we need to keep track of how late tasks can start
and how late they can finish, before they will affect the end date
of the project. Or when we need to know how much slippage we
can afford in our project. We're already on a Gantt chart here,
where we see blue bars, representing the tasks, some have a
thinner black bar in the middle representing progress either for
tasks that are all done or partially done. And we have the black
diamonds for milestones and the black bars for summary tasks
and they're hovering over there tasks that they summarize.
When we ask Project to display critical tasks, they'll be
represented by red bars and blue bars will represent non-critical
tasks.
Graphic
By default, the Microsoft Project 2013 interface consists of a
Quick Access Toolbar of frequently-use commands, and a
ribbon with tabs such as, TASK, RESOURCE, and PROJECT.
The project plan is displayed below these elements.
In this example, a project plan is open in Gantt Chart view and
on the ribbon, the TASK tab is selected.
The Gantt chart the instructor is referring to contains blue
horizontal bars of different lengths that indicate the tasks, a
black line inside the task line indicate task progress, black
diamonds to indicate project milestones, and thick black bars to
indicate summary tasks.
So let's view the critical path. We'll go up to the GANTT
CHART TOOLS contextual tab, FORMAT, and in the Bar Styles
35. group I'll click on the checkbox for Critical Tasks. And so we
can see that of the tasks that are not yet complete, Project
displays the critical tasks on the critical path as red bars. Some
with progress bars because they have started but not yet
finished. And for instance, "Identify sponsors and stakeholders"
task has a progress bar in it and so does "Define 'best of breed'
training processes." And the rest of the red critical tasks are
without progress bars because they have not yet started. The
tasks that are done are no longer considered critical so they're
not red. So being able to view the critical path of a project and
understand what it shows, is essential to being able to manage a
project effectively.
Graphic
The GANTT CHART TOOLS - FORMAT contextual tab
includes groups such as, Columns, Bar Styles, and Gantt Chart
Style. The Bar Style group contains the options: Format,
Critical Tasks, Slack, Late Tasks, Task Path, Baseline, and
Slippage.
The instructor selects the Critical Tasks checkbox and the Gantt
chart is modified so that critical tasks are now indicated by
horizontal, red bars.
Slack is the amount of time a task can slip without delaying the
project finish date. To view slack, we're already on a Gantt
chart and let's go to the GANTT CHART TOOLScontextual tab,
FORMAT, on the ribbon and in the Bar Styles group let's check
the box called Slack and a thin dark stripe to the right of the
Gantt bar represents the amount of total slack for that task. For
example, after the "Determined project scope" task we see that
thin dark bar. And it rolls up to the summary bar as well. By
default, tasks on the critical path have a default value of No
Slack. Since they are critical tasks, they must be completed on
time in order for the project to finish on time. So you'll never
see a thin black bar after any red task because they're critical.
So one thing you'll want to do while you're planning and
managing your project is to view the total slack time to know
36. which tasks could slip, and how much, before they impact the
finish date of the project.
Graphic
The instructor selects the Slack checkbox and the Gantt chart is
modified so that thin dark lines extend from the bas of certain
tasks.
Viewing Potential Schedule Performance Problems
Learning Objective
After completing this topic, you should be able to
· use tools to view schedule issues in Project 2013
1. Demo: Using the Task Inspector
Project has a built-in feature called Task Inspector. It identifies
any issues that may impact your project schedule. To use the
Task Inspector, we're already on a Gantt Chart view, and we'll
go to the TASK tab of the ribbon. And in the Tasks group the
first of these three buttons that are one above the other says,
"Inspect" when you point to it. And I could just click on the
square part of the button or I can drop-down the list and
choose Inspect Task. And the Task Inspector opens a new pane
to the left. With the Task Inspector pane open, we can select a
task and we'll see any issues that need to be addressed displayed
in the left pane. For example I'll click on Conduct
interview(s) and you can see in the Task Inspector pane on the
left it identifies the task, it tells us that resources are over-
allocated due to work on other tasks.
Graphic
By default, the Microsoft Project 2013 interface consists of a
Quick Access Toolbar of frequently-use commands, and a
ribbon with tabs such as, TASK, RESOURCE, and PROJECT.
The project plan is displayed below these elements.
In this example, a project plan is open in Gantt Chart view and
on the ribbon, the VIEW tab is selected.
The TASK tab includes the Tasks group with the options:
Manually Schedule, Auto Schedule, Inspect, Move Task, and
37. Schedule Mode.
The Inspect drop-down contains the options: Inspect Task,
Show Warnings, Show Suggestions, and Show Ignored
Problems. Clicking Inspect Task opens the Task Inspector pane.
The pane displays the name of the selected task, any identified
issues, and suggested solutions, for example.
So this Alex is working on more than just this one task. And
beside some other information about the schedule at the bottom,
it also is nice enough to give us the suggestions. So we could
move the task to our resource's next available time – Alex's next
available time – to reschedule that task so it's not overallocated.
Or another avenue is we could view overallocated resources in
the Team Planner. And then once we find what we find in the
Team Planner, like what other tasks are during that same time
period, then we can take action from there. So the Task
Inspector not only helps you know what issues exist, it offers
suggestions for how to address the issue. So as a project
manager you would want to know of any issues impacting your
projects. So now you know that the Task Inspector can provide
you with this very useful information.
Graphic
The Task Inspector pane also provides information such as the
task's start and finish dates.
Project includes a useful tool to visually identify any tasks that
are late in the schedule. Right now we're seeing a regular Gantt
chart where the bars representing tasks are blue. It does not
distinguish between late ones and ones that are either on time or
ahead. I'll show you how to see late tasks displayed differently.
We're on the Gantt chart. We'll go to the GANTT CHART
TOOLS contextual tab called FORMAT on the ribbon, and in
the Bar Styles group, I'll click on Late Tasks. And so now in the
Gantt chart, Project is displaying the late tasks as gray bars. For
instance, this "Identify sponsors and stakeholders" task, we're
partway done on it but not far enough to be considered on time.
38. So we're late with that. Another one, "Define 'best of breed'
training processes" – again we're partway done with that. We're
in progress but not far enough along to be considered on time or
ahead. So as you are managing a project, when you would like
to see which tasks are late for where you are in time right now,
ask Project to show you the late tasks.
Graphic
A project is open in Gantt Chart view and the TASK tab is
selected.
The GANTT CHART TOOLS - FORMAT tab includes the Bar
Styles group, with the options: Format, Critical Tasks, Slack,
Late Tasks, Task Path, Baseline, and Slippage.
Activity: Analyze Project Progress
Learning Objective
After completing this topic, you should be able to
· use tools for identifying and assessing schedule issues in
Project 2013
Exercise overview
Now we have a few questions.
Supplement
Selecting the link title opens the resource in a new browser
window.
Job Aid
Access the job aid Analyzing Project Progress to review options
for analyzing project progress in Project 2013.
In this exercise, you're required to analyze project progress in
Project 2013.
This involves the following tasks:
· identifying project performance variances and
· inspecting a task for any issues
Identifying variances
Question
You want to check whether any project tasks are running behind
schedule.
39. You've clicked the VIEW tab, what do you do next?
Options:
1. Click Gantt Chart
2. Click Task Usage
3. Click Team Planner
4. Select Tracking Gantt
5. Select Variance
Answer
Correct answer(s):
1. Click Gantt Chart
Question
Which task or set of tasks has a variance of 0.25 days in its
Start date?
The Northglenn_new_center_progress_activity file is open in
the Project 2013 window. The TASK tab is open with the View,
Clipboard, Font, Schedule, Tasks, Insert, Properties, and
Editing sections visible. The current project view is the Gantt
Chart, with the Variance table applied. The first six tasks are
visible in the variance table with starting variances totalling 0,
0.25, 0.25, 0, 0.25, 0.25, and 0.25 respectively.
Options:
1. Task 6
2. Tasks 1, 2, and 6
3. All the listed tasks except task 3
4. Task 3
Answer
Option 1: Correct. The Start Variance column indicates a 0.25
variance in the start date for task 6. So the actual start date for
the task is a quarter of a day out from the planned start date.
Option 2: Incorrect. Tasks 1 and 2 have a 0.25 variance in their
finish dates, rather than in their start dates.
Option 3: Incorrect. Tasks 1, 2, and 4 have a variance of 0.25
days in their finish dates only. There's no variance in their start
dates.
Option 4: Incorrect. There's no variance in the start or finish
date for task 3.
40. Correct answer(s):
1. Task 6
Question
You want to check that tasks with a finish variance aren't on the
critical path, and determine what slack is available.
Which tab on the ribbon contains the options you use to do this?
The TASK tab is open on the ribbon. Among the other tabs are
the GANTT CHART TOOLS - FORMAT contextual tab, the
PROJECT tab, and the VIEW tab.
Options:
1. GANTT CHART TOOLS - FORMAT
2. VIEW
3. PROJECT
4. REPORT
Answer
Correct answer(s):
1. GANTT CHART TOOLS - FORMAT
Inspecting a task
Question
You want to check whether any resource or scheduling issues
affect the first task in a project.
You've already clicked row header 1 to select the task, what do
you do next?
Options:
1. Open the Task Inspector
2. Move the task
3. Change the schedule mode
Answer
Option 1: Correct. The Task Inspector shows this type of
information, and can be accessed from the Tasks group on the
TASK tab.
Option 2: Incorrect. Moving the task will change the task order,
but doesn't provide information about resource and scheduling
issues.
41. Option 3: Incorrect. Although you can switch between manually
scheduling tasks and making them automatically scheduled, this
doesn't provide information about resource and scheduling
issues.
Correct answer(s):
1. Open the Task Inspector
Task variances have been identified and a specific task has been
inspected for any issues in Project 2013.Updating Progress
Information
Purpose: Use this job aid to review ways to update the progress
information for a project in Project 2013.
Updating progress on a project
Method
Effect
Enter the estimated percentage complete for relevant tasks
Project automatically alters the actual and remaining work
values for the tasks, based on the new percentage complete
values
Reschedule incomplete work on a task
Project automatically adjusts the start date for the task to
provide an updated record of progress on the task
Create a new project baseline
Saves the current details, including progress information, for
the project so they can be recovered or compared to later
versions of the project information
Manually enter actual work and remaining work information for
specific tasks
Updates only the values you enter for the tasks
Open the Project Information dialog box and make changes to
the project details there
Enables you to make changes to the entire project, rather than
just to individual tasks
Course: Tools for Tracking Project Performance in Project 2013
Topic: Activity: Perform End-of-phase Progress
UpdatesAnalyzing Project Progress
Purpose: Use this job aid to review options for analyzing
42. project progress in Project 2013.
Accessing the Gantt Chart and Tracking Gantt views
Options for viewing critical tasks, slack, and late tasks
Course: Tools for Tracking Project Performance in Project 2013
Topic: Activity: Analyze Project Progress