SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
Bachelor of Quantity Surveying (Honours)
INTEGRATED ASSIGNMENT:
MEASUREMENT I (QSB60104)
CONSTRUCTION TECHNOLOGY I (BLD 60104)
BUILDING MATERIALS (BLD 62003)
SITE VISIT REPORT
STUDENT NAME:LIM ZI SHAN
STUDENT ID NO.:0320372
DATE OF SUBMISSION: 27.12.2015 FRIDAY
Introduction
A site visit was conducted by Sr.Ang Fuey Lin and Ms. Azrina on 19 November
2015. The location of the site visit was at Sekyen 2A, Antara Gapi, Hulu Selangor,
Selangor. A total of 83 students took part in this site visit. The agenda of this site visit is
to provide an opportunity for students to learn how a pad footing is constructed and
what are the materials used for constructing a pad footing. Valuable information were
shared among the students and the contractors regarding the visit especially on the
operation of the project.
The objective of this site visit is to let students understand the basics of the
construction process. Student can witness the usage of construction equipment on site
including the mechanical plants. This is also an opportunity for students to explore and
identify the types of materials and technology on site. At the end of the site visit, student
are able to explain the construction of buildings and the scientific principles that
underpin the design and construction.
Before leaving for the site visit, students were given all the safety measures that
need to be taken at the construction site. Students are required to wear their helmet and
proper attire so that it would not cause any accidents or any inconvenience to the
authorities at the site. All the students gathered at the university at 8 a.m. and leave
around 8.45 a.m. After traveling by bus for an hour, we reached the construction site
around 9.45 a.m. We were introduced to the contractors who would be guiding us
throughout the site visit. We were given a short brief about the safety measures at the
site by the contractors.
The overview plan of the
construction site.
Detail drawing for the pad footing,
stating their diameter and sizes.
Organizational chart of the
project.
Content / Technical Observation
The first thing we saw when we walked into the construction site is
reinforcement bars. There were high tensile steel rods and mild yield
reinforcements which is arranged accordingly to their diameter and types. Sr.
Ang has also provided us more details about the bend for reinforcement bars and
the links. The lecturers and contractors gave us some time to take photos of the
surroundings for the report purpose and proceeded to our next location of the
construction site shortly after.
Proceeding to the next section of the site, we saw pad footing that is
already done, leaving only the stump above the ground and the footing covered
by the soil. As we were moving on to the next location, we can see brick bonds
that are used for the buildings which is stretcher bond. Different types of material
in construction can be found along the path in the site such as claybricks,
aluminum that is used as rood support, timber as formwork and scaffolding, and
cement for constructing the concrete.
Next, we headed to another section where the workers are in
progress of constructing the pad footing. The contractor explained to us the
process of the construction for pad footing. First of all, the surveyor will mark the
position for the house as to provide convenience for the workers to able to mark
another position for the square of pad footing. The workers will conduct a 1.5 m
deep of excavation for pad footing of any sizes. By following the measurement
from the detail drawing, the workers will build the formwork for the footing with
the given sizes. Most of the formworks are constructed using timber. After
constructing the formwork, the workers will lay the lean concrete as base before
they started putting in the reinforcement bars. They will place the reinforcement
bars for the footing based on what has given to them in the detail drawing. The
stump for the footing will be added into the footing and it has to be done as
stated in the detail drawing regarding the number of stumps and links in the
stump. After that, they will start constructing the concrete for the footing. The
formwork of the stump will begin and the workers will bury the footing as to cover
them up to enable the construction of the ground beam. The ground beam act as
the frame of the house. The ground slab which is the floor for the house, can only
be constructed after the ground beam has been constructed. The workers will
flatten the soil to construct ground slab and then inject the termiticide to prevent
termite infestation. Workers will construct a lean concrete for the ground slab and
then they will start adding mesh fabric reinforcement(BRC) with the correct sizes
and diameter. The materials used in constructing a pad footing is timber for
formworks, concrete for lean concrete and reinforced concrete of the footing,
stumps, beam and slab, reinforcement bars and BRC to strengthen the support
for the building.
After taking all the photos and getting the information we needed which
used up quite some time, the contractor then providing us information about the
houses being built there, Type 1 (from the overview plan) buildings are all flat
houses and type 2A houses are step-down houses, both of these houses used
piling as their foundation. 2B houses are step-up houses, where they used piling
foundation for the side and corner houses and piling foundation for the middle
houses however the foundation for some of the houses still depends on the soil
condition of that location.
By the time we reach the end of the site, the contractor brought us to the
cabin of the site where they kept all the detail drawings of the project and he
gave us his time to let us ask him questions to make sure that we got the
information we needed. Before we leave, all of us shook hands with the 3
contractors who have been guiding and explaining to us all the time to express
our gratitude to them.
Color schemes proposed for the houses at
the construction site.
Figure 4 : Heavy machinery that is used on
the construction site.
Figure 1 : Roof support.
Figure 3 : Cement mixer.
Figure 2 : The building is
constructed with stretcher bond.
Figure 1 : Roof support.Figure 1 : Roof support.
Figure 6 : Links or stirrups .
Figure 5 : 12 meter long steel bar which
Ms. Ang had told us about during her
lectures.
Figure 7 : Reinforcement bars.
Figure 15: Mesh fabric reinforcement
(BRC).
Figure 9 : Bend of a steel bar.
Figure 8 : Tying wires to tie the rebars
together.
Figure 13 : The worker is dismantling the
formwork for the footing
Figure 12 : Link of a column.
Figure 14 : Workers are constructing
formwork for stump.
Figure 16 : Various types of roof tiles
including Double Roman, angle section
plain tiles, etc.
Figure 17 : Ground beam, ground slab
and stump for the building.
Figure 4 : The workers are setting
up the formwork for ground beam.
Figure 18 : Claybrick that is used in
the construction site.
Figure 14 : The types of doorknobs
and locksets for the houses.
Figure 15 : Double Roman roof tiles
from Frontier.
Figure 10 : Independent scaffolding .
Figure 16 : Temporary works which
is a resting area for the workers.
Conclusion
At the end of the site visit, by outdoor learning experience, I have
understand that it is important to take safety measures at any construction sites
to prevent any accidents that may happen to you or anyone else. To me, this site
visit has given me the opportunity to experience new things and understand more
about the job scope of each profession that is involved in a construction project.
It is crucial for them to work together because they need each other for things to
work out in a construction project.
I have acquired better understanding on what I’ve been learning in
this semester such as how does stirrups looked like, how pad footing is
constructed, or what kind of materials are used in constructing pad footing. Being
able to witness the process of constructing a pad footing is a meaningful
experience to me. I am able to relate it to what I’ve learned from the books.
There are some situation where the foundation of the building can be different
from the other building based on the condition of the soil, and not just using the
same foundation for the same type of the building.
I am also able to identify materials that is used during the site visit
and what is the purpose for using it for that particular reason. Having to work
under such harsh sunlight is both tiring and dangerous, accidents may happen
and it can cause serious injuries. We have to appreciate and be thankful for
those who involved in the construction field.

More Related Content

What's hot

Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit ReportHasif Alias
 
Site report
Site reportSite report
Site reportYunshi94
 
Construction Materials site visit report
Construction Materials site visit report Construction Materials site visit report
Construction Materials site visit report Batoul Alshamali
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015Joyce HweeMin
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)Jia Hong Mui
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit ReportZIyeeTan
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Chin Tze Wei
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1Yap Xin
 
PPT on industrial summer training in civil engineer
PPT  on industrial summer training in civil engineer PPT  on industrial summer training in civil engineer
PPT on industrial summer training in civil engineer ramit raj
 
Site visit report.
Site visit report.Site visit report.
Site visit report.Man Yee
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1Nabeel Joomun
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction siteUmair Ali
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONROHITASH ROJ
 
Construction Site Visit
Construction Site VisitConstruction Site Visit
Construction Site VisitMaliha Mehr
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report I'mMiss Lily
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION Ved Jangid
 
Construction site report
Construction site reportConstruction site report
Construction site reportRavi Kant Sahu
 

What's hot (20)

Building Construction
Building ConstructionBuilding Construction
Building Construction
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Site report
Site reportSite report
Site report
 
Construction Materials site visit report
Construction Materials site visit report Construction Materials site visit report
Construction Materials site visit report
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1
 
PPT on industrial summer training in civil engineer
PPT  on industrial summer training in civil engineer PPT  on industrial summer training in civil engineer
PPT on industrial summer training in civil engineer
 
Site visit report.
Site visit report.Site visit report.
Site visit report.
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
 
Construction Site Visit
Construction Site VisitConstruction Site Visit
Construction Site Visit
 
site report
site reportsite report
site report
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
 
Construction site report
Construction site reportConstruction site report
Construction site report
 

Similar to School of Architecture Site Visit Report

Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement reportKailyn Lee
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 
Site report algel
Site report algelSite report algel
Site report algelAlgel Yee
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorKai Yun Pang
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit reportMomo Poyi
 
CT, BM & MEASUREMENT Report
CT, BM & MEASUREMENT ReportCT, BM & MEASUREMENT Report
CT, BM & MEASUREMENT Reporttianji96
 
Site report
Site reportSite report
Site reportvaylu
 
Integrated assignment site report
Integrated assignment site reportIntegrated assignment site report
Integrated assignment site reportw ss
 
Site-Report (1).docx
Site-Report (1).docxSite-Report (1).docx
Site-Report (1).docxShze Hwa Lee
 
Measurement assignment site report
Measurement assignment site reportMeasurement assignment site report
Measurement assignment site reportSyafiq Zariful
 
site report
site reportsite report
site reportszelun
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)I'mMiss Lily
 
individual site report sem 1 degree
individual site report sem 1 degreeindividual site report sem 1 degree
individual site report sem 1 degreeLam Wee
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShareYung Kai
 

Similar to School of Architecture Site Visit Report (20)

Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
Site report
Site reportSite report
Site report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site report algel
Site report algelSite report algel
Site report algel
 
Site report
Site reportSite report
Site report
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
CT, BM & MEASUREMENT Report
CT, BM & MEASUREMENT ReportCT, BM & MEASUREMENT Report
CT, BM & MEASUREMENT Report
 
Site report
Site reportSite report
Site report
 
Integrated assignment site report
Integrated assignment site reportIntegrated assignment site report
Integrated assignment site report
 
Site-Report (1).docx
Site-Report (1).docxSite-Report (1).docx
Site-Report (1).docx
 
Site report
Site reportSite report
Site report
 
SITE REPORT
SITE REPORTSITE REPORT
SITE REPORT
 
Report
ReportReport
Report
 
Measurement assignment site report
Measurement assignment site reportMeasurement assignment site report
Measurement assignment site report
 
site report
site reportsite report
site report
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
individual site report sem 1 degree
individual site report sem 1 degreeindividual site report sem 1 degree
individual site report sem 1 degree
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShare
 

More from Zi Shan

Building Integration of Solar Energy BQSAUG15
Building Integration of Solar Energy BQSAUG15Building Integration of Solar Energy BQSAUG15
Building Integration of Solar Energy BQSAUG15Zi Shan
 
Board Presentation for BM CT
Board Presentation for BM CTBoard Presentation for BM CT
Board Presentation for BM CTZi Shan
 
Psychology Comic Strip Presentation Slides FNBE 0814
Psychology Comic Strip Presentation Slides FNBE 0814Psychology Comic Strip Presentation Slides FNBE 0814
Psychology Comic Strip Presentation Slides FNBE 0814Zi Shan
 
Social psychology video presentation FNBE 0814
Social psychology video presentation FNBE 0814Social psychology video presentation FNBE 0814
Social psychology video presentation FNBE 0814Zi Shan
 
Social Psychology Video Report FNBE 0814
Social Psychology Video Report FNBE 0814Social Psychology Video Report FNBE 0814
Social Psychology Video Report FNBE 0814Zi Shan
 
Accounting Assignment 1 Financial Ratio Analysis FNBE 0814
Accounting Assignment 1 Financial Ratio Analysis FNBE 0814Accounting Assignment 1 Financial Ratio Analysis FNBE 0814
Accounting Assignment 1 Financial Ratio Analysis FNBE 0814Zi Shan
 
Social Psychology Individual Journal FNBE 0814
Social Psychology Individual Journal FNBE 0814Social Psychology Individual Journal FNBE 0814
Social Psychology Individual Journal FNBE 0814Zi Shan
 
Vomitspawn hotel business plan
Vomitspawn hotel business planVomitspawn hotel business plan
Vomitspawn hotel business planZi Shan
 
Assignment 1 compare contrast essay
Assignment 1 compare contrast essayAssignment 1 compare contrast essay
Assignment 1 compare contrast essayZi Shan
 
ENGLISH ESSAY
ENGLISH ESSAYENGLISH ESSAY
ENGLISH ESSAYZi Shan
 
Magazine
MagazineMagazine
MagazineZi Shan
 
CL Final Project Landscape Project
CL Final Project Landscape ProjectCL Final Project Landscape Project
CL Final Project Landscape ProjectZi Shan
 
Better Livable Town Bloop
Better Livable Town BloopBetter Livable Town Bloop
Better Livable Town BloopZi Shan
 
Interior architecture ICI Project 1
Interior architecture ICI Project 1Interior architecture ICI Project 1
Interior architecture ICI Project 1Zi Shan
 
Constructed Landscape Project 1 Experiential Landscape
Constructed Landscape Project 1 Experiential LandscapeConstructed Landscape Project 1 Experiential Landscape
Constructed Landscape Project 1 Experiential LandscapeZi Shan
 

More from Zi Shan (15)

Building Integration of Solar Energy BQSAUG15
Building Integration of Solar Energy BQSAUG15Building Integration of Solar Energy BQSAUG15
Building Integration of Solar Energy BQSAUG15
 
Board Presentation for BM CT
Board Presentation for BM CTBoard Presentation for BM CT
Board Presentation for BM CT
 
Psychology Comic Strip Presentation Slides FNBE 0814
Psychology Comic Strip Presentation Slides FNBE 0814Psychology Comic Strip Presentation Slides FNBE 0814
Psychology Comic Strip Presentation Slides FNBE 0814
 
Social psychology video presentation FNBE 0814
Social psychology video presentation FNBE 0814Social psychology video presentation FNBE 0814
Social psychology video presentation FNBE 0814
 
Social Psychology Video Report FNBE 0814
Social Psychology Video Report FNBE 0814Social Psychology Video Report FNBE 0814
Social Psychology Video Report FNBE 0814
 
Accounting Assignment 1 Financial Ratio Analysis FNBE 0814
Accounting Assignment 1 Financial Ratio Analysis FNBE 0814Accounting Assignment 1 Financial Ratio Analysis FNBE 0814
Accounting Assignment 1 Financial Ratio Analysis FNBE 0814
 
Social Psychology Individual Journal FNBE 0814
Social Psychology Individual Journal FNBE 0814Social Psychology Individual Journal FNBE 0814
Social Psychology Individual Journal FNBE 0814
 
Vomitspawn hotel business plan
Vomitspawn hotel business planVomitspawn hotel business plan
Vomitspawn hotel business plan
 
Assignment 1 compare contrast essay
Assignment 1 compare contrast essayAssignment 1 compare contrast essay
Assignment 1 compare contrast essay
 
ENGLISH ESSAY
ENGLISH ESSAYENGLISH ESSAY
ENGLISH ESSAY
 
Magazine
MagazineMagazine
Magazine
 
CL Final Project Landscape Project
CL Final Project Landscape ProjectCL Final Project Landscape Project
CL Final Project Landscape Project
 
Better Livable Town Bloop
Better Livable Town BloopBetter Livable Town Bloop
Better Livable Town Bloop
 
Interior architecture ICI Project 1
Interior architecture ICI Project 1Interior architecture ICI Project 1
Interior architecture ICI Project 1
 
Constructed Landscape Project 1 Experiential Landscape
Constructed Landscape Project 1 Experiential LandscapeConstructed Landscape Project 1 Experiential Landscape
Constructed Landscape Project 1 Experiential Landscape
 

Recently uploaded

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 

Recently uploaded (20)

TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 

School of Architecture Site Visit Report

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN Bachelor of Quantity Surveying (Honours) INTEGRATED ASSIGNMENT: MEASUREMENT I (QSB60104) CONSTRUCTION TECHNOLOGY I (BLD 60104) BUILDING MATERIALS (BLD 62003) SITE VISIT REPORT STUDENT NAME:LIM ZI SHAN STUDENT ID NO.:0320372 DATE OF SUBMISSION: 27.12.2015 FRIDAY
  • 2. Introduction A site visit was conducted by Sr.Ang Fuey Lin and Ms. Azrina on 19 November 2015. The location of the site visit was at Sekyen 2A, Antara Gapi, Hulu Selangor, Selangor. A total of 83 students took part in this site visit. The agenda of this site visit is to provide an opportunity for students to learn how a pad footing is constructed and what are the materials used for constructing a pad footing. Valuable information were shared among the students and the contractors regarding the visit especially on the operation of the project. The objective of this site visit is to let students understand the basics of the construction process. Student can witness the usage of construction equipment on site including the mechanical plants. This is also an opportunity for students to explore and identify the types of materials and technology on site. At the end of the site visit, student are able to explain the construction of buildings and the scientific principles that underpin the design and construction. Before leaving for the site visit, students were given all the safety measures that need to be taken at the construction site. Students are required to wear their helmet and proper attire so that it would not cause any accidents or any inconvenience to the authorities at the site. All the students gathered at the university at 8 a.m. and leave around 8.45 a.m. After traveling by bus for an hour, we reached the construction site around 9.45 a.m. We were introduced to the contractors who would be guiding us throughout the site visit. We were given a short brief about the safety measures at the site by the contractors.
  • 3. The overview plan of the construction site. Detail drawing for the pad footing, stating their diameter and sizes. Organizational chart of the project.
  • 4. Content / Technical Observation The first thing we saw when we walked into the construction site is reinforcement bars. There were high tensile steel rods and mild yield reinforcements which is arranged accordingly to their diameter and types. Sr. Ang has also provided us more details about the bend for reinforcement bars and the links. The lecturers and contractors gave us some time to take photos of the surroundings for the report purpose and proceeded to our next location of the construction site shortly after. Proceeding to the next section of the site, we saw pad footing that is already done, leaving only the stump above the ground and the footing covered by the soil. As we were moving on to the next location, we can see brick bonds that are used for the buildings which is stretcher bond. Different types of material in construction can be found along the path in the site such as claybricks, aluminum that is used as rood support, timber as formwork and scaffolding, and cement for constructing the concrete. Next, we headed to another section where the workers are in progress of constructing the pad footing. The contractor explained to us the process of the construction for pad footing. First of all, the surveyor will mark the position for the house as to provide convenience for the workers to able to mark another position for the square of pad footing. The workers will conduct a 1.5 m deep of excavation for pad footing of any sizes. By following the measurement
  • 5. from the detail drawing, the workers will build the formwork for the footing with the given sizes. Most of the formworks are constructed using timber. After constructing the formwork, the workers will lay the lean concrete as base before they started putting in the reinforcement bars. They will place the reinforcement bars for the footing based on what has given to them in the detail drawing. The stump for the footing will be added into the footing and it has to be done as stated in the detail drawing regarding the number of stumps and links in the stump. After that, they will start constructing the concrete for the footing. The formwork of the stump will begin and the workers will bury the footing as to cover them up to enable the construction of the ground beam. The ground beam act as the frame of the house. The ground slab which is the floor for the house, can only be constructed after the ground beam has been constructed. The workers will flatten the soil to construct ground slab and then inject the termiticide to prevent termite infestation. Workers will construct a lean concrete for the ground slab and then they will start adding mesh fabric reinforcement(BRC) with the correct sizes and diameter. The materials used in constructing a pad footing is timber for formworks, concrete for lean concrete and reinforced concrete of the footing, stumps, beam and slab, reinforcement bars and BRC to strengthen the support for the building. After taking all the photos and getting the information we needed which used up quite some time, the contractor then providing us information about the
  • 6. houses being built there, Type 1 (from the overview plan) buildings are all flat houses and type 2A houses are step-down houses, both of these houses used piling as their foundation. 2B houses are step-up houses, where they used piling foundation for the side and corner houses and piling foundation for the middle houses however the foundation for some of the houses still depends on the soil condition of that location. By the time we reach the end of the site, the contractor brought us to the cabin of the site where they kept all the detail drawings of the project and he gave us his time to let us ask him questions to make sure that we got the information we needed. Before we leave, all of us shook hands with the 3 contractors who have been guiding and explaining to us all the time to express our gratitude to them.
  • 7. Color schemes proposed for the houses at the construction site.
  • 8. Figure 4 : Heavy machinery that is used on the construction site. Figure 1 : Roof support. Figure 3 : Cement mixer. Figure 2 : The building is constructed with stretcher bond. Figure 1 : Roof support.Figure 1 : Roof support.
  • 9. Figure 6 : Links or stirrups . Figure 5 : 12 meter long steel bar which Ms. Ang had told us about during her lectures. Figure 7 : Reinforcement bars.
  • 10. Figure 15: Mesh fabric reinforcement (BRC). Figure 9 : Bend of a steel bar. Figure 8 : Tying wires to tie the rebars together.
  • 11. Figure 13 : The worker is dismantling the formwork for the footing Figure 12 : Link of a column. Figure 14 : Workers are constructing formwork for stump.
  • 12. Figure 16 : Various types of roof tiles including Double Roman, angle section plain tiles, etc. Figure 17 : Ground beam, ground slab and stump for the building. Figure 4 : The workers are setting up the formwork for ground beam.
  • 13. Figure 18 : Claybrick that is used in the construction site. Figure 14 : The types of doorknobs and locksets for the houses. Figure 15 : Double Roman roof tiles from Frontier.
  • 14. Figure 10 : Independent scaffolding . Figure 16 : Temporary works which is a resting area for the workers.
  • 15. Conclusion At the end of the site visit, by outdoor learning experience, I have understand that it is important to take safety measures at any construction sites to prevent any accidents that may happen to you or anyone else. To me, this site visit has given me the opportunity to experience new things and understand more about the job scope of each profession that is involved in a construction project. It is crucial for them to work together because they need each other for things to work out in a construction project. I have acquired better understanding on what I’ve been learning in this semester such as how does stirrups looked like, how pad footing is constructed, or what kind of materials are used in constructing pad footing. Being able to witness the process of constructing a pad footing is a meaningful experience to me. I am able to relate it to what I’ve learned from the books. There are some situation where the foundation of the building can be different from the other building based on the condition of the soil, and not just using the same foundation for the same type of the building. I am also able to identify materials that is used during the site visit and what is the purpose for using it for that particular reason. Having to work under such harsh sunlight is both tiring and dangerous, accidents may happen and it can cause serious injuries. We have to appreciate and be thankful for those who involved in the construction field.