1. 1
School of Architecture, Buildings and Design
Bachelor of Quantity Surveying (Honours)
Sem I March/2015
Individual Assignment:
SITE REPORT
Name: Siong Jia Yii
Student ID: 0318239
Subjects:
Measurement I [QSB60104]
= Sr. Ang Fuey Lin
Building Materials [BLD62003]
= Ms Myzatul Aishah Binti Kamarazaly
Construction Technology I [BLD60104]
= Ms Azrina Binti Md Yaakob
2. 2
CONTENT
1.0 Content 2
2.0 Introduction 3
3.0 Objective 4
4.0 Introduction to the site 5-6
5.0 Reportof the site visit
- Technical observation 7-14
- Types of reinforced concrete grade 15-16
- Type of foundation used 17
6.0 Conclusion 18
7.0 Annexes 19
3. 3
INTRODUCTION
In this project, students are required to do a report on a technical
site visit to a construction site. Students need to observe and explore the
site technically in order to complete this project by meeting all the
requirements. There are 3 subjects are involved in this project, which is
Building Materials, Measurement I and Construction Technology I.
Different task is given from each subject to all students. ForMeasurement
I, students need to make technical observations on a site and write report
with photos and description. For Building Materials, students required to
identify the grade of reinforced concrete used in construction site for
column, slab, beam and foundation and explain the advantages and also
disadvantages of these concrete grade used. For Construction Technology
I, students have to identify and explain the type of foundation used in site
with advantages and disadvantages.
4. 4
OBJECTIVE
Understand the basics of the construction process.
Understand the practical aspect of construction techniques in
comparison to the theory aspectin books and its application on
site.
Exposure to actual working environment on site including
uncertainty circumstances e.g. weather.
Ability to communicate with the construction team members on
site and to see the importance of teamwork in the building team.
Witness the usage of construction equipment on site including
mechanical plants.
Explore and identify various types of building materials and
technology on site.
Awareness of the importance of safety on site and understanding of
safety problems and site conditions.
Recognize the items measurable for sub-structure and reinforced
concrete frame works.
5. 5
INTRODUCTION TO SITE
On 26th June 2015, a construction site visit to The Andes
Construction Site is organized by Ms Ang Fuey Lin to all BQS Sem 1
students. Attendance is compulsory. The site is near to Taylor’s
University with around 15 minutes car distance.
Location of the construction site
The construction site is strategically located at the borderline of
Puchong and Bukit Jalil which is very convenient for transportation,
especially KIDEX Skyway that gives road users a lot of advantages.
Before the site visit get started, lecturer had collected students’
name, I.C and student ID to mark our attendance easily. She had
separated all students into 2 groups and gave us some brief on safety
precautions such as wearing helmet and properattire. The first group is
left from campus at 7:30am sharp and the second group is left at 8:30am.
Bus fee per student is RM15.
6. 6
For this site project, The Andes is comprising two towers of
condominium and villa.
Site Plan
Piling Plan
7. 7
Measurement I: Technical Observation
Upon arrival, students were all checked to have wearing proper
attire and helmet to ensure our safety during site visit. Project manager,
Mr James Siow is briefly introduced about the site by providing us a
process reportof the construction site.
Figure 1:
Mr James Siow, project manager
with green shirt is giving some
introduction in front of students.
A temporary work – office is
spotted behind.
Figure 2:
An information board which
showing companies that involved
in this project.
Hoarding is used as defence of the
site from unauthorized trespasser.
Figure 3:
A temporary work –
Accommodaton for workers is
spotted at the corner of site.
Genset is provided as
temporary power supply for
the workers.
8. 8
After briefing, students were formed into groups with 8 people and
led by a site worker per group for further exploration and understanding of
the site. Along the way, the supervisor keep reminding us to be careful of
the ground to ensure our safety. Since the construction is only partially
completed, we only managed to view slab, column, wall, pilecap and also
excavation.
The supervisor led us down to the basement construction by using
a temporary stairs that only fixed into the soil which is very unstable.
Figure 4:
This is a basement construction
taken from original ground level.
Red and white plastic line is used to
stop lawful visitors from stepping
forward.
Figure 5:
Students going down
carefully by a temporary
stairs.
9. 9
The first thing I saw after walked down safely from stairs is
reinforcement bars that used in basement slab. The supervisor told us that
mesh fabric would only be used started from first floor.
Figure 6:
Reinforcement bars used in
the basement slab. This
showing the part that have not
been covered by reinforced
concrete.
Figure 7:
Plastic Sheets is used to
protect the slab concrete.
Figure 8:
Synthetic Fibres is used to
prevent the concrete loss.
10. 10
There are many columns spotted on the basement slab. Some of it
had formwork and reinforcement bars installed while some are done with
reinforced concrete poured and formwork had also been removed. Each
column is less than 4m2 which means that it weighed 8.5 tonne. (1m2 =
2.2 tonne)
Figure 9:
Column that wait for reinforced
concrete to be poured.
Figure 10:
A so called “penimbang” is
hang on the column to ensure
the formwork of column is
straight.
Figure 11:
There are many holes on the
concrete of column with pipes
installed is used to stabilize
and strengthen the concrete.
11. 11
Figure 12:
There is a tower crane in the
site that used to lift heavy
loads.
Figure 13:
Scaffolding are spotted in the
site too.
Figure 14:
There are walls around the
sides above the slab with
formwork and reinforcement
bars installed.
Figure 15:
Water stop is installed in the
wall to prevent water from
entering into basement.
12. 12
After exploring for every single part of basement construction, the
supervisor then brought us to the next two areas which is doing piling
works and also excavation. There is no beam found in the site because it
had been covered underground.
Figure 16:
This photo shows the inner
side of formwork of the wall.
Figure 17:
The component that hold by
supervisor is used to tie the
formwork of walls as shown in
the Figure 13.
Figure 18:
Construction of pile cap in the
pit excavation. Steel sheet
piles are used to prevent the
soil from leaking into the
excavation.
13. 13
Figure 19:
An excavator is spotted while
excavating soil.
Figure 20:
This area is where the biggest
pilecap among all of the
pilecaps in the site get
constructed. This pilecap
weighed around 85 tonne.
Figure 21:
Bored piles is used at the site
to support high building that
has heavy vertical load.
14. 14
There were also some construction materials found at the site,
which is:
i) ii)
Figure 22:
Precast bored piles
Figure 23:
50mm diameter concrete cover
is spotted.
Figure 24:
Wastage found at the site is not properly
deal with. The construction team only let it
flow to the drain.
15. 15
Building Materials:
Grades of Concrete Used for Slab, Beam, Foundation
and Column
Grade 35
Reinforced concrete Grade 35 is used for slab, beam and foundation.
Advantages:
- It is cheaper than Grade 40.
- It is commonly used in construction industry.
- It has better resistance to fire.
- It has Long service life with low maintenance cost.
Disadvantages:
- It has low compressive strength compared to Grade 40.
- It can cracks easily under service load as the grade of reinforced
concrete is low.
- Its ability to resist sulphate attack is lower than Grade 40.
Slab Foundation
16. 16
Grade 45
Reinforced concrete Grade 45 is used for columns at basement.
Advantages:
- It can maintain the size of column uniform throughout the
building height.
- Ability to earthquake resistance is greater than Grade 35.
- It has higher strength to resist more loads.
- Higher modulus of elasticity, which increases stability and
reduces deflections.
Disadvantages:
- More expensive than Grade 35.
- It is lack of adequate research under field conditions.
- High-performance standards must meet consistently.
- Careful and high quality materials selection is necessary.
Column
17. 17
Construction Technology I: Type of Foundation Used
Pile foundation
Advantages:
- Length can be readily varied to suit varying ground conditions.
- It can be installed in very large diameters.
- End enlargement up to two or three diameters are possible in
clays.
- Material of piles is not dependent on handling or driving
conditions.
- It can be installed in very long lengths.
Disadvantages:
- Concrete is not placed under ideal conditions and cannot be
subsequently inspected.
- Water under artesian pressure may pipe up pile shaft washing
out cement.
- It cannot be readily extended above ground level especially in
river and marine structures.
- Boring methods may loosen sandy or gravely soils requiring
base grouting to achieve economic base resistance.
18. 18
CONCLUSION
I have learned a lot of things which cannot be found in the books or
notes in this site visit. This is my first time to enter a site as a lawful
visitor and see how a site looks like clearly. A lot of equipment and
complicated techniques used for the construction such as tower crane,
scaffolding, excavator, bull dozer and etc. Now I knew how hard it is to
build a building under scorching sun and dusty environment. This site
visit is a really great time for students to learn and understand
construction which is very helpful in our future. I hope that Ms Ang could
organize such activity again for us to visit site again.