Time Management In Fidic Red
Book 2017
Project (PRMG-080)
MOHAMED ISMAIL KOTB
AUC ID : 700201232
SUBMITTED TO
Dr. Bahaa el shael
Contents
Fidic Red Book 2017
Project Parties
Agreement or Determination
Time for Completion
Commencement, Delays and Suspension
Sequence of payment
FIDIC and its Dispute Resolution Provisions
Typical Sequence of Dispute
Fidic Red Book 2017
• Design and Engineering (incl. BoQs) is done by Employer or Employer’s
Representative.
• Tenderers fill in their unit prices into the existing BoQs.
• Final amount is not fixed, payments are done based on the real amounts
executed. (Exceptions are available eg: lump-sum conracts).
• Employer carries the risk for contract amount increases.
• The better the design, the flawless the project implementation.
• Tender evaluations are relatively simpler.
Project Parties
Project
Parties
Engineer
• the person named in the
Contract Data appointed
by the Employer to act
as the Engineer for the
purposes of the Contract
Employer
• he person named as the
employer in the Contract
Data and the legal
successors in title to this
person
Contractor
• the person(s) named as
contractor in the Letter
of Tender accepted by
the Employer and the
legal successors in title
of such person(s).
Typical Sequence of Events in Agreement or Determination under
Sub-Clause 3.7
Scenario(1) Agreement is reached within 42 days, error found in the Engineer’s Notice of agreement and corrected
Typical Sequence of Events in Agreement or Determination under
Sub-Clause 3.7
Scenario(2) The Parties’ early advice that agreement cannot be reached and so Engineer’s determination is necessary,
no error in Engineer’s determination.
Typical Sequence of Events in Agreement or Determination under
Sub-Clause 3.7
Scenario(3) No agreement within 42 days, Engineer determines within 42 days, error found in the Engineer’s
determination and corrected.
The Time for Completion Sequence During Contracts for Construction
Commencement, Delays and Suspension(sec-8)
• 8.1 Commencement of Works
• Before the
Commencement Date
not less than 14 days
• Or
• The Commencement
Date shall be within 42
days after the
Contractor receives the
Letter of Acceptance.
Engineer(Notice
the contractor to
commence the
work)
Commence the
work
Contractor
Time for Completion
Time for
completion
Contractor
Whole works
complete with
in
time
Taking over of the
works & section
clause 10.1
8.3Programme
Contractor
• submit an initial
programme for the
execution of the Works
to the Engineer within
28 days after receiving
the Notice
Commencement of
Works.
• submit a revised
programme for the
actual progress of the
Works.
Engineer
• Review the initial
programme and gives
the notice within 21
days after receiving the
initial programme
• Review each revised
programme and gives
the notice within 14
days after receiving a
revised programme
The Contractor shall
submit a revised
programme within 14
days after receiving this
Noticeto the Engineer
Notice of No-objection
• The Contractor shall
proceed in
accordance with the
Programme
Engineer
give the
Notice
Yes
No
Initial programme
initial
programme
Commencement
Date and the
Time for
Completion
the date right of
access to and
possession of
the Site
Execution
strategy
the order of
execution works
timing of each
stage of
Design (if any) Procurement
Submission of
documents
construction,
erection,
installation
nominated
Subcontractor
works
Testing &
inspection
Schedule & WBS
all activities
Logically linked
the earliest,
latest start,
finish dates and
the float
the critical path
Milestones
Revised programme
Revised
programme
Progress
actual progress
to date
Delays
any delay to such
progress
effects of delay
Prosals to
overcome the
effects of any delay
Supporting report
Execution works
Execution
Method
Required recourses
Personnel Equipment
significant
change(s)
8.4 Advance Warning
• The Engineer may request the Contractor to submit a proposal under
Sub-Clause 13.3.2 [Variation by Request for Proposal] to avoid or
minimize the effects of such event(s) or circumstance(s).
8.5 Extension of Time for Completion
• The Contractor shall be entitled subject to Sub-Clause 20.2 [Claims
• For Payment and/or EOT] to Extension of Time if and to the extent
that
• completion for the purposes of Sub-Clause 10.1 [Taking Over the
Works and
• Sections] is or will be delayed by any of the following causes:
Measure works
which increases
the quantity
more than
10%causes a
delay to
completion
Contractor
• Review
measured
quantities
• Increase, but
not decrease
the total EOT
Engineer
8.5 Extension of Time for Completion (EOT)
EOT
Causes
Variation
Unforeseen
climatic
conditions
Unavailabilit
y of labor,
material,or
equipment
Delays
caused by
the employer
Assessed in
accordance
rules and procedures
stated in the Special
Provisions
as appropriate taking
due regard of all
relevant
circumstances).
Concurrent Delay
8.6 Delays Caused by Authorities
DelaysCaused
byAuthorities
Contractor has diligently followed the
procedures laid down by the relevant
legally constituted public authorities
authorities or entities delay or disrupt the
Contractor’s work
delay or disruption was Unforeseeable,
Contractor consider Clause 8.4 (EOT for
completion)
8.7 Rate of Progress
1- slow progress to complete the Works
2- progress has fallen (or will fall) behind the Programme
3- the initial programme has not yet become the Programme
1-instruct the Contractor to submit the revised methods to expedite progress and complete the Works
2-gives a Notice to the Contractor stating otherwise, the Contractor shall adopt these revised methods
1-if these revised methods cause the Employer to incur additional costs, the Employer shall be entitled subject to
Sub-Clause 20.2 [Claims For Payment and/or EOT] to payment of these costs by the Contractor, in addition to Delay
Damages (if any).
2-termination under Sub-Clause 15.2 [Termination for Contractor’s Default] before completion of the Works. These
Delay Damages
Contractor
Engineer
Employer
8.8 Delay Damages
Delay Damages
Contractor
Fails to comply with
Sub-Clause 8.2 [Time
for Completion]
Fraud, gross
negligence,
deliberate default or
reckless misconduct
by the Contractor.
Employer
[Claims ForPayment
and/or EOT] to
payment of Delay
Damages by the
Contractor
Delay Damages shall
be the amount stated
in the Contract Data
paid for every day
between the relevant
Time and relevant
Date of Completion
of the Works
8.9 Employer’s Suspension
• protect, store and
secure such part or all
of the Works against
any deterioration, loss
or damage
Contractor
• instruct to suspend
progress of part or all of
the Works
• state the date and
cause of the suspension
Engineer
8.10 Consequences of Employer’s Suspension
Contractor entitled to EOT, or to
payment of the Cost incurred
• If the Contractor suffers delay and/or incurs
Cost from complying with an Engineer’s
instruction under Sub-Clause 8.9 [Employer’s
Suspension] and/or from resuming the work
under Sub-Clause 8.13 [Resumption of Work]
Contractor not entitled to EOT, or to payment
of the Cost incurred, in making good:
• (a) the consequences of the Contractor’s faulty or defective
• (b) any deterioration, loss or damage caused by the Contractor
8.11 Payment for Plant and Materials after Employer’s
Suspension
Materials which have not
been delivered to Site, if:
the work on Plant, or delivery
of Plant and/or Materials, has
been suspended for more
than 28 days and
the Plant and/or Materials
were scheduled, and ready
for delivery to the Site during
the suspension period
reasonable evidence that the
Plant and/or Materials
comply with the Contract
the Contractor has marked
the Plant and/or Materials as
the Employer’s property in
accordance with the
Engineer’s instructions.
The Contractor shall be
entitled to
payment of the value Plant
and/or Materials which have
not been delivered to Site if
8.12 Prolonged Suspension
Suspension has
continued for more than 84 days
The Contractor may give a Notice
to the Engineer
requesting permission to proceed
If the Engineer does not give a
Notice within 28 days
after receiving the Contractor’s
Notice
the Contractor may agree to a
further suspension in which case
the Parties may agree the EOT
and/or Cost Plus Profit, and/or
payment for suspended Plant
and/or Materials, arising from
the total period of suspension
if the Parties not agree after
giving a (second) Notice to the
Engineer, treat the suspension as
an omission of the affected part
of the Works with immediate
effect including release from any
further obligation to protect,
store and secure
If the suspension affects the
whole of the Works, the
Contractor may give a Notice of
termination
8.13 Resumption of Work
Engineer
• Give Notice to
the contractor
to proceed
the suspended
work
Contractor
• resume work
after receiving
the Notice
from the
Engineer
Engineer
• record any
deterioration,
loss, damage
or defect in
the Works or
Plant or
Materials
during the
suspension
Contractor
• Make good all
such
deterioration,
loss, damage
or defect to
comply with
the Contract
Typical Sequence of payment Events Envisaged in clause 14
FIDIC 1999 and its Dispute Resolution Provisions
FIDIC Procedure for Employer/Contractor’s Claims
28 day Notice of Claim to Engineer
42 day “Fully Detailed Claim”
to Engineer
“Final Claim” 28 days after end of effects
42 days after receipt of claim
Engineer’s Response
Clause 3.5 Engineer to“Agree or Determine”
Clause 20.1
Contractor’s Claims
Clause 3.5
Determinations
Agreement/Determination
given effect unless revised under Clause 20
FIDIC 1999 and its Dispute Resolution Provisions(cont.)
Reference to Dispute Adjudication Board (DAB)
(1 or 3 people)
DAB Decision
within 84 days of reference
“Amicable Settlement” stage
ICC Arbitration
within 56 days after Notice of Dissatisfaction
Clause 20.2
Clause 20.4
Clause 20.5
Clause 20.6
No Notice of Dissatisfaction
within 28 days of Decision
Notice of Dissatisfaction
within 28 days after 84 days of reference
No DAB Decision
within 84 days of reference
Notice of Dissatisfaction
within 28 days of Decision
DAB Decision
final and binding
FIDIC 1999 and its Dispute Resolution Provisions(cont.)
Employer or Engineer gives
notice and particulars to Contractor
Clause 3.5 Engineer to
“Agree or Determine”
Clause 2.5
Employer’s Claims
Clause 3.5
Determinations
Reference to Dispute Adjudication Board (DAB)
(1 or 3 people)
“Amicable Settlement” stage
ICC Arbitration
within 56 days after Notice of Dissatisfaction
Clause 20.5
Clause 20.6
Clauses 20.2 and 20.4
(See previous diagram for
full Clause 20.4 procedure)
Agreement/Determination given
effect unless revised
under Clause 20
FIDIC 2017 and its Dispute Resolution Provisions
Event for Claim
28 day Notice of Claim to
Engineer
(No) the claiming Party shall
not be entitled to any claim
Engineer shall give a Notice
to the claiming Party, within
14 days after receiving the
Notice of Claim
(No) valid Notice
(yes) the other Party
disagrees &review by
the Engineer
Fully Detailed claim
84 days after the event
giving rise to the Claim
the Engineer shall, within
14 days after this time limit
has expired, give a Notice to
the claiming Party
accordingly.
FIDIC 2017 and its Dispute Resolution
Provisions
FIDIC 2017 and its Dispute Resolution Provisions
Typical Sequence of Dispute Events Envisaged in clause 21
Time management in fidic red book 2017(prmg080 project)

More Related Content

What's hot

FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
Shantanu Kumar Behera
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Fidic
FidicFidic
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
Ayush Joshi
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Moustafa Ismail Abu Dief
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
CNC
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
PachyCarmona1
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
Gattupalli Naresh, PMP
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Francis Ho
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
McLachlan Lister Pty Limited
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
Jeff B
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
Francis Ho
 

What's hot (20)

FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Fidic
FidicFidic
Fidic
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 

Similar to Time management in fidic red book 2017(prmg080 project)

Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
Avinash Kumar Gupta
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
EdenBekele5
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
Shivam Sood
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
ssuserb7dd601
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
ssuser6d14e4
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
brainquisitive
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
MahSobeh
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
Yee Len Wan
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
SAJJAD KHUDHUR ABBAS
 
ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
drmujahidkhan85
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
Yong Sy
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
NathannielGonzales1
 

Similar to Time management in fidic red book 2017(prmg080 project) (20)

Cl presentation
Cl presentationCl presentation
Cl presentation
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)
 
ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)
 
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Cl report final
Cl report finalCl report final
Cl report final
 
ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 

More from mohamed Ismail

1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf
1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf
1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf
mohamed Ismail
 
Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...
Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...
Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...
mohamed Ismail
 
Creep Load of concrete_ECP-201_ Ch.4 _Lecture 9.pdf
Creep Load of concrete_ECP-201_ Ch.4  _Lecture 9.pdfCreep Load of concrete_ECP-201_ Ch.4  _Lecture 9.pdf
Creep Load of concrete_ECP-201_ Ch.4 _Lecture 9.pdf
mohamed Ismail
 
Creep of Concrete زحف الخرسانة ECP-201_ Ch.4 _Lecture 8.pdf
Creep of Concrete زحف الخرسانة ECP-201_ Ch.4  _Lecture 8.pdfCreep of Concrete زحف الخرسانة ECP-201_ Ch.4  _Lecture 8.pdf
Creep of Concrete زحف الخرسانة ECP-201_ Ch.4 _Lecture 8.pdf
mohamed Ismail
 
ECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdf
ECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdfECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdf
ECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdf
mohamed Ismail
 
ECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdf
ECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdfECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdf
ECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdf
mohamed Ismail
 
ECP-201_ Ch.4 Temprature Load_Lecture 4.pdf
ECP-201_ Ch.4 Temprature Load_Lecture 4.pdfECP-201_ Ch.4 Temprature Load_Lecture 4.pdf
ECP-201_ Ch.4 Temprature Load_Lecture 4.pdf
mohamed Ismail
 
ECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdf
ECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdfECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdf
ECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdf
mohamed Ismail
 
ECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdf
ECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdfECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdf
ECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdf
mohamed Ismail
 
ECP-201_ Ch.4 Live Load_Lecture 1.pdf
ECP-201_ Ch.4 Live Load_Lecture 1.pdfECP-201_ Ch.4 Live Load_Lecture 1.pdf
ECP-201_ Ch.4 Live Load_Lecture 1.pdf
mohamed Ismail
 
Dead Load -Examples_ شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdf
Dead Load -Examples_  شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdfDead Load -Examples_  شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdf
Dead Load -Examples_ شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdf
mohamed Ismail
 
ECP-201_ Ch.3 Dead Load_Lecture 1.pdf
ECP-201_ Ch.3 Dead Load_Lecture 1.pdfECP-201_ Ch.3 Dead Load_Lecture 1.pdf
ECP-201_ Ch.3 Dead Load_Lecture 1.pdf
mohamed Ismail
 
Reliability and LRFD Specification شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...
Reliability and LRFD Specification   شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...Reliability and LRFD Specification   شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...
Reliability and LRFD Specification شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...
mohamed Ismail
 
Resistance and resistance factor in LRFD شرح الكود المصرى للأحمال ECP-201_ C...
Resistance and resistance factor in LRFD  شرح الكود المصرى للأحمال ECP-201_ C...Resistance and resistance factor in LRFD  شرح الكود المصرى للأحمال ECP-201_ C...
Resistance and resistance factor in LRFD شرح الكود المصرى للأحمال ECP-201_ C...
mohamed Ismail
 
LRFD Load combination ECP-201_ Ch.2 _Lecture 3.pdf
LRFD  Load combination ECP-201_ Ch.2 _Lecture 3.pdfLRFD  Load combination ECP-201_ Ch.2 _Lecture 3.pdf
LRFD Load combination ECP-201_ Ch.2 _Lecture 3.pdf
mohamed Ismail
 
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdfECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdf
mohamed Ismail
 
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdfECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdf
mohamed Ismail
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
mohamed Ismail
 
ECP-201_ Ch.2 Definitions of Design Loads _Lecture 1.pdf
ECP-201_ Ch.2 Definitions of Design Loads _Lecture 1.pdfECP-201_ Ch.2 Definitions of Design Loads _Lecture 1.pdf
ECP-201_ Ch.2 Definitions of Design Loads _Lecture 1.pdf
mohamed Ismail
 
ECP-201_ Ch.1 Introduction- LEC2 _Part 2.pdf
ECP-201_ Ch.1 Introduction- LEC2 _Part 2.pdfECP-201_ Ch.1 Introduction- LEC2 _Part 2.pdf
ECP-201_ Ch.1 Introduction- LEC2 _Part 2.pdf
mohamed Ismail
 

More from mohamed Ismail (20)

1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf
1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf
1-The Most Leaning towers in the world_ ECP-201_Lecture 12.pdf
 
Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...
Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...
Dynamic Load on Buildings الأحمال الديناميكية على المبانى _ECP-201_ Ch.4 _Lec...
 
Creep Load of concrete_ECP-201_ Ch.4 _Lecture 9.pdf
Creep Load of concrete_ECP-201_ Ch.4  _Lecture 9.pdfCreep Load of concrete_ECP-201_ Ch.4  _Lecture 9.pdf
Creep Load of concrete_ECP-201_ Ch.4 _Lecture 9.pdf
 
Creep of Concrete زحف الخرسانة ECP-201_ Ch.4 _Lecture 8.pdf
Creep of Concrete زحف الخرسانة ECP-201_ Ch.4  _Lecture 8.pdfCreep of Concrete زحف الخرسانة ECP-201_ Ch.4  _Lecture 8.pdf
Creep of Concrete زحف الخرسانة ECP-201_ Ch.4 _Lecture 8.pdf
 
ECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdf
ECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdfECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdf
ECP-201_ Ch.4 Shrinkage Load for Concrete in ECP_Lecture 7.pdf
 
ECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdf
ECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdfECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdf
ECP-201_ Ch.4 Shrinkage Types of Concrete_Lecture 6.pdf
 
ECP-201_ Ch.4 Temprature Load_Lecture 4.pdf
ECP-201_ Ch.4 Temprature Load_Lecture 4.pdfECP-201_ Ch.4 Temprature Load_Lecture 4.pdf
ECP-201_ Ch.4 Temprature Load_Lecture 4.pdf
 
ECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdf
ECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdfECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdf
ECP-201_ Ch.4 Horizontal Loads on Parapet _Lecture 3.pdf
 
ECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdf
ECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdfECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdf
ECP-201_ Ch.4 Live Load on Roofs and Examples _Lecture 2.pdf
 
ECP-201_ Ch.4 Live Load_Lecture 1.pdf
ECP-201_ Ch.4 Live Load_Lecture 1.pdfECP-201_ Ch.4 Live Load_Lecture 1.pdf
ECP-201_ Ch.4 Live Load_Lecture 1.pdf
 
Dead Load -Examples_ شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdf
Dead Load -Examples_  شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdfDead Load -Examples_  شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdf
Dead Load -Examples_ شرح الكود المصرى للأحمال ECP-201_ Ch.3 _Lecture 2.pdf
 
ECP-201_ Ch.3 Dead Load_Lecture 1.pdf
ECP-201_ Ch.3 Dead Load_Lecture 1.pdfECP-201_ Ch.3 Dead Load_Lecture 1.pdf
ECP-201_ Ch.3 Dead Load_Lecture 1.pdf
 
Reliability and LRFD Specification شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...
Reliability and LRFD Specification   شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...Reliability and LRFD Specification   شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...
Reliability and LRFD Specification شرح الكود المصرى للأحمال ECP-201_ Ch.2 _...
 
Resistance and resistance factor in LRFD شرح الكود المصرى للأحمال ECP-201_ C...
Resistance and resistance factor in LRFD  شرح الكود المصرى للأحمال ECP-201_ C...Resistance and resistance factor in LRFD  شرح الكود المصرى للأحمال ECP-201_ C...
Resistance and resistance factor in LRFD شرح الكود المصرى للأحمال ECP-201_ C...
 
LRFD Load combination ECP-201_ Ch.2 _Lecture 3.pdf
LRFD  Load combination ECP-201_ Ch.2 _Lecture 3.pdfLRFD  Load combination ECP-201_ Ch.2 _Lecture 3.pdf
LRFD Load combination ECP-201_ Ch.2 _Lecture 3.pdf
 
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdfECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2B_Example.pdf
 
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdfECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdf
ECP-201_ Ch.2 Load combinations (ASD & LRFD )_Lecture 2.pdf
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
 
ECP-201_ Ch.2 Definitions of Design Loads _Lecture 1.pdf
ECP-201_ Ch.2 Definitions of Design Loads _Lecture 1.pdfECP-201_ Ch.2 Definitions of Design Loads _Lecture 1.pdf
ECP-201_ Ch.2 Definitions of Design Loads _Lecture 1.pdf
 
ECP-201_ Ch.1 Introduction- LEC2 _Part 2.pdf
ECP-201_ Ch.1 Introduction- LEC2 _Part 2.pdfECP-201_ Ch.1 Introduction- LEC2 _Part 2.pdf
ECP-201_ Ch.1 Introduction- LEC2 _Part 2.pdf
 

Recently uploaded

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 

Recently uploaded (20)

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 

Time management in fidic red book 2017(prmg080 project)

  • 1. Time Management In Fidic Red Book 2017 Project (PRMG-080) MOHAMED ISMAIL KOTB AUC ID : 700201232 SUBMITTED TO Dr. Bahaa el shael
  • 2. Contents Fidic Red Book 2017 Project Parties Agreement or Determination Time for Completion Commencement, Delays and Suspension Sequence of payment FIDIC and its Dispute Resolution Provisions Typical Sequence of Dispute
  • 3. Fidic Red Book 2017 • Design and Engineering (incl. BoQs) is done by Employer or Employer’s Representative. • Tenderers fill in their unit prices into the existing BoQs. • Final amount is not fixed, payments are done based on the real amounts executed. (Exceptions are available eg: lump-sum conracts). • Employer carries the risk for contract amount increases. • The better the design, the flawless the project implementation. • Tender evaluations are relatively simpler.
  • 4. Project Parties Project Parties Engineer • the person named in the Contract Data appointed by the Employer to act as the Engineer for the purposes of the Contract Employer • he person named as the employer in the Contract Data and the legal successors in title to this person Contractor • the person(s) named as contractor in the Letter of Tender accepted by the Employer and the legal successors in title of such person(s).
  • 5. Typical Sequence of Events in Agreement or Determination under Sub-Clause 3.7 Scenario(1) Agreement is reached within 42 days, error found in the Engineer’s Notice of agreement and corrected
  • 6. Typical Sequence of Events in Agreement or Determination under Sub-Clause 3.7 Scenario(2) The Parties’ early advice that agreement cannot be reached and so Engineer’s determination is necessary, no error in Engineer’s determination.
  • 7. Typical Sequence of Events in Agreement or Determination under Sub-Clause 3.7 Scenario(3) No agreement within 42 days, Engineer determines within 42 days, error found in the Engineer’s determination and corrected.
  • 8. The Time for Completion Sequence During Contracts for Construction
  • 9. Commencement, Delays and Suspension(sec-8) • 8.1 Commencement of Works • Before the Commencement Date not less than 14 days • Or • The Commencement Date shall be within 42 days after the Contractor receives the Letter of Acceptance. Engineer(Notice the contractor to commence the work) Commence the work Contractor
  • 10. Time for Completion Time for completion Contractor Whole works complete with in time Taking over of the works & section clause 10.1
  • 11. 8.3Programme Contractor • submit an initial programme for the execution of the Works to the Engineer within 28 days after receiving the Notice Commencement of Works. • submit a revised programme for the actual progress of the Works. Engineer • Review the initial programme and gives the notice within 21 days after receiving the initial programme • Review each revised programme and gives the notice within 14 days after receiving a revised programme The Contractor shall submit a revised programme within 14 days after receiving this Noticeto the Engineer Notice of No-objection • The Contractor shall proceed in accordance with the Programme Engineer give the Notice Yes No
  • 12. Initial programme initial programme Commencement Date and the Time for Completion the date right of access to and possession of the Site Execution strategy the order of execution works timing of each stage of Design (if any) Procurement Submission of documents construction, erection, installation nominated Subcontractor works Testing & inspection Schedule & WBS all activities Logically linked the earliest, latest start, finish dates and the float the critical path Milestones
  • 13. Revised programme Revised programme Progress actual progress to date Delays any delay to such progress effects of delay Prosals to overcome the effects of any delay Supporting report Execution works Execution Method Required recourses Personnel Equipment significant change(s)
  • 14. 8.4 Advance Warning • The Engineer may request the Contractor to submit a proposal under Sub-Clause 13.3.2 [Variation by Request for Proposal] to avoid or minimize the effects of such event(s) or circumstance(s).
  • 15. 8.5 Extension of Time for Completion • The Contractor shall be entitled subject to Sub-Clause 20.2 [Claims • For Payment and/or EOT] to Extension of Time if and to the extent that • completion for the purposes of Sub-Clause 10.1 [Taking Over the Works and • Sections] is or will be delayed by any of the following causes: Measure works which increases the quantity more than 10%causes a delay to completion Contractor • Review measured quantities • Increase, but not decrease the total EOT Engineer
  • 16. 8.5 Extension of Time for Completion (EOT) EOT Causes Variation Unforeseen climatic conditions Unavailabilit y of labor, material,or equipment Delays caused by the employer Assessed in accordance rules and procedures stated in the Special Provisions as appropriate taking due regard of all relevant circumstances). Concurrent Delay
  • 17. 8.6 Delays Caused by Authorities DelaysCaused byAuthorities Contractor has diligently followed the procedures laid down by the relevant legally constituted public authorities authorities or entities delay or disrupt the Contractor’s work delay or disruption was Unforeseeable, Contractor consider Clause 8.4 (EOT for completion)
  • 18. 8.7 Rate of Progress 1- slow progress to complete the Works 2- progress has fallen (or will fall) behind the Programme 3- the initial programme has not yet become the Programme 1-instruct the Contractor to submit the revised methods to expedite progress and complete the Works 2-gives a Notice to the Contractor stating otherwise, the Contractor shall adopt these revised methods 1-if these revised methods cause the Employer to incur additional costs, the Employer shall be entitled subject to Sub-Clause 20.2 [Claims For Payment and/or EOT] to payment of these costs by the Contractor, in addition to Delay Damages (if any). 2-termination under Sub-Clause 15.2 [Termination for Contractor’s Default] before completion of the Works. These Delay Damages Contractor Engineer Employer
  • 19. 8.8 Delay Damages Delay Damages Contractor Fails to comply with Sub-Clause 8.2 [Time for Completion] Fraud, gross negligence, deliberate default or reckless misconduct by the Contractor. Employer [Claims ForPayment and/or EOT] to payment of Delay Damages by the Contractor Delay Damages shall be the amount stated in the Contract Data paid for every day between the relevant Time and relevant Date of Completion of the Works
  • 20. 8.9 Employer’s Suspension • protect, store and secure such part or all of the Works against any deterioration, loss or damage Contractor • instruct to suspend progress of part or all of the Works • state the date and cause of the suspension Engineer
  • 21. 8.10 Consequences of Employer’s Suspension Contractor entitled to EOT, or to payment of the Cost incurred • If the Contractor suffers delay and/or incurs Cost from complying with an Engineer’s instruction under Sub-Clause 8.9 [Employer’s Suspension] and/or from resuming the work under Sub-Clause 8.13 [Resumption of Work] Contractor not entitled to EOT, or to payment of the Cost incurred, in making good: • (a) the consequences of the Contractor’s faulty or defective • (b) any deterioration, loss or damage caused by the Contractor
  • 22. 8.11 Payment for Plant and Materials after Employer’s Suspension Materials which have not been delivered to Site, if: the work on Plant, or delivery of Plant and/or Materials, has been suspended for more than 28 days and the Plant and/or Materials were scheduled, and ready for delivery to the Site during the suspension period reasonable evidence that the Plant and/or Materials comply with the Contract the Contractor has marked the Plant and/or Materials as the Employer’s property in accordance with the Engineer’s instructions. The Contractor shall be entitled to payment of the value Plant and/or Materials which have not been delivered to Site if
  • 23. 8.12 Prolonged Suspension Suspension has continued for more than 84 days The Contractor may give a Notice to the Engineer requesting permission to proceed If the Engineer does not give a Notice within 28 days after receiving the Contractor’s Notice the Contractor may agree to a further suspension in which case the Parties may agree the EOT and/or Cost Plus Profit, and/or payment for suspended Plant and/or Materials, arising from the total period of suspension if the Parties not agree after giving a (second) Notice to the Engineer, treat the suspension as an omission of the affected part of the Works with immediate effect including release from any further obligation to protect, store and secure If the suspension affects the whole of the Works, the Contractor may give a Notice of termination
  • 24. 8.13 Resumption of Work Engineer • Give Notice to the contractor to proceed the suspended work Contractor • resume work after receiving the Notice from the Engineer Engineer • record any deterioration, loss, damage or defect in the Works or Plant or Materials during the suspension Contractor • Make good all such deterioration, loss, damage or defect to comply with the Contract
  • 25. Typical Sequence of payment Events Envisaged in clause 14
  • 26. FIDIC 1999 and its Dispute Resolution Provisions FIDIC Procedure for Employer/Contractor’s Claims 28 day Notice of Claim to Engineer 42 day “Fully Detailed Claim” to Engineer “Final Claim” 28 days after end of effects 42 days after receipt of claim Engineer’s Response Clause 3.5 Engineer to“Agree or Determine” Clause 20.1 Contractor’s Claims Clause 3.5 Determinations Agreement/Determination given effect unless revised under Clause 20
  • 27. FIDIC 1999 and its Dispute Resolution Provisions(cont.) Reference to Dispute Adjudication Board (DAB) (1 or 3 people) DAB Decision within 84 days of reference “Amicable Settlement” stage ICC Arbitration within 56 days after Notice of Dissatisfaction Clause 20.2 Clause 20.4 Clause 20.5 Clause 20.6 No Notice of Dissatisfaction within 28 days of Decision Notice of Dissatisfaction within 28 days after 84 days of reference No DAB Decision within 84 days of reference Notice of Dissatisfaction within 28 days of Decision DAB Decision final and binding
  • 28. FIDIC 1999 and its Dispute Resolution Provisions(cont.) Employer or Engineer gives notice and particulars to Contractor Clause 3.5 Engineer to “Agree or Determine” Clause 2.5 Employer’s Claims Clause 3.5 Determinations Reference to Dispute Adjudication Board (DAB) (1 or 3 people) “Amicable Settlement” stage ICC Arbitration within 56 days after Notice of Dissatisfaction Clause 20.5 Clause 20.6 Clauses 20.2 and 20.4 (See previous diagram for full Clause 20.4 procedure) Agreement/Determination given effect unless revised under Clause 20
  • 29. FIDIC 2017 and its Dispute Resolution Provisions Event for Claim 28 day Notice of Claim to Engineer (No) the claiming Party shall not be entitled to any claim Engineer shall give a Notice to the claiming Party, within 14 days after receiving the Notice of Claim (No) valid Notice (yes) the other Party disagrees &review by the Engineer Fully Detailed claim 84 days after the event giving rise to the Claim the Engineer shall, within 14 days after this time limit has expired, give a Notice to the claiming Party accordingly.
  • 30. FIDIC 2017 and its Dispute Resolution Provisions
  • 31. FIDIC 2017 and its Dispute Resolution Provisions
  • 32. Typical Sequence of Dispute Events Envisaged in clause 21