SlideShare a Scribd company logo
FIDIC FORM
OF
CONTRACT
- CONTRACT LAWS & REGULATION
M. Tech (Construction Engineering Management), 2nd Semester.
KIIT UNIVERSITY.
WHAT IS FIDIC?
• FIDIC - Fédération Internationale Des Ingénieurs-Conseils.
• Founded – 1913
• Located – Geneva, Switzerland
• Best Known for: - Dredgers Contract; Short Form of Contract;
Construction Contract; Plant & DB Contract; DBO Contract;
and EPC/Turnkey Contract.
French Term
TIMELINE
SEPTEMBER
1999
Till Date
Founded
22 July 1913
• Red Book – Civil Engineering Construction
• Yellow Book – Electrical & Mech Works
• Orange Book – Design-Build & Turnkey Contracts
• Red Book – Construction for Building &
Engineering Works designed by Employer.
• Yellow Book – Plant & DB Works for
Electrical & Mech Works by Contractor
• Silver Book – EPC/ Turnkey Projects
• Green Book – Short Form of Contract
2017
• Priority of Contract Documents (Sub-Clause 5.2).
• Role of Engineer (Sub-Clause 1.1 (a-iv), 2.1, 2.4, 2.6 & 67.1).
• Instruction in Writing (Sub-Clause 2.5).
• Programme to be Submitted (Sub-Clause 14.1).
• Cash Flow Estimate to be Submitted (Sub-Clause 14.3).
• Performance Security (Sub-Clause 10.1).
• Insurance (Sub-Clause 25.1)
FIDIC RED BOOK CLAUSES
Various Important Sub-Clauses
• Delay of Drawing and Instruction by the Engineer. (Sub-Clause 6.3/6.4).
• Occurrence of Unforeseeable Physical Obstructions or Conditions. (Sub-Clause 12.2)
• Discovery of Fossils, Coin, Articles of value, etc. (Sub-Clause 27.1)
• Execution of additional test required by Engineer. (Sub-Clause 36.5)
• Suspension of the Work instructed by the Engineer. (Sub-Clause 40.1/ 40.2/ 40.3)
• Employer’s failure to give Possession of the Site and Access Thereto (Sub-Clause 42.1/42.2)
• Contractor’s Entitlement to Suspend Work (Sub-Clause 69.4)
• Extension of Time for Completion (Sub-Clause 44.1/ 44.2/ 44.3)
EVENTS ENTITLING CONTRACTOR FOR EXTENSION OF TIME AND COST.
• Incorrect Setting Out Data given by Engineer. (Sub-Clause 17.1).
• Loss or Damage due to Employer's Risk Event. (Sub-Clause 20.3)
• Facilities for other Contractor. (Sub-Clause 31.2)
• Uncovering of the Work. (Sub-Clause 38.2)
• Remedying Defect not Attributable to the Contractor. (Sub-Clause 49.3)
• Contractor to Search. (Sub-Clause 50.1)
EVENTS ENTITLING CONTRACTOR FOR COST ALONE.
• Variations. (Sub-Clause 51.1, 51.2 & 52.1)
• Variation exceeding 15% of Contract Price. (Sub-Clause 52.3)
• Provisional Sums. (Sub-Clause 58).
• Delayed Payment. (Sub-Clause 60.1)
• Special Risks. (Sub-Clause 65.1 to 65.6)
• Increase or Decrease of Cost. (Sub-Clause 70.1)
• Subsequent Legislation. (Sub-Clause 70.2)
• Notice of Claim. (Sub-Clause 53.1 to 53.3)
DISPUTES
• A disagreement arising out of a contract.
• Implies an assertion of right by one party and repudiation by the other.
• In First Instance, if claim by the contractors demanded, then it is submitted to the
Project Engineer/Project Management Consultant.
• If disagreed, this becomes a dispute.
• Clause 67 – Dispute Settlement Clause in FIDIC. – 3 Stage Process.
Engineer’s Decision Amicable Settlement. Arbitration.
DISPUTE REVIEW BOARD (DRB) Clause – 67.1
• Traditional method of resolution of dispute.
• Constant monitoring by visiting site during the construction and is advised of the
contract.
• Consists of 3 members.
• The members are appointed by each party.
• The third member who becomes the chairman, is selected by two members and approved by the
parties.
• The members are expected to have: -
• Experience with the Type of Construction.
• Familiarity with Interpreting Contract Documents.
• Adequate Background in the Construction Industry.
• The must not have any Affiliation with the Parties.
• After recording submissions, they suggest for settlement, if not, they put in further
efforts or pursue litigations or arbitrations.
ADR MECHANISM A D R
ALTERNATIVE
DISPUTE
RESOLUTION
Four Basic Methods of Dealing Disputes:-
• Negotiation
• Mediation
• Conciliation
• Arbitration.
CLAIM
CLAIM is a demand or assertion by one of the parties seeking, as a matter of right, adjustment
or interpretation of contract terms, payment of money, extension of time or other reliefs w.r.t.
terms of contract.
Construction Claims:-
• Conflicting Conditions of Contract.
• Delay in Supply of Drawings by the Client.
• Incorrect Drawing Supplied by the Client.
• Drawing/ Specifications Discrepancies.
• Insufficient Specifications.
• Late Information/ Approval by Client.
• Discovery of Fossil, Coins, Articles or Value.
• Execution of Additional Test Required by the Client.
• Suspension/Termination of Work by Client.
• Delay in Commencement of the Project.
• Damage Due to Force Majeure.
• Loss or Damage to Works due to the Use or Occupation by the Employer.
• Bad Weather.
• Variation in Total Contract Price.
• Delay in Supply of Materials, When the same is in Client’s Scope.
• Delay in Payment by the Client.
CLASSIFICATION OF CLAIM
• CONTRACTUAL CLAIMS.
• EXTRA CONTRACTUAL CLAIMS.
• QUANTUM MERUIT CLAIMS
• EX-GRATIA CLAIMS.
• COUNTER CLAIMS.
THANK YOU

More Related Content

What's hot

FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
PachyCarmona1
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
ssuserb337ce1
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
irkportal
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Moustafa Ismail Abu Dief
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
Melvin Lim
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
Kheng Hoe Advocates
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
Michael Audu
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
Moustafa Ismail Abu Dief
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
Moustafa Ismail Abu Dief
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
M Maged Hegazy, LLM, MBA, CCP, P3O
 

What's hot (20)

FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 

Similar to Fidic Form of Contract.

ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
drmujahidkhan85
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
DonaAlisyahSiregar
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
IrfanAwan25
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
Delhi Technological University
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
Delhi Technological University
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Rae Davies
 
Construction Contract PPT.ppt
Construction Contract PPT.pptConstruction Contract PPT.ppt
Construction Contract PPT.ppt
MohammedAbdu46
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
ssuser32da691
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
NesrElhandasa1
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
Rae Davies
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
Aditya Mane
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
Gerald R. (Jerry) Genge
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
Delhi Technological University
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
ByishimoBTCChef
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
Delhi Technological University
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
Delhi Technological University
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
Vance Ang
 

Similar to Fidic Form of Contract. (20)

ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Construction Contract PPT.ppt
Construction Contract PPT.pptConstruction Contract PPT.ppt
Construction Contract PPT.ppt
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 

Fidic Form of Contract.

  • 1. FIDIC FORM OF CONTRACT - CONTRACT LAWS & REGULATION M. Tech (Construction Engineering Management), 2nd Semester. KIIT UNIVERSITY.
  • 2. WHAT IS FIDIC? • FIDIC - Fédération Internationale Des Ingénieurs-Conseils. • Founded – 1913 • Located – Geneva, Switzerland • Best Known for: - Dredgers Contract; Short Form of Contract; Construction Contract; Plant & DB Contract; DBO Contract; and EPC/Turnkey Contract. French Term
  • 3. TIMELINE SEPTEMBER 1999 Till Date Founded 22 July 1913 • Red Book – Civil Engineering Construction • Yellow Book – Electrical & Mech Works • Orange Book – Design-Build & Turnkey Contracts • Red Book – Construction for Building & Engineering Works designed by Employer. • Yellow Book – Plant & DB Works for Electrical & Mech Works by Contractor • Silver Book – EPC/ Turnkey Projects • Green Book – Short Form of Contract 2017
  • 4. • Priority of Contract Documents (Sub-Clause 5.2). • Role of Engineer (Sub-Clause 1.1 (a-iv), 2.1, 2.4, 2.6 & 67.1). • Instruction in Writing (Sub-Clause 2.5). • Programme to be Submitted (Sub-Clause 14.1). • Cash Flow Estimate to be Submitted (Sub-Clause 14.3). • Performance Security (Sub-Clause 10.1). • Insurance (Sub-Clause 25.1) FIDIC RED BOOK CLAUSES Various Important Sub-Clauses
  • 5. • Delay of Drawing and Instruction by the Engineer. (Sub-Clause 6.3/6.4). • Occurrence of Unforeseeable Physical Obstructions or Conditions. (Sub-Clause 12.2) • Discovery of Fossils, Coin, Articles of value, etc. (Sub-Clause 27.1) • Execution of additional test required by Engineer. (Sub-Clause 36.5) • Suspension of the Work instructed by the Engineer. (Sub-Clause 40.1/ 40.2/ 40.3) • Employer’s failure to give Possession of the Site and Access Thereto (Sub-Clause 42.1/42.2) • Contractor’s Entitlement to Suspend Work (Sub-Clause 69.4) • Extension of Time for Completion (Sub-Clause 44.1/ 44.2/ 44.3) EVENTS ENTITLING CONTRACTOR FOR EXTENSION OF TIME AND COST.
  • 6. • Incorrect Setting Out Data given by Engineer. (Sub-Clause 17.1). • Loss or Damage due to Employer's Risk Event. (Sub-Clause 20.3) • Facilities for other Contractor. (Sub-Clause 31.2) • Uncovering of the Work. (Sub-Clause 38.2) • Remedying Defect not Attributable to the Contractor. (Sub-Clause 49.3) • Contractor to Search. (Sub-Clause 50.1) EVENTS ENTITLING CONTRACTOR FOR COST ALONE.
  • 7. • Variations. (Sub-Clause 51.1, 51.2 & 52.1) • Variation exceeding 15% of Contract Price. (Sub-Clause 52.3) • Provisional Sums. (Sub-Clause 58). • Delayed Payment. (Sub-Clause 60.1) • Special Risks. (Sub-Clause 65.1 to 65.6) • Increase or Decrease of Cost. (Sub-Clause 70.1) • Subsequent Legislation. (Sub-Clause 70.2) • Notice of Claim. (Sub-Clause 53.1 to 53.3)
  • 8. DISPUTES • A disagreement arising out of a contract. • Implies an assertion of right by one party and repudiation by the other. • In First Instance, if claim by the contractors demanded, then it is submitted to the Project Engineer/Project Management Consultant. • If disagreed, this becomes a dispute. • Clause 67 – Dispute Settlement Clause in FIDIC. – 3 Stage Process. Engineer’s Decision Amicable Settlement. Arbitration.
  • 9. DISPUTE REVIEW BOARD (DRB) Clause – 67.1 • Traditional method of resolution of dispute. • Constant monitoring by visiting site during the construction and is advised of the contract. • Consists of 3 members. • The members are appointed by each party. • The third member who becomes the chairman, is selected by two members and approved by the parties.
  • 10. • The members are expected to have: - • Experience with the Type of Construction. • Familiarity with Interpreting Contract Documents. • Adequate Background in the Construction Industry. • The must not have any Affiliation with the Parties. • After recording submissions, they suggest for settlement, if not, they put in further efforts or pursue litigations or arbitrations.
  • 11. ADR MECHANISM A D R ALTERNATIVE DISPUTE RESOLUTION Four Basic Methods of Dealing Disputes:- • Negotiation • Mediation • Conciliation • Arbitration.
  • 12. CLAIM CLAIM is a demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of contract terms, payment of money, extension of time or other reliefs w.r.t. terms of contract. Construction Claims:- • Conflicting Conditions of Contract. • Delay in Supply of Drawings by the Client. • Incorrect Drawing Supplied by the Client. • Drawing/ Specifications Discrepancies. • Insufficient Specifications. • Late Information/ Approval by Client. • Discovery of Fossil, Coins, Articles or Value. • Execution of Additional Test Required by the Client.
  • 13. • Suspension/Termination of Work by Client. • Delay in Commencement of the Project. • Damage Due to Force Majeure. • Loss or Damage to Works due to the Use or Occupation by the Employer. • Bad Weather. • Variation in Total Contract Price. • Delay in Supply of Materials, When the same is in Client’s Scope. • Delay in Payment by the Client.
  • 14. CLASSIFICATION OF CLAIM • CONTRACTUAL CLAIMS. • EXTRA CONTRACTUAL CLAIMS. • QUANTUM MERUIT CLAIMS • EX-GRATIA CLAIMS. • COUNTER CLAIMS.