SlideShare a Scribd company logo
1 of 19
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Episode 28 : Project
Management Contract
CONTRACTOR’S SCOPE OF SUPPLY AND SERVICES
• Contractor has to supply everything necessary to ensure proper operation of the
plant within the battery limits
• a supply schedule may be integrated in the contract
Contractor’s
scope of supply
• 1 m in front of the building
• i.e : the plant manufacturer has to supply everything included in this area
Battery limit
Supply
• building and steel construction
• (HVAC) of the building
• all plant components such as
vessels, apparatuses
• pipework and fittings
• insulations
• measuring and control equipment
• electrical equipment
• control devices
• construction of the access routes
• parks or external works
• labelling of components, pipework
• spare parts for a determined
operating period
Duty /Service
• preparation of the documentation
requiredfor approval
• planning
• representation of plant engineering
towards the relevant authorities
• complete design and construction
of the plant
• assembly
• commissioning
• prepare monthly project progress
report , update of the time
schedules
• preparation of the complete plant
documentation
• training of the employer ’ s
operating staff
Documentation
• Description of the continuous
function charts – basis for the
development of the control
engineering program.
• Description of disturbances ‐The “
operation manual” usually contains
a description of disturbances and
their removal.
• Determination of a specifi c
documentation system
EMPLOYER’SSCOPEOFSUPPLY&SERVICES
Typical services of the employer are:
1) Obtaining official approvals
2) Commissioning experts
3) Provision of the documents required for planning, such as site
plan, data on soil conditions etc.
4) Supply of utilities for commissioning
5) Free of charge provision of areas for site facilities
6) Free of charge supply of power and water to the building site.
Possible
interfaces
disposal
lines
supply lines
access
routes
electric
interfaces
control
engineering
interface
product
lines
Live steam, potable
water, process water,
compressed air,
starting materials etc.
Exhaust air, waste
water, rainwater etc.
In case of a decentralized
operated plant extension
that is going to be
connected to an already
existing central control
room
High, mean and low
voltage power supply
-LIQUIDATED DAMAGES
-A DAMAGE CLAIM OF THE EMPLOYER AGAINST THE
CONTRACTOR
-0.5% OF THE CONTRACT PRICE IS PENALTY IF MISSED
THE DEADLINE
EITHER PER WEEK/DAYS.
- PENALTY 5% OF THE CONTRACT PRICE IS MAXIMUM.
‐Claim in time ‐> project management will always be
concerned to establish proof of a disruption to the
employer.Therefore, contractor is not responsible for
the missed deadline and thus the claim for damages
expires.
‐Force Majeur ‐> neither of the parties responsible for
the delay or disruption causes by storm/earthquakes.
‐Deadlines have to be adjusted in a mutual agreement
DEADLINES / PENALTIES
Warranties/penalties
6
 The guaranties or warranties the
plant has to fulfill are stipulated
(Required as a condition of a
contract or agreement)
 Term “design warranties ” is
frequently used.
 At first, the guaranty itself is
described, then the duration of
the guaranty, called warranty
period is determined.
 Finally, for individual guaranties
penalties may be agreed.
 Some examples are given below:
 Power consumption :Whenever the guaranteed
power consumption is exceeded, the contracto
shall pay to the employer a lump sum of 3 4,000
per kWh/h of additional consumption.
 General liability period for all design warranties o
the plant is often determined.Typical warranty
periods are in the range of two years. Furtherm
separate periods can be assigned to individual
warranties.
 Example: In case of the corrosion warranty e.g.
liability period of up to five years is required.
DEFECTS/ACCEPTANCE
Patent Defects
 Revealed within framework of
inspection & testing
 ‘site‐inspections’ test on completion
are carried out of operator’s engineer
& project management of plant take
part
 plant tour results in a list of defects
that have to be worked off
Latent Defects
 Defects or damages not revealed
during assembly & commissioning
 Occur after acceptance during normal
operation of plant
Test on completion/acceptance ‐‐> one of the most important milestone in the
execution of the project. Indicates official end of project from plant manufacturer’s
point of view
Acceptance :
1) Beginning of warranty period
2) Trigger event for the last @ penultimate installment/payment
3) Determination of liquidated damages (if applicable)
Acceptance will be sealed by test certificated signed by both parties.
Contractor has to fulfill  1) complete & faultless performance of all goods &
services
2) successful completion of test run/guarantee run
Payment of plant usually occurs in installments.
“TERMSOF PAYMENT” –Conditions of payments agreed between
buyer & seller.These terms specify the period
allowed to a buyer to pay off the amount due.
“BONDS” –Written & signed promise to pay a certain sum of money
on a certain date, or on fulfillment of a specified condition.
All documented contracts & loan agreements are bonds.
Note: Apart from purchase price, “TERMSOF PAYMENT” are important
component of contract negotiations.
Prices / Terms of Payment / Bonds
• Ready money
• Eg: Petty cash, bank
account balance.
• Deferred payment basis
• Eg: Deferred payment
period of 30 days.
Cash OpenAccount SecuredAccount
• Full payment or
satisfaction is
guaranteed by pledge of
something worth equal
or greater.
 Claims management is required to manage the
unexpected and unavoidable costs to avoid profit
margin is melt away.
 Alterations
 Additions: additional supply or services which are not
contractually specified
 Omissions: Supply and services contained in the
contract which are not realized owing to certain
circumstances
 Alterations:Alterations of equipment or services.
 Two forms of claims
 Cost claims
 Claims in time
 For the successful enforcement of a claim, it is
recommended to take the following steps:
 Cause of the claim/disruption
 Justification based on the contract
 Evaluation of costs or delay
 Negotiation and substantiation of the claim
10
 At any time until the
completion of work.
 Employer will remunerate
the contractor for
 supply and services
rendered.
 unpreventable costs from
initiated production
measures.
 orders with subcontractors.
 Interrupt
 No extra cost be able to
claim for a two-weeks
interruption of project unless
the suspension exceeds the
period of two weeks.
 Cost incurred will be added
to contract price.
 Responsibility of
contractor’s management.
11
• It’s cover the risks during the phase of assembly.
• Apart from accident-caused damages on persons/ equipment
and the risk of fire.
• It is belongs to the scope of services of employer.
Erection all risks
insurances
• The risks of transport of materials and components to the
construction site.
• The transport risk depends significantly on the distances
and the means of transport used.
Transport
insurance
• Plant manufacturers can protect themselves against design
errors.
• Since the evaluation of risks related to design errors is
difficult and faulty design may result in considerable
damages, the costs for design insurance contracts are
correspondingly high.
• The payment of the installments will be effected in the
respective foreign. Therefore losses due to currency
fluctuations may occur.
• The plant manufacturer can protect himself or herself against
this by concluding a currency insurance contract.
Design
insurance
Currency
insurance
 Duration of the insurance
 Determination of a retention
 Place of insurance
 Amount insured
 Insurance benefit in the event of damage
 Determination of the insurance premium
* All the aspects insurance industry are ruled by legal regulations or by
General Conditions of Insurance.*
Which contracting party concludes the respective
insurance?
Information
and
Documentation
Objective is to protect their know how
against competitor
-Shall be treated
confidentially
-Can not be exposed
to other parties
without employer’s
permission
Excluded for
employees, nor
professional
consultant and for
legal proceeding
 Any provision of this order be held or declared invalid
by a competent court of jurisdiction.
 Invalidity shall not affect other the provisions of this
order.
 There may be contradictions between the legal and
binding regulations and clauses of a project contract.
 To prevent comprehensive contract from being
contested, in such cases the severability clause
stipulates that only the contradictory provision has to
be adapted.
 The short unconditional written confirmation of the order -
without repetition of the text - is deemed to be the
acceptance of this order.
 It often happens that the contractor does not provide an
unconditional confirmation of order.
 The reference “ without repetition of the text ” is also
worth mentioning.
 With this, the author of the contract protects himself
against “ small ” modifications the other party may
introduce in its own favour, hoping it may not be noticed.
There is, in fact, a great risk of overlooking small
modifications since the repeated reading of the same
document makes one “ blind ” .
 Example
 During the contract negotiations, the provision of the plant
labelling has turned out to be a question at issue.
 The labelling has not been included in the offer of the
plant manufacturer and thus not included in the price.
 The operator insisted on the provision of the labelling at a
purchase price
 The operator submits the contract to the plant
manufacturer on the assumption that he will give in
 The plant manufacturer accepts the order in writing,
however, he expresses reservation with regard to the plant
labelling
 This means that the plant manufacturer can claim extra
costs in terms of an addition for the provision of the
labelling.
 Extreme caution required when signing documents.
 Since the legal provisions connected with the
signatures are very country-specific, therefore, people
who have power of signature must be extra
understand about the legal provisions that is carried
on.
 However, most of the companies have their own
continuative and detailed signature policy.
Thanks for Watching
Please follow me / SAJJAD KHUDHUR ABBAS

More Related Content

What's hot

Handbook For Process Plant Project Engineers - Peter Watermeyer
Handbook For Process Plant Project Engineers - Peter WatermeyerHandbook For Process Plant Project Engineers - Peter Watermeyer
Handbook For Process Plant Project Engineers - Peter WatermeyerVeerender Putta
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Commissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsCommissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsDoina Dobre, P.Eng, GSC
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical CompletionsAndy Lang
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Good Contract Management;A municipality perspective
Good Contract Management;A municipality perspectiveGood Contract Management;A municipality perspective
Good Contract Management;A municipality perspectiveJB Nartey
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guidelineZuzi Evangelista
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guidelineMahmoud Ezz
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Processd_mackay
 

What's hot (17)

Handbook For Process Plant Project Engineers - Peter Watermeyer
Handbook For Process Plant Project Engineers - Peter WatermeyerHandbook For Process Plant Project Engineers - Peter Watermeyer
Handbook For Process Plant Project Engineers - Peter Watermeyer
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Commissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsCommissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating Considerations
 
COE
COECOE
COE
 
Resume_AG
Resume_AGResume_AG
Resume_AG
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 
Mohamed elsayed updated
Mohamed elsayed updatedMohamed elsayed updated
Mohamed elsayed updated
 
Good Contract Management;A municipality perspective
Good Contract Management;A municipality perspectiveGood Contract Management;A municipality perspective
Good Contract Management;A municipality perspective
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guideline
 
ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guideline
 
Contractor safety management system (csms)
Contractor safety management system (csms)Contractor safety management system (csms)
Contractor safety management system (csms)
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 

Viewers also liked

Management Service Contracts
Management Service ContractsManagement Service Contracts
Management Service ContractsJuanfeMoraB
 
Management service contracts
Management service contractsManagement service contracts
Management service contractsnicomartinez24
 
Management service contracts allan y viana
Management service contracts allan y vianaManagement service contracts allan y viana
Management service contracts allan y vianaYina Jas
 
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Antonio Coladarce
 
Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Frank.
 
How Economic Value Management can be Applied to Power Plant Management
How Economic Value Management can be Applied to Power Plant ManagementHow Economic Value Management can be Applied to Power Plant Management
How Economic Value Management can be Applied to Power Plant ManagementPar Sut
 
Management service contracts
Management service contractsManagement service contracts
Management service contractslova56
 
Smp_contract_management_storyboard_v1
Smp_contract_management_storyboard_v1Smp_contract_management_storyboard_v1
Smp_contract_management_storyboard_v1Joy Gomez
 
management service contract
management service contractmanagement service contract
management service contract3015485667
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...HIMADRI BANERJI
 
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Bodman PLC
 
Licensing entry mode
Licensing entry modeLicensing entry mode
Licensing entry modeYina Jas
 
Wilco Construction Project Presentation
Wilco Construction Project PresentationWilco Construction Project Presentation
Wilco Construction Project PresentationThanh Nguyen
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
International market entry strategies By mrittika wahid
International market entry strategies By mrittika wahidInternational market entry strategies By mrittika wahid
International market entry strategies By mrittika wahidTuan Bishwamitra Chowdhury
 
Service Contracts Lifecycle Management
Service Contracts Lifecycle ManagementService Contracts Lifecycle Management
Service Contracts Lifecycle ManagementMohan Dutt
 

Viewers also liked (20)

Management Service Contracts
Management Service ContractsManagement Service Contracts
Management Service Contracts
 
Négociation contractuelle
Négociation  contractuelle Négociation  contractuelle
Négociation contractuelle
 
Management service contracts
Management service contractsManagement service contracts
Management service contracts
 
Management service contracts allan y viana
Management service contracts allan y vianaManagement service contracts allan y viana
Management service contracts allan y viana
 
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
 
EU-Contract Project
EU-Contract ProjectEU-Contract Project
EU-Contract Project
 
Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016
 
Opain s.a
Opain s.aOpain s.a
Opain s.a
 
How Economic Value Management can be Applied to Power Plant Management
How Economic Value Management can be Applied to Power Plant ManagementHow Economic Value Management can be Applied to Power Plant Management
How Economic Value Management can be Applied to Power Plant Management
 
Management service contracts
Management service contractsManagement service contracts
Management service contracts
 
Smp_contract_management_storyboard_v1
Smp_contract_management_storyboard_v1Smp_contract_management_storyboard_v1
Smp_contract_management_storyboard_v1
 
management service contract
management service contractmanagement service contract
management service contract
 
claims management framework
 claims management framework claims management framework
claims management framework
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
 
Licensing entry mode
Licensing entry modeLicensing entry mode
Licensing entry mode
 
Wilco Construction Project Presentation
Wilco Construction Project PresentationWilco Construction Project Presentation
Wilco Construction Project Presentation
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
International market entry strategies By mrittika wahid
International market entry strategies By mrittika wahidInternational market entry strategies By mrittika wahid
International market entry strategies By mrittika wahid
 
Service Contracts Lifecycle Management
Service Contracts Lifecycle ManagementService Contracts Lifecycle Management
Service Contracts Lifecycle Management
 

Similar to Episode 28 : Project Management Contract

Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Construction plan
Construction planConstruction plan
Construction planMianusama14
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Indonesia
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
2.12 procurement management 1
2.12  procurement management 12.12  procurement management 1
2.12 procurement management 1reddvise
 
Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013Weero Koster
 
Construction practices
Construction practicesConstruction practices
Construction practicesArun Kurali
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptxVasuV18
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreementChirag Jain
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 

Similar to Episode 28 : Project Management Contract (20)

Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Surat warranty
Surat warrantySurat warranty
Surat warranty
 
Construction plan
Construction planConstruction plan
Construction plan
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
2.12 procurement management 1
2.12  procurement management 12.12  procurement management 1
2.12 procurement management 1
 
Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptx
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 

More from SAJJAD KHUDHUR ABBAS

PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECTPROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECT
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECTSAJJAD KHUDHUR ABBAS
 
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...SAJJAD KHUDHUR ABBAS
 
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...SAJJAD KHUDHUR ABBAS
 
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...SAJJAD KHUDHUR ABBAS
 
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...SAJJAD KHUDHUR ABBAS
 
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...SAJJAD KHUDHUR ABBAS
 
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...SAJJAD KHUDHUR ABBAS
 
Production of 100 mt distilled monoglyceride (dmg)
Production of 100 mt distilled monoglyceride (dmg)Production of 100 mt distilled monoglyceride (dmg)
Production of 100 mt distilled monoglyceride (dmg)SAJJAD KHUDHUR ABBAS
 
Episode 66 : Renewable Energy Technologies
Episode 66 :  Renewable Energy TechnologiesEpisode 66 :  Renewable Energy Technologies
Episode 66 : Renewable Energy TechnologiesSAJJAD KHUDHUR ABBAS
 
Episode 65 : Membrane separation processes
Episode 65 :  Membrane separation processesEpisode 65 :  Membrane separation processes
Episode 65 : Membrane separation processesSAJJAD KHUDHUR ABBAS
 
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...SAJJAD KHUDHUR ABBAS
 
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 62 :  MATERIAL BALANCE FOR REACTING SYSTEM Episode 62 :  MATERIAL BALANCE FOR REACTING SYSTEM
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM SAJJAD KHUDHUR ABBAS
 
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM SAJJAD KHUDHUR ABBAS
 
Episode 60 : Pinch Diagram and Heat Integration
Episode 60 :  Pinch Diagram and Heat IntegrationEpisode 60 :  Pinch Diagram and Heat Integration
Episode 60 : Pinch Diagram and Heat IntegrationSAJJAD KHUDHUR ABBAS
 
Episode 59 : Introduction of Process Integration
Episode 59 :  Introduction of Process IntegrationEpisode 59 :  Introduction of Process Integration
Episode 59 : Introduction of Process IntegrationSAJJAD KHUDHUR ABBAS
 
Episode 58 : Tools Integration Examples
Episode 58 :  Tools Integration ExamplesEpisode 58 :  Tools Integration Examples
Episode 58 : Tools Integration ExamplesSAJJAD KHUDHUR ABBAS
 
Episode 57 : Simulation for Design and Analysis
Episode 57 : Simulation for Design and AnalysisEpisode 57 : Simulation for Design and Analysis
Episode 57 : Simulation for Design and AnalysisSAJJAD KHUDHUR ABBAS
 
Episode 56 : Simulation for design and analysis
Episode 56 :  Simulation for design and analysis Episode 56 :  Simulation for design and analysis
Episode 56 : Simulation for design and analysis SAJJAD KHUDHUR ABBAS
 
Episode 55 : Conceptual Process Synthesis-Design
Episode 55 :  Conceptual Process Synthesis-DesignEpisode 55 :  Conceptual Process Synthesis-Design
Episode 55 : Conceptual Process Synthesis-DesignSAJJAD KHUDHUR ABBAS
 

More from SAJJAD KHUDHUR ABBAS (20)

PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECTPROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECT
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
 
Electric cars
Electric carsElectric cars
Electric cars
 
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
 
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
 
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
 
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
 
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
 
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
 
Production of 100 mt distilled monoglyceride (dmg)
Production of 100 mt distilled monoglyceride (dmg)Production of 100 mt distilled monoglyceride (dmg)
Production of 100 mt distilled monoglyceride (dmg)
 
Episode 66 : Renewable Energy Technologies
Episode 66 :  Renewable Energy TechnologiesEpisode 66 :  Renewable Energy Technologies
Episode 66 : Renewable Energy Technologies
 
Episode 65 : Membrane separation processes
Episode 65 :  Membrane separation processesEpisode 65 :  Membrane separation processes
Episode 65 : Membrane separation processes
 
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
 
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 62 :  MATERIAL BALANCE FOR REACTING SYSTEM Episode 62 :  MATERIAL BALANCE FOR REACTING SYSTEM
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM
 
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
 
Episode 60 : Pinch Diagram and Heat Integration
Episode 60 :  Pinch Diagram and Heat IntegrationEpisode 60 :  Pinch Diagram and Heat Integration
Episode 60 : Pinch Diagram and Heat Integration
 
Episode 59 : Introduction of Process Integration
Episode 59 :  Introduction of Process IntegrationEpisode 59 :  Introduction of Process Integration
Episode 59 : Introduction of Process Integration
 
Episode 58 : Tools Integration Examples
Episode 58 :  Tools Integration ExamplesEpisode 58 :  Tools Integration Examples
Episode 58 : Tools Integration Examples
 
Episode 57 : Simulation for Design and Analysis
Episode 57 : Simulation for Design and AnalysisEpisode 57 : Simulation for Design and Analysis
Episode 57 : Simulation for Design and Analysis
 
Episode 56 : Simulation for design and analysis
Episode 56 :  Simulation for design and analysis Episode 56 :  Simulation for design and analysis
Episode 56 : Simulation for design and analysis
 
Episode 55 : Conceptual Process Synthesis-Design
Episode 55 :  Conceptual Process Synthesis-DesignEpisode 55 :  Conceptual Process Synthesis-Design
Episode 55 : Conceptual Process Synthesis-Design
 

Recently uploaded

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Episode 28 : Project Management Contract

  • 1. SAJJAD KHUDHUR ABBAS Ceo , Founder & Head of SHacademy Chemical Engineering , Al-Muthanna University, Iraq Oil & Gas Safety and Health Professional – OSHACADEMY Trainer of Trainers (TOT) - Canadian Center of Human Development Episode 28 : Project Management Contract
  • 2. CONTRACTOR’S SCOPE OF SUPPLY AND SERVICES • Contractor has to supply everything necessary to ensure proper operation of the plant within the battery limits • a supply schedule may be integrated in the contract Contractor’s scope of supply • 1 m in front of the building • i.e : the plant manufacturer has to supply everything included in this area Battery limit Supply • building and steel construction • (HVAC) of the building • all plant components such as vessels, apparatuses • pipework and fittings • insulations • measuring and control equipment • electrical equipment • control devices • construction of the access routes • parks or external works • labelling of components, pipework • spare parts for a determined operating period Duty /Service • preparation of the documentation requiredfor approval • planning • representation of plant engineering towards the relevant authorities • complete design and construction of the plant • assembly • commissioning • prepare monthly project progress report , update of the time schedules • preparation of the complete plant documentation • training of the employer ’ s operating staff Documentation • Description of the continuous function charts – basis for the development of the control engineering program. • Description of disturbances ‐The “ operation manual” usually contains a description of disturbances and their removal. • Determination of a specifi c documentation system
  • 3. EMPLOYER’SSCOPEOFSUPPLY&SERVICES Typical services of the employer are: 1) Obtaining official approvals 2) Commissioning experts 3) Provision of the documents required for planning, such as site plan, data on soil conditions etc. 4) Supply of utilities for commissioning 5) Free of charge provision of areas for site facilities 6) Free of charge supply of power and water to the building site.
  • 4. Possible interfaces disposal lines supply lines access routes electric interfaces control engineering interface product lines Live steam, potable water, process water, compressed air, starting materials etc. Exhaust air, waste water, rainwater etc. In case of a decentralized operated plant extension that is going to be connected to an already existing central control room High, mean and low voltage power supply
  • 5. -LIQUIDATED DAMAGES -A DAMAGE CLAIM OF THE EMPLOYER AGAINST THE CONTRACTOR -0.5% OF THE CONTRACT PRICE IS PENALTY IF MISSED THE DEADLINE EITHER PER WEEK/DAYS. - PENALTY 5% OF THE CONTRACT PRICE IS MAXIMUM. ‐Claim in time ‐> project management will always be concerned to establish proof of a disruption to the employer.Therefore, contractor is not responsible for the missed deadline and thus the claim for damages expires. ‐Force Majeur ‐> neither of the parties responsible for the delay or disruption causes by storm/earthquakes. ‐Deadlines have to be adjusted in a mutual agreement DEADLINES / PENALTIES
  • 6. Warranties/penalties 6  The guaranties or warranties the plant has to fulfill are stipulated (Required as a condition of a contract or agreement)  Term “design warranties ” is frequently used.  At first, the guaranty itself is described, then the duration of the guaranty, called warranty period is determined.  Finally, for individual guaranties penalties may be agreed.  Some examples are given below:  Power consumption :Whenever the guaranteed power consumption is exceeded, the contracto shall pay to the employer a lump sum of 3 4,000 per kWh/h of additional consumption.  General liability period for all design warranties o the plant is often determined.Typical warranty periods are in the range of two years. Furtherm separate periods can be assigned to individual warranties.  Example: In case of the corrosion warranty e.g. liability period of up to five years is required.
  • 7. DEFECTS/ACCEPTANCE Patent Defects  Revealed within framework of inspection & testing  ‘site‐inspections’ test on completion are carried out of operator’s engineer & project management of plant take part  plant tour results in a list of defects that have to be worked off Latent Defects  Defects or damages not revealed during assembly & commissioning  Occur after acceptance during normal operation of plant Test on completion/acceptance ‐‐> one of the most important milestone in the execution of the project. Indicates official end of project from plant manufacturer’s point of view Acceptance : 1) Beginning of warranty period 2) Trigger event for the last @ penultimate installment/payment 3) Determination of liquidated damages (if applicable) Acceptance will be sealed by test certificated signed by both parties. Contractor has to fulfill  1) complete & faultless performance of all goods & services 2) successful completion of test run/guarantee run
  • 8. Payment of plant usually occurs in installments. “TERMSOF PAYMENT” –Conditions of payments agreed between buyer & seller.These terms specify the period allowed to a buyer to pay off the amount due. “BONDS” –Written & signed promise to pay a certain sum of money on a certain date, or on fulfillment of a specified condition. All documented contracts & loan agreements are bonds. Note: Apart from purchase price, “TERMSOF PAYMENT” are important component of contract negotiations. Prices / Terms of Payment / Bonds • Ready money • Eg: Petty cash, bank account balance. • Deferred payment basis • Eg: Deferred payment period of 30 days. Cash OpenAccount SecuredAccount • Full payment or satisfaction is guaranteed by pledge of something worth equal or greater.
  • 9.  Claims management is required to manage the unexpected and unavoidable costs to avoid profit margin is melt away.  Alterations  Additions: additional supply or services which are not contractually specified  Omissions: Supply and services contained in the contract which are not realized owing to certain circumstances  Alterations:Alterations of equipment or services.
  • 10.  Two forms of claims  Cost claims  Claims in time  For the successful enforcement of a claim, it is recommended to take the following steps:  Cause of the claim/disruption  Justification based on the contract  Evaluation of costs or delay  Negotiation and substantiation of the claim 10
  • 11.  At any time until the completion of work.  Employer will remunerate the contractor for  supply and services rendered.  unpreventable costs from initiated production measures.  orders with subcontractors.  Interrupt  No extra cost be able to claim for a two-weeks interruption of project unless the suspension exceeds the period of two weeks.  Cost incurred will be added to contract price.  Responsibility of contractor’s management. 11
  • 12. • It’s cover the risks during the phase of assembly. • Apart from accident-caused damages on persons/ equipment and the risk of fire. • It is belongs to the scope of services of employer. Erection all risks insurances • The risks of transport of materials and components to the construction site. • The transport risk depends significantly on the distances and the means of transport used. Transport insurance • Plant manufacturers can protect themselves against design errors. • Since the evaluation of risks related to design errors is difficult and faulty design may result in considerable damages, the costs for design insurance contracts are correspondingly high. • The payment of the installments will be effected in the respective foreign. Therefore losses due to currency fluctuations may occur. • The plant manufacturer can protect himself or herself against this by concluding a currency insurance contract. Design insurance Currency insurance
  • 13.  Duration of the insurance  Determination of a retention  Place of insurance  Amount insured  Insurance benefit in the event of damage  Determination of the insurance premium * All the aspects insurance industry are ruled by legal regulations or by General Conditions of Insurance.* Which contracting party concludes the respective insurance?
  • 14. Information and Documentation Objective is to protect their know how against competitor -Shall be treated confidentially -Can not be exposed to other parties without employer’s permission Excluded for employees, nor professional consultant and for legal proceeding
  • 15.  Any provision of this order be held or declared invalid by a competent court of jurisdiction.  Invalidity shall not affect other the provisions of this order.  There may be contradictions between the legal and binding regulations and clauses of a project contract.  To prevent comprehensive contract from being contested, in such cases the severability clause stipulates that only the contradictory provision has to be adapted.
  • 16.  The short unconditional written confirmation of the order - without repetition of the text - is deemed to be the acceptance of this order.  It often happens that the contractor does not provide an unconditional confirmation of order.  The reference “ without repetition of the text ” is also worth mentioning.  With this, the author of the contract protects himself against “ small ” modifications the other party may introduce in its own favour, hoping it may not be noticed. There is, in fact, a great risk of overlooking small modifications since the repeated reading of the same document makes one “ blind ” .
  • 17.  Example  During the contract negotiations, the provision of the plant labelling has turned out to be a question at issue.  The labelling has not been included in the offer of the plant manufacturer and thus not included in the price.  The operator insisted on the provision of the labelling at a purchase price  The operator submits the contract to the plant manufacturer on the assumption that he will give in  The plant manufacturer accepts the order in writing, however, he expresses reservation with regard to the plant labelling  This means that the plant manufacturer can claim extra costs in terms of an addition for the provision of the labelling.
  • 18.  Extreme caution required when signing documents.  Since the legal provisions connected with the signatures are very country-specific, therefore, people who have power of signature must be extra understand about the legal provisions that is carried on.  However, most of the companies have their own continuative and detailed signature policy.
  • 19. Thanks for Watching Please follow me / SAJJAD KHUDHUR ABBAS