The document discusses delays, suspension, and damages related to construction contracts according to FIDIC, CPWD, and NHAI standards.
[1] FIDIC provisions allow for extension of time and damages for contractor delays caused by authorities, as well as damages for failure to meet completion deadlines and consequences of employer suspension. [2] CPWD provides for compensation for contractor delay at 1% of the contract value per month of delay, up to 10%, as well as extensions for employer suspensions. [3] NHAI specifies damages for failure to provide land of 0.05% of the contract price per day per meter and allows time extensions for related delays.