SlideShare a Scribd company logo
SUBMITTED BY:
ANIL YADAV
ASHOK PERSHAD
DHIRAJ GAUR
MANOJ
MUKUL VERMA
FIDIC
Fédération Internationale Des Ingénieurs-Conseils - FIDIC
FIDIC is the French acronym for the International Federation of
Consulting Engineers.
FIDIC was founded in 1913 to promote the professional interests
of the member associations and to disseminate information of
interest to members of its component national associations
Today FIDIC membership numbers more than 60 countries and
represents most of the private practice consulting engineers in
the world. Only associations of consulting engineers are eligible
for FIDIC membership.
During the past half century, the International Federation of
Consulting Engineers (FIDIC) has devoted itself to the
compilation of management documents for all kinds of projects,
among which the FIDIC Conditions of Contract are of the highest
influence and are the most popular application.
New Edition FIDIC
The new models include :
FIDIC Conditions of Contract for Construction, the (New
Red Book)
FIDIC Conditions of Contract for Plant and Design/Build,
the (New Yellow Book)
FIDIC Conditions of Contract for EPC Turnkey Projects,
the (Silver Book)
FIDIC Short Form of Contract, the (Green Book)
FIDIC Conditions of Contract (new edition) raised a higher
requirement to the Parties concerned in the area of contract
management 12
APPLICATION
Applicability under Various Project Delivery and Contracting System:
 1. The “New Red Book” can be used in any kind of Engineering
Construction Contract.
 2. The “New Yellow Book” applies to the lump sum contract project
where the Contractor takes participation in the design work.
 3. The “Silver Book” applies to the turnkey projects of infrastructures or
large-scale factories, where the Contractor takes on more work and risk
while the Employer’s participation is small (private financing or
government financing), but it is strictly defined upon the investment
and construction period.
 4. The “Green Book” can be used in all kinds of small-scale projects.
 5. Altogether, these four Contract Conditions can be applied to nearly
every kind of project, expect for that of managing contracting or simply
consulting or designing
FIDIC
The first edition of FIDIC Conditions of Contract for
Works of Civil Engineering Construction (use “Red
Book” in the following) was compiled in 1957,and
later its second, third, and fourth edition were issued
in 1963, 1977, and 1987 respectively.
FIDIC
With the investigation of the governments,
employers, contractors and consulting engineers all
over the world about their application of the “Red
Book”, 204 findings reports were returned.
According to the findings, the FIDIC Contract
Committee organized a group of experts to compile
the new Contract Condition models to be applied in
the 21stcentury.
High-quality Provisions and Logical Clause
Sequencing:
 Compared with the original “Red Book”, the “New
Red Book” has163 clauses, nearly 40% being
freshly compiled. An additional 40% were modified
and given supplements. Only 20% were kept intact.
The old edition adopted ICE’s disorderly style bit
in the clause sequence, while in the new edition,
the related sub-clauses are put into one clause
when possible, and convenient to the users.
Green Book -
Low value,
simple works
100%0%
Amount of design by Contractor
•RisktransfertoContractor
•Certaintyofoutturnprice
Red
Yellow
Silver
OLD NEW
Civil
‘Red Book’
4th Edition
1987,1992
Construction
(mainly)
Employer-
Design
1999
Typical Sequence of dispute Events Envisaged in
Clause 20
20.2 Parties
appoint
the DAB
20.4 A Party
refers a dispute
to the DAB
Parties present
submissions to the DAB
20.4 A Party may
issue a “notice of
dissatisfaction”
DAB gives its decision
< 28d < 84d < 28d < 56d
Amicable Settlement
The Parties in a FIDIC Contract
The Current (1999) Red Book – Basic Features
The Current (1999) Red Book – Basic Features
1. Suitable for all civil works projects where main responsibility for
design lies with Employer (or his Engineer).
2. Some design may, of course, be carried out by Contractor.
3. Administration of Contract and supervision by Engineer.
4. Approval of work, payment and claims certified by Engineer.
5. Work done is measured, payment according to Bill of Quantities.
6. Option for payment on lump sum basis.
7. Balanced / fair risk-sharing.
More specific provisions concerning the rights &
obligations of the contracting parties
Taking the clause of Employer’s default as an example,
there are 3 points added to the new red book: two of them
are concerned with payments. This shows the strict
requirement for the employer. However the contractor
should institute a quality assurance system and submit to
the engineer to audit any aspect of the system before
execution.
Monthly progress report shall be prepared by contractor to
submit to engineer every month, otherwise, payment won’t
be given.
Any kind of Bribe can result in contractors default.
All of the above are high requirements from the contractor.
To solve the problem of Back payment using
world wide reference
Since the problem of Employers financial vacancy or
contractor financing are originating world wide, the relative
clause and regulations are added into FIDIC condition of
contract
The employers shall submit within 28 days, after receiving
any request from contractor reasonable agreement that
financial agreement has been made.
If the employer intends to make any significant change to
his financial agreement, he shall give notice to contractor
with detailed particulars.
To Solve the Problem of Back Payment using
World Wide Experience for Reference:
It is reported that the back payment and debt
between the engineering units in China have added
up to 280 billion (RMB), which is mostly
Employer’s (government included) default to the
Contractor. The problem has greatly influenced the
construction corporations that their economic
strength were weakened. The market needs a legal
system to provide a guarantee for free and fair
competition.
 Since the problems of the Employer’s financial vacancy or
Contractor financing are originating worldwide, the relative clauses
and regulations are added into FIDIC Conditions of Contract:
 Employer’s financial arrangement. The Employer shall submit
within 28 days after receiving any request from the Contractor
reasonable evidence that financial arrangement has been made. If
the Employer intends to make any material change to his financial
arrangement, he shall give notice to the Contractor with detailed
particulars.
 If the Employer fails to execute in accordance with this clause, the
Contractor may, after giving a 21 days’ notice to the Employer,
suspend the work or reduce production output as a kind of warning;
if the Contractor does not receive any reasonable financial
arrangement certificate within 42 days after giving the warning, he
shall be entitled to terminate the Contract, for it is the Employer’s
default. Also the Contractor can get all the compensation earned on
the condition of Employer’s default.
 Contractor Financed Project’s execution. It is specially set up in the
Particular Conditions an Example Provisions for Contractor
Finance, which defines that if it is Contractor financing and he has
committed to the project, the Employer shall deliver a bank
payment guarantee to the Contractor within 28 days after both
parties have entered into the Contract Agreement. If the Contractor
does not receive the guarantee, the Engineer shall not issue the
notice to commence. It is defined in the guarantee that if the
Employer fails to make payment in full by the date 14 days after the
expiry of the period specified in the contract as that within which
such payment should have been made, the Contractor shall been
entitled to demand for payment from the bank with a certificate,
Contractor’s signatures which must be authenticated by his bankers
or by a notary public.

More Related Content

What's hot

FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
Gattupalli Naresh, PMP
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
PachyCarmona1
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
Jeff B
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
Yash Patel
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
CNC
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
Francis Ho
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
Moustafa Ismail Abu Dief
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Moustafa Ismail Abu Dief
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi
SN Panigrahi, PMP
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
Kheng Hoe Advocates
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 

What's hot (20)

FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 

Viewers also liked

Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
Weero Koster
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
helensuni
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
Rajesh Sharma
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
HIMADRI BANERJI
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
Pankaj K Sinha
 
Conciliation & Mediation
Conciliation & MediationConciliation & Mediation
Conciliation & MediationTuhin Sarkar
 
Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreementabdmuhaiminyunus
 
Ippc6 bpp
Ippc6 bppIppc6 bpp
Ippc6 bpp
Dr. Paul Davis
 
Hasselbalch costablecken examining the relationship between barriers and curr...
Hasselbalch costablecken examining the relationship between barriers and curr...Hasselbalch costablecken examining the relationship between barriers and curr...
Hasselbalch costablecken examining the relationship between barriers and curr...
Dr. Paul Davis
 
Ippc 6 presentation
Ippc 6 presentationIppc 6 presentation
Ippc 6 presentation
Dr. Paul Davis
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
M Maged Hegazy, LLM, MBA, CCP, P3O
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
Melvin Lim
 
Conciliation
ConciliationConciliation
ConciliationDolly03
 

Viewers also liked (16)

Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Conciliation & Mediation
Conciliation & MediationConciliation & Mediation
Conciliation & Mediation
 
Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Epc Vs Epcm
 
fidic-contracts
fidic-contractsfidic-contracts
fidic-contracts
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
Ippc6 bpp
Ippc6 bppIppc6 bpp
Ippc6 bpp
 
Hasselbalch costablecken examining the relationship between barriers and curr...
Hasselbalch costablecken examining the relationship between barriers and curr...Hasselbalch costablecken examining the relationship between barriers and curr...
Hasselbalch costablecken examining the relationship between barriers and curr...
 
Ippc 6 presentation
Ippc 6 presentationIppc 6 presentation
Ippc 6 presentation
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Conciliation
ConciliationConciliation
Conciliation
 

Similar to Fidic law1

dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
afadlalla
 
12953021.ppt
12953021.ppt12953021.ppt
12953021.ppt
Amith Soyza
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdf
sajidkhan82714
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
Aditya Mane
 
17 10 16
17 10 1617 10 16
17 10 16
Suhaib Jibran
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
Syafiq Zariful
 
FIDIC 2019
FIDIC 2019FIDIC 2019
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
ssuser4ae21a
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
ManaliChitranshi
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
ByishimoBTCChef
 
Fidic.pptx
Fidic.pptxFidic.pptx
Fidic.pptx
Zeeshan Yousaf
 
Chapter two.pptx
Chapter two.pptxChapter two.pptx
Chapter two.pptx
TeshomeMogez
 
Business Excellence and Enhancement of ROI by Dr Punit Sethi
Business Excellence and Enhancement of ROI by Dr Punit SethiBusiness Excellence and Enhancement of ROI by Dr Punit Sethi
Business Excellence and Enhancement of ROI by Dr Punit Sethi
Dr Punit Sethi, CEO- Real Estate, Infra, Smart Cities, AH
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
DonaAlisyahSiregar
 
2017 Tunnel Journal on Emerald Book and GBR
2017 Tunnel Journal on Emerald Book and GBR2017 Tunnel Journal on Emerald Book and GBR
2017 Tunnel Journal on Emerald Book and GBR
andrewng540722
 
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
Cerasela Angelescu
 
FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
Mohammed Fadlalla ,PMP ®
 
Fidic db-yellow-book
Fidic db-yellow-bookFidic db-yellow-book
Fidic db-yellow-book
Vedants Sharma
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
Arissa Loh
 

Similar to Fidic law1 (20)

dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
 
12953021.ppt
12953021.ppt12953021.ppt
12953021.ppt
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdf
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
 
17 10 16
17 10 1617 10 16
17 10 16
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
FIDIC 2019
FIDIC 2019FIDIC 2019
FIDIC 2019
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Fidic.pptx
Fidic.pptxFidic.pptx
Fidic.pptx
 
Chapter two.pptx
Chapter two.pptxChapter two.pptx
Chapter two.pptx
 
Business Excellence and Enhancement of ROI by Dr Punit Sethi
Business Excellence and Enhancement of ROI by Dr Punit SethiBusiness Excellence and Enhancement of ROI by Dr Punit Sethi
Business Excellence and Enhancement of ROI by Dr Punit Sethi
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
2017 Tunnel Journal on Emerald Book and GBR
2017 Tunnel Journal on Emerald Book and GBR2017 Tunnel Journal on Emerald Book and GBR
2017 Tunnel Journal on Emerald Book and GBR
 
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
 
Fidic db-yellow-book
Fidic db-yellow-bookFidic db-yellow-book
Fidic db-yellow-book
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 

More from dhiraj.gaur

Presentation cvp analysis 140908
Presentation cvp analysis 140908Presentation cvp analysis 140908
Presentation cvp analysis 140908dhiraj.gaur
 
O.b.airtel final
O.b.airtel finalO.b.airtel final
O.b.airtel finaldhiraj.gaur
 
Nirma case study_abhishek
Nirma case study_abhishekNirma case study_abhishek
Nirma case study_abhishekdhiraj.gaur
 
Investment management
Investment managementInvestment management
Investment managementdhiraj.gaur
 
Enterprise business systems1
Enterprise business systems1Enterprise business systems1
Enterprise business systems1dhiraj.gaur
 
final presentation
final presentationfinal presentation
final presentationdhiraj.gaur
 
integrative negotiation
integrative negotiationintegrative negotiation
integrative negotiationdhiraj.gaur
 
Hid security analysisproject_201209_final
Hid security analysisproject_201209_finalHid security analysisproject_201209_final
Hid security analysisproject_201209_finaldhiraj.gaur
 
Hid finalfinal project
Hid finalfinal projectHid finalfinal project
Hid finalfinal projectdhiraj.gaur
 
Hid fiscal policy
Hid fiscal policyHid fiscal policy
Hid fiscal policydhiraj.gaur
 
Hid penalties and prosecution
Hid penalties and prosecutionHid penalties and prosecution
Hid penalties and prosecutiondhiraj.gaur
 
Hid operations strategy
Hid operations strategyHid operations strategy
Hid operations strategydhiraj.gaur
 

More from dhiraj.gaur (20)

Presentation cvp analysis 140908
Presentation cvp analysis 140908Presentation cvp analysis 140908
Presentation cvp analysis 140908
 
China culture
China  cultureChina  culture
China culture
 
Rm tutorial
Rm tutorialRm tutorial
Rm tutorial
 
O.b.airtel final
O.b.airtel finalO.b.airtel final
O.b.airtel final
 
Nirma case study_abhishek
Nirma case study_abhishekNirma case study_abhishek
Nirma case study_abhishek
 
Upi case study
Upi   case studyUpi   case study
Upi case study
 
Tata
TataTata
Tata
 
Investment management
Investment managementInvestment management
Investment management
 
Enterprise business systems1
Enterprise business systems1Enterprise business systems1
Enterprise business systems1
 
final presentation
final presentationfinal presentation
final presentation
 
group 2
group 2group 2
group 2
 
integrative negotiation
integrative negotiationintegrative negotiation
integrative negotiation
 
som project
som projectsom project
som project
 
Hid fin project
Hid fin projectHid fin project
Hid fin project
 
Hid security analysisproject_201209_final
Hid security analysisproject_201209_finalHid security analysisproject_201209_final
Hid security analysisproject_201209_final
 
Hid finalfinal project
Hid finalfinal projectHid finalfinal project
Hid finalfinal project
 
Hid fiscal policy
Hid fiscal policyHid fiscal policy
Hid fiscal policy
 
Hid penalties and prosecution
Hid penalties and prosecutionHid penalties and prosecution
Hid penalties and prosecution
 
Hid operations strategy
Hid operations strategyHid operations strategy
Hid operations strategy
 
Hid mgcg
Hid mgcgHid mgcg
Hid mgcg
 

Recently uploaded

chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
Safe PaaS
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 

Recently uploaded (20)

chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 

Fidic law1

  • 1. SUBMITTED BY: ANIL YADAV ASHOK PERSHAD DHIRAJ GAUR MANOJ MUKUL VERMA FIDIC
  • 2. Fédération Internationale Des Ingénieurs-Conseils - FIDIC FIDIC is the French acronym for the International Federation of Consulting Engineers. FIDIC was founded in 1913 to promote the professional interests of the member associations and to disseminate information of interest to members of its component national associations Today FIDIC membership numbers more than 60 countries and represents most of the private practice consulting engineers in the world. Only associations of consulting engineers are eligible for FIDIC membership. During the past half century, the International Federation of Consulting Engineers (FIDIC) has devoted itself to the compilation of management documents for all kinds of projects, among which the FIDIC Conditions of Contract are of the highest influence and are the most popular application.
  • 3. New Edition FIDIC The new models include : FIDIC Conditions of Contract for Construction, the (New Red Book) FIDIC Conditions of Contract for Plant and Design/Build, the (New Yellow Book) FIDIC Conditions of Contract for EPC Turnkey Projects, the (Silver Book) FIDIC Short Form of Contract, the (Green Book) FIDIC Conditions of Contract (new edition) raised a higher requirement to the Parties concerned in the area of contract management 12
  • 4. APPLICATION Applicability under Various Project Delivery and Contracting System:  1. The “New Red Book” can be used in any kind of Engineering Construction Contract.  2. The “New Yellow Book” applies to the lump sum contract project where the Contractor takes participation in the design work.  3. The “Silver Book” applies to the turnkey projects of infrastructures or large-scale factories, where the Contractor takes on more work and risk while the Employer’s participation is small (private financing or government financing), but it is strictly defined upon the investment and construction period.  4. The “Green Book” can be used in all kinds of small-scale projects.  5. Altogether, these four Contract Conditions can be applied to nearly every kind of project, expect for that of managing contracting or simply consulting or designing
  • 5. FIDIC The first edition of FIDIC Conditions of Contract for Works of Civil Engineering Construction (use “Red Book” in the following) was compiled in 1957,and later its second, third, and fourth edition were issued in 1963, 1977, and 1987 respectively.
  • 6. FIDIC With the investigation of the governments, employers, contractors and consulting engineers all over the world about their application of the “Red Book”, 204 findings reports were returned. According to the findings, the FIDIC Contract Committee organized a group of experts to compile the new Contract Condition models to be applied in the 21stcentury.
  • 7. High-quality Provisions and Logical Clause Sequencing:  Compared with the original “Red Book”, the “New Red Book” has163 clauses, nearly 40% being freshly compiled. An additional 40% were modified and given supplements. Only 20% were kept intact. The old edition adopted ICE’s disorderly style bit in the clause sequence, while in the new edition, the related sub-clauses are put into one clause when possible, and convenient to the users.
  • 8. Green Book - Low value, simple works 100%0% Amount of design by Contractor •RisktransfertoContractor •Certaintyofoutturnprice Red Yellow Silver
  • 9. OLD NEW Civil ‘Red Book’ 4th Edition 1987,1992 Construction (mainly) Employer- Design 1999
  • 10. Typical Sequence of dispute Events Envisaged in Clause 20 20.2 Parties appoint the DAB 20.4 A Party refers a dispute to the DAB Parties present submissions to the DAB 20.4 A Party may issue a “notice of dissatisfaction” DAB gives its decision < 28d < 84d < 28d < 56d Amicable Settlement
  • 11. The Parties in a FIDIC Contract
  • 12. The Current (1999) Red Book – Basic Features The Current (1999) Red Book – Basic Features 1. Suitable for all civil works projects where main responsibility for design lies with Employer (or his Engineer). 2. Some design may, of course, be carried out by Contractor. 3. Administration of Contract and supervision by Engineer. 4. Approval of work, payment and claims certified by Engineer. 5. Work done is measured, payment according to Bill of Quantities. 6. Option for payment on lump sum basis. 7. Balanced / fair risk-sharing.
  • 13. More specific provisions concerning the rights & obligations of the contracting parties Taking the clause of Employer’s default as an example, there are 3 points added to the new red book: two of them are concerned with payments. This shows the strict requirement for the employer. However the contractor should institute a quality assurance system and submit to the engineer to audit any aspect of the system before execution. Monthly progress report shall be prepared by contractor to submit to engineer every month, otherwise, payment won’t be given. Any kind of Bribe can result in contractors default. All of the above are high requirements from the contractor.
  • 14. To solve the problem of Back payment using world wide reference Since the problem of Employers financial vacancy or contractor financing are originating world wide, the relative clause and regulations are added into FIDIC condition of contract The employers shall submit within 28 days, after receiving any request from contractor reasonable agreement that financial agreement has been made. If the employer intends to make any significant change to his financial agreement, he shall give notice to contractor with detailed particulars.
  • 15. To Solve the Problem of Back Payment using World Wide Experience for Reference: It is reported that the back payment and debt between the engineering units in China have added up to 280 billion (RMB), which is mostly Employer’s (government included) default to the Contractor. The problem has greatly influenced the construction corporations that their economic strength were weakened. The market needs a legal system to provide a guarantee for free and fair competition.
  • 16.  Since the problems of the Employer’s financial vacancy or Contractor financing are originating worldwide, the relative clauses and regulations are added into FIDIC Conditions of Contract:  Employer’s financial arrangement. The Employer shall submit within 28 days after receiving any request from the Contractor reasonable evidence that financial arrangement has been made. If the Employer intends to make any material change to his financial arrangement, he shall give notice to the Contractor with detailed particulars.  If the Employer fails to execute in accordance with this clause, the Contractor may, after giving a 21 days’ notice to the Employer, suspend the work or reduce production output as a kind of warning; if the Contractor does not receive any reasonable financial arrangement certificate within 42 days after giving the warning, he shall be entitled to terminate the Contract, for it is the Employer’s default. Also the Contractor can get all the compensation earned on the condition of Employer’s default.
  • 17.  Contractor Financed Project’s execution. It is specially set up in the Particular Conditions an Example Provisions for Contractor Finance, which defines that if it is Contractor financing and he has committed to the project, the Employer shall deliver a bank payment guarantee to the Contractor within 28 days after both parties have entered into the Contract Agreement. If the Contractor does not receive the guarantee, the Engineer shall not issue the notice to commence. It is defined in the guarantee that if the Employer fails to make payment in full by the date 14 days after the expiry of the period specified in the contract as that within which such payment should have been made, the Contractor shall been entitled to demand for payment from the bank with a certificate, Contractor’s signatures which must be authenticated by his bankers or by a notary public.