24 July 2017SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1
LECTURE FOUR
‫وبركاته‬ ‫هللا‬ ‫ورحمة‬ ‫عليكن‬ ‫السالم‬
2017
.
Training Course:
Saudi Council of Engineers
FIDIC Forms of Contracts
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2
Over View
2 THE EMPLOYER
2.1 Right of Access to the Site
2.2 Permits, Licences or Approvals
2.3 Employer's Personnel LEC. 3
2.4 Employer's Financial Arrangements
2.5 Employer's Claims
3 THE ENGINEER
3.1 Engineer's Duties and Authority
3.2 Delegation by the Engineer
3.3 Instructions of the Engineer
3.4 Replacement of the Engineer
3.5 Determinations LEC 3
4 THE CONTRACTOR
4.1 Contractor's General Obligations
4.2 Performance Security
4.3 Contractor's Representative
4.4 Subcontractors
4.5 Assignment of Benefit of Subcontract
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3
Over View
4.6 Co-operation
4.7 Setting Out
4.8 Safety Procedures
4.9 Quality Assurance
4.10 Site Data
4.11 Sufficiency of the Accepted Contract Amount
4.12 Unforeseeable Physical Conditions
4.13 Rights of Way and Facilities
4.14 Avoidance of Interference
4. 1 5 Access Route
4.16 Transport of Goods
4.17 Contractor's Equipment
4.18 Protection of the Environment
4.19 Electricity, Water and Gas
4.20 Employer's Equipment and Free-Issue Material
4.21 Progress Reports
4.22 Security of the Site
4.23 Contractor's Operations on Site
4.24 Fossils
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 4
Over View
5 NOMINATED SUBCONTRACTORS
5.1 Definition of "nominated Subcontractor"
5.2 Objection to Nomination
5.3 Payments to nominated Subcontractors
5.4 Evidence of Payments
6 STAFF AND LABOUR
6.1 Engagement of Staff and Labour
6.2 Rates of Wages and Conditions of Labour
6.3 Persons in the Service of Employer
6.4 Labour Laws
6.5 Working Hours
6.6 Facilities for Staff and Labour
6. 7 Health and Safety
6.8 Contractor's Superintendence
6.9 Contractor’s Personnel
6.10 Records of Contractor's Personnel and Equipment
6.11 Disorderly Conduct
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 5
Over View
7 PLANT, MATERIALS AND WORKMANSHIP
7.1 Manner of Execution
7.2 Samples
7.3 Inspection 7.4 Testing
7.5 Rejection 7.6 Remedial Work
7. 7 Ownership of Plant and Materials
7.8 Royalties
8 COMMENCEMENT, DELAYS,AND SUSPENSION
8.1 Commencement of Works
8.2 Time for Completion
8.3 Programme
8.4 Extension of Time for Completion
8.5 Delays Caused by Authorities
8.6 Rate of Progress 8.7 Delay Damages
8.8 Suspension of Work
8.9 Consequences of Suspension
8.10 Payment for Plant and Materials in Event of Suspension
8.11 Prolonged Suspension
8.12 Resumption of Work
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 6
Definitions
4.1 Contractor's General Obligations
Design/ limited.
 Execute/ complete/ remedy the Works as per Contract
 The Contractor shall provide the Plant and Contractor's
Documents specified in the Contract. and all Contractor's
Personnel. Goods. consumables and other things and services.
 Provide all whether of a temporary/permanent nature required .
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 7
Definitions
4.1 Contractor's General Obligations
 Responsible for adequacy, stability, safety of Site operations
and
 of all methods of construction.
Except specified in the Contract, the Contractor
(i) responsible for all Contractor's Documents.
Temporary Works. and such design in accordance with the
Contract. and
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 8
Definitions
4.1 Contractor's General Obligations
(ii) shall not otherwise be responsible for the design or
specification of the Permanent Works.
 The Contractor shall. whenever required by the Engineer.
submit details of MOS for work execution.
 If the Contract specifies that the Contractor shall design any
part, then :
 the Contractor shall submit to the Engineer the Contractor's
Document of this part in accordance with S.Cl.1.4 Law &Lang.
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 9
Definitions
4.2 Performance Security
 The Contractor is required to provide to the Employer PS
within 28 days after receiving the Letter of Acceptance LOA
in the form annexed to the Particular Conditions
 Amount as per Appendix to Tender.
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 10
Definitions
4.2 Performance Security
 The PS to remain valid until the Contractor has executed and
completed the Works which would give an expiry date
corresponding to the anticipated Completion Date (and not the
date of Taking Over described in Sub - Clauses 10.1 and 10.2).
 The Employer shall return the PS to the Contractor within 21
days after receiving a copy of the Performance Certificate. (
S.Cl. 11.9)
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 11
Definitions
4.3 Contractor's Representative
• appoint the Contractor ‟ s Representative/ PM- site M.
• give him all authority to act on the Contractor ‟ s behalf.
• The Contractor ‟ s Representative and his key staff shall be
fluent in the language ( S.Cl. 1.4)
4.4 Subcontractors
• The Contractor shall not subcontract the whole of the Works.
• shall be responsible for acts or defaults of any Subcontractor.
as if they were the acts or defaults of the Contractor. Unless
otherwise stated in the P. Conditions
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 12
Definitions
4.5 Assignment of Benefit of Subcontract
In case the obligations of the Subcontractor may extend beyond
the expiry date of the relevant Defects Notification Period.
(Elevators, HVAC-) to be extended.
4.6 Co-operation
The Contractor shall. as specified in the Contract or as instructed
by the Engineer. Allows:
(a) the Employer's Personnel
(b) any other contractors employed by the Employer.
(c) the personnel of any legally constituted public authorities.
who may be employed in the execution on/or near Site of any
work not included in Contract.
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV
13
Definitions
4.8 Safety Procedures
(a) comply with all applicable safety regulations.
(b) take care for the safety of persons entitled to be on the Site.
(c) reasonable efforts to keep the Site Works clear of obstruction.
4.7 Setting Out
• Commonly provided by the Eng. on behalf of the Employer.
• Contractor responsible for setting out the and shall notify the
Engineer of any errors observed.
• If the Contractor incurs additional cost or is delayed for
incorrect data, he is entitled to an EOT for any delay together
with payment of his additional costs plus reasonable profit.
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 14
Definitions
4.8 Safety Procedures- Continued
(d) Fencing, lighting. Guarding, watching of the Works.
(e) Any Temporary Works (including roadways. Footways), for
the use and protection of the public and of owners and occupiers
of adjacent land.
4.9 Quality Assurance
„The Contractor is required to institute a QA system to
demonstrate compliance with requirements of the Contract.‟
 may choose to confirm his intentions to comply with ISO
9001 as part of his tender submittal.
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 15
Definitions
4.10 Site Data
 By the Employer, prior to the Base Date and after also, all
relevant data in the Employer's possession on sub-surface and
hydrological conditions at the Site, environmental aspects.
4.11 Sufficiency of the Accepted Contract Amount‘
(a) have satisfied himself as to the correctness, sufficiency of the
accepted Contract Amount, and
(b) has based on the data. Interpret., necessary info., inspections.
Examine and satisfaction as to all relevant matters referred to in
S.Cl. 4.10 [Site Data].
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 16
Definitions - Unforeseeable Physical Conditions
‘Unforeseeable ‟ is (S.Cl 1.1.6.8) as meaning „ not reasonably
foreseeable by an experienced contractor by the date for
submission of the Tender ‟
4.12 Unforeseeable Physical Conditions
If the Contractor encounters adverse physical conditions which
he considers to have been „ Unforeseeable ‟ , he shall:
• Notice ( details) to the Engineer/ copy the Employer,
• Entitled to an EOT and payment of any cost arising as a
consequence of the unforeseeable physical conditions.
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC-
IV
17
Definitions - Unforeseeable Physical Conditions
4.12 Unforeseeable Physical Conditions
Continue executing the Works, using reasonable appropriate and
Engineer‟s instruction- may constitute a Variation, Clause 13
[Variations and Adjustments] shall apply.
• The Eng. May make deduction for favorable conditions.
After notice and inspecting and/or investigating- Engineer S.CL
3.5 [Determinations] to determine:
(i) whether and extent physical conditions were Unforeseeable.
and (ii) the matters of EOT and additional payment.
24 July 2017
Event analysis- Q
 In your project, describe the Role of the Contract parties if an
Unforeseen physical conditions were experienced on the site-
the project contract is based on the FIDIC Red Book, 1999-
Provide any necessary assumption:
• Case 1 you represent Contractor’s Project manager/ Contract manager.
……………………………………………………………………
……………………………………………………………………
…………………………………………………………………….
• Analyzed by Eng:
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1824 July 2017
Event analysis- Q
 In your project, describe the Role of the Contract parties if an
Unforeseen physical conditions were experienced on the site-
the project contract is based on the FIDIC Red Book, 1999-
Provide any necessary assumption:
• Case 2 you represent the Engineer:
……………………………………………………………………
……………………………………………………………………
…………………………………………………………………….
• Analyzed by Eng:
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1924 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 20
Definitions
4.13 Rights of Way and Facilities
• If the Contractor requires other/ additional rights of access, in
addition, the Contractor may wish to occupy areas out of Site
 The Contractor has the duty to obtain such rights
of way and use of the areas at his own risk and cost.
4.14 Avoidance of interference
Contractor shall not interfere improperly with: (a) the
convenience of the public. Or (b) the access to and use and all
roads and footpaths.
Indemnify, the Employer harmless against, from all damages
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 21
Definitions
4.15 Access Route
Contractor have been satisfied/ suitability and availability of
access routes to Site.
4.16 Transport of Goods
Unless stated in P. Conditions
Notice before 21 days of delivery date.
Contractor/ packing, loading, transporting. receiving. unloading,
storing and protection : and
Contractor indemnifies, hold the Employer harmless against ,
from all damages, losses and expenses. and pay all claims arising
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 22
Definitions
4.17 Contractor’s Equipment
• Equipment/ exclusively intended for the execution of Works
• Major equipment - permission from Engineer before removal.
4.18 Protection of Environment
 The Contractor shall take all reasonable steps to protect the
environment (both on and off the Site)
these requirements cost impact to be evaluated in the tender.
4.19 Electricity, Water and Gas
The Contractor is responsible of all power. water and other
services he may require.
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 23
Definitions
4.20 Employer’s Equipment and Free-Issue Material
• Employer's Equipment/ available for the use of the Contractor
as per the Contract.
4.21 Progress Reports
• monthly P reports prepared by the Contractor 6 copies
• The first report shall cover the period up to the end of 1st M.
• Reports shall be submitted monthly before 7th
• Reporting continue till the Contractor has completed all work.
• Contents include: …………..
4.22 Security of the Site
Contractor/ for keeping in the Site. authorized persons/ limited Contractor‟s….
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 24
Definitions
4.23 Contractor’s Operations on Site
• Contractor shall confine operations to Site, additional areas
agreed by the Engineer as working areas.
• Precautions to keep Contractor‟s Equipment and Personnel
within the Site, additional areas, off adjacent land.
4.24 Fossils
All fossils. coins. articles of value or antiquity. and structures and
other remains or items of geological or archaeological interest
found on the Site shall be placed under the care and authority of
the Employer. reasonable precautions for protection.
24 July 2017
Employer’s Responsibilities
• Cl.2
o Provides Access to the Site
• (not access & other areas – Cl.14.15 & 14.23)
o Assists Contractor with Permits
o Clause 16.1 Financial Arrangements ( Suspension-
Variations)
o Employer‟s claim notice
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2624 July 2017
Employer’s Responsibilities “continued”
• Assigning the Engineer Cl.3.1
• Cl.14.7 Payments
• Cl.20.2 appointment of DAB members
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2724 July 2017
Engineer’s Responsibilities
• Contract Management
• Maintain Employer's coordination and approvals
• Acts for Employer as Cl.3.5–“Fair determination”
• Cl.3.0 administration
o Ensure fair management to avoid violations
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2824 July 2017
Engineer’s Responsibilities
o Coordinate with the Employer for changes and
contract amendment
o Acts as an Employer representative
o Power of the Engineer is limited to relieve the
parties of duties or obligations etc.
To be continued in the next LEC.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2924 July 2017
Q&A
Conditions of Contract for ……………….Projects . which are
recommended where one entity takes total responsibility for the
design and execution of an engineering project. Under the usual
arrangements for this type of contract , the entity carries out all the
Engineering, Procurement and Construction: providing a fully
equipped facility , ready for operation (at the "turn of the key").
 This type of contract is usually negotiated between the parties,
choose the correct contract:
Answer:
A. The New Silver Book EPC Turnkey.
B. Red Book
C. Yellow Book
D. White Book Eng: ……..
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3024 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 31
……………. conditions of Contract for ………..
Which are recommended for building or engineering works
designed by the Employer or by his representative, the Engineer.
Under the usual arrangements for this type of contract, the
Contractor constructs the works in accordance with a design
provided by the Employer. However, the works may include
some elements of Contractor-designed civil, mechanical,
electrical and/or construction works.
Answer:
A. The New Silver Book EPC Turnkey.
B. Red Book construction
C. Yellow Book Plant des.- build
D. White Book construction Eng:…………..
Q&A
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 32
Q. The ………………….... Conditions of Contract for Plant and
………-Build. which are recommended for the provision of
electrical and/or mechanical plant , and for the design, and
execution of building or engineering works. Under the usual
arrangements for this type of contract, the Contractor designs
and provides, in accordance with the Employer‟s requirements,
plant and/or other works; which may include any combination of
civil, mechanical , electrical and/or construction works.
Answer:
A. The New Silver Book EPC Turnkey.
B. Red Book construction
C. Yellow Book Plant des.- build
D. Green Book construction Eng: …………
Q&A
24 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 33
The New green Book. These Conditions of Contract are recommended for engineering
and building work of relatively small capital value( 500,000$ -1,000,000$). However,
depending on the type of work and the circumstances, the Conditions may be suitable
for contracts of considerably greater value. They are considered most likely to be
suitable for fairly simple or repetitive work or work of short duration without the need
for specialist sub-contracts. This form may also be suitable for contracts which include ,
or wholly comprise contractor-designed civil engineering , building, mechanical and/or
electrical works.
Answer:
A. The New Silver Book EPC Turnkey.
B. Red Book construction
C. Yellow Book Plant des.- build
D. Green Book construction
Q&A
24 July 2017
Comparison between Red/Y/Silver
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3424 July 2017
Comparison between Red/Y/Silver
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3524 July 2017
Comparison between Red/Y/Silver
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3624 July 2017
Comparison between Red/Y/Silver
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3724 July 2017
Comparison between Red/Y/Silver
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3824 July 2017
Comparison between Red/Y/Silver
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3924 July 2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 40
End of
LECTURE Four
Thanks
‫وبركاته‬ ‫هللا‬ ‫ورحوة‬ ‫عليكن‬ ‫السالم‬
‫هللا‬ ‫أهاى‬ ‫فى‬
24 July 2017

More Related Content

What's hot

FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
Shantanu Kumar Behera
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
ssuserb337ce1
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
Essam Lotffy, PMP®, CCP®
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
Jeff B
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
Dr K M SONI
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Contract Administration Presentation
Contract Administration PresentationContract Administration Presentation
Contract Administration Presentation
Yanet Ormeno
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
Moustafa Ismail Abu Dief
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
Fidic
FidicFidic
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
CNC
 

What's hot (20)

FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Contract Administration Presentation
Contract Administration PresentationContract Administration Presentation
Contract Administration Presentation
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Fidic
FidicFidic
Fidic
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 

Similar to Training fidic moustafa ismail 2017 _ lec 4

Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8
Moustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Moustafa Ismail Abu Dief
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 
UON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfUON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdf
HabtamuGaroma3
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
Bahzad5
 
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
ssuser6d14e4
 
Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020
Moustafa Ismail Abu Dief
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
Egyptian Engineers Association
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..Rajesh Prasad
 
From NEC3 to NEC4 ECC
From NEC3 to NEC4 ECCFrom NEC3 to NEC4 ECC
From NEC3 to NEC4 ECC
Ir Albert YEU FCIArb MICE
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Moustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Moustafa Ismail Abu Dief
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
ssuser4ae21a
 
Annexure-2.pdf
Annexure-2.pdfAnnexure-2.pdf
Annexure-2.pdf
ParasaramSrinivas
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
Freelancelanders
 
Julian Scott - Contract Law and CDM 2007 Regulations
Julian Scott -  Contract Law and CDM 2007 RegulationsJulian Scott -  Contract Law and CDM 2007 Regulations
Julian Scott - Contract Law and CDM 2007 Regulations
Khalida Suleymanova
 

Similar to Training fidic moustafa ismail 2017 _ lec 4 (20)

Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7B
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
UON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfUON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdf
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
 
Cl report final
Cl report finalCl report final
Cl report final
 
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
 
Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..
 
From NEC3 to NEC4 ECC
From NEC3 to NEC4 ECCFrom NEC3 to NEC4 ECC
From NEC3 to NEC4 ECC
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Annexure-2.pdf
Annexure-2.pdfAnnexure-2.pdf
Annexure-2.pdf
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
 
Julian Scott - Contract Law and CDM 2007 Regulations
Julian Scott -  Contract Law and CDM 2007 RegulationsJulian Scott -  Contract Law and CDM 2007 Regulations
Julian Scott - Contract Law and CDM 2007 Regulations
 
Jc Cdm Presentation May 08
Jc Cdm Presentation May 08Jc Cdm Presentation May 08
Jc Cdm Presentation May 08
 

More from Moustafa Ismail Abu Dief

Fidic 2017 engineering
Fidic 2017 engineeringFidic 2017 engineering
Fidic 2017 engineering
Moustafa Ismail Abu Dief
 
Yellow book session bimarabia
Yellow book session bimarabiaYellow book session bimarabia
Yellow book session bimarabia
Moustafa Ismail Abu Dief
 
CMC certification
CMC certificationCMC certification
CMC certification
Moustafa Ismail Abu Dief
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Moustafa Ismail Abu Dief
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
Moustafa Ismail Abu Dief
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
Moustafa Ismail Abu Dief
 
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
Moustafa Ismail Abu Dief
 
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
Moustafa Ismail Abu Dief
 
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
Moustafa Ismail Abu Dief
 
Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14...
Ss 07 cost engineering management  training- nov 2017  moustafa part ii ch 14...Ss 07 cost engineering management  training- nov 2017  moustafa part ii ch 14...
Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14...
Moustafa Ismail Abu Dief
 
Ss 06 cost engineering management training- nov 2017 - moustafa part ii ch 1...
Ss 06 cost engineering management  training- nov 2017 - moustafa part ii ch 1...Ss 06 cost engineering management  training- nov 2017 - moustafa part ii ch 1...
Ss 06 cost engineering management training- nov 2017 - moustafa part ii ch 1...
Moustafa Ismail Abu Dief
 
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
Moustafa Ismail Abu Dief
 
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10
 Ss 05 Cost engineering management  training- nov 2017 - moustafa part ii ch 10 Ss 05 Cost engineering management  training- nov 2017 - moustafa part ii ch 10
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10
Moustafa Ismail Abu Dief
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Moustafa Ismail Abu Dief
 
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Moustafa Ismail Abu Dief
 
Ss 2 cost engineering management training- 2017 -dr moustafa ismail ch 5-6
Ss 2 cost engineering management  training- 2017 -dr  moustafa ismail  ch  5-6Ss 2 cost engineering management  training- 2017 -dr  moustafa ismail  ch  5-6
Ss 2 cost engineering management training- 2017 -dr moustafa ismail ch 5-6
Moustafa Ismail Abu Dief
 
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Cfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismailCfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismail
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Moustafa Ismail Abu Dief
 
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
Moustafa Ismail Abu Dief
 

More from Moustafa Ismail Abu Dief (18)

Fidic 2017 engineering
Fidic 2017 engineeringFidic 2017 engineering
Fidic 2017 engineering
 
Yellow book session bimarabia
Yellow book session bimarabiaYellow book session bimarabia
Yellow book session bimarabia
 
CMC certification
CMC certificationCMC certification
CMC certification
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
 
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
 
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
 
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
 
Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14...
Ss 07 cost engineering management  training- nov 2017  moustafa part ii ch 14...Ss 07 cost engineering management  training- nov 2017  moustafa part ii ch 14...
Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14...
 
Ss 06 cost engineering management training- nov 2017 - moustafa part ii ch 1...
Ss 06 cost engineering management  training- nov 2017 - moustafa part ii ch 1...Ss 06 cost engineering management  training- nov 2017 - moustafa part ii ch 1...
Ss 06 cost engineering management training- nov 2017 - moustafa part ii ch 1...
 
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
 
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10
 Ss 05 Cost engineering management  training- nov 2017 - moustafa part ii ch 10 Ss 05 Cost engineering management  training- nov 2017 - moustafa part ii ch 10
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
 
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
 
Ss 2 cost engineering management training- 2017 -dr moustafa ismail ch 5-6
Ss 2 cost engineering management  training- 2017 -dr  moustafa ismail  ch  5-6Ss 2 cost engineering management  training- 2017 -dr  moustafa ismail  ch  5-6
Ss 2 cost engineering management training- 2017 -dr moustafa ismail ch 5-6
 
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Cfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismailCfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismail
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
 
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
 

Recently uploaded

addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 

Recently uploaded (20)

addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 

Training fidic moustafa ismail 2017 _ lec 4

  • 1. 24 July 2017SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1 LECTURE FOUR ‫وبركاته‬ ‫هللا‬ ‫ورحمة‬ ‫عليكن‬ ‫السالم‬ 2017 . Training Course: Saudi Council of Engineers FIDIC Forms of Contracts
  • 2. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2 Over View 2 THE EMPLOYER 2.1 Right of Access to the Site 2.2 Permits, Licences or Approvals 2.3 Employer's Personnel LEC. 3 2.4 Employer's Financial Arrangements 2.5 Employer's Claims 3 THE ENGINEER 3.1 Engineer's Duties and Authority 3.2 Delegation by the Engineer 3.3 Instructions of the Engineer 3.4 Replacement of the Engineer 3.5 Determinations LEC 3 4 THE CONTRACTOR 4.1 Contractor's General Obligations 4.2 Performance Security 4.3 Contractor's Representative 4.4 Subcontractors 4.5 Assignment of Benefit of Subcontract 24 July 2017
  • 3. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3 Over View 4.6 Co-operation 4.7 Setting Out 4.8 Safety Procedures 4.9 Quality Assurance 4.10 Site Data 4.11 Sufficiency of the Accepted Contract Amount 4.12 Unforeseeable Physical Conditions 4.13 Rights of Way and Facilities 4.14 Avoidance of Interference 4. 1 5 Access Route 4.16 Transport of Goods 4.17 Contractor's Equipment 4.18 Protection of the Environment 4.19 Electricity, Water and Gas 4.20 Employer's Equipment and Free-Issue Material 4.21 Progress Reports 4.22 Security of the Site 4.23 Contractor's Operations on Site 4.24 Fossils 24 July 2017
  • 4. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 4 Over View 5 NOMINATED SUBCONTRACTORS 5.1 Definition of "nominated Subcontractor" 5.2 Objection to Nomination 5.3 Payments to nominated Subcontractors 5.4 Evidence of Payments 6 STAFF AND LABOUR 6.1 Engagement of Staff and Labour 6.2 Rates of Wages and Conditions of Labour 6.3 Persons in the Service of Employer 6.4 Labour Laws 6.5 Working Hours 6.6 Facilities for Staff and Labour 6. 7 Health and Safety 6.8 Contractor's Superintendence 6.9 Contractor’s Personnel 6.10 Records of Contractor's Personnel and Equipment 6.11 Disorderly Conduct 24 July 2017
  • 5. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 5 Over View 7 PLANT, MATERIALS AND WORKMANSHIP 7.1 Manner of Execution 7.2 Samples 7.3 Inspection 7.4 Testing 7.5 Rejection 7.6 Remedial Work 7. 7 Ownership of Plant and Materials 7.8 Royalties 8 COMMENCEMENT, DELAYS,AND SUSPENSION 8.1 Commencement of Works 8.2 Time for Completion 8.3 Programme 8.4 Extension of Time for Completion 8.5 Delays Caused by Authorities 8.6 Rate of Progress 8.7 Delay Damages 8.8 Suspension of Work 8.9 Consequences of Suspension 8.10 Payment for Plant and Materials in Event of Suspension 8.11 Prolonged Suspension 8.12 Resumption of Work 24 July 2017
  • 6. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 6 Definitions 4.1 Contractor's General Obligations Design/ limited.  Execute/ complete/ remedy the Works as per Contract  The Contractor shall provide the Plant and Contractor's Documents specified in the Contract. and all Contractor's Personnel. Goods. consumables and other things and services.  Provide all whether of a temporary/permanent nature required . 24 July 2017
  • 7. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 7 Definitions 4.1 Contractor's General Obligations  Responsible for adequacy, stability, safety of Site operations and  of all methods of construction. Except specified in the Contract, the Contractor (i) responsible for all Contractor's Documents. Temporary Works. and such design in accordance with the Contract. and 24 July 2017
  • 8. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 8 Definitions 4.1 Contractor's General Obligations (ii) shall not otherwise be responsible for the design or specification of the Permanent Works.  The Contractor shall. whenever required by the Engineer. submit details of MOS for work execution.  If the Contract specifies that the Contractor shall design any part, then :  the Contractor shall submit to the Engineer the Contractor's Document of this part in accordance with S.Cl.1.4 Law &Lang. 24 July 2017
  • 9. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 9 Definitions 4.2 Performance Security  The Contractor is required to provide to the Employer PS within 28 days after receiving the Letter of Acceptance LOA in the form annexed to the Particular Conditions  Amount as per Appendix to Tender. 24 July 2017
  • 10. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 10 Definitions 4.2 Performance Security  The PS to remain valid until the Contractor has executed and completed the Works which would give an expiry date corresponding to the anticipated Completion Date (and not the date of Taking Over described in Sub - Clauses 10.1 and 10.2).  The Employer shall return the PS to the Contractor within 21 days after receiving a copy of the Performance Certificate. ( S.Cl. 11.9) 24 July 2017
  • 11. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 11 Definitions 4.3 Contractor's Representative • appoint the Contractor ‟ s Representative/ PM- site M. • give him all authority to act on the Contractor ‟ s behalf. • The Contractor ‟ s Representative and his key staff shall be fluent in the language ( S.Cl. 1.4) 4.4 Subcontractors • The Contractor shall not subcontract the whole of the Works. • shall be responsible for acts or defaults of any Subcontractor. as if they were the acts or defaults of the Contractor. Unless otherwise stated in the P. Conditions 24 July 2017
  • 12. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 12 Definitions 4.5 Assignment of Benefit of Subcontract In case the obligations of the Subcontractor may extend beyond the expiry date of the relevant Defects Notification Period. (Elevators, HVAC-) to be extended. 4.6 Co-operation The Contractor shall. as specified in the Contract or as instructed by the Engineer. Allows: (a) the Employer's Personnel (b) any other contractors employed by the Employer. (c) the personnel of any legally constituted public authorities. who may be employed in the execution on/or near Site of any work not included in Contract. 24 July 2017
  • 13. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 13 Definitions 4.8 Safety Procedures (a) comply with all applicable safety regulations. (b) take care for the safety of persons entitled to be on the Site. (c) reasonable efforts to keep the Site Works clear of obstruction. 4.7 Setting Out • Commonly provided by the Eng. on behalf of the Employer. • Contractor responsible for setting out the and shall notify the Engineer of any errors observed. • If the Contractor incurs additional cost or is delayed for incorrect data, he is entitled to an EOT for any delay together with payment of his additional costs plus reasonable profit. 24 July 2017
  • 14. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 14 Definitions 4.8 Safety Procedures- Continued (d) Fencing, lighting. Guarding, watching of the Works. (e) Any Temporary Works (including roadways. Footways), for the use and protection of the public and of owners and occupiers of adjacent land. 4.9 Quality Assurance „The Contractor is required to institute a QA system to demonstrate compliance with requirements of the Contract.‟  may choose to confirm his intentions to comply with ISO 9001 as part of his tender submittal. 24 July 2017
  • 15. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 15 Definitions 4.10 Site Data  By the Employer, prior to the Base Date and after also, all relevant data in the Employer's possession on sub-surface and hydrological conditions at the Site, environmental aspects. 4.11 Sufficiency of the Accepted Contract Amount‘ (a) have satisfied himself as to the correctness, sufficiency of the accepted Contract Amount, and (b) has based on the data. Interpret., necessary info., inspections. Examine and satisfaction as to all relevant matters referred to in S.Cl. 4.10 [Site Data]. 24 July 2017
  • 16. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 16 Definitions - Unforeseeable Physical Conditions ‘Unforeseeable ‟ is (S.Cl 1.1.6.8) as meaning „ not reasonably foreseeable by an experienced contractor by the date for submission of the Tender ‟ 4.12 Unforeseeable Physical Conditions If the Contractor encounters adverse physical conditions which he considers to have been „ Unforeseeable ‟ , he shall: • Notice ( details) to the Engineer/ copy the Employer, • Entitled to an EOT and payment of any cost arising as a consequence of the unforeseeable physical conditions. 24 July 2017
  • 17. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 17 Definitions - Unforeseeable Physical Conditions 4.12 Unforeseeable Physical Conditions Continue executing the Works, using reasonable appropriate and Engineer‟s instruction- may constitute a Variation, Clause 13 [Variations and Adjustments] shall apply. • The Eng. May make deduction for favorable conditions. After notice and inspecting and/or investigating- Engineer S.CL 3.5 [Determinations] to determine: (i) whether and extent physical conditions were Unforeseeable. and (ii) the matters of EOT and additional payment. 24 July 2017
  • 18. Event analysis- Q  In your project, describe the Role of the Contract parties if an Unforeseen physical conditions were experienced on the site- the project contract is based on the FIDIC Red Book, 1999- Provide any necessary assumption: • Case 1 you represent Contractor’s Project manager/ Contract manager. …………………………………………………………………… …………………………………………………………………… ……………………………………………………………………. • Analyzed by Eng: SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1824 July 2017
  • 19. Event analysis- Q  In your project, describe the Role of the Contract parties if an Unforeseen physical conditions were experienced on the site- the project contract is based on the FIDIC Red Book, 1999- Provide any necessary assumption: • Case 2 you represent the Engineer: …………………………………………………………………… …………………………………………………………………… ……………………………………………………………………. • Analyzed by Eng: SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1924 July 2017
  • 20. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 20 Definitions 4.13 Rights of Way and Facilities • If the Contractor requires other/ additional rights of access, in addition, the Contractor may wish to occupy areas out of Site  The Contractor has the duty to obtain such rights of way and use of the areas at his own risk and cost. 4.14 Avoidance of interference Contractor shall not interfere improperly with: (a) the convenience of the public. Or (b) the access to and use and all roads and footpaths. Indemnify, the Employer harmless against, from all damages 24 July 2017
  • 21. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 21 Definitions 4.15 Access Route Contractor have been satisfied/ suitability and availability of access routes to Site. 4.16 Transport of Goods Unless stated in P. Conditions Notice before 21 days of delivery date. Contractor/ packing, loading, transporting. receiving. unloading, storing and protection : and Contractor indemnifies, hold the Employer harmless against , from all damages, losses and expenses. and pay all claims arising 24 July 2017
  • 22. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 22 Definitions 4.17 Contractor’s Equipment • Equipment/ exclusively intended for the execution of Works • Major equipment - permission from Engineer before removal. 4.18 Protection of Environment  The Contractor shall take all reasonable steps to protect the environment (both on and off the Site) these requirements cost impact to be evaluated in the tender. 4.19 Electricity, Water and Gas The Contractor is responsible of all power. water and other services he may require. 24 July 2017
  • 23. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 23 Definitions 4.20 Employer’s Equipment and Free-Issue Material • Employer's Equipment/ available for the use of the Contractor as per the Contract. 4.21 Progress Reports • monthly P reports prepared by the Contractor 6 copies • The first report shall cover the period up to the end of 1st M. • Reports shall be submitted monthly before 7th • Reporting continue till the Contractor has completed all work. • Contents include: ………….. 4.22 Security of the Site Contractor/ for keeping in the Site. authorized persons/ limited Contractor‟s…. 24 July 2017
  • 24. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 24 Definitions 4.23 Contractor’s Operations on Site • Contractor shall confine operations to Site, additional areas agreed by the Engineer as working areas. • Precautions to keep Contractor‟s Equipment and Personnel within the Site, additional areas, off adjacent land. 4.24 Fossils All fossils. coins. articles of value or antiquity. and structures and other remains or items of geological or archaeological interest found on the Site shall be placed under the care and authority of the Employer. reasonable precautions for protection. 24 July 2017
  • 25.
  • 26. Employer’s Responsibilities • Cl.2 o Provides Access to the Site • (not access & other areas – Cl.14.15 & 14.23) o Assists Contractor with Permits o Clause 16.1 Financial Arrangements ( Suspension- Variations) o Employer‟s claim notice SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2624 July 2017
  • 27. Employer’s Responsibilities “continued” • Assigning the Engineer Cl.3.1 • Cl.14.7 Payments • Cl.20.2 appointment of DAB members SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2724 July 2017
  • 28. Engineer’s Responsibilities • Contract Management • Maintain Employer's coordination and approvals • Acts for Employer as Cl.3.5–“Fair determination” • Cl.3.0 administration o Ensure fair management to avoid violations SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2824 July 2017
  • 29. Engineer’s Responsibilities o Coordinate with the Employer for changes and contract amendment o Acts as an Employer representative o Power of the Engineer is limited to relieve the parties of duties or obligations etc. To be continued in the next LEC. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2924 July 2017
  • 30. Q&A Conditions of Contract for ……………….Projects . which are recommended where one entity takes total responsibility for the design and execution of an engineering project. Under the usual arrangements for this type of contract , the entity carries out all the Engineering, Procurement and Construction: providing a fully equipped facility , ready for operation (at the "turn of the key").  This type of contract is usually negotiated between the parties, choose the correct contract: Answer: A. The New Silver Book EPC Turnkey. B. Red Book C. Yellow Book D. White Book Eng: …….. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3024 July 2017
  • 31. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 31 ……………. conditions of Contract for ……….. Which are recommended for building or engineering works designed by the Employer or by his representative, the Engineer. Under the usual arrangements for this type of contract, the Contractor constructs the works in accordance with a design provided by the Employer. However, the works may include some elements of Contractor-designed civil, mechanical, electrical and/or construction works. Answer: A. The New Silver Book EPC Turnkey. B. Red Book construction C. Yellow Book Plant des.- build D. White Book construction Eng:………….. Q&A 24 July 2017
  • 32. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 32 Q. The ………………….... Conditions of Contract for Plant and ………-Build. which are recommended for the provision of electrical and/or mechanical plant , and for the design, and execution of building or engineering works. Under the usual arrangements for this type of contract, the Contractor designs and provides, in accordance with the Employer‟s requirements, plant and/or other works; which may include any combination of civil, mechanical , electrical and/or construction works. Answer: A. The New Silver Book EPC Turnkey. B. Red Book construction C. Yellow Book Plant des.- build D. Green Book construction Eng: ………… Q&A 24 July 2017
  • 33. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 33 The New green Book. These Conditions of Contract are recommended for engineering and building work of relatively small capital value( 500,000$ -1,000,000$). However, depending on the type of work and the circumstances, the Conditions may be suitable for contracts of considerably greater value. They are considered most likely to be suitable for fairly simple or repetitive work or work of short duration without the need for specialist sub-contracts. This form may also be suitable for contracts which include , or wholly comprise contractor-designed civil engineering , building, mechanical and/or electrical works. Answer: A. The New Silver Book EPC Turnkey. B. Red Book construction C. Yellow Book Plant des.- build D. Green Book construction Q&A 24 July 2017
  • 34. Comparison between Red/Y/Silver SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3424 July 2017
  • 35. Comparison between Red/Y/Silver SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3524 July 2017
  • 36. Comparison between Red/Y/Silver SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3624 July 2017
  • 37. Comparison between Red/Y/Silver SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3724 July 2017
  • 38. Comparison between Red/Y/Silver SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3824 July 2017
  • 39. Comparison between Red/Y/Silver SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3924 July 2017
  • 40. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 40 End of LECTURE Four Thanks ‫وبركاته‬ ‫هللا‬ ‫ورحوة‬ ‫عليكن‬ ‫السالم‬ ‫هللا‬ ‫أهاى‬ ‫فى‬ 24 July 2017