- Having a brief of FIDIC
- Understand the steps and stages of Contract Management Using FIDIC.
- Understand the Role of PM during construction project to protect the organization Business case.
- Having a brief of FIDIC
- Understand the steps and stages of Contract Management Using FIDIC.
- Understand the Role of PM during construction project to protect the organization Business case.
The Second Edition of the Rainbow Suite is considerably longer, more detailed. The update addresses issues raised by users over the past 18 years and reflects current international best practice. The presentation analysis changes in Yellow & Silver Books as they apply to EPC & PPP Contracts from the perspectives of Public Entities, Contractors and Lenders.
A thorough analysis of FIDIC and it implication on COnstruction industry explained in this presentation for the beginners. It has been broken down to simplified version
Construction Contracts Management based on UK common law using more than 40 cases of law with references from the UK, USA regulations, and international rules plus some examples from standard forms of construction contracts such as JCT, NEC & FIDIC.
Determination of compensation due to a grant of EOT under FIDIC Conditions creates certain issues and the Society of Construction Law has set up a Protocol to overcome most of these issues with a well laid out procedure.
Training Slides of An Overview of the FIDIC FORMS OF CONTRACTand Contracts Committee Activities .
For further information regarding the course, please contact:
info@asia-masters.com
www.asia-masters.com
The Second Edition of the Rainbow Suite is considerably longer, more detailed. The update addresses issues raised by users over the past 18 years and reflects current international best practice. The presentation analysis changes in Yellow & Silver Books as they apply to EPC & PPP Contracts from the perspectives of Public Entities, Contractors and Lenders.
A thorough analysis of FIDIC and it implication on COnstruction industry explained in this presentation for the beginners. It has been broken down to simplified version
Construction Contracts Management based on UK common law using more than 40 cases of law with references from the UK, USA regulations, and international rules plus some examples from standard forms of construction contracts such as JCT, NEC & FIDIC.
Determination of compensation due to a grant of EOT under FIDIC Conditions creates certain issues and the Society of Construction Law has set up a Protocol to overcome most of these issues with a well laid out procedure.
Training Slides of An Overview of the FIDIC FORMS OF CONTRACTand Contracts Committee Activities .
For further information regarding the course, please contact:
info@asia-masters.com
www.asia-masters.com
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTIONBahzad5
FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS
CONDITIONS OF CONTRACT
FOR WORKS OF CIVIL
ENGINEERING CONSTRUCTION
PART I GENERAL CONDITIONS
WITH FORMS OF TENDER AND AGREEMENT
FOURTH EDITION 1987
Reprinted 1988 with editorial amendments
Reprinted 1992 with further amendments
35.م
مبادرة
#تواصل_تطوير
المحاضرة الخامسة والثلاثون من المبادرة مع
الدكتور/ مصطفى إسماعيل
بعنوان
التخفيف من مطالبات مشروعات التشييد
من خلال مشاركة المقاول المبكرة للمشروع
التاسعة مساء بتوقيت مكة المكرمة الإثنين20يوليو2020
وذلك عبر تطبيق زووم من خلال الرابط
https://us02web.zoom.us/meeting/register/tZUkdOCrqzksGtVth9CWe-pj5-zDaaMMKwiN
علما ان هناك بث مباشر للمحاضرة على صفحة فيس بوك
وقناة يوتيوب الخاصة بجمعية المهندسين المصريين
رابط قناة اليوتيوب
https://www.youtube.com/user/EEAchannal
للتواصل مع إدارة المبادرة عبر قناة التليجرام
https://t.me/EEAKSA
رابط اللينكدان والمكتبة الالكترونية
https://www.linkedin.com/company/eeaksa-egyptian-engineers-association/
رابط حساب تويتر
https://twitter.com/eeaksa
رابط التسجيل العام للمحاضرات
https://forms.gle/vVmw7L187tiATRPw9
Development agency will prepare the Technical Specification Document for each individual SRU and
will get it approved by airworthiness agency through HAL. Also, the electrical ICD need to be
generated by Development agency.
Essential
2 4.iv
Development agency will submit the application for airworthiness assessment of store, TAB (Type
approval basis), ACP (Airworthiness Certification Plan) and Quality Assurance Plan (QAP) documents
in co-ordination with HAL to airworthiness agencies for approval.
Essential
3 4.v
Development agency will carry out the TRR, PDR, CDR & TARB with prior intimation (min. 15 working
days) to HAL and airworthiness agencies.
Essential
4 4.vi
Development agency will develop all necessary Design documents, Process documents & Test
Documents required for airworthiness certification and will get the approval by airworthiness agency
through HAL.
Essential
5 4.vii
Development agency will do necessary procurement of raw material required for fabrication of
prototypes, along with CoC traceable to OEM as per approved Bill of Material. Essential
6 4.viii
Development agency will develop tools and fixtures required for fabrication of prototypes and get it
approved from airworthiness agencies. Essential
7 4.ix
Development agency will fabricate the prototype (02 nos. of each types of SRU) as per approved
design / process document to meet the requirement of approved Technical Specification. Essential
8 4.x
The fabricated SRU will be Form, Fit, Function and Integration (FFFI) substitution of required
respective SRU. Essential
9 4.xi
A test rig is to be developed and fabricated for carrying out the functional tests and get it approved
from airworthiness agencies.
Development agency will prepare the Technical Specification Document for each individual SRU and
will get it approved by airworthiness agency through HAL. Also, the electrical ICD need to be
generated by Development agency.
Essential
2 4.iv
Development agency will submit the application for airworthiness assessment of store, TAB (Type
approval basis), ACP (Airworthiness Certification Plan) and Quality Assurance Plan (QAP) documents
in co-ordination with HAL to airworthiness agencies for approval.
Essential
3 4.v
Development agency will carry out the TRR, PDR, CDR & TARB with prior intimation (min. 15 working
days) to HAL and airworthiness agencies.
Essential
4 4.vi
Development agency will develop all necessary Design documents, Process documents & Test
Documents required for airworthiness certification and will get the approval by airworthiness agency
through HAL.
Essential
5 4.vii
Development agency will do necessary procurement of raw material required for fabrication of
prototypes, along with CoC traceable to OEM as per approved Bill of Material. Essential
6 4.viii
Development agency will develop tools and fixtures required for fabrication of prototypes and get it
approved from airworthiness agencies. Essential
7 4.ix
Development agency will fabricate th
Good contracts will take into account CDM 2007 arrangements. Learn from these practical examples when drafting your contracts - presentation by Julian Scott of Squire Sanders exclusively for ARMSA Consulting wind energy clients.
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10Moustafa Ismail Abu Dief
Cost Management training course, Certified cost professional certification preparation course.
Cost Engineering- Commercial management- tendering and bedding.Process product manufacturing- skills and knowledge of cost engineering
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfKamal Acharya
The College Bus Management system is completely developed by Visual Basic .NET Version. The application is connect with most secured database language MS SQL Server. The application is develop by using best combination of front-end and back-end languages. The application is totally design like flat user interface. This flat user interface is more attractive user interface in 2017. The application is gives more important to the system functionality. The application is to manage the student’s details, driver’s details, bus details, bus route details, bus fees details and more. The application has only one unit for admin. The admin can manage the entire application. The admin can login into the application by using username and password of the admin. The application is develop for big and small colleges. It is more user friendly for non-computer person. Even they can easily learn how to manage the application within hours. The application is more secure by the admin. The system will give an effective output for the VB.Net and SQL Server given as input to the system. The compiled java program given as input to the system, after scanning the program will generate different reports. The application generates the report for users. The admin can view and download the report of the data. The application deliver the excel format reports. Because, excel formatted reports is very easy to understand the income and expense of the college bus. This application is mainly develop for windows operating system users. In 2017, 73% of people enterprises are using windows operating system. So the application will easily install for all the windows operating system users. The application-developed size is very low. The application consumes very low space in disk. Therefore, the user can allocate very minimum local disk space for this application.
Vaccine management system project report documentation..pdfKamal Acharya
The Division of Vaccine and Immunization is facing increasing difficulty monitoring vaccines and other commodities distribution once they have been distributed from the national stores. With the introduction of new vaccines, more challenges have been anticipated with this additions posing serious threat to the already over strained vaccine supply chain system in Kenya.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSEDuvanRamosGarzon1
AIRCRAFT GENERAL
The Single Aisle is the most advanced family aircraft in service today, with fly-by-wire flight controls.
The A318, A319, A320 and A321 are twin-engine subsonic medium range aircraft.
The family offers a choice of engines
Automobile Management System Project Report.pdfKamal Acharya
The proposed project is developed to manage the automobile in the automobile dealer company. The main module in this project is login, automobile management, customer management, sales, complaints and reports. The first module is the login. The automobile showroom owner should login to the project for usage. The username and password are verified and if it is correct, next form opens. If the username and password are not correct, it shows the error message.
When a customer search for a automobile, if the automobile is available, they will be taken to a page that shows the details of the automobile including automobile name, automobile ID, quantity, price etc. “Automobile Management System” is useful for maintaining automobiles, customers effectively and hence helps for establishing good relation between customer and automobile organization. It contains various customized modules for effectively maintaining automobiles and stock information accurately and safely.
When the automobile is sold to the customer, stock will be reduced automatically. When a new purchase is made, stock will be increased automatically. While selecting automobiles for sale, the proposed software will automatically check for total number of available stock of that particular item, if the total stock of that particular item is less than 5, software will notify the user to purchase the particular item.
Also when the user tries to sale items which are not in stock, the system will prompt the user that the stock is not enough. Customers of this system can search for a automobile; can purchase a automobile easily by selecting fast. On the other hand the stock of automobiles can be maintained perfectly by the automobile shop manager overcoming the drawbacks of existing system.
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
1. 24 July 2017SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1
LECTURE FOUR
وبركاته هللا ورحمة عليكن السالم
2017
.
Training Course:
Saudi Council of Engineers
FIDIC Forms of Contracts
2. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2
Over View
2 THE EMPLOYER
2.1 Right of Access to the Site
2.2 Permits, Licences or Approvals
2.3 Employer's Personnel LEC. 3
2.4 Employer's Financial Arrangements
2.5 Employer's Claims
3 THE ENGINEER
3.1 Engineer's Duties and Authority
3.2 Delegation by the Engineer
3.3 Instructions of the Engineer
3.4 Replacement of the Engineer
3.5 Determinations LEC 3
4 THE CONTRACTOR
4.1 Contractor's General Obligations
4.2 Performance Security
4.3 Contractor's Representative
4.4 Subcontractors
4.5 Assignment of Benefit of Subcontract
24 July 2017
3. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3
Over View
4.6 Co-operation
4.7 Setting Out
4.8 Safety Procedures
4.9 Quality Assurance
4.10 Site Data
4.11 Sufficiency of the Accepted Contract Amount
4.12 Unforeseeable Physical Conditions
4.13 Rights of Way and Facilities
4.14 Avoidance of Interference
4. 1 5 Access Route
4.16 Transport of Goods
4.17 Contractor's Equipment
4.18 Protection of the Environment
4.19 Electricity, Water and Gas
4.20 Employer's Equipment and Free-Issue Material
4.21 Progress Reports
4.22 Security of the Site
4.23 Contractor's Operations on Site
4.24 Fossils
24 July 2017
4. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 4
Over View
5 NOMINATED SUBCONTRACTORS
5.1 Definition of "nominated Subcontractor"
5.2 Objection to Nomination
5.3 Payments to nominated Subcontractors
5.4 Evidence of Payments
6 STAFF AND LABOUR
6.1 Engagement of Staff and Labour
6.2 Rates of Wages and Conditions of Labour
6.3 Persons in the Service of Employer
6.4 Labour Laws
6.5 Working Hours
6.6 Facilities for Staff and Labour
6. 7 Health and Safety
6.8 Contractor's Superintendence
6.9 Contractor’s Personnel
6.10 Records of Contractor's Personnel and Equipment
6.11 Disorderly Conduct
24 July 2017
5. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 5
Over View
7 PLANT, MATERIALS AND WORKMANSHIP
7.1 Manner of Execution
7.2 Samples
7.3 Inspection 7.4 Testing
7.5 Rejection 7.6 Remedial Work
7. 7 Ownership of Plant and Materials
7.8 Royalties
8 COMMENCEMENT, DELAYS,AND SUSPENSION
8.1 Commencement of Works
8.2 Time for Completion
8.3 Programme
8.4 Extension of Time for Completion
8.5 Delays Caused by Authorities
8.6 Rate of Progress 8.7 Delay Damages
8.8 Suspension of Work
8.9 Consequences of Suspension
8.10 Payment for Plant and Materials in Event of Suspension
8.11 Prolonged Suspension
8.12 Resumption of Work
24 July 2017
6. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 6
Definitions
4.1 Contractor's General Obligations
Design/ limited.
Execute/ complete/ remedy the Works as per Contract
The Contractor shall provide the Plant and Contractor's
Documents specified in the Contract. and all Contractor's
Personnel. Goods. consumables and other things and services.
Provide all whether of a temporary/permanent nature required .
24 July 2017
7. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 7
Definitions
4.1 Contractor's General Obligations
Responsible for adequacy, stability, safety of Site operations
and
of all methods of construction.
Except specified in the Contract, the Contractor
(i) responsible for all Contractor's Documents.
Temporary Works. and such design in accordance with the
Contract. and
24 July 2017
8. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 8
Definitions
4.1 Contractor's General Obligations
(ii) shall not otherwise be responsible for the design or
specification of the Permanent Works.
The Contractor shall. whenever required by the Engineer.
submit details of MOS for work execution.
If the Contract specifies that the Contractor shall design any
part, then :
the Contractor shall submit to the Engineer the Contractor's
Document of this part in accordance with S.Cl.1.4 Law &Lang.
24 July 2017
9. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 9
Definitions
4.2 Performance Security
The Contractor is required to provide to the Employer PS
within 28 days after receiving the Letter of Acceptance LOA
in the form annexed to the Particular Conditions
Amount as per Appendix to Tender.
24 July 2017
10. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 10
Definitions
4.2 Performance Security
The PS to remain valid until the Contractor has executed and
completed the Works which would give an expiry date
corresponding to the anticipated Completion Date (and not the
date of Taking Over described in Sub - Clauses 10.1 and 10.2).
The Employer shall return the PS to the Contractor within 21
days after receiving a copy of the Performance Certificate. (
S.Cl. 11.9)
24 July 2017
11. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 11
Definitions
4.3 Contractor's Representative
• appoint the Contractor ‟ s Representative/ PM- site M.
• give him all authority to act on the Contractor ‟ s behalf.
• The Contractor ‟ s Representative and his key staff shall be
fluent in the language ( S.Cl. 1.4)
4.4 Subcontractors
• The Contractor shall not subcontract the whole of the Works.
• shall be responsible for acts or defaults of any Subcontractor.
as if they were the acts or defaults of the Contractor. Unless
otherwise stated in the P. Conditions
24 July 2017
12. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 12
Definitions
4.5 Assignment of Benefit of Subcontract
In case the obligations of the Subcontractor may extend beyond
the expiry date of the relevant Defects Notification Period.
(Elevators, HVAC-) to be extended.
4.6 Co-operation
The Contractor shall. as specified in the Contract or as instructed
by the Engineer. Allows:
(a) the Employer's Personnel
(b) any other contractors employed by the Employer.
(c) the personnel of any legally constituted public authorities.
who may be employed in the execution on/or near Site of any
work not included in Contract.
24 July 2017
13. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV
13
Definitions
4.8 Safety Procedures
(a) comply with all applicable safety regulations.
(b) take care for the safety of persons entitled to be on the Site.
(c) reasonable efforts to keep the Site Works clear of obstruction.
4.7 Setting Out
• Commonly provided by the Eng. on behalf of the Employer.
• Contractor responsible for setting out the and shall notify the
Engineer of any errors observed.
• If the Contractor incurs additional cost or is delayed for
incorrect data, he is entitled to an EOT for any delay together
with payment of his additional costs plus reasonable profit.
24 July 2017
14. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 14
Definitions
4.8 Safety Procedures- Continued
(d) Fencing, lighting. Guarding, watching of the Works.
(e) Any Temporary Works (including roadways. Footways), for
the use and protection of the public and of owners and occupiers
of adjacent land.
4.9 Quality Assurance
„The Contractor is required to institute a QA system to
demonstrate compliance with requirements of the Contract.‟
may choose to confirm his intentions to comply with ISO
9001 as part of his tender submittal.
24 July 2017
15. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 15
Definitions
4.10 Site Data
By the Employer, prior to the Base Date and after also, all
relevant data in the Employer's possession on sub-surface and
hydrological conditions at the Site, environmental aspects.
4.11 Sufficiency of the Accepted Contract Amount‘
(a) have satisfied himself as to the correctness, sufficiency of the
accepted Contract Amount, and
(b) has based on the data. Interpret., necessary info., inspections.
Examine and satisfaction as to all relevant matters referred to in
S.Cl. 4.10 [Site Data].
24 July 2017
16. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 16
Definitions - Unforeseeable Physical Conditions
‘Unforeseeable ‟ is (S.Cl 1.1.6.8) as meaning „ not reasonably
foreseeable by an experienced contractor by the date for
submission of the Tender ‟
4.12 Unforeseeable Physical Conditions
If the Contractor encounters adverse physical conditions which
he considers to have been „ Unforeseeable ‟ , he shall:
• Notice ( details) to the Engineer/ copy the Employer,
• Entitled to an EOT and payment of any cost arising as a
consequence of the unforeseeable physical conditions.
24 July 2017
17. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC-
IV
17
Definitions - Unforeseeable Physical Conditions
4.12 Unforeseeable Physical Conditions
Continue executing the Works, using reasonable appropriate and
Engineer‟s instruction- may constitute a Variation, Clause 13
[Variations and Adjustments] shall apply.
• The Eng. May make deduction for favorable conditions.
After notice and inspecting and/or investigating- Engineer S.CL
3.5 [Determinations] to determine:
(i) whether and extent physical conditions were Unforeseeable.
and (ii) the matters of EOT and additional payment.
24 July 2017
18. Event analysis- Q
In your project, describe the Role of the Contract parties if an
Unforeseen physical conditions were experienced on the site-
the project contract is based on the FIDIC Red Book, 1999-
Provide any necessary assumption:
• Case 1 you represent Contractor’s Project manager/ Contract manager.
……………………………………………………………………
……………………………………………………………………
…………………………………………………………………….
• Analyzed by Eng:
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1824 July 2017
19. Event analysis- Q
In your project, describe the Role of the Contract parties if an
Unforeseen physical conditions were experienced on the site-
the project contract is based on the FIDIC Red Book, 1999-
Provide any necessary assumption:
• Case 2 you represent the Engineer:
……………………………………………………………………
……………………………………………………………………
…………………………………………………………………….
• Analyzed by Eng:
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 1924 July 2017
20. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 20
Definitions
4.13 Rights of Way and Facilities
• If the Contractor requires other/ additional rights of access, in
addition, the Contractor may wish to occupy areas out of Site
The Contractor has the duty to obtain such rights
of way and use of the areas at his own risk and cost.
4.14 Avoidance of interference
Contractor shall not interfere improperly with: (a) the
convenience of the public. Or (b) the access to and use and all
roads and footpaths.
Indemnify, the Employer harmless against, from all damages
24 July 2017
21. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 21
Definitions
4.15 Access Route
Contractor have been satisfied/ suitability and availability of
access routes to Site.
4.16 Transport of Goods
Unless stated in P. Conditions
Notice before 21 days of delivery date.
Contractor/ packing, loading, transporting. receiving. unloading,
storing and protection : and
Contractor indemnifies, hold the Employer harmless against ,
from all damages, losses and expenses. and pay all claims arising
24 July 2017
22. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 22
Definitions
4.17 Contractor’s Equipment
• Equipment/ exclusively intended for the execution of Works
• Major equipment - permission from Engineer before removal.
4.18 Protection of Environment
The Contractor shall take all reasonable steps to protect the
environment (both on and off the Site)
these requirements cost impact to be evaluated in the tender.
4.19 Electricity, Water and Gas
The Contractor is responsible of all power. water and other
services he may require.
24 July 2017
23. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 23
Definitions
4.20 Employer’s Equipment and Free-Issue Material
• Employer's Equipment/ available for the use of the Contractor
as per the Contract.
4.21 Progress Reports
• monthly P reports prepared by the Contractor 6 copies
• The first report shall cover the period up to the end of 1st M.
• Reports shall be submitted monthly before 7th
• Reporting continue till the Contractor has completed all work.
• Contents include: …………..
4.22 Security of the Site
Contractor/ for keeping in the Site. authorized persons/ limited Contractor‟s….
24 July 2017
24. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 24
Definitions
4.23 Contractor’s Operations on Site
• Contractor shall confine operations to Site, additional areas
agreed by the Engineer as working areas.
• Precautions to keep Contractor‟s Equipment and Personnel
within the Site, additional areas, off adjacent land.
4.24 Fossils
All fossils. coins. articles of value or antiquity. and structures and
other remains or items of geological or archaeological interest
found on the Site shall be placed under the care and authority of
the Employer. reasonable precautions for protection.
24 July 2017
25.
26. Employer’s Responsibilities
• Cl.2
o Provides Access to the Site
• (not access & other areas – Cl.14.15 & 14.23)
o Assists Contractor with Permits
o Clause 16.1 Financial Arrangements ( Suspension-
Variations)
o Employer‟s claim notice
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2624 July 2017
27. Employer’s Responsibilities “continued”
• Assigning the Engineer Cl.3.1
• Cl.14.7 Payments
• Cl.20.2 appointment of DAB members
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2724 July 2017
28. Engineer’s Responsibilities
• Contract Management
• Maintain Employer's coordination and approvals
• Acts for Employer as Cl.3.5–“Fair determination”
• Cl.3.0 administration
o Ensure fair management to avoid violations
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2824 July 2017
29. Engineer’s Responsibilities
o Coordinate with the Employer for changes and
contract amendment
o Acts as an Employer representative
o Power of the Engineer is limited to relieve the
parties of duties or obligations etc.
To be continued in the next LEC.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 2924 July 2017
30. Q&A
Conditions of Contract for ……………….Projects . which are
recommended where one entity takes total responsibility for the
design and execution of an engineering project. Under the usual
arrangements for this type of contract , the entity carries out all the
Engineering, Procurement and Construction: providing a fully
equipped facility , ready for operation (at the "turn of the key").
This type of contract is usually negotiated between the parties,
choose the correct contract:
Answer:
A. The New Silver Book EPC Turnkey.
B. Red Book
C. Yellow Book
D. White Book Eng: ……..
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 3024 July 2017
31. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 31
……………. conditions of Contract for ………..
Which are recommended for building or engineering works
designed by the Employer or by his representative, the Engineer.
Under the usual arrangements for this type of contract, the
Contractor constructs the works in accordance with a design
provided by the Employer. However, the works may include
some elements of Contractor-designed civil, mechanical,
electrical and/or construction works.
Answer:
A. The New Silver Book EPC Turnkey.
B. Red Book construction
C. Yellow Book Plant des.- build
D. White Book construction Eng:…………..
Q&A
24 July 2017
32. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 32
Q. The ………………….... Conditions of Contract for Plant and
………-Build. which are recommended for the provision of
electrical and/or mechanical plant , and for the design, and
execution of building or engineering works. Under the usual
arrangements for this type of contract, the Contractor designs
and provides, in accordance with the Employer‟s requirements,
plant and/or other works; which may include any combination of
civil, mechanical , electrical and/or construction works.
Answer:
A. The New Silver Book EPC Turnkey.
B. Red Book construction
C. Yellow Book Plant des.- build
D. Green Book construction Eng: …………
Q&A
24 July 2017
33. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- IV 33
The New green Book. These Conditions of Contract are recommended for engineering
and building work of relatively small capital value( 500,000$ -1,000,000$). However,
depending on the type of work and the circumstances, the Conditions may be suitable
for contracts of considerably greater value. They are considered most likely to be
suitable for fairly simple or repetitive work or work of short duration without the need
for specialist sub-contracts. This form may also be suitable for contracts which include ,
or wholly comprise contractor-designed civil engineering , building, mechanical and/or
electrical works.
Answer:
A. The New Silver Book EPC Turnkey.
B. Red Book construction
C. Yellow Book Plant des.- build
D. Green Book construction
Q&A
24 July 2017