Suspension and
Termination by
Contractor
Contract and Legal Aspects in Construction Management
ENGR. NATHANNIEL P. GONZALES
MSCM-1A
TOPICS
Introduction
Termination by
Contractor
Contractor’s Obligations
After Termination
Payment After
Termination by Contractor
02
01
03
05
04
06
Suspension by
Contractor
Other Related Topics
Defining Contract Suspension and
Termination
Introduction
01
What is Work Suspension?
is the suspension of a project ordered by either
a site owner or contractor to resolve an issue
involving an aspect of
the construction process.
What is Contract Termination?
the process of ending a contract before the
obligations within it have been fulfilled by all
parties..
Suspension
by Contractor
02
Contractor’s Rights to Suspend
Construction Work
TheRightoftheContractortoSuspendWork Operation
Suspension
By
Contractor
the Engineer fails to certify in
accordance with Sub-Clause 14.6
[Issue of IPC];
the Employer fails to provide reasonable
evidence in accordance with Sub-Clause
2.4 [Employer’s Financial Arrangements];
the Employer fails
to comply with:
the Employer fails to comply with
Sub-Clause 14.7 [Payment];
a binding agreement, or final and
binding determination under Sub-
Clause 3.7 [Agreement or
Determination];
a decision of the DAAB under 21.4
[Obtaining DAAB’s Decision]
(whether binding or final and
binding)
the Contractor may, not less than 21 days
after giving a Notice to the Employer (which
Notice shall state that it is given under this
Sub-Clause 16.1), suspend work (or reduce
the rate of work) unless and until the
Employer has remedied such a default.
This action shall not prejudice the
Contractor’s entitlements to financing
charges under Sub-Clause 14.8
[Delayed Payment] and to termination
under Sub-Clause 16.2 [Termination by
Contractor].
If the Employer subsequently remedies the
default as described in the above Notice
before the Contractor gives a Notice of
termination under Sub-Clause 16.2
[Termination by Contractor], the Contractor
shall resume normal working as soon as is
reasonably practicable.
If the Contractor suffers delay and/or incurs
Cost as a result of suspending work (or
reducing the rate of work) in accordance
with this Sub-Clause, the Contractor shall
be entitled subject to Sub-Clause 20.2
[Claims For Payment and/or EOT] to EOT
and/or payment of such Cost Plus Profit.
Termination by
Contractor
Contractor’s Entitlement to Terminate
the Contract Agreement
03
Termination of the Contract under
this Clause shall not prejudice any
other rights of the Contractor, under
the Contract or otherwise.
The Contractor shall be entitled to
give a Notice (which shall state that it
is given under this Sub-Clause 16.2.1)
to the Employer of the Contractor’s
intention to terminate the Contract or,
in the case of sub-paragraph (g)(ii),
(h), (i) or (j) below a Notice of
termination, if:
NOTICE
TheRightoftheContractortoTerminate Contract
h.
c.
i.
a.
f.
e.
d.
Termination
by
Contractor
the Contractor does not
receive the reasonable
evidence within 42 days
after giving a Notice
under Sub-Clause 16.1
[Suspension by
Contractor] in respect of
a failure to comply with
Sub-Clause 2.4
[Employer’s Financial
Arrangements];
TheRightoftheContractortoTerminate Contract
h.
c.
i.
f.
e.
d.
Termination
by
Contractor
the Engineer fails,
within 56 days after
receiving a
Statement and
supporting
documents, to
issue the relevant
Payment
Certificate;
TheRightoftheContractortoTerminate Contract
h.
c.
i.
f.
e.
d.
Termination
by
Contractor
the Contractor does
not receive the
amount due under
any Payment
Certificate within 42
days after the expiry
of the time stated in
Sub-Clause 14.7
[Payment];
TheRightoftheContractortoTerminate Contract
h.
i.
f.
e.
d.
Termination
by
Contractor
the Employer fails to comply
with:
i. a binding agreement, or
final and binding
determination under Sub-
Clause 3.7 [Agreement or
Determination]; or
ii. a decision of the DAAB
under 21.4 [Obtaining
DAAB’s Decision] (whether
binding or final and binding)
and such failure constitutes
a material breach of the
Employer’s obligations
under the Contract;
TheRightoftheContractortoTerminate Contract
h.
i.
f.
Termination
by
Contractor
the Employer
substantially fails to
perform, and such
failure constitutes a
material breach of, the
Employer’s obligations
under the Contract;
e.
TheRightoftheContractortoTerminate Contract
h.
i.
Termination
by
Contractor
the Contractor does
not receive a Notice of
the Commencement
Date under Sub-
Clause 8.1
[Commencement of
Works] within 84 days
after receiving the
Letter of Acceptance;
f.
TheRightoftheContractortoTerminate Contract
h.
i.
Termination
by
Contractor
the Employer:
i. fails to comply with
Sub-Clause 1.6
[Contract
Agreement], or
ii. assigns the
Contract without the
required agreement
under Sub-Clause
1.7 [Assignment];
TheRightoftheContractortoTerminate Contract
i.
Termination
by
Contractor
a prolonged
suspension affects the
whole of the Works as
described in sub-
paragraph (b) of Sub-
Clause 8.12
[Prolonged
Suspension];
h.
TheRightoftheContractortoTerminate Contract
Termination
by
Contractor
the Employer becomes bankrupt
or insolvent; goes into
liquidation, administration,
reorganisation, winding-up or
dissolution; becomes subject to
the appointment of a liquidator,
receiver, administrator, manager
or trustee; enters into a
composition or arrangement with
the Employer’s creditors; or any
act is done or any event occurs
which is analogous to or has a
similar effect to any of these acts
or events under applicable
Laws; or
i.
TheRightoftheContractortoTerminate Contract
Termination
by
Contractor
the Employer is found,
based on reasonable
evidence, to have
engaged in corrupt,
fraudulent, collusive or
coercive practice at
any time in relation to
the Works or to the
Contract.
Termination
Day 14
The Contractor can
Issue 2nd Notice for
Termination
Day “N”
2nd Notice Received
by Employer
1st Notice Received
by Employer
Day 1
Date of Termination
However, in the case of sub-paragraph
(g)(ii), (h), (i) or (j) of Sub-Clause 16.2.1
[Notice], by giving a Notice under Sub-
Clause 16.2.1 the Contractor may terminate
the Contract immediately and the date of
termination shall be the date the Employer
receives this Notice.
If the Contractor suffers delay and/or incurs
Cost during the above period of 14 days, the
Contractor shall be entitled subject to Sub-
Clause 20.2 [Claims For Payment and/or
EOT] to EOT and/or payment of such Cost
Plus Profit.
Contractor’s Obligations
After Termination
Cessation and Removal of
Contractor’s Equipment and Turning
Over of Documents, Plant and
Materials Paid
04
After termination of the Contract under Sub-
Clause 15.5 [Termination for Employer’s
Convenience], Sub-Clause 16.2
[Termination by Contractor] or Sub-Clause
18.5 [Optional Termination], the Contractor
shall promptly:
Contractor’s
Obligations
remove all other
Goods from the
Site, except as
necessary for
safety, and leave
the Site.
c.
cease all further work,
except for such work as
may have been instructed
by the Engineer for the
protection of life or property
or for the safety of the
Works. If the Contractor
incurs Cost as a result of
carrying out such
instructed work the
Contractor shall be entitled
subject to Sub-Clause 20.2
[Claims For Payment
and/or EOT] to be paid
such Cost Plus Profit;
a.
deliver to the
Engineer all
Contractor’s
Documents, Plant,
Materials and other
work for which the
Contractor has
received payment;
and
b.
Payment After
Termination by
Contractor
Employer’s Payment to
Contractor
05
After termination under Sub-
Clause 16.2 [Termination by
Contractor], the Employer shall
promptly:
Payment toContractorAfterTermination
b.
a.
Payments
Other Related
Topics
Work Suspension and Termination
by Contractor
06
CIAPConditionsforContractor’sWorkSuspension&Termination
Should the Owner suspend the work
without just cause for more than an
aggregate period of fifteen (15) days
without the Contractor's consent.
d.
Should the Owner fail to deliver at the
construction site Owner-
supplied/furnished construction
materials and/or equipment, for the
scope of work along the critical path,
beyond fifteen (15) days after its
scheduled date for delivery as provided
for in the Contract.
e.
Should approval of Variation Orders for
additional works along the critical path
be delayed beyond fifteen (15) days
after submission for approval by the
Owner or by its duly designated
Representative.
f.
Should an order of any court or other
public authority caused the work to be
stopped or suspended for an aggregate
period of ninety (90) days through no
act or fault of the Contractor or its
employees.
a.
Should the Owner fail to pay
the Contractor the approved
Request for Payment as
provided in Article 22.05.
b.
Should the Owner fail to
Pay the Contractor any
sum within thirty (30) days
after its award by
arbitration.
c.
Should the suspension be necessary for proper
execution of the Work or by reason of weather or
other conditions affecting the safety of the works
and/or the Contractor’s workers, the Contractor
may request the Owner to suspend work in
accordance with the applicable provision or
provisions of Article 27.02.
The Contractor shall be entitled to
an equitable adjustment of
Completion Time and/or Contract
Price for suspension of work due to
the above circumstances.
2016 Revised IRR of RA
9184 Conditions
The contractor or its duly authorized
representative shall have the right to suspend
work operation on any or all projects/activities
along the critical path of activities after fifteen
(15) calendar days from date of receipt of
written notice from the contractor to the district
engineer/regional director/consultant or
equivalent official, as the case may be, due to
the following:
Suspension of Work
a. There exist right-of-
way problems which
prohibit the
contractor from
performing work in
accordance with the
approved
construction
schedule.
b. Requisite
construction plans
which must be
owner-furnished are
not issued to the
contractor precluding
any work called for
by such plans.
c. Peace and order conditions make it
extremely dangerous, if not
possible, to work. However, this
condition must be certified in writing
by the Philippine National Police
(PNP) station which has
responsibility over the affected area
and confirmed by the Department of
Interior and Local Government
(DILG) Regional Director.
d. There is failure on the
part of the procuring
entity to deliver
government-furnished
materials and
equipment as
stipulated in the
contract.
e. Delay in the payment of
contractor's claim for progress
billing beyond forty-five (45)
calendar days from the time
the contractor's claim has
been certified to by the
procuring entity’s authorized
representative that the
documents are complete
unless there are justifiable
reasons thereof which shall be
communicated in writing to the
contractor.
The Contractor may terminate its
contract with the Procuring Entity if
the works are completely stopped for
a continuous period of at least sixty
(60) calendar days through no fault of
its own, due to any of the following
reasons:
Termination by
Contractor/Consultant
a. Failure of the
Procuring Entity to
deliver, within a
reasonable time,
supplies, materials,
right-of-way, or other
items it is obligated to
furnish under the
terms of the contract;
or
b. The prosecution of
the work is disrupted
by the adverse
peace and order
situation, as certified
by the Armed Forces
of the Philippines
Provincial
Commander and
approved by the
Secretary of National
Defense.
Examples…
Sample Template for
Work Suspension Order
Source: DPWH D.O. 46 S.2022
No WSO to be
issued due to
intermittent
conditions which
renders the site
unworkable
Shall not be
issued right at the
start of the
contract effectivity
if it’s due to ROW
problem
WSO Form
should be
used
Conditions for Issuing W.S.O.
Source: DPWH D.O. 42 S.2020
Sample Template for
Continuation of Work
Suspension Order
Source: DPWH D.O. 46 S.2022
Within 5
days before
the lapse of
W.S.O
In
consideration
of the
delegated
authority
C.W.S.O.
Form as
prescribed
Conditions for Issuing C.W.S.O.
Source: DPWH D.O. 72 S.2019
TIMEFRAME IN THE PREPARATION/REVIEW/EVALUATION AND APPROVAL OF WORK SUSPENSION
ORDER, CONTINUANCE OF WORK SUSPENSION ORDER AND CONTRACT TIME EXTENSION
Source: DPWH D.O. 42 S.2020
Source: DPWH D.O. 42 S.2020
Source: DPWH D.O. 42 S.2020
CRÉDITOS: Esta plantilla de presentación fue
creada por Slidesgo, que incluye iconos de
Flaticon, infografías e imágenes de Freepik
THANK
YOU!
Por favor, conserva esta diapositiva para atribuirnos
Do You Have Questions?
Nathannielgonzales@gmail.com
09982455652
DPWH Masbate 3rd DEO

Suspension and Termination by Contractor Presentation.pptx

  • 1.
    Suspension and Termination by Contractor Contractand Legal Aspects in Construction Management ENGR. NATHANNIEL P. GONZALES MSCM-1A
  • 2.
    TOPICS Introduction Termination by Contractor Contractor’s Obligations AfterTermination Payment After Termination by Contractor 02 01 03 05 04 06 Suspension by Contractor Other Related Topics
  • 3.
    Defining Contract Suspensionand Termination Introduction 01
  • 4.
    What is WorkSuspension? is the suspension of a project ordered by either a site owner or contractor to resolve an issue involving an aspect of the construction process.
  • 5.
    What is ContractTermination? the process of ending a contract before the obligations within it have been fulfilled by all parties..
  • 6.
  • 7.
    TheRightoftheContractortoSuspendWork Operation Suspension By Contractor the Engineerfails to certify in accordance with Sub-Clause 14.6 [Issue of IPC]; the Employer fails to provide reasonable evidence in accordance with Sub-Clause 2.4 [Employer’s Financial Arrangements]; the Employer fails to comply with: the Employer fails to comply with Sub-Clause 14.7 [Payment]; a binding agreement, or final and binding determination under Sub- Clause 3.7 [Agreement or Determination]; a decision of the DAAB under 21.4 [Obtaining DAAB’s Decision] (whether binding or final and binding)
  • 8.
    the Contractor may,not less than 21 days after giving a Notice to the Employer (which Notice shall state that it is given under this Sub-Clause 16.1), suspend work (or reduce the rate of work) unless and until the Employer has remedied such a default.
  • 9.
    This action shallnot prejudice the Contractor’s entitlements to financing charges under Sub-Clause 14.8 [Delayed Payment] and to termination under Sub-Clause 16.2 [Termination by Contractor].
  • 10.
    If the Employersubsequently remedies the default as described in the above Notice before the Contractor gives a Notice of termination under Sub-Clause 16.2 [Termination by Contractor], the Contractor shall resume normal working as soon as is reasonably practicable.
  • 11.
    If the Contractorsuffers delay and/or incurs Cost as a result of suspending work (or reducing the rate of work) in accordance with this Sub-Clause, the Contractor shall be entitled subject to Sub-Clause 20.2 [Claims For Payment and/or EOT] to EOT and/or payment of such Cost Plus Profit.
  • 12.
    Termination by Contractor Contractor’s Entitlementto Terminate the Contract Agreement 03
  • 13.
    Termination of theContract under this Clause shall not prejudice any other rights of the Contractor, under the Contract or otherwise.
  • 14.
    The Contractor shallbe entitled to give a Notice (which shall state that it is given under this Sub-Clause 16.2.1) to the Employer of the Contractor’s intention to terminate the Contract or, in the case of sub-paragraph (g)(ii), (h), (i) or (j) below a Notice of termination, if: NOTICE
  • 15.
    TheRightoftheContractortoTerminate Contract h. c. i. a. f. e. d. Termination by Contractor the Contractordoes not receive the reasonable evidence within 42 days after giving a Notice under Sub-Clause 16.1 [Suspension by Contractor] in respect of a failure to comply with Sub-Clause 2.4 [Employer’s Financial Arrangements];
  • 16.
    TheRightoftheContractortoTerminate Contract h. c. i. f. e. d. Termination by Contractor the Engineerfails, within 56 days after receiving a Statement and supporting documents, to issue the relevant Payment Certificate;
  • 17.
    TheRightoftheContractortoTerminate Contract h. c. i. f. e. d. Termination by Contractor the Contractordoes not receive the amount due under any Payment Certificate within 42 days after the expiry of the time stated in Sub-Clause 14.7 [Payment];
  • 18.
    TheRightoftheContractortoTerminate Contract h. i. f. e. d. Termination by Contractor the Employerfails to comply with: i. a binding agreement, or final and binding determination under Sub- Clause 3.7 [Agreement or Determination]; or ii. a decision of the DAAB under 21.4 [Obtaining DAAB’s Decision] (whether binding or final and binding) and such failure constitutes a material breach of the Employer’s obligations under the Contract;
  • 19.
    TheRightoftheContractortoTerminate Contract h. i. f. Termination by Contractor the Employer substantiallyfails to perform, and such failure constitutes a material breach of, the Employer’s obligations under the Contract; e.
  • 20.
    TheRightoftheContractortoTerminate Contract h. i. Termination by Contractor the Contractordoes not receive a Notice of the Commencement Date under Sub- Clause 8.1 [Commencement of Works] within 84 days after receiving the Letter of Acceptance; f.
  • 21.
    TheRightoftheContractortoTerminate Contract h. i. Termination by Contractor the Employer: i.fails to comply with Sub-Clause 1.6 [Contract Agreement], or ii. assigns the Contract without the required agreement under Sub-Clause 1.7 [Assignment];
  • 22.
    TheRightoftheContractortoTerminate Contract i. Termination by Contractor a prolonged suspensionaffects the whole of the Works as described in sub- paragraph (b) of Sub- Clause 8.12 [Prolonged Suspension]; h.
  • 23.
    TheRightoftheContractortoTerminate Contract Termination by Contractor the Employerbecomes bankrupt or insolvent; goes into liquidation, administration, reorganisation, winding-up or dissolution; becomes subject to the appointment of a liquidator, receiver, administrator, manager or trustee; enters into a composition or arrangement with the Employer’s creditors; or any act is done or any event occurs which is analogous to or has a similar effect to any of these acts or events under applicable Laws; or i.
  • 24.
    TheRightoftheContractortoTerminate Contract Termination by Contractor the Employeris found, based on reasonable evidence, to have engaged in corrupt, fraudulent, collusive or coercive practice at any time in relation to the Works or to the Contract.
  • 25.
    Termination Day 14 The Contractorcan Issue 2nd Notice for Termination Day “N” 2nd Notice Received by Employer 1st Notice Received by Employer Day 1 Date of Termination
  • 26.
    However, in thecase of sub-paragraph (g)(ii), (h), (i) or (j) of Sub-Clause 16.2.1 [Notice], by giving a Notice under Sub- Clause 16.2.1 the Contractor may terminate the Contract immediately and the date of termination shall be the date the Employer receives this Notice.
  • 27.
    If the Contractorsuffers delay and/or incurs Cost during the above period of 14 days, the Contractor shall be entitled subject to Sub- Clause 20.2 [Claims For Payment and/or EOT] to EOT and/or payment of such Cost Plus Profit.
  • 28.
    Contractor’s Obligations After Termination Cessationand Removal of Contractor’s Equipment and Turning Over of Documents, Plant and Materials Paid 04
  • 29.
    After termination ofthe Contract under Sub- Clause 15.5 [Termination for Employer’s Convenience], Sub-Clause 16.2 [Termination by Contractor] or Sub-Clause 18.5 [Optional Termination], the Contractor shall promptly:
  • 30.
    Contractor’s Obligations remove all other Goodsfrom the Site, except as necessary for safety, and leave the Site. c. cease all further work, except for such work as may have been instructed by the Engineer for the protection of life or property or for the safety of the Works. If the Contractor incurs Cost as a result of carrying out such instructed work the Contractor shall be entitled subject to Sub-Clause 20.2 [Claims For Payment and/or EOT] to be paid such Cost Plus Profit; a. deliver to the Engineer all Contractor’s Documents, Plant, Materials and other work for which the Contractor has received payment; and b.
  • 31.
  • 32.
    After termination underSub- Clause 16.2 [Termination by Contractor], the Employer shall promptly:
  • 33.
  • 34.
    Other Related Topics Work Suspensionand Termination by Contractor 06
  • 35.
    CIAPConditionsforContractor’sWorkSuspension&Termination Should the Ownersuspend the work without just cause for more than an aggregate period of fifteen (15) days without the Contractor's consent. d. Should the Owner fail to deliver at the construction site Owner- supplied/furnished construction materials and/or equipment, for the scope of work along the critical path, beyond fifteen (15) days after its scheduled date for delivery as provided for in the Contract. e. Should approval of Variation Orders for additional works along the critical path be delayed beyond fifteen (15) days after submission for approval by the Owner or by its duly designated Representative. f. Should an order of any court or other public authority caused the work to be stopped or suspended for an aggregate period of ninety (90) days through no act or fault of the Contractor or its employees. a. Should the Owner fail to pay the Contractor the approved Request for Payment as provided in Article 22.05. b. Should the Owner fail to Pay the Contractor any sum within thirty (30) days after its award by arbitration. c.
  • 36.
    Should the suspensionbe necessary for proper execution of the Work or by reason of weather or other conditions affecting the safety of the works and/or the Contractor’s workers, the Contractor may request the Owner to suspend work in accordance with the applicable provision or provisions of Article 27.02.
  • 37.
    The Contractor shallbe entitled to an equitable adjustment of Completion Time and/or Contract Price for suspension of work due to the above circumstances.
  • 38.
    2016 Revised IRRof RA 9184 Conditions
  • 39.
    The contractor orits duly authorized representative shall have the right to suspend work operation on any or all projects/activities along the critical path of activities after fifteen (15) calendar days from date of receipt of written notice from the contractor to the district engineer/regional director/consultant or equivalent official, as the case may be, due to the following: Suspension of Work
  • 40.
    a. There existright-of- way problems which prohibit the contractor from performing work in accordance with the approved construction schedule.
  • 41.
    b. Requisite construction plans whichmust be owner-furnished are not issued to the contractor precluding any work called for by such plans.
  • 42.
    c. Peace andorder conditions make it extremely dangerous, if not possible, to work. However, this condition must be certified in writing by the Philippine National Police (PNP) station which has responsibility over the affected area and confirmed by the Department of Interior and Local Government (DILG) Regional Director.
  • 43.
    d. There isfailure on the part of the procuring entity to deliver government-furnished materials and equipment as stipulated in the contract.
  • 44.
    e. Delay inthe payment of contractor's claim for progress billing beyond forty-five (45) calendar days from the time the contractor's claim has been certified to by the procuring entity’s authorized representative that the documents are complete unless there are justifiable reasons thereof which shall be communicated in writing to the contractor.
  • 45.
    The Contractor mayterminate its contract with the Procuring Entity if the works are completely stopped for a continuous period of at least sixty (60) calendar days through no fault of its own, due to any of the following reasons: Termination by Contractor/Consultant
  • 46.
    a. Failure ofthe Procuring Entity to deliver, within a reasonable time, supplies, materials, right-of-way, or other items it is obligated to furnish under the terms of the contract; or
  • 47.
    b. The prosecutionof the work is disrupted by the adverse peace and order situation, as certified by the Armed Forces of the Philippines Provincial Commander and approved by the Secretary of National Defense.
  • 48.
    Examples… Sample Template for WorkSuspension Order Source: DPWH D.O. 46 S.2022
  • 49.
    No WSO tobe issued due to intermittent conditions which renders the site unworkable Shall not be issued right at the start of the contract effectivity if it’s due to ROW problem WSO Form should be used Conditions for Issuing W.S.O. Source: DPWH D.O. 42 S.2020
  • 50.
    Sample Template for Continuationof Work Suspension Order Source: DPWH D.O. 46 S.2022
  • 51.
    Within 5 days before thelapse of W.S.O In consideration of the delegated authority C.W.S.O. Form as prescribed Conditions for Issuing C.W.S.O.
  • 52.
  • 54.
    TIMEFRAME IN THEPREPARATION/REVIEW/EVALUATION AND APPROVAL OF WORK SUSPENSION ORDER, CONTINUANCE OF WORK SUSPENSION ORDER AND CONTRACT TIME EXTENSION Source: DPWH D.O. 42 S.2020
  • 55.
  • 57.
  • 60.
    CRÉDITOS: Esta plantillade presentación fue creada por Slidesgo, que incluye iconos de Flaticon, infografías e imágenes de Freepik THANK YOU! Por favor, conserva esta diapositiva para atribuirnos Do You Have Questions? Nathannielgonzales@gmail.com 09982455652 DPWH Masbate 3rd DEO

Editor's Notes

  • #8 These failures constitute a material breach of the Employer’s obligations under the Contract
  • #26 Unless the Employer remedies the matter described in a Notice given under Sub-Clause 16.2.1 [Notice] within 14 days of receiving the Notice, the Contractor may by giving a second Notice to the Employer immediately terminate the Contract. The date of termination shall then be the date the Employer receives this second Notice.
  • #34 These failures constitute a material breach of the Employer’s obligations under the Contract
  • #36 These failures constitute a material breach of the Employer’s obligations under the Contract
  • #43 Unless the Employer remedies the matter described in a Notice given under Sub-Clause 16.2.1 [Notice] within 14 days of receiving the Notice, the Contractor may by giving a second Notice to the Employer immediately terminate the Contract. The date of termination shall then be the date the Employer receives this second Notice.