PROFESSIONAL
PRACTICE 2
CHRISTINA HO CHIA HUI
LOO SIAH MONG
YEONG POH LING
CONSTRUCTION
DELAYS AND
EXTENSION OF
TIME
INTRODUCTION
Construction delays arising during construction which cause completion
date to be breached
DELAYS
Categories of delays : -
➢ Delay caused by Contractor (Clause 21.1)
➢ Delay caused by Employer (Clause 23.8) - 15 relevant events
➢ Delay caused by Third Parties ( Neutral Event) (Clause 23.8) - 9 relevant events
DELAY BY CONTRACTOR
Reasons :
● Not having sufficient labour force or plant on site
● Not having necessary materials when needed
● Poor site management/co-ordination/experience
● Failure to pay workers or sub-contractors
Contractual Effects :
● Not entitle to claim for EOT
● No reimbursement for loss and expense
● Employer can be compensated by the way of LD
● Employer may terminate the contractor’s employment if delay is too long
DELAY BY EMPLOYER
15 Relevant Events under clause 23.8
Contractual Effects :
● Contractor entitlement to claim for EOT
● Contractor entitle to claim for loss and expense
● Employer cannot impose LD because is own fault
● If delay is serious, contractor can terminate his employment
DELAY BY THIRD PARTIES (NEUTRAL EVENTS)
● Weather, Act of God, Natural Justices
● 9 Relevant Events
● Not the fault of contractor or employer
● They have to bare with their own responsibilities
Contractual Effects :
● Contractor entitled to EOT
● Contractor not entitled to lose and expense
● Employer cannot imposed LD
● Contractor and employer should share the burden of delay
EXTENSION OF TIME
Procedure of EOT
STEP 1 : Giving of notice
- Must give a written notice of intention to claim for EOT. It is a condition precedent to
any EOT.
STEP 2 : Official Application
- Must submit official application within 28 days after the end of the event.
EXTENSION OF TIME
1. Decision to claim for EOT ( is up to the contractor )
2. Failure to submit claim application
3. Written notice shall be a condition precedent to an entitlement of EOT
Case Study 1: Syarikat Tan Lim Bent & Rakan-Rakan v Pulai Jaya S/B (1992)
It was held that this is an expressed condition, contractor must comply. Contractor may lose the case because he failed to submit
written notice.
Case Study 2 : Turner Corporation Ltd v Austotel Pty Ltd (1997)
It was held contractor cannot rely on acts of prevention by employer for not giving written notice. He must give notice which would
have negated the effect of that preventing conduct.
Principles for Granting EOT (Architect have to make decision)
1. Before granting EOT, architect have to consider certain items
- In writing - Have materially disrupted the regular progress of works
- Fall within clause 23.8 - Nett effective delay must be assessed based on approved
- Prevent further losses or delays work programme
2. Issue of the certificate of EOT (Architect have to make 2 decision)
- Reject totally with reasons
- Grant an appropriate EOT and issue certificate of EOT
3. Timing of Issue
- Within 6 weeks from the contractor's application, architect must decide an
issue
4. Delay by NSC
5. Obligations of Architect
- To assess the length of EOT, architect must act reasonably, fairly and
impartially
- Failure to assess application and issue EOT is a breach
6. Consequences of Not Granting Contractor’s Application
● If architect default in granting EOT
● Employer will loses the rights to impose liquidated damages
● It is a breach of contract
● Architect liable to the employer in tort (negligence) / for breach of contract (services)
For contractor, initial course of action : i) Make a fresh application
ii) Appeal to employer
iii) Contractor can refer the dispute to Arbitration
Can EOT be granted Prospectively or Retrospectively?
1. Clause 23.4
- Architect may issue the written notice of rejection or the certification of EOT before / after
the Completion Date
- Architect can make & approve EOT backward / forward
2. Situations can arise
- Contractor’s submission of his particulars under clauses 23 very near to the completion date
3. Retrospectively
- Contractor submit one week before the completion date
- Architect will assess EOT after completion date
EOT After The Issuance Of Certificate of Non-Completion(CNC)
1. If contractor doesn’t complete, architect must issue CNC to contractor. If not employer cannot
impose liquidated damages
2. When clause 23.9 is read together with clause 22.3 the granting of subsequent EOT will
revoke the CNC
3. When CNC is cancelled, employer have to return the surplus liquidated damages.
4. If contractor again fails to complete by the new completion date, a new CNC will be issued by
architect.
EOT PROVISIONS
● Employer cannot set new completion date
● Contractor have to complete within a
reasonable time
● Time become at large
● Employer loses the rights to impose
liquidated damages
EOT PROVISIONS
● Completion date can be extended,
if there is a delay
● Employer can set new completion date
● Preserves employer’s contractual rights to
impose liquidated damages
● Prevents time become at large
Implications Of Time For Completion Being At Large
1. Original completion date no longer apply
2. there is no definite completion date to work towards
3. Contractor have to complete within a reasonable time
4. Employer loses his right to imposes liquidated damages
5. Contractor’s liability is limited to general damages
LIQUIDATED DAMAGES
In order to a successful claim for liquidated damages, Employer have to comply with the
following pre-conditions :
➢ Contract contains express clause enabling the deduction of the liquidated damages
➢ The liquidated clause must be valid and enforceable
➢ Details of liquidated damages must be clearly indicated
➢ Specific contractual procedure must be strictly complied
➢ Must be definite date fixed in contract from which damages can run
➢ Employer has not waived his right to deduct the liquidated damages
Amount of damages that need to be paid to the injured party to collect as compensation upon a specific
breach in a contract.
CASE STUDY
Case 1
➢ Selva Kumar a/l Murugiah v. Thiagarajah a/l Retnasamy [1995] 2 MLJ 817
Case 2
➢ Johor Coastal Development Sdn Bhd v. Constrajaya Sdn Bhd [2009] 4 CLJ 569
Question 1: As a Consultant assessing an extension of time
application by the Contractor, what are the initial checklist
and the principles to be applied?
● The application must be in writing
● Causes of delay must be under Clause 23.8
● Contractor must have taken all practical steps to mitigate
● Delays must be ‘materially’ disrupted the regular progress of the works, resulting in the
completion date being breached
● The ‘nett effective’ delay must be assessed based on approved work programme under
Clause 3.5
Question 2: What are the purpose of an extension of time clauses in
most standard contract and its implications? What is the implication
of a Certificate of Non-Completion? What is the difference between
general damages and liquidated damages?
Purpose of EOT
Employer entitled to impose liquidated damages due to the delay caused by contractor.
Contractor in will be granted EOT due to delays caused by employer. (Clause 23.8)
If there is no EOT provision, the contractor’s liability will be limited to general damages not liquidated
damages.
Implication of EOT
If there is EOT provision, completion date can be extended and new completion date can be set. It preserves
the employer’s contractual right to impose liquidated damages to the contractor. It also prevent the completion
time to be ‘at large’.
If there is no EOT provision, time will be ‘at large’, contractor will have to complete the project at a
reasonable time.
Implication of certificate of Non completion ( 22.3 & 23.9)
A formal return notice for the contractor, it gives the employer the right to impose liquidated damage to
the contractor.
If EOT is issued after issuance of CNC, employer shall return the surplus amount of liquidated damages
imposed to the contractor.
General damages Liquidated Damages
No EOT provision With EOT provision
Hard to prove (no basis to follow) Easier to prove ( master programme as basis)
No fixed amount Fixed amount
Differences between General damages & Liquidated damages
Question 3: What are concurrent delays? Is the Contractor
entitled to extension of time and loss and expense if there
are concurrent delays by Employer and Contractor?
Concurrent Delays
● Simultaneous delays caused by the contractor and employer
● Two or more delay events occurring within the same time period
● Affecting the project schedule and project completion date
● but not all of those events enable to claim an extension of time or loss and expense
Contractor entitled to extension of time and loss and expense if
● Have the valid reason and certify by Architect and consultant Quantity Surveyor.
QUESTIONS
Q1 : What are the effects of construction projects delay?
Q2 : What are the examples of grounds for challenging extension of time certificate ?
(In what event can the contractor challenge the EOT certificate that is issued by the
Architect?)
Q3 : If Nominated Sub-Contractor goes bankrupt, can the contractor claim for EoT? If
yes what is the relevant clause?
ANSWER FOR Q1
➢ Cost overrun
- Contractor extend insurance policies (claimable)
- Contractor’s fault, employer has the rights to impose liquidated damages
➢ Time overrun
- Contractor claims for EOT
- New completion date
➢ Dispute (Arbitration)
ANSWER FOR Q2
➢ Certificate not given time
➢ Certificate no in the correct format
➢ Certificate issued by unauthorised person
➢ Addressee of certificate not named
➢ Decision to extend time improperly delegated
➢ Certificate not given fairly
➢ Contractual procedures not followed
ANSWER FOR Q3
23.8 (i)
THANK YOU

More Related Content

What's hot

Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
Kheng Hoe Advocates
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
Melvin Lim
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
Trace96
 
PP1 report
PP1 reportPP1 report
PP1 report
Doreen Yeo
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
Pang Khai Shuen
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
Dayat Mohamad
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
Haziq1511
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
wendyteosy
 
Cl compilation
Cl compilationCl compilation
Cl compilation
Jessyca Than
 
Site possession
Site possessionSite possession
Site possession
Amir Ibrahim
 
Software assignment 1
Software assignment 1Software assignment 1
Software assignment 1
Timun Loh
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
Kai Yun Pang
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
lucaschinsheng
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
Kheng Hoe Advocates
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
Yee Len Wan
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
Ngo Jia Haur
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
seenyeeyong
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
Pui Chun Shian
 

What's hot (20)

Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
 
PP1 report
PP1 reportPP1 report
PP1 report
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Site possession
Site possessionSite possession
Site possession
 
Software assignment 1
Software assignment 1Software assignment 1
Software assignment 1
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 

Similar to Professional practice 2

Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
Yee Len Wan
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
Lin Hui
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
EdenBekele5
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
Loay Ghazaleh MBA, BSc Civil Eng.
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
Ayush Joshi
 
Seminar
SeminarSeminar
Seminar
kohwenqi
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
Farah Sham
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
Kai Yun Pang
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
mohammedAlmusawi11
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
Avinash Kumar Gupta
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
Werksmans Construction & Engineering Seminar - Jason Smit presentation
Werksmans Construction & Engineering Seminar - Jason Smit presentationWerksmans Construction & Engineering Seminar - Jason Smit presentation
Werksmans Construction & Engineering Seminar - Jason Smit presentation
Werksmans Attorneys
 

Similar to Professional practice 2 (20)

Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Seminar
SeminarSeminar
Seminar
 
Site Possession
Site PossessionSite Possession
Site Possession
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Pp2 p7
Pp2   p7Pp2   p7
Pp2 p7
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Werksmans Construction & Engineering Seminar - Jason Smit presentation
Werksmans Construction & Engineering Seminar - Jason Smit presentationWerksmans Construction & Engineering Seminar - Jason Smit presentation
Werksmans Construction & Engineering Seminar - Jason Smit presentation
 

More from ahmong4

Be slides
Be slidesBe slides
Be slides
ahmong4
 
Final csi slides
Final csi slidesFinal csi slides
Final csi slides
ahmong4
 
BREAKDOWN OF COST CALCULATIONS
BREAKDOWN OF COST CALCULATIONSBREAKDOWN OF COST CALCULATIONS
BREAKDOWN OF COST CALCULATIONS
ahmong4
 
BENCHMARK PROJECT ALLOCATION
BENCHMARK PROJECT ALLOCATIONBENCHMARK PROJECT ALLOCATION
BENCHMARK PROJECT ALLOCATION
ahmong4
 
cost appraisal
cost appraisalcost appraisal
cost appraisal
ahmong4
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0
ahmong4
 
Fm assignment
Fm assignmentFm assignment
Fm assignment
ahmong4
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
ahmong4
 
Csi journal
Csi journalCsi journal
Csi journal
ahmong4
 
Measurement 4
Measurement 4Measurement 4
Measurement 4
ahmong4
 
Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)
ahmong4
 
Final es4 sorry boss pdf
Final es4 sorry boss pdf Final es4 sorry boss pdf
Final es4 sorry boss pdf
ahmong4
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
ahmong4
 
Pp1 group presentation
Pp1 group presentation Pp1 group presentation
Pp1 group presentation
ahmong4
 
Eca presentation slides
Eca presentation slidesEca presentation slides
Eca presentation slides
ahmong4
 
Eca forms final
Eca forms final Eca forms final
Eca forms final
ahmong4
 
Estimating presentation 1
Estimating presentation 1Estimating presentation 1
Estimating presentation 1
ahmong4
 
Software app slides
Software app slidesSoftware app slides
Software app slides
ahmong4
 
Software full
Software fullSoftware full
Software full
ahmong4
 
Mong construction techonology 3 report
Mong construction techonology 3 reportMong construction techonology 3 report
Mong construction techonology 3 report
ahmong4
 

More from ahmong4 (20)

Be slides
Be slidesBe slides
Be slides
 
Final csi slides
Final csi slidesFinal csi slides
Final csi slides
 
BREAKDOWN OF COST CALCULATIONS
BREAKDOWN OF COST CALCULATIONSBREAKDOWN OF COST CALCULATIONS
BREAKDOWN OF COST CALCULATIONS
 
BENCHMARK PROJECT ALLOCATION
BENCHMARK PROJECT ALLOCATIONBENCHMARK PROJECT ALLOCATION
BENCHMARK PROJECT ALLOCATION
 
cost appraisal
cost appraisalcost appraisal
cost appraisal
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0
 
Fm assignment
Fm assignmentFm assignment
Fm assignment
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
 
Csi journal
Csi journalCsi journal
Csi journal
 
Measurement 4
Measurement 4Measurement 4
Measurement 4
 
Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)
 
Final es4 sorry boss pdf
Final es4 sorry boss pdf Final es4 sorry boss pdf
Final es4 sorry boss pdf
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
Pp1 group presentation
Pp1 group presentation Pp1 group presentation
Pp1 group presentation
 
Eca presentation slides
Eca presentation slidesEca presentation slides
Eca presentation slides
 
Eca forms final
Eca forms final Eca forms final
Eca forms final
 
Estimating presentation 1
Estimating presentation 1Estimating presentation 1
Estimating presentation 1
 
Software app slides
Software app slidesSoftware app slides
Software app slides
 
Software full
Software fullSoftware full
Software full
 
Mong construction techonology 3 report
Mong construction techonology 3 reportMong construction techonology 3 report
Mong construction techonology 3 report
 

Recently uploaded

Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 

Recently uploaded (20)

Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 

Professional practice 2

  • 1. PROFESSIONAL PRACTICE 2 CHRISTINA HO CHIA HUI LOO SIAH MONG YEONG POH LING
  • 3. INTRODUCTION Construction delays arising during construction which cause completion date to be breached
  • 4. DELAYS Categories of delays : - ➢ Delay caused by Contractor (Clause 21.1) ➢ Delay caused by Employer (Clause 23.8) - 15 relevant events ➢ Delay caused by Third Parties ( Neutral Event) (Clause 23.8) - 9 relevant events
  • 5. DELAY BY CONTRACTOR Reasons : ● Not having sufficient labour force or plant on site ● Not having necessary materials when needed ● Poor site management/co-ordination/experience ● Failure to pay workers or sub-contractors Contractual Effects : ● Not entitle to claim for EOT ● No reimbursement for loss and expense ● Employer can be compensated by the way of LD ● Employer may terminate the contractor’s employment if delay is too long
  • 6. DELAY BY EMPLOYER 15 Relevant Events under clause 23.8 Contractual Effects : ● Contractor entitlement to claim for EOT ● Contractor entitle to claim for loss and expense ● Employer cannot impose LD because is own fault ● If delay is serious, contractor can terminate his employment
  • 7. DELAY BY THIRD PARTIES (NEUTRAL EVENTS) ● Weather, Act of God, Natural Justices ● 9 Relevant Events ● Not the fault of contractor or employer ● They have to bare with their own responsibilities Contractual Effects : ● Contractor entitled to EOT ● Contractor not entitled to lose and expense ● Employer cannot imposed LD ● Contractor and employer should share the burden of delay
  • 8. EXTENSION OF TIME Procedure of EOT STEP 1 : Giving of notice - Must give a written notice of intention to claim for EOT. It is a condition precedent to any EOT. STEP 2 : Official Application - Must submit official application within 28 days after the end of the event.
  • 9. EXTENSION OF TIME 1. Decision to claim for EOT ( is up to the contractor ) 2. Failure to submit claim application 3. Written notice shall be a condition precedent to an entitlement of EOT Case Study 1: Syarikat Tan Lim Bent & Rakan-Rakan v Pulai Jaya S/B (1992) It was held that this is an expressed condition, contractor must comply. Contractor may lose the case because he failed to submit written notice. Case Study 2 : Turner Corporation Ltd v Austotel Pty Ltd (1997) It was held contractor cannot rely on acts of prevention by employer for not giving written notice. He must give notice which would have negated the effect of that preventing conduct.
  • 10. Principles for Granting EOT (Architect have to make decision) 1. Before granting EOT, architect have to consider certain items - In writing - Have materially disrupted the regular progress of works - Fall within clause 23.8 - Nett effective delay must be assessed based on approved - Prevent further losses or delays work programme 2. Issue of the certificate of EOT (Architect have to make 2 decision) - Reject totally with reasons - Grant an appropriate EOT and issue certificate of EOT
  • 11. 3. Timing of Issue - Within 6 weeks from the contractor's application, architect must decide an issue 4. Delay by NSC 5. Obligations of Architect - To assess the length of EOT, architect must act reasonably, fairly and impartially - Failure to assess application and issue EOT is a breach
  • 12. 6. Consequences of Not Granting Contractor’s Application ● If architect default in granting EOT ● Employer will loses the rights to impose liquidated damages ● It is a breach of contract ● Architect liable to the employer in tort (negligence) / for breach of contract (services) For contractor, initial course of action : i) Make a fresh application ii) Appeal to employer iii) Contractor can refer the dispute to Arbitration
  • 13. Can EOT be granted Prospectively or Retrospectively? 1. Clause 23.4 - Architect may issue the written notice of rejection or the certification of EOT before / after the Completion Date - Architect can make & approve EOT backward / forward 2. Situations can arise - Contractor’s submission of his particulars under clauses 23 very near to the completion date 3. Retrospectively - Contractor submit one week before the completion date - Architect will assess EOT after completion date
  • 14. EOT After The Issuance Of Certificate of Non-Completion(CNC) 1. If contractor doesn’t complete, architect must issue CNC to contractor. If not employer cannot impose liquidated damages 2. When clause 23.9 is read together with clause 22.3 the granting of subsequent EOT will revoke the CNC 3. When CNC is cancelled, employer have to return the surplus liquidated damages. 4. If contractor again fails to complete by the new completion date, a new CNC will be issued by architect.
  • 15. EOT PROVISIONS ● Employer cannot set new completion date ● Contractor have to complete within a reasonable time ● Time become at large ● Employer loses the rights to impose liquidated damages EOT PROVISIONS ● Completion date can be extended, if there is a delay ● Employer can set new completion date ● Preserves employer’s contractual rights to impose liquidated damages ● Prevents time become at large
  • 16. Implications Of Time For Completion Being At Large 1. Original completion date no longer apply 2. there is no definite completion date to work towards 3. Contractor have to complete within a reasonable time 4. Employer loses his right to imposes liquidated damages 5. Contractor’s liability is limited to general damages
  • 17. LIQUIDATED DAMAGES In order to a successful claim for liquidated damages, Employer have to comply with the following pre-conditions : ➢ Contract contains express clause enabling the deduction of the liquidated damages ➢ The liquidated clause must be valid and enforceable ➢ Details of liquidated damages must be clearly indicated ➢ Specific contractual procedure must be strictly complied ➢ Must be definite date fixed in contract from which damages can run ➢ Employer has not waived his right to deduct the liquidated damages Amount of damages that need to be paid to the injured party to collect as compensation upon a specific breach in a contract.
  • 18. CASE STUDY Case 1 ➢ Selva Kumar a/l Murugiah v. Thiagarajah a/l Retnasamy [1995] 2 MLJ 817 Case 2 ➢ Johor Coastal Development Sdn Bhd v. Constrajaya Sdn Bhd [2009] 4 CLJ 569
  • 19. Question 1: As a Consultant assessing an extension of time application by the Contractor, what are the initial checklist and the principles to be applied?
  • 20. ● The application must be in writing ● Causes of delay must be under Clause 23.8 ● Contractor must have taken all practical steps to mitigate ● Delays must be ‘materially’ disrupted the regular progress of the works, resulting in the completion date being breached ● The ‘nett effective’ delay must be assessed based on approved work programme under Clause 3.5
  • 21. Question 2: What are the purpose of an extension of time clauses in most standard contract and its implications? What is the implication of a Certificate of Non-Completion? What is the difference between general damages and liquidated damages?
  • 22. Purpose of EOT Employer entitled to impose liquidated damages due to the delay caused by contractor. Contractor in will be granted EOT due to delays caused by employer. (Clause 23.8) If there is no EOT provision, the contractor’s liability will be limited to general damages not liquidated damages. Implication of EOT If there is EOT provision, completion date can be extended and new completion date can be set. It preserves the employer’s contractual right to impose liquidated damages to the contractor. It also prevent the completion time to be ‘at large’. If there is no EOT provision, time will be ‘at large’, contractor will have to complete the project at a reasonable time.
  • 23. Implication of certificate of Non completion ( 22.3 & 23.9) A formal return notice for the contractor, it gives the employer the right to impose liquidated damage to the contractor. If EOT is issued after issuance of CNC, employer shall return the surplus amount of liquidated damages imposed to the contractor. General damages Liquidated Damages No EOT provision With EOT provision Hard to prove (no basis to follow) Easier to prove ( master programme as basis) No fixed amount Fixed amount Differences between General damages & Liquidated damages
  • 24. Question 3: What are concurrent delays? Is the Contractor entitled to extension of time and loss and expense if there are concurrent delays by Employer and Contractor?
  • 25. Concurrent Delays ● Simultaneous delays caused by the contractor and employer ● Two or more delay events occurring within the same time period ● Affecting the project schedule and project completion date ● but not all of those events enable to claim an extension of time or loss and expense Contractor entitled to extension of time and loss and expense if ● Have the valid reason and certify by Architect and consultant Quantity Surveyor.
  • 26. QUESTIONS Q1 : What are the effects of construction projects delay? Q2 : What are the examples of grounds for challenging extension of time certificate ? (In what event can the contractor challenge the EOT certificate that is issued by the Architect?) Q3 : If Nominated Sub-Contractor goes bankrupt, can the contractor claim for EoT? If yes what is the relevant clause?
  • 27. ANSWER FOR Q1 ➢ Cost overrun - Contractor extend insurance policies (claimable) - Contractor’s fault, employer has the rights to impose liquidated damages ➢ Time overrun - Contractor claims for EOT - New completion date ➢ Dispute (Arbitration)
  • 28. ANSWER FOR Q2 ➢ Certificate not given time ➢ Certificate no in the correct format ➢ Certificate issued by unauthorised person ➢ Addressee of certificate not named ➢ Decision to extend time improperly delegated ➢ Certificate not given fairly ➢ Contractual procedures not followed

Editor's Notes

  1. Delays of a project can be categorised into 3 categories which are delays caused by contractor, employer and third parties which is the neutral event
  2. The common delay caused by the contractor are not having sufficient labour force or plant on site, not having necessary materials when needed (not enough materials which caused work cannot be done until the next delivery of materials), poor site management/co-ordination/ lack of experience( do not know how to plan properly), and lastly failure to pay workers or sub-contractors. If a delays is caused by contractor, contractor have to compesate employer by the way of LD. Contractor is not entitled to claim for EOT, no reimbursement for loss and expenss, employer can be compesated by the way of LD, and employer may terminate the contractor ‘s employment if delay is too long.
  3. . For the delay caused by employer is listed under clause 23.8 If the causes of delay are fall under this clause, the contractor is entitle to claim for EOT. If delay is caused by employer, contractor entitle to claim for EOT, contractor get monetary compesation by way of lose and expense, employer cannot impose LD because is his own fault,and if the delay is so serious, the contractor may want to terminate the employment.
  4. For the delay caused by neutral events which are the weather,act of god and the natural justices. There are 9 relevant events in the PAM Contract. Neutral events is not the fault of the contractor and employer as well. They have to bare with their own responsibilities. The contractor is entitled to claim for EOT but will not be compensated with money because not employer’s fault, employer cannot imposed LD as it is not the contractor fault, contractor and employer should share the burden of delay since nobody fault.
  5. Case 1: employer was ask by the federal court to prove the actual damage even though under clause 22.2 reads that both party is agreed with the amount stated in the contract. Case 2: Employer still have to prove the actual damage. Court had made decision where there will be some case that damage can be easily calculated that will have to prove and some case that calculation is complex does not need to prove. The decision is still up to the court decision whether it is a complex or non complex case. JKR (diff) JKR- no notice required to apply for EOT
  6. As a consultant assessing an extension of time application by contractor, the initial checklist and the principles to be applied are the consultants have to check whether the application is in writing form. The causes of delay must be fall within Clause 23.8. If it is not under this clause then it will be rejected. Contractor must have taken all practical steps to mitigate the delay which to prevent further losses or prevent further delay. The delays must be materially disrupted the completion date or the progress of the works, if it does not affect then cannot claim for EOT. The nett effective delay must be assessed based on approved work programme.The approved work programme is the basis of the EOT. EOT cannot be claimed without work programme. Clause 3.5 mentioned that master programme must submit within 2 weeks from the date of letter of award for approval.
  7. PURPOSE It gives the benefits to the employer to impose liquidated damages to the contractor if its contractor’s default in causing the delays. It gives benefits to the contractor to have extended time in completing the project due to the delays caused by employer under clause 23.8 relevant event. In the event if there is no EOT provision, the contractor’s liability will be limited to general damages not liquidated damages. IMPLICATION If its contractor default in delaying the works, it gives the right to the employer impose liquidated damages to the contractor. If it's employer default, the contractor will be granted for EOT contractor will (avoid the liability to pay to pay liquidated damages). If there is no EOT provision, time will be at large, contractor will have to complete the project at a reasonable time.
  8. This certificate gives the formal return notice for the contractor to inform the contractor that they have failed to complete their works on time agreed in the contract and it gives the employer the right to impose liquidated damage to the contractor. In the event if EOT is issued after issuance of CNC, employer is to return the surplus amount of liquidated damages to the contractor. General damages is only exist if there is no EOT provision in the contract while LD is an agreed amount stated in the contract by both parties in the event if any party breach the contract.