SlideShare a Scribd company logo
THERMAL POWER PLANT
OPERATIONS
Simulator Part 1- Day1
MANOHAR TATWAWADI
Director, tops
9372167165, mtatwawadi@gmail.com
ELECTRICAL CHARGING
• The first step is to establish power supply for
the auxiliaries at least for cooling water /GS
water pumps
• The power supply will be required for the
Instrument Air and Service air compressors.
• For Station Lighting , other station auxiliaries
and in the Water Treatment Plant.
• The power supply may be taken from the
440/220KV GRID by Station Transformers
Care to be Taken
• Get the clearance from Switchyard for charging the
400kv/220kv breakers of the station transformers.
• Check that all CTs & PTs in the switchyard are in order
• Before charging breaker, check the isolators.
• Generally always charge the HV side breaker of the
transformers first
• Mostly all 11kv, 6.6kv, 415V boards are charged from
both sides with their respective Bus Couplers in OFF
position
• Before charging check all the transformer protections
are in service.
STATION TRANSFORMER
• All the Electrical Supply required for the station is from
the Station Transformer (generally a (220/400)/6.6KV).
The station transformer capacity is approximately 20%
of the generating capacity. The supply may be changed
over to Unit Auxiliary Transformer, after the unit is
synchronized.
• The 6.6 KV station boards are charged by charging the
station transformer from the HV side (220/400KV side)
of the transformer first. The isolators of the 400kv side
breaker are closed and then the breaker is made ON.
• The incomers to the station boards are made ON to
charge the bus bars in the Board.
CHARGING OF STATION BOARDS
CHARGNG OF UNIT BOARDS 6.6 KV (UAT A & UAT B)
UNIT TRANSFORMER
16.5KV /6.6KV 20/25MVA
UNIT TRANSFORMER
16.5KV /6.6KV 20/25MVA
Charging of LT 6.6kv/440V Boards
• Charge Boiler Boards
• Charge Turbine Boards
• Station Service Boards
• Standby Board
• New Emergency Board
• Emergency Board and
• Main Lighting Distribution Board
CHARGING OF GS AND DM WATER
• The River water Pumps, pump water for the whole
requirement of water to the TPS. This water pumped
by the RWP is sent to the WT Plant where it is treated
& stored and then made available as G.S. water.
• The General water service pumps for all auxiliaries
cooling systems are started and all cooling water
systems are charged. The overhead GS water tanks are
also filled up. The tanks are provided so as to act as
buffer in case the pumps trip or not available for some
time.
Water Cycle Establishment
• General Water System will be charged first so that it
caters the need of cooling water to all auxiliaries.
• Two GS Pumps will be started for the purpose.
• Instrument Air and Service Air Compressors will be
started when cooling water is available
• The WT Plant will be started and DM water from the
WT Plant will be made available
• DM Intermediate Tank will be filled to its full capacity.
• DM Makeup will be started for filling DM Overhead
tanks.
CHARGING OF GS WATER
The General water service pumps for all auxiliaries cooling systems are started and all cooling water systems are
charged. The overhead GS water tanks are also filled up. The tanks are provided so as to act as buffer in case the
pumps trip or not available for some time.
Charging of DM and GS Water
• After the cooling water is available for Instrument and
service air compressors, the compressors can be
started and Instrument and Service air is made
available for the operation of valves, Atomisation etc.
• From the WT Plant, the DM water will be available
now. The Intermediate DM Tank is filled up by opening
valves DM4 and DM5 and DM Makeup pumps can be
started after the Intermediate Tank Level reaches more
than 2M.
• There are two Emergency DM tanks provided in case
of failure of DM Pumps. These tanks are filled by DM
Makeup Pumps by opening the respective valves.
TYPICAL DM MAKEUP SYSTEM
DM MAKEUP AND COND CYCLE
• The Unit Drain Tank and Condenser may be filled up
with the help of DM Make up pumps by opening the
respective valves. (UDT level 2M & Condenser Level
3M).
• The Condensate Cycle can be taken into service at this
time. There are Three No of CEPs. Two are running and
one standby. The First CEP to be started is started with
its Discharge Bypass valve 10% open, so that it
develops some header pressure. (More than
14kg/cm2, otherwise the started CEP will trip on “CEP
Discharge Header Pressure Low”.) Once a pressure of
20kg/cm2 is reached, the discharge valve of the CEP is
opened.
DM MAKEUP AND COND CYCLE
• Before the CEP is started the condensate line
upto the deaerator is made through (All Heaters
Inlet / Outlet Valves open & Bypass Valves
Closed). The main Condenser level control valve
is also kept closed. (MC36 Valve closed).
• After starting the CEP and opening the discharge
valve, Main Condenser level Control Valve (MC36)
can be opened and the flow to Deaerator can be
observed.
CONDENSATE CYCLE CHARGING
The Deaerator can now be filled up by opening the Main Condensate Control Valve MC36
slightly. (About 5%). The Condenser Hotwell Level in the process will come down. The
Condensate Level has to be maintained by the Condensate makeup valve CV6 or CV7. Once
the Deaerator level reaches to about 4M close the Main Condensate Control Valve MC36 and
stop the make up to condenser
BOILER DRUM FILLING & Feed water system
• The Vents of the boiler drum shall be opened for boiler drum
filling. Also the Economiser Recirculation Valve must be
opened before starting the boiler drum filling. By starting
Boiler Filling Pump and making the circuit through for boiler
filling through the Boiler Drain header, the Boiler Drum can
now be filled up to NORMAL Level. (0.6 M).
• Boiler Drum can also be filled by opening the Feed Control
Station Low Load Line valves, the economizer inlet valve and
the boiler filling pump discharge line to FCS valve.
• After the drum Filling is done up to the normal Level , the
boiler filling valve can now be closed. The Economiser vent
valves shall also be closed as water comes out from
Economoser Vents.
• The Drum Vents and the Economiser Recirculation will be
kept open, till there is pressure in the boiler drum.
FEED WATER SYSTEM & BOILER DRUM FILLING
Feed water system
Turbine Side Activities
• Start AC LOP, AC Seal Oil Pump
• After filling the oil lines fully, start Starting Oil Pump,
observe Relay Oil Pressure 18kg/cm2.
• Lubricating Oil Pressure 4kg/cm2 before oil coolers and
1kg/cm2 after coolers
• Take trials of DC LOP and DC Seal Oil Pumps by tripping the
respective AC Pumps.
• Stop AC Lub oil and AC Seal oil Pumps. Start JOP
• Check the lub oil and seal oil pressures, if OK
• Start Barring Gear motor and check the speed of the
turbine rotor.
• Start the Hydrogen Filling in the Generator. Observe the
pressure and Purity of Hydrogen in the Generator
TURBINE OIL SYSTEM 270 MW
Seal Oil System 210 MW
Hydrogen Filling in Generator
We have Achieved
• Whole Thermal Power Plant has been electrified
• GS water made available to all auxiliaries for cooling.
Overhead GS Tank Levels 3.5M
• Cooling Towers taken in service
• Instrument Air/ Service Air Pressure 6.5kg/cm2
• Unit Drain Tank, Emergency DM Tank, Condenser,
Deaerator and boiler drum filled with DM water.
• Condensate cycle charged with DM water
• Starting Oil Pump for Turbine Lub Oil, Seal Oil and relay oil
started.
• Turbine Rotor put on barring
• Hydrogen filling in Generator started.
We have Achieved
• Instrument air/service air pressure 6.5kg/cm2
• DM Intermediate Tank Level 4.5M
• Unit Drain Tank Full to its capacity
• Condenser Hotwell Level 3M
• Deaerator Level 4M
• Boiler Drum Level 0.6M
• SOP running, AC Lub oil & Seal oil Pumps OFF
Governing Oil Pres. 18kg/cm2,
• H2/seal oil Differential Pressure 0.9 to 1 kg/cm2
• Lub oil pres. 4kg/cm2, 1kg/cm2 before, after cooler.
• Barring gear ON Turbine rotor speed 3 to 4 RPM
Operational Tests
• Condenser level low, Deaerator level low,
Boiler Drum level low, UDT level low and DM
intertank level low reset.
• Starting of DC Lub oil and Seal oil Pumps on
Turbine lub oil pr low, seal oil pr low.
• Airheater AC motor tripping and DC / Air
motor starting
• All aux are getting cooling water
THERMAL POWER PLANT OPERATIONS

More Related Content

What's hot

Condensate system
Condensate systemCondensate system
Condensate system
RAVI PAL SINGH
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)
Billa ParameswaraRao
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
Gaurav Kaushik
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
Nitin Patel
 
Aprds system
Aprds systemAprds system
Aprds system
Arpit Shrivastava
 
TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE
Manohar Tatwawadi
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Manohar Tatwawadi
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
SURAJ KUMAR
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
Manohar Tatwawadi
 
210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING 210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING
Nitin Patel
 
660 mw turbo governing & protection system
660 mw turbo  governing & protection system660 mw turbo  governing & protection system
660 mw turbo governing & protection system
Ashvani Shukla
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations Training
Manohar Tatwawadi
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
SHIVAJI CHOUDHURY
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
anujkumarsingh79
 
Heat rate of thermal power plant
Heat rate of thermal power plantHeat rate of thermal power plant
Heat rate of thermal power plant
Manohar Tatwawadi
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
Ashish Kumar Jain
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
SHIVAJI CHOUDHURY
 
Boiler circulation theory
Boiler circulation theoryBoiler circulation theory
Boiler circulation theory
NaumanKalshekar
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to Knowledge
Anshuman Tyagi
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
Manohar Tatwawadi
 

What's hot (20)

Condensate system
Condensate systemCondensate system
Condensate system
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
Aprds system
Aprds systemAprds system
Aprds system
 
TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
 
210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING 210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING
 
660 mw turbo governing & protection system
660 mw turbo  governing & protection system660 mw turbo  governing & protection system
660 mw turbo governing & protection system
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations Training
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
Heat rate of thermal power plant
Heat rate of thermal power plantHeat rate of thermal power plant
Heat rate of thermal power plant
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Boiler circulation theory
Boiler circulation theoryBoiler circulation theory
Boiler circulation theory
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to Knowledge
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
 

Similar to THERMAL POWER PLANT OPERATIONS

EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
suryanshsingh836763
 
Turbine operation.pptx
Turbine operation.pptxTurbine operation.pptx
Turbine operation.pptx
DhananjayaTripathy1
 
TG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.pptTG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.ppt
soumenmandal47
 
Turbine Start Up.pptx
Turbine Start Up.pptxTurbine Start Up.pptx
Turbine Start Up.pptx
ssuser0cdaa1
 
Piping system
Piping systemPiping system
Piping system
Rajneesh20042010
 
Hydro Power Plant Auxaleries
Hydro Power Plant AuxaleriesHydro Power Plant Auxaleries
Hydro Power Plant Auxaleries
Mahajan Saurabh
 
Power Plant Simulator, Unloading and shutting the Turbogenerator
Power Plant Simulator, Unloading and shutting the TurbogeneratorPower Plant Simulator, Unloading and shutting the Turbogenerator
Power Plant Simulator, Unloading and shutting the Turbogenerator
Manohar Tatwawadi
 
Boiler ppt
Boiler pptBoiler ppt
Boiler ppt
Er Ramgarhia
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
MBouderbala
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
yusuf699644
 
Oil production 2
Oil production 2Oil production 2
Oil production 2
Muhammed Lateef
 
Power Plant Operations.pdf
Power Plant Operations.pdfPower Plant Operations.pdf
Power Plant Operations.pdf
Manohar Tatwawadi
 
Final Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxFinal Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptx
BhimarajuKanireddy
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
ssuser9e9be71
 
Module 1 heating - steam (wecompress.com)
Module 1   heating - steam (wecompress.com)Module 1   heating - steam (wecompress.com)
Module 1 heating - steam (wecompress.com)
DeepakSingh1807
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
ssuser8006c7
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
ArmaanKhan92
 
Rankine
RankineRankine
POWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEPOWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINE
Manohar Tatwawadi
 
Inspection and Testing of various electrical equipment
Inspection and Testing of various electrical equipmentInspection and Testing of various electrical equipment
Inspection and Testing of various electrical equipment
AkankshaSharma570781
 

Similar to THERMAL POWER PLANT OPERATIONS (20)

EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
 
Turbine operation.pptx
Turbine operation.pptxTurbine operation.pptx
Turbine operation.pptx
 
TG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.pptTG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.ppt
 
Turbine Start Up.pptx
Turbine Start Up.pptxTurbine Start Up.pptx
Turbine Start Up.pptx
 
Piping system
Piping systemPiping system
Piping system
 
Hydro Power Plant Auxaleries
Hydro Power Plant AuxaleriesHydro Power Plant Auxaleries
Hydro Power Plant Auxaleries
 
Power Plant Simulator, Unloading and shutting the Turbogenerator
Power Plant Simulator, Unloading and shutting the TurbogeneratorPower Plant Simulator, Unloading and shutting the Turbogenerator
Power Plant Simulator, Unloading and shutting the Turbogenerator
 
Boiler ppt
Boiler pptBoiler ppt
Boiler ppt
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Oil production 2
Oil production 2Oil production 2
Oil production 2
 
Power Plant Operations.pdf
Power Plant Operations.pdfPower Plant Operations.pdf
Power Plant Operations.pdf
 
Final Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxFinal Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptx
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
Module 1 heating - steam (wecompress.com)
Module 1   heating - steam (wecompress.com)Module 1   heating - steam (wecompress.com)
Module 1 heating - steam (wecompress.com)
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
 
Rankine
RankineRankine
Rankine
 
POWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEPOWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINE
 
Inspection and Testing of various electrical equipment
Inspection and Testing of various electrical equipmentInspection and Testing of various electrical equipment
Inspection and Testing of various electrical equipment
 

More from Manohar Tatwawadi

Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3
Manohar Tatwawadi
 
Green building concepts and good building practices
Green building concepts and good building practicesGreen building concepts and good building practices
Green building concepts and good building practices
Manohar Tatwawadi
 
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler EfficiencyAuxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
Manohar Tatwawadi
 
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIESCOMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
Manohar Tatwawadi
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
Manohar Tatwawadi
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1
Manohar Tatwawadi
 
Cooling towers in thermal power plants
Cooling towers in thermal power plantsCooling towers in thermal power plants
Cooling towers in thermal power plants
Manohar Tatwawadi
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stations
Manohar Tatwawadi
 
Cost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSCost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPS
Manohar Tatwawadi
 
Environmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power StationsEnvironmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power Stations
Manohar Tatwawadi
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Manohar Tatwawadi
 
Fuels and Combustion Equations
Fuels and Combustion EquationsFuels and Combustion Equations
Fuels and Combustion Equations
Manohar Tatwawadi
 
Basics of thermal power stations
Basics of thermal power stationsBasics of thermal power stations
Basics of thermal power stations
Manohar Tatwawadi
 
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / MillsEffect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Manohar Tatwawadi
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
Manohar Tatwawadi
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
Manohar Tatwawadi
 
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
Manohar Tatwawadi
 
Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power Plants
Manohar Tatwawadi
 
Swot Analysis
Swot AnalysisSwot Analysis
Swot Analysis
Manohar Tatwawadi
 
Boiler Drum level measurement in Thermal Power Stations
Boiler Drum level measurement in Thermal Power StationsBoiler Drum level measurement in Thermal Power Stations
Boiler Drum level measurement in Thermal Power Stations
Manohar Tatwawadi
 

More from Manohar Tatwawadi (20)

Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3
 
Green building concepts and good building practices
Green building concepts and good building practicesGreen building concepts and good building practices
Green building concepts and good building practices
 
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler EfficiencyAuxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
 
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIESCOMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1
 
Cooling towers in thermal power plants
Cooling towers in thermal power plantsCooling towers in thermal power plants
Cooling towers in thermal power plants
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stations
 
Cost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSCost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPS
 
Environmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power StationsEnvironmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power Stations
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
 
Fuels and Combustion Equations
Fuels and Combustion EquationsFuels and Combustion Equations
Fuels and Combustion Equations
 
Basics of thermal power stations
Basics of thermal power stationsBasics of thermal power stations
Basics of thermal power stations
 
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / MillsEffect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / Mills
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
 
Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power Plants
 
Swot Analysis
Swot AnalysisSwot Analysis
Swot Analysis
 
Boiler Drum level measurement in Thermal Power Stations
Boiler Drum level measurement in Thermal Power StationsBoiler Drum level measurement in Thermal Power Stations
Boiler Drum level measurement in Thermal Power Stations
 

Recently uploaded

Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Design and optimization of ion propulsion drone
Design and optimization of ion propulsion droneDesign and optimization of ion propulsion drone
Design and optimization of ion propulsion drone
bjmsejournal
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
riddhimaagrawal986
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 

Recently uploaded (20)

Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Design and optimization of ion propulsion drone
Design and optimization of ion propulsion droneDesign and optimization of ion propulsion drone
Design and optimization of ion propulsion drone
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 

THERMAL POWER PLANT OPERATIONS

  • 1. THERMAL POWER PLANT OPERATIONS Simulator Part 1- Day1 MANOHAR TATWAWADI Director, tops 9372167165, mtatwawadi@gmail.com
  • 2. ELECTRICAL CHARGING • The first step is to establish power supply for the auxiliaries at least for cooling water /GS water pumps • The power supply will be required for the Instrument Air and Service air compressors. • For Station Lighting , other station auxiliaries and in the Water Treatment Plant. • The power supply may be taken from the 440/220KV GRID by Station Transformers
  • 3. Care to be Taken • Get the clearance from Switchyard for charging the 400kv/220kv breakers of the station transformers. • Check that all CTs & PTs in the switchyard are in order • Before charging breaker, check the isolators. • Generally always charge the HV side breaker of the transformers first • Mostly all 11kv, 6.6kv, 415V boards are charged from both sides with their respective Bus Couplers in OFF position • Before charging check all the transformer protections are in service.
  • 4. STATION TRANSFORMER • All the Electrical Supply required for the station is from the Station Transformer (generally a (220/400)/6.6KV). The station transformer capacity is approximately 20% of the generating capacity. The supply may be changed over to Unit Auxiliary Transformer, after the unit is synchronized. • The 6.6 KV station boards are charged by charging the station transformer from the HV side (220/400KV side) of the transformer first. The isolators of the 400kv side breaker are closed and then the breaker is made ON. • The incomers to the station boards are made ON to charge the bus bars in the Board.
  • 6. CHARGNG OF UNIT BOARDS 6.6 KV (UAT A & UAT B) UNIT TRANSFORMER 16.5KV /6.6KV 20/25MVA UNIT TRANSFORMER 16.5KV /6.6KV 20/25MVA
  • 7. Charging of LT 6.6kv/440V Boards • Charge Boiler Boards • Charge Turbine Boards • Station Service Boards • Standby Board • New Emergency Board • Emergency Board and • Main Lighting Distribution Board
  • 8. CHARGING OF GS AND DM WATER • The River water Pumps, pump water for the whole requirement of water to the TPS. This water pumped by the RWP is sent to the WT Plant where it is treated & stored and then made available as G.S. water. • The General water service pumps for all auxiliaries cooling systems are started and all cooling water systems are charged. The overhead GS water tanks are also filled up. The tanks are provided so as to act as buffer in case the pumps trip or not available for some time.
  • 9. Water Cycle Establishment • General Water System will be charged first so that it caters the need of cooling water to all auxiliaries. • Two GS Pumps will be started for the purpose. • Instrument Air and Service Air Compressors will be started when cooling water is available • The WT Plant will be started and DM water from the WT Plant will be made available • DM Intermediate Tank will be filled to its full capacity. • DM Makeup will be started for filling DM Overhead tanks.
  • 10. CHARGING OF GS WATER The General water service pumps for all auxiliaries cooling systems are started and all cooling water systems are charged. The overhead GS water tanks are also filled up. The tanks are provided so as to act as buffer in case the pumps trip or not available for some time.
  • 11. Charging of DM and GS Water • After the cooling water is available for Instrument and service air compressors, the compressors can be started and Instrument and Service air is made available for the operation of valves, Atomisation etc. • From the WT Plant, the DM water will be available now. The Intermediate DM Tank is filled up by opening valves DM4 and DM5 and DM Makeup pumps can be started after the Intermediate Tank Level reaches more than 2M. • There are two Emergency DM tanks provided in case of failure of DM Pumps. These tanks are filled by DM Makeup Pumps by opening the respective valves.
  • 13. DM MAKEUP AND COND CYCLE • The Unit Drain Tank and Condenser may be filled up with the help of DM Make up pumps by opening the respective valves. (UDT level 2M & Condenser Level 3M). • The Condensate Cycle can be taken into service at this time. There are Three No of CEPs. Two are running and one standby. The First CEP to be started is started with its Discharge Bypass valve 10% open, so that it develops some header pressure. (More than 14kg/cm2, otherwise the started CEP will trip on “CEP Discharge Header Pressure Low”.) Once a pressure of 20kg/cm2 is reached, the discharge valve of the CEP is opened.
  • 14. DM MAKEUP AND COND CYCLE • Before the CEP is started the condensate line upto the deaerator is made through (All Heaters Inlet / Outlet Valves open & Bypass Valves Closed). The main Condenser level control valve is also kept closed. (MC36 Valve closed). • After starting the CEP and opening the discharge valve, Main Condenser level Control Valve (MC36) can be opened and the flow to Deaerator can be observed.
  • 15. CONDENSATE CYCLE CHARGING The Deaerator can now be filled up by opening the Main Condensate Control Valve MC36 slightly. (About 5%). The Condenser Hotwell Level in the process will come down. The Condensate Level has to be maintained by the Condensate makeup valve CV6 or CV7. Once the Deaerator level reaches to about 4M close the Main Condensate Control Valve MC36 and stop the make up to condenser
  • 16. BOILER DRUM FILLING & Feed water system • The Vents of the boiler drum shall be opened for boiler drum filling. Also the Economiser Recirculation Valve must be opened before starting the boiler drum filling. By starting Boiler Filling Pump and making the circuit through for boiler filling through the Boiler Drain header, the Boiler Drum can now be filled up to NORMAL Level. (0.6 M). • Boiler Drum can also be filled by opening the Feed Control Station Low Load Line valves, the economizer inlet valve and the boiler filling pump discharge line to FCS valve. • After the drum Filling is done up to the normal Level , the boiler filling valve can now be closed. The Economiser vent valves shall also be closed as water comes out from Economoser Vents. • The Drum Vents and the Economiser Recirculation will be kept open, till there is pressure in the boiler drum.
  • 17. FEED WATER SYSTEM & BOILER DRUM FILLING
  • 19. Turbine Side Activities • Start AC LOP, AC Seal Oil Pump • After filling the oil lines fully, start Starting Oil Pump, observe Relay Oil Pressure 18kg/cm2. • Lubricating Oil Pressure 4kg/cm2 before oil coolers and 1kg/cm2 after coolers • Take trials of DC LOP and DC Seal Oil Pumps by tripping the respective AC Pumps. • Stop AC Lub oil and AC Seal oil Pumps. Start JOP • Check the lub oil and seal oil pressures, if OK • Start Barring Gear motor and check the speed of the turbine rotor. • Start the Hydrogen Filling in the Generator. Observe the pressure and Purity of Hydrogen in the Generator
  • 21. Seal Oil System 210 MW
  • 22. Hydrogen Filling in Generator
  • 23. We have Achieved • Whole Thermal Power Plant has been electrified • GS water made available to all auxiliaries for cooling. Overhead GS Tank Levels 3.5M • Cooling Towers taken in service • Instrument Air/ Service Air Pressure 6.5kg/cm2 • Unit Drain Tank, Emergency DM Tank, Condenser, Deaerator and boiler drum filled with DM water. • Condensate cycle charged with DM water • Starting Oil Pump for Turbine Lub Oil, Seal Oil and relay oil started. • Turbine Rotor put on barring • Hydrogen filling in Generator started.
  • 24. We have Achieved • Instrument air/service air pressure 6.5kg/cm2 • DM Intermediate Tank Level 4.5M • Unit Drain Tank Full to its capacity • Condenser Hotwell Level 3M • Deaerator Level 4M • Boiler Drum Level 0.6M • SOP running, AC Lub oil & Seal oil Pumps OFF Governing Oil Pres. 18kg/cm2, • H2/seal oil Differential Pressure 0.9 to 1 kg/cm2 • Lub oil pres. 4kg/cm2, 1kg/cm2 before, after cooler. • Barring gear ON Turbine rotor speed 3 to 4 RPM
  • 25. Operational Tests • Condenser level low, Deaerator level low, Boiler Drum level low, UDT level low and DM intertank level low reset. • Starting of DC Lub oil and Seal oil Pumps on Turbine lub oil pr low, seal oil pr low. • Airheater AC motor tripping and DC / Air motor starting • All aux are getting cooling water