SlideShare a Scribd company logo
1 of 59
COMMISSIONING
HYDRO POWER STATION
Dam
Reservoir
Power intake (Penstock)
Power house
•Turbine
•Draft tube
•Main inlet valve
•Generator
•Bus Duct
•Field Excitation System
•Governing System
•SCADA System
•Station Transformer
•Balance of Plant
•Protection system & switchgear
•LV/ HV distribution
•DC, UPS Battery
Switch Yard
Following are the main components of a Hydroelectric Power Plant
INTRODUCTION
Dome
Stator
Rotor
Generator Shaft
Turbine Shaft
Spiral Casing
Stay Ring
Runner
Draft Tube
COMMISSIONING
Definition
•Testing of new equipments to check
its conformity with contractual
specifications, as well as operation of
the equipment until formally
accepted by the Customer.
•Commissioning usually occurs after
first erection of a new unit.
Commissioning
activities consist
of various tests:
•Pre-commissioning tests
•Prior to filling waterways
•After filling waterways
•Initial Run test
•Test Run
COMMISSIONING
READINESS CRITERION
Commissioning activities in hydro project begin with the filling of waterways on
the down stream side (common tailrace) and up stream side (Head Race or
Penstock) of the machine. This implies readiness of hydro set which broadly
comprises of following equipments and their readiness criteria :
1. Draft Tube and Liner, Spiral casing, Tail Race Channel, Penstock and gates etc. for
their erection and checks from the point of view of cleanliness, civil grouting work for
the hollow portions between metal and concrete contact surfaces etc.
2. It is to be ensured that there is no impediments in the free flow of water from any
projecting lumps of concrete/reinforcement rods etc.
3. The grouting plugs have been welded and flush grinded as per Drawing requirement
and no obstruction exists from any local bending of metallic liners etc. in the water
path.
4. Painting work of underwater parts with black anticorrosive paint has been completed.
The Machine itself has been made ready mechanically along with its auxiliaries. This will
include the following major equipments/systems/works and other preparations :
Turbine & Turbine Pit :
1. Runner blade and chamber clearances have been checked and found OK to ensure that
no rubbing is likely to occur during start up and running.
2. Air inflated repair seal of Turbine shaft is ‘OFF’ and cooling water to working seal will
be available when CW system is charged.
3. Turbine bearing oil is at proper level – neither too high nor too low – let the drawing be
followed at this stage. Keep record of pumping holes in the skirt if provided-whether
plugged and how many.
4. Manual/Auto greasing of guide vanes etc. has been done for smooth operation.
5. Easy mobility along with sufficient lighting both AC/DC provided in the pit.
READINESS CRITERION
6. Dry stroking of guide apparatus/ MIV have been done upto full rated oil pressure of
OPU through governor. Record Opening/Closing and damping times.
7. Dowelling work etc. of bearing housing etc. has been completed.
8. Fulfillment of all requirements given in O&M manuals/check lists of the project to
be ensured.
9. De-watering of draft tube checked twice by closing the draft tube gates.
10. Turbine top cover drainage system is operational and in Auto to avoid turbine pit
flooding during first filling of TRC and subsequently during penstock filling etc.
Preferably additional pumping arrangement, not dependent on Electric Supply (i.e.
Air Operated) be provided as quantity of leakage water from shaft, Guide vane cup
seals, etc. is not known at this time. This is more necessary when starting a machine
after a long delay after erection.
READINESS CRITERION
Generator & Generator Barrel :
1. Generator and its sub assemblies have been fully erected as per drawing and cleaned
with dry compressed air/cloth. Check top and bottom air guide clearances which
should be at least 8-10 mm ( as per drawing requirement) from the rotor fan blades.
2. Stator/Rotor gap must be free from any foreign object which is usually checked by
taking a rope all around the gap along the full height of the stator core.
3. Check and ensure that Generator barrel/bracket areas are free from foreign objects,
hanging wires/cables, loose electrical connections, loose clamps etc.
4. Bearing vapour seal segments may not be assembled in position during initial runs to
avoid likelihood of rubbing until performance in terms of vibration and wobble is
proved up to full speed (This is not applicable for vapour seals of wool felt type).
5. Initial bedding of slip ring carbon brushes, cleaning of slip rings etc. has been done.
Carbon brushes to be kept disengaged from the slip rings, during initial runs as no
excitation is to be given during this time. Should be in for proper bedding .
READINESS CRITERION
6. Dowelling of stator frame/brackets etc. has been done and secondary concreting of
Stator and lower bracket foundations have fully cured. Epoxy grouting of foundation
bolts to be ensured. Tightening of all bolts and their locking particularly of the
rotor/rotor lead clamps/pole to pole joints etc. to be carefully checked.
7. Generator Barrel water mist Fire Extinguishing system commissioned and kept ready in
manual/Auto mode, which is to be switched on prior to voltage build up/
synchronisation/loading.
8. Brake system is already tested for reliable lifting and release 10 times from HP
compressor/pressure reducer air system or L P air system along with Limit Switch
operation for indication/control. Free operation of brakes to be ensured. Auto operation
of Brake is to be disabled during initial period (Brake Air Pressure should be adjusted
for 4-5 Kg/cm2 ). Brakes should be applied at a speed as given in design which is usually
20 to 25% of rated speed). Required oil should be filled up in air filter unit.
READINESS CRITERION
9. Generator bearing’s oil should be at proper level as per Drawing and this should be
marked in gauge glass. Operation of low/high level float switches should be checked.
10. Performance of HS Lube system to be proved. Check lifting of Rotor from HS lube
pressure by 4 dial gauges placed at  X and  Y positions i.e at 4 points to know
amount and uniformity of lift all around. The HS Lube pressure should not exceed
specified design value. Safety relief valve to be adjusted depending on the pressure
required for jacking. HP lub oil pressure switches/gauge to be adjusted for normal &
low pressure. Ensure no loose connections in the electrical circuits to avoid sparking
and consequent fire hazard in these enclosed spaces.
READINESS CRITERION
1. 440 V 3 Phase AC supply
2. 240 V 1 Phase A.C. supply
3. 220 V DC or 110 V D.C. Power supply system
4. 48 V DC Power supply system
5. Dewatering, Drainage and leakage collection system and their pumping arrangement.
6. 11 KV or 13.75 KV along with cable etc. for commissioning of excitation system.
7. 24 V DC power supply system.
8. The intake gates, draft tube gates and butterfly valves are tested for safe and reliable
operation and equipped with operator personnel and telephonic connection .
9. Oil supply system.
10. Compressed air system.
11. Completion of cable laying , termination @ earthing
12. 240 V AC UPS supply.
PRE- REQUISITES FOR
COMMISSIONING
13. Readiness of water conducting system .
14. Civil works in the vicinity of active and sensitive electrical and mechanical
machinery/equipment are finalized. Floors are clean and dry.
15. Station earthling system is in full and reliable condition.
16. Main fire fighting system for the power house cavern in safe operating
condition, including the portable fire extinguishers.
17. Ventilation, illuminations, communication, and Air-conditioning available
on a permanent base.
18. Readiness of protective covers, guards ladders and covering of floor holes
and pits.
PRE- REQUISITES FOR
COMMISSIONING
PRE-COMMISSIONING
TEST/CHECKS
Pre-
commissioning
Tests:
• Test between completion of
erection of the equipment and
initial run.
• Tests/Checks prior to filling
waterways
• Tests/Checks after filling of
waterways
TEST/CHECKS PRIOR TO
FILLING WATERWAYS
1. Inspection of all the turbine waterways and removal of all
foreign or loose objects.
2. Calibration of scales for wicket gate opening and where
applicable, for runner blades, needles and deflectors
including their cam relationships; and also measurement
of clearances.
3. Operation of pressure oil units, MIV, governors, automatic
and manually operated starting and stopping devices and
signaling devices.
4. Oil levels and pressures in governing system; Condition of
all oil filters.
TESTS/CHECKS PRIOR TO
FILLING WATERWAYS
5. Protective devices such as oil level and temperature alarms and
relays, with adjustment if needed.
6. Times of opening and closing of governing elements, i.e. wicket
gates, runner blades of turbines with movable blades, needles
and deflectors of impulse turbines.
7. MIV opening and closing times.
8. Bearing and seal clearances and functioning of hydrostatic
lubrication system.
TESTS/CHECKS PRIOR TO
FILLING WATERWAYS
9. Operation of drainage pumps and dewatering pumps.
10. Oil, grease and water supply to all bearings and seals
requiring lubrication or cooling.
11. Operation of braking system of the unit.
TESTS/CHECKS
AFTER FILLING WATERWAYS
1. The Tail water gate shall be opened first after filling the draft
tube and spiral case up to tail water level through a filling
valve of the draft tube gates. Check for leaks is to be made.
The whole waterway should be filled slowly and manually
through a bypass valve of the penstock.
2. Operation of emergency protection devices which actuates
the intake gate/MIV and closure of guide vanes and stoppage
of machine is to be checked.
3. If the protective devices and emergency closing system work
satisfactorily, and no unusual leakage or deformation is
observed, Initial run of the Machine can be initiated.
INITIAL RUN
After the permission for initial run, locking devices and brakes are
released and the turbine wicket gates or needles are opened
under manual control, slowly as per manufacturer’s
recommendations and bring the speed up to at least the minimum
stated value.
If any noise, scraping or other abnormal phenomena is observed,
the unit should be shut down immediately and thorough inspection
is to be carried out to find out the cause of the problem and rectify
the same.
•Time
•Unit speed
•Servomotor stroke
•Temperature of bearing
•Shaft run out
Measurements
Items:
•Tachometer
•Dial indicator
Instruments to
be used:
INITIAL RUN
TEST RUN
•Mechanical Spinning
without Excitation
•Spinning with Excitation
•Synchronization with the
grid
•Load run and Load
Rejection Tests
Test
Run
consists
of :
MECH. SPINNING WITHOUT
EXCITATION
1. The unit is kept under manual control at or above starting
speed until bearing temperatures are stabilized.
2. If any temperature is excessive or increases too rapidly, the
unit shall be shut down and the causes of this phenomenon is
to be investigated and corrected.
3. If all goes well, the unit speed shall be increased in
prearranged steps up to the rated value, remaining at each
successive speed until the rate of rise of all bearing
temperatures is satisfactory to the manufacturer's
recommendation.
During each speed step of test run, at least the following
measurements / observations should be made:
1. Deformation of covers and bearing supports
2. Noise or vibration in the turbine and/or generator
3. Operating conditions for the oil pressure and other pumps.
4. Condition of oil in the bearings and pressure oil systems. If
water is observed in oil, the leaks shall be located and
eliminated. If oil foaming is observed, the cause shall be
located and eliminated.
5. Temperatures of bearings and lubricating oil.
6. Shaft run out at turbine and generator bearings and axial
displacement of rotating parts is measured.
7. At some agreed speed value, the action of braking system
shall be checked.
MECH. SPINNING WITHOUT
EXCITATION
• Tachometer
• Vibration meter (Structure)
• Dial indicator
• Thermometer
Instruments
to be used:
MECH. SPINNING WITHOUT
EXCITATION
SPINNING WITH EXCITATION
 After bearing run, the machine is prepared for short
circuit test.
 For this test, we do three phase shorting at generator
terminal then the excitation is increased from zero up
to the full load stator current.
 During this test, operation and stability test of
differential protections are also checked.
 After SCC test, we go for high voltage test for stator
winding.
BASIC TEST CIRCUIT
FOR SCC TEST
SCC TEST
A
B
C
SCC TEST
SCHEMATIC CONNECTION DIAGRAM FOR
SCC TEST
HV TEST FOR STATOR WINDING
 Used for testing the dielectric strength of generator
stator winding insulation.
 For less than 10MW, test voltage (r.m.s.) shall be
1000V+2*Rated voltage; subject to minimum of 1.5kV.
 For machines with a rated voltage 6 kV or greater,
when power frequency equipment is not available, then
by agreement a DC test may be carried out at a voltage
1.7 times the r.m.s. values to be chosen in case of AC
test.
 For more than 10 MW, Test Voltage (r.m.s.) shall be
For voltage less than and equal
to 24kV
2*Rated voltage + 1000 V
For voltage more than 24kV Subject to agreement
OCC TEST
 After successfully completing the HV test, OCC test is
carried out.
 In OCC test, excitation cable is restored and voltage is
build up to rated voltage in steps of 1KV. Then, Open
Circuit Characteristic Curve is drawn.
 Operation of Stator earth fault protection is also checked by
creating actual earth and performance test of all voltage
relays is also carried out .
BASIC TEST CIRCUIT
FOR OCC TEST
SCHEMATIC CONNECTION DIAGRAM FOR
OCC TEST
SYNCHRONIZATION WITH THE GRID
• Phase sequence of Generator voltage and Grid
voltage must be the same.
• Two voltages must be equal, i.e. IV1I - IV2I=0.
• The generator frequency must be nearly equal to
the Grid frequency, i.e. f1- f2 ≈ 0.
• At the instant of synchronizing, the two voltages
must be almost co-phasal, i.e. Ø1 – Ø2 ≈ 0.
The
following
conditions
must be
satisfied:
Finally the machine is synchronized with the grid at
the partial load.
 The degree of criticality of these parameters are in the
following order:
∆Ø, ∆V, ∆f.
 The inertia of the incoming machine being very small
against that of the grid, even with considerable ∆f, the
machine will easily be pulled into synchronism.
 Voltage difference, if large, can result in heavy exchange of
VAR and can result in voltage fluctuations, if large enough
leading to instability.
 Large ∆Ø can result in heavy exchange if MW, often good
enough to cause torsional damage to the shaft system.
SYNCHRONIZATION WITH THE GRID
LOAD RUN AND
LOAD REJECTION TESTS
When the generator and switching equipment has been
declared ready for operation , the unit is synchronized.
During the load rejection tests, all necessary precautions shall
be taken to ensure that rated values of penstock and
turbine stresses will not be exceeded. Such precaution
may include setting governor timing.
When adjustments are made on governor or regulating devices
all tests which might be affected by the adjustment shall
be repeated.
• To check the output of the unit with an agreed
accuracy.
• To check the unit for instability, vibration or
cavitations in the range of guaranteed loads.
• To check the functioning of governor and
regulating devices, as well as that of the entire
unit.
• To determine the momentary pressure and speed
variations of the unit and to find their extreme
values. To adjust the closing times of the wicket
gates, needle valves and deflectors to minimize
over speeding of the unit within the permissible
limit of pressure variation
• To permit testing of the operation of other
hydraulic and electrical equipment, including
protection and other automatic devices.
PURPOSES:
LOAD RUN AND
LOAD REJECTION TESTS
PROCEDURE:
 The load shall be increased in steps and load rejection test made at
successively higher loads up to the maximum expected to be placed
on the unit. For example: rejections may be made at 25%, 50%, 75%
and 100% of the rated load as well as from the maximum load that
may be agreed upon.
 Two rejections shall be made at each load. One rejection is made
under governor control to no load gate or needle opening, the other
may be an emergency shutdown by stop solenoid.
 If specified, load rejection tests shall be made by means of the
emergency valve or by any other emergency device.
 After the completion of each load rejection test, the pressure rise and
turbine speed rise data shall be analyzed to ensure that the specified
safe limits will not be exceeded during the next higher load rejection
test.
LOAD RUN AND
LOAD REJECTION TESTS
Observations, Measurements and Recordings:
LOAD RUN AND
LOAD REJECTION TESTS
• Head and tail water level
• Generator output.
• Wicket gate or needle opening (where applicable)
• Pressure at turbine inlet and outlet
• Pressures and levels in oil pressure systems
• Operating times of oil pressure pumps.
• Temperatures in bearings.
• Noise levels, if values are specified in the
contract.
• Abnormal noises if any.
• Vibration and other displacement of rotating and
fixed parts.
• Action of air-admission devices if any.
Applicable
for Steady
State
Operation:
Observations, Measurements and Recordings:
LOAD RUN AND
LOAD REJECTION TESTS
• Head and tail water levels
• Generator output
• Strokes and closing times of wicket gates or
needles where applicable.
• Pressure at the turbine inlet and outlet.
• Level variations at intake and surge tanks
• Pressure drop in the oil pressure system in the
process of governing, and variation of level in
the oil pressure reservoir.
• Noise levels, if values are specified in the
contract.
• Abnormal noises, if any.
• Vibration and other displacement of rotating and
fixed parts.
• Action of braking jets in case of Pelton turbine.
Load
rejection
and
subsequent
tests:
COMMERCIAL RUN
After meeting all the
contractual requirements of
operation, the machine can
be declared ready for
Commercial Run.
ILLUSTRATIVE
PHOTOGRAPHS
Generator Barrel & Turbine Pit
LOWERING
OF STATOR
STATOR SECTION
GENERATOR
ROTOR
LOWERING OF ROTOR
DRAFT TUBE
ERECTION
STAY RING
SPIRAL CASING
HYDROSTATIC
TESTING
TURBINE RUNNER
TURBINE SHAFT
TOP COVER & TURBINE
ASSEMBLY
LOWER BRACKET
ASSEMBLY OF MIV
BUTTERFLY TYPE SPHERICAL TYPE
171839416-commissioning-of-hydro-ppt.ppt

More Related Content

Similar to 171839416-commissioning-of-hydro-ppt.ppt

J D J
J D JJ D J
J D Jjjinesh
 
railway workshop jodhpur
railway workshop jodhpurrailway workshop jodhpur
railway workshop jodhpurkalumutha
 
railway workshop jodhpur
railway workshop jodhpur railway workshop jodhpur
railway workshop jodhpur kalumutha
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trialNagesh H
 
Turbine Start Up.pptx
Turbine Start Up.pptxTurbine Start Up.pptx
Turbine Start Up.pptxssuser0cdaa1
 
Production Operator
Production OperatorProduction Operator
Production OperatorPravin Xavier
 
THERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSTHERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSManohar Tatwawadi
 
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdfOn Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdfKhalidAyaz3
 
A guide for firetube boiler testes
A guide for firetube boiler   testesA guide for firetube boiler   testes
A guide for firetube boiler testesederpitapeva
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGAshish Kumar Jain
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdfyusuf699644
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdfMBouderbala
 
EDGAR P AGUILAR
EDGAR  P AGUILAREDGAR  P AGUILAR
EDGAR P AGUILARedgar aguilar
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintananceAnasMirza10
 
Replacement Parts Industries (RPI) Everything You Ever Wanted to Know About S...
Replacement Parts Industries (RPI) Everything You Ever Wanted to Know About S...Replacement Parts Industries (RPI) Everything You Ever Wanted to Know About S...
Replacement Parts Industries (RPI) Everything You Ever Wanted to Know About S...Intermountain Clinical Instrumentation Society
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing SystemSalil Vaidya
 

Similar to 171839416-commissioning-of-hydro-ppt.ppt (20)

J D J
J D JJ D J
J D J
 
railway workshop jodhpur
railway workshop jodhpurrailway workshop jodhpur
railway workshop jodhpur
 
railway workshop jodhpur
railway workshop jodhpur railway workshop jodhpur
railway workshop jodhpur
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
Turbine Start Up.pptx
Turbine Start Up.pptxTurbine Start Up.pptx
Turbine Start Up.pptx
 
Production Operator
Production OperatorProduction Operator
Production Operator
 
THERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSTHERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONS
 
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdfOn Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
 
A guide for firetube boiler testes
A guide for firetube boiler   testesA guide for firetube boiler   testes
A guide for firetube boiler testes
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
Governing system
Governing systemGoverning system
Governing system
 
Turbine operation.pptx
Turbine operation.pptxTurbine operation.pptx
Turbine operation.pptx
 
Separatore pa 605
Separatore pa 605Separatore pa 605
Separatore pa 605
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
EDGAR P AGUILAR
EDGAR  P AGUILAREDGAR  P AGUILAR
EDGAR P AGUILAR
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintanance
 
Replacement Parts Industries (RPI) Everything You Ever Wanted to Know About S...
Replacement Parts Industries (RPI) Everything You Ever Wanted to Know About S...Replacement Parts Industries (RPI) Everything You Ever Wanted to Know About S...
Replacement Parts Industries (RPI) Everything You Ever Wanted to Know About S...
 
Plant Air & Inst Air.ppt
Plant Air & Inst Air.pptPlant Air & Inst Air.ppt
Plant Air & Inst Air.ppt
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĂŁo Esperancinha
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Study on Air-Water & Water-Water Heat Exchange in a Finned ďťżTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ďťżTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned ďťżTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ďťżTube ExchangerAnamika Sarkar
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Study on Air-Water & Water-Water Heat Exchange in a Finned ďťżTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ďťżTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned ďťżTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ďťżTube Exchanger
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

171839416-commissioning-of-hydro-ppt.ppt

  • 2.
  • 3. Dam Reservoir Power intake (Penstock) Power house •Turbine •Draft tube •Main inlet valve •Generator •Bus Duct •Field Excitation System •Governing System •SCADA System •Station Transformer •Balance of Plant •Protection system & switchgear •LV/ HV distribution •DC, UPS Battery Switch Yard Following are the main components of a Hydroelectric Power Plant INTRODUCTION
  • 4. Dome Stator Rotor Generator Shaft Turbine Shaft Spiral Casing Stay Ring Runner Draft Tube
  • 5.
  • 6.
  • 7.
  • 8.
  • 9. COMMISSIONING Definition •Testing of new equipments to check its conformity with contractual specifications, as well as operation of the equipment until formally accepted by the Customer. •Commissioning usually occurs after first erection of a new unit.
  • 10. Commissioning activities consist of various tests: •Pre-commissioning tests •Prior to filling waterways •After filling waterways •Initial Run test •Test Run COMMISSIONING
  • 11. READINESS CRITERION Commissioning activities in hydro project begin with the filling of waterways on the down stream side (common tailrace) and up stream side (Head Race or Penstock) of the machine. This implies readiness of hydro set which broadly comprises of following equipments and their readiness criteria : 1. Draft Tube and Liner, Spiral casing, Tail Race Channel, Penstock and gates etc. for their erection and checks from the point of view of cleanliness, civil grouting work for the hollow portions between metal and concrete contact surfaces etc. 2. It is to be ensured that there is no impediments in the free flow of water from any projecting lumps of concrete/reinforcement rods etc. 3. The grouting plugs have been welded and flush grinded as per Drawing requirement and no obstruction exists from any local bending of metallic liners etc. in the water path. 4. Painting work of underwater parts with black anticorrosive paint has been completed.
  • 12. The Machine itself has been made ready mechanically along with its auxiliaries. This will include the following major equipments/systems/works and other preparations : Turbine & Turbine Pit : 1. Runner blade and chamber clearances have been checked and found OK to ensure that no rubbing is likely to occur during start up and running. 2. Air inflated repair seal of Turbine shaft is ‘OFF’ and cooling water to working seal will be available when CW system is charged. 3. Turbine bearing oil is at proper level – neither too high nor too low – let the drawing be followed at this stage. Keep record of pumping holes in the skirt if provided-whether plugged and how many. 4. Manual/Auto greasing of guide vanes etc. has been done for smooth operation. 5. Easy mobility along with sufficient lighting both AC/DC provided in the pit. READINESS CRITERION
  • 13. 6. Dry stroking of guide apparatus/ MIV have been done upto full rated oil pressure of OPU through governor. Record Opening/Closing and damping times. 7. Dowelling work etc. of bearing housing etc. has been completed. 8. Fulfillment of all requirements given in O&M manuals/check lists of the project to be ensured. 9. De-watering of draft tube checked twice by closing the draft tube gates. 10. Turbine top cover drainage system is operational and in Auto to avoid turbine pit flooding during first filling of TRC and subsequently during penstock filling etc. Preferably additional pumping arrangement, not dependent on Electric Supply (i.e. Air Operated) be provided as quantity of leakage water from shaft, Guide vane cup seals, etc. is not known at this time. This is more necessary when starting a machine after a long delay after erection. READINESS CRITERION
  • 14. Generator & Generator Barrel : 1. Generator and its sub assemblies have been fully erected as per drawing and cleaned with dry compressed air/cloth. Check top and bottom air guide clearances which should be at least 8-10 mm ( as per drawing requirement) from the rotor fan blades. 2. Stator/Rotor gap must be free from any foreign object which is usually checked by taking a rope all around the gap along the full height of the stator core. 3. Check and ensure that Generator barrel/bracket areas are free from foreign objects, hanging wires/cables, loose electrical connections, loose clamps etc. 4. Bearing vapour seal segments may not be assembled in position during initial runs to avoid likelihood of rubbing until performance in terms of vibration and wobble is proved up to full speed (This is not applicable for vapour seals of wool felt type). 5. Initial bedding of slip ring carbon brushes, cleaning of slip rings etc. has been done. Carbon brushes to be kept disengaged from the slip rings, during initial runs as no excitation is to be given during this time. Should be in for proper bedding . READINESS CRITERION
  • 15. 6. Dowelling of stator frame/brackets etc. has been done and secondary concreting of Stator and lower bracket foundations have fully cured. Epoxy grouting of foundation bolts to be ensured. Tightening of all bolts and their locking particularly of the rotor/rotor lead clamps/pole to pole joints etc. to be carefully checked. 7. Generator Barrel water mist Fire Extinguishing system commissioned and kept ready in manual/Auto mode, which is to be switched on prior to voltage build up/ synchronisation/loading. 8. Brake system is already tested for reliable lifting and release 10 times from HP compressor/pressure reducer air system or L P air system along with Limit Switch operation for indication/control. Free operation of brakes to be ensured. Auto operation of Brake is to be disabled during initial period (Brake Air Pressure should be adjusted for 4-5 Kg/cm2 ). Brakes should be applied at a speed as given in design which is usually 20 to 25% of rated speed). Required oil should be filled up in air filter unit. READINESS CRITERION
  • 16. 9. Generator bearing’s oil should be at proper level as per Drawing and this should be marked in gauge glass. Operation of low/high level float switches should be checked. 10. Performance of HS Lube system to be proved. Check lifting of Rotor from HS lube pressure by 4 dial gauges placed at  X and  Y positions i.e at 4 points to know amount and uniformity of lift all around. The HS Lube pressure should not exceed specified design value. Safety relief valve to be adjusted depending on the pressure required for jacking. HP lub oil pressure switches/gauge to be adjusted for normal & low pressure. Ensure no loose connections in the electrical circuits to avoid sparking and consequent fire hazard in these enclosed spaces. READINESS CRITERION
  • 17. 1. 440 V 3 Phase AC supply 2. 240 V 1 Phase A.C. supply 3. 220 V DC or 110 V D.C. Power supply system 4. 48 V DC Power supply system 5. Dewatering, Drainage and leakage collection system and their pumping arrangement. 6. 11 KV or 13.75 KV along with cable etc. for commissioning of excitation system. 7. 24 V DC power supply system. 8. The intake gates, draft tube gates and butterfly valves are tested for safe and reliable operation and equipped with operator personnel and telephonic connection . 9. Oil supply system. 10. Compressed air system. 11. Completion of cable laying , termination @ earthing 12. 240 V AC UPS supply. PRE- REQUISITES FOR COMMISSIONING
  • 18. 13. Readiness of water conducting system . 14. Civil works in the vicinity of active and sensitive electrical and mechanical machinery/equipment are finalized. Floors are clean and dry. 15. Station earthling system is in full and reliable condition. 16. Main fire fighting system for the power house cavern in safe operating condition, including the portable fire extinguishers. 17. Ventilation, illuminations, communication, and Air-conditioning available on a permanent base. 18. Readiness of protective covers, guards ladders and covering of floor holes and pits. PRE- REQUISITES FOR COMMISSIONING
  • 19. PRE-COMMISSIONING TEST/CHECKS Pre- commissioning Tests: • Test between completion of erection of the equipment and initial run. • Tests/Checks prior to filling waterways • Tests/Checks after filling of waterways
  • 20. TEST/CHECKS PRIOR TO FILLING WATERWAYS 1. Inspection of all the turbine waterways and removal of all foreign or loose objects. 2. Calibration of scales for wicket gate opening and where applicable, for runner blades, needles and deflectors including their cam relationships; and also measurement of clearances. 3. Operation of pressure oil units, MIV, governors, automatic and manually operated starting and stopping devices and signaling devices. 4. Oil levels and pressures in governing system; Condition of all oil filters.
  • 21. TESTS/CHECKS PRIOR TO FILLING WATERWAYS 5. Protective devices such as oil level and temperature alarms and relays, with adjustment if needed. 6. Times of opening and closing of governing elements, i.e. wicket gates, runner blades of turbines with movable blades, needles and deflectors of impulse turbines. 7. MIV opening and closing times. 8. Bearing and seal clearances and functioning of hydrostatic lubrication system.
  • 22. TESTS/CHECKS PRIOR TO FILLING WATERWAYS 9. Operation of drainage pumps and dewatering pumps. 10. Oil, grease and water supply to all bearings and seals requiring lubrication or cooling. 11. Operation of braking system of the unit.
  • 23. TESTS/CHECKS AFTER FILLING WATERWAYS 1. The Tail water gate shall be opened first after filling the draft tube and spiral case up to tail water level through a filling valve of the draft tube gates. Check for leaks is to be made. The whole waterway should be filled slowly and manually through a bypass valve of the penstock. 2. Operation of emergency protection devices which actuates the intake gate/MIV and closure of guide vanes and stoppage of machine is to be checked. 3. If the protective devices and emergency closing system work satisfactorily, and no unusual leakage or deformation is observed, Initial run of the Machine can be initiated.
  • 24. INITIAL RUN After the permission for initial run, locking devices and brakes are released and the turbine wicket gates or needles are opened under manual control, slowly as per manufacturer’s recommendations and bring the speed up to at least the minimum stated value. If any noise, scraping or other abnormal phenomena is observed, the unit should be shut down immediately and thorough inspection is to be carried out to find out the cause of the problem and rectify the same.
  • 25. •Time •Unit speed •Servomotor stroke •Temperature of bearing •Shaft run out Measurements Items: •Tachometer •Dial indicator Instruments to be used: INITIAL RUN
  • 26. TEST RUN •Mechanical Spinning without Excitation •Spinning with Excitation •Synchronization with the grid •Load run and Load Rejection Tests Test Run consists of :
  • 27. MECH. SPINNING WITHOUT EXCITATION 1. The unit is kept under manual control at or above starting speed until bearing temperatures are stabilized. 2. If any temperature is excessive or increases too rapidly, the unit shall be shut down and the causes of this phenomenon is to be investigated and corrected. 3. If all goes well, the unit speed shall be increased in prearranged steps up to the rated value, remaining at each successive speed until the rate of rise of all bearing temperatures is satisfactory to the manufacturer's recommendation.
  • 28. During each speed step of test run, at least the following measurements / observations should be made: 1. Deformation of covers and bearing supports 2. Noise or vibration in the turbine and/or generator 3. Operating conditions for the oil pressure and other pumps. 4. Condition of oil in the bearings and pressure oil systems. If water is observed in oil, the leaks shall be located and eliminated. If oil foaming is observed, the cause shall be located and eliminated. 5. Temperatures of bearings and lubricating oil. 6. Shaft run out at turbine and generator bearings and axial displacement of rotating parts is measured. 7. At some agreed speed value, the action of braking system shall be checked. MECH. SPINNING WITHOUT EXCITATION
  • 29. • Tachometer • Vibration meter (Structure) • Dial indicator • Thermometer Instruments to be used: MECH. SPINNING WITHOUT EXCITATION
  • 30. SPINNING WITH EXCITATION  After bearing run, the machine is prepared for short circuit test.  For this test, we do three phase shorting at generator terminal then the excitation is increased from zero up to the full load stator current.  During this test, operation and stability test of differential protections are also checked.  After SCC test, we go for high voltage test for stator winding. BASIC TEST CIRCUIT FOR SCC TEST
  • 34. HV TEST FOR STATOR WINDING  Used for testing the dielectric strength of generator stator winding insulation.  For less than 10MW, test voltage (r.m.s.) shall be 1000V+2*Rated voltage; subject to minimum of 1.5kV.  For machines with a rated voltage 6 kV or greater, when power frequency equipment is not available, then by agreement a DC test may be carried out at a voltage 1.7 times the r.m.s. values to be chosen in case of AC test.  For more than 10 MW, Test Voltage (r.m.s.) shall be For voltage less than and equal to 24kV 2*Rated voltage + 1000 V For voltage more than 24kV Subject to agreement
  • 35. OCC TEST  After successfully completing the HV test, OCC test is carried out.  In OCC test, excitation cable is restored and voltage is build up to rated voltage in steps of 1KV. Then, Open Circuit Characteristic Curve is drawn.  Operation of Stator earth fault protection is also checked by creating actual earth and performance test of all voltage relays is also carried out . BASIC TEST CIRCUIT FOR OCC TEST
  • 37. SYNCHRONIZATION WITH THE GRID • Phase sequence of Generator voltage and Grid voltage must be the same. • Two voltages must be equal, i.e. IV1I - IV2I=0. • The generator frequency must be nearly equal to the Grid frequency, i.e. f1- f2 ≈ 0. • At the instant of synchronizing, the two voltages must be almost co-phasal, i.e. Ø1 – Ø2 ≈ 0. The following conditions must be satisfied: Finally the machine is synchronized with the grid at the partial load.
  • 38.  The degree of criticality of these parameters are in the following order: Ư, ∆V, ∆f.  The inertia of the incoming machine being very small against that of the grid, even with considerable ∆f, the machine will easily be pulled into synchronism.  Voltage difference, if large, can result in heavy exchange of VAR and can result in voltage fluctuations, if large enough leading to instability.  Large Ư can result in heavy exchange if MW, often good enough to cause torsional damage to the shaft system. SYNCHRONIZATION WITH THE GRID
  • 39. LOAD RUN AND LOAD REJECTION TESTS When the generator and switching equipment has been declared ready for operation , the unit is synchronized. During the load rejection tests, all necessary precautions shall be taken to ensure that rated values of penstock and turbine stresses will not be exceeded. Such precaution may include setting governor timing. When adjustments are made on governor or regulating devices all tests which might be affected by the adjustment shall be repeated.
  • 40. • To check the output of the unit with an agreed accuracy. • To check the unit for instability, vibration or cavitations in the range of guaranteed loads. • To check the functioning of governor and regulating devices, as well as that of the entire unit. • To determine the momentary pressure and speed variations of the unit and to find their extreme values. To adjust the closing times of the wicket gates, needle valves and deflectors to minimize over speeding of the unit within the permissible limit of pressure variation • To permit testing of the operation of other hydraulic and electrical equipment, including protection and other automatic devices. PURPOSES: LOAD RUN AND LOAD REJECTION TESTS
  • 41. PROCEDURE:  The load shall be increased in steps and load rejection test made at successively higher loads up to the maximum expected to be placed on the unit. For example: rejections may be made at 25%, 50%, 75% and 100% of the rated load as well as from the maximum load that may be agreed upon.  Two rejections shall be made at each load. One rejection is made under governor control to no load gate or needle opening, the other may be an emergency shutdown by stop solenoid.  If specified, load rejection tests shall be made by means of the emergency valve or by any other emergency device.  After the completion of each load rejection test, the pressure rise and turbine speed rise data shall be analyzed to ensure that the specified safe limits will not be exceeded during the next higher load rejection test. LOAD RUN AND LOAD REJECTION TESTS
  • 42. Observations, Measurements and Recordings: LOAD RUN AND LOAD REJECTION TESTS • Head and tail water level • Generator output. • Wicket gate or needle opening (where applicable) • Pressure at turbine inlet and outlet • Pressures and levels in oil pressure systems • Operating times of oil pressure pumps. • Temperatures in bearings. • Noise levels, if values are specified in the contract. • Abnormal noises if any. • Vibration and other displacement of rotating and fixed parts. • Action of air-admission devices if any. Applicable for Steady State Operation:
  • 43. Observations, Measurements and Recordings: LOAD RUN AND LOAD REJECTION TESTS • Head and tail water levels • Generator output • Strokes and closing times of wicket gates or needles where applicable. • Pressure at the turbine inlet and outlet. • Level variations at intake and surge tanks • Pressure drop in the oil pressure system in the process of governing, and variation of level in the oil pressure reservoir. • Noise levels, if values are specified in the contract. • Abnormal noises, if any. • Vibration and other displacement of rotating and fixed parts. • Action of braking jets in case of Pelton turbine. Load rejection and subsequent tests:
  • 44. COMMERCIAL RUN After meeting all the contractual requirements of operation, the machine can be declared ready for Commercial Run.
  • 46. Generator Barrel & Turbine Pit
  • 56. TOP COVER & TURBINE ASSEMBLY
  • 58. ASSEMBLY OF MIV BUTTERFLY TYPE SPHERICAL TYPE