SlideShare a Scribd company logo
1 of 30
TURBINE START-UP
Presented By:
M.V.Pande
Dy.Director
General Operation Philosophy
➢Achieving and maintaining the required output of the unit
➢Maintaining plant conditions at their optimum efficiency
➢Inspection for plant deterioration by studying the operation trends of main
equipments and their auxiliaries (condition monitoring). The maintenance
logs can be generated from this information.
➢T
esting of stand-by plant auxiliaries, protective devices, alarms and
automatic cut-in feature.
➢Changing over of auxiliaries depending on their running hours.
➢Generation of shift logs, event logs, post trip logs etc.
➢Readiness to respond to abnormal conditions.
General Preparation for Start-up
• It should be ensured that all the repair works on turbine
system have been completed and all the permits are
are healthy and in
cancelled ensuring that equipments
operative condition
• First of all bring all the electrical equipments to a state of
readiness i.e., switch-on the necessary switchgear for
motors, valve actuators, controls protections and monitoring
system
• After this, carry out the necessary interlocks and protection
checks feasible under stationary condition of turbine.
Certain tests and checks require bypassing of certain
interlocks. All such deliberate bypassing of interlocks must
be prominently displayed in the control room during the test.
After the test, all interlocks and protections should be
brought to normal state
General Preparation for Start-up
• Various valves as per the scheme are to be kept in open
or close position. It must be ensured that these valves are
kept up in the required position. The isolating valves for all
measuring control and protective device should be kept in
fully open position
• Turbine oil quality should be checked for viscosity,
neutralization number, sludges etc. If required, the oil
should be drained from MOT and topped up with fresh oil
in order to restore the quality
• Condenser tube leakage should be checked by charging
the CW system and watching the increase in hot well
level. If good amount of leakage is noticed, then action
must be taken to plug the leaking tubes
Turbine Start-up Requirements
Turbine start-ups are classified as cold start-up, warm start-up and hot
start-up depending on the HP turbine metal temperature as follows:
If HPT metal temperature >350oC -Hot start-up
If HPT metal temperature between 150 - 350oC -Warm start-up If
HPT metal temperature < 150oC -Cold start-up
The start-up procedure decides following aspects:
• i) Steam parameters suitability viz. pressure and temperature & its
raising rates.
• ii) Soaking time for turbine and main valves
• iii) Turbine speed raising, loading rates
• iv) T
otal time required reaching the full load.
Turbine Start-up Requirements
❖ Generally absolute cold start-up of turbine takes 6 hours to
reach the full load
❖ The turbine after two hours shutdown may require only
half an hour to one hour to reach the full load (depending
on boiler load)
❖ The rate of rise of steam parameters and turbine
parameters, (speed, load) are specified by start-up curves
for the regime. Operators should provide necessary time
for proper soaking of turbine at specified speeds (600 and
3000 rpm), as shown by the curves, for permitting
expansions at normal rate. This will give good temperature
& load margins after synchronization
Cold Start-up Steps
1. Pre-start checks and testing of supplies
2. Establishing lube oil and jacking oil system
3. Putting turbine on barring gear
4. Warming of main steam pipe lines (steam line drains
and turbine SLC drains must be kept open)
5. Pulling-up vacuum in condenser by starting ejector
6. Establishing turbine gland sealing (at about 0.2
kg/cm2 vacuum)
7. Putting main ejector into service (at about 0.7 – 0.8
kg/cm2 vacuum) and withdrawing starting ejector.
Normal vacuum of 0.91 kg/cm2 is obtained.
8. Charging of reheater through HP-LP Bypass system
9. Building of steam parameters suitable to turbine
condition, viz. for cold start-up parameters are as
follows:
Cold Start-up Steps
M.S. H.R.H.
Pressure 30- 35 kg/cm2
T
emperature 320o – 350oC
Flow 95 –100 t/hr
10-12 kc/cm2
320o – 350oC
10. Warm-up of turbine stop valves (ESV & IV) to get the TSE
margins >30oK & fulfillment of steam pressure and
temperature criteria (X1, X2,X3)
11. Turbine trip resetting by bringing S.L.L.D. to zero
position.
12.Opening of stop valves (ESV & IV) by raising the SLLD
(starting device) to 42% and 56% respectively
13. Warming of HP control valves by opening warm-up
control drains valves through warm-up controller
Cold Start-up Steps
14. Fulfillment of steam temperature criteria with respect to mid wall
temperature of turbine metal to ensure that main steam temperature is
greater than turbine metal temperature & degree of superheat is >
50oC as recommended by criteria curves X4 and X5 respectively. TSE
margins are ensured greater than 35oK
15. Preparing the electro-hydraulic governing system ready for operation
by setting the speed & load controller reference values & keeping
hydraulic governor as back-up by raising speeder gear position to
100%
16. Turbine rolling to 600 rpm through speed controller
17. Soaking of turbine at 600 rpm to fulfilled X6 criterion (approx. 1 hr),
which ensures the proper warming of HP turbine with respect to main
steam temperature. Turbine parameters monitoring
18. Speed raising to 3000 rpm by setting speed reference value at 3000
rpm without stopping in between
X5 Criterion- M.S. Temperature
X5 Criterion- H.R.H. Temperature
Cold Start-up Steps
19.Soaking of turbine at 3000 rpm to fulfilled X7 criterion (approx. 45
min.), which ensures proper warming of IP turbine with respect to
HRH temperature. Monitoring turbine expansion and shaft/bearing
vibration trend
20.Ensuring TSE upper temperature margin of turbine greater than
35oK
21. Synchronization of generator to grid
22. Load raising to 10% (20MW) through speed reference setter.
23. Closing of all manual operated drains
24.Ensuring closure of HP-LP bypass valves by increasing pressure
set point above M.S. pressure
25. Check that load controller becomes active at about 20 MW.
26. Raising the M.S. pr. to 50 kg/cm2 by taking coal mill into service
and load is raised to 40 MW
27.Charging of LP heaters from steam side and putting the level
controllers of LPH 2 & 3 on auto
Cold Start-up Steps
28. T
aking second coal mill into service and raising steam pressure. Ensure
that HP bypass set point is kept at higher value than actual pressure
29.Raise the turbogenerator load to 100 MW. T
ake HP heaters into service.
30.Establish second air cycle, second BFP
, third coal mill and raise the
steam parameters
31.Changing over the deaerator pegging steam supply from CRH to
extraction-4 at about 55% load (when the NRVs release is obtained).
32.Raising the load to 150 MW
33. T
aking the fourth coal mill into service. Put at least two mills on Auto.
Stabilize the M.S. pressure at about 140 kg/cm2
34.Putting CMC in to service after adjusting the M.S. Pressure set point to
match with actual pressure
35.Raising the turbogenerator load to 210 MW through unit target load set
point at CMC
36.Monitoring of turbovisory parameters, viz. absolute expansion, differential
expansions, axial shift, bearing & shaft vibrations, casing temperatures at
admission and exhaust locations, bearing temperatures
Turbine Oil System
Check that:
➢ MOT level is normal ( 0+350 mm ) and basket
strainers are cleaned
➢ Fire protection shut-off valve is closed and solenoid is
reset at turbine floor and in MOT room.
➢ Readiness of Lube oil pumps and JOPs
➢ Sub-group control of oil system "Auto-ON"
➢ Ensure one of the lube oil coolers is in service from
oil side and water side.
Turbine Oil System
Turbine Oil System
Turbine Oil System
Operation :
• AOP and JOP can be started manually from PCR or on auto
through “SLC-ON” or through SGC "Auto-ON"
• T
ake the standby trial of AOP
, EOP and JOP
• Watch drop in MOT level after AOP is started (280 mm).
• Put temperature controller SLC "ON"
• Watch the oil temperature at oil cooler outlet and ensure that it is
maintains between 40o – 45oC by temperature controller
Watch following parameters :
-Discharge pressure of AOP : 6.5 kg/cm2
i)
ii)
iii)
-Oil Pressure before cooler
-Oil pressure after cooler
:
:
5.4 kg/cm2
4.8 kg/cm2
-MOT level
-Jacking Oil Pressure
:
:
+ 25 mm
120 kg/cm2
Turbine Oil System
When the turbine is running, check the bearing drain oil temperature and
babbit temperatures :
• Bearing drain oil temperature :
• Journal bearing babbit temperature :
• Thrust bearing babbit temperature :
•
•
•
•
•
•
•
•
•
•
•
< 60oC
< 90oC
< 110oC
Permissives for starting turning gear :
Seal oil to H2 DP
Seal oil pressure TE & EE
H2 gas pressure
H2 purity
Liquid in generator
:
:
:
:
:
> 1 kg/cm2
> 4.4 kg/cm2
> 3.3 kg/cm2
> 97%
Not present
Turning gear can be started by opening gate valve either manually or
through SLC. Observe that turbine speed on turning gear is as follows :
When no vacuum in condenser
At normal vacuum condition
:
:
110 – 120 rpm
150 – 160 rpm
Turbine Oil System
After turning gear is ON,AOP amperes will increase to 125Afrom 105A.
AOP
, JOP and turning gear trip and pick-up speeds are as follows :
➢ When MOP takes over, the discharge oil pressure will be 8.5 – 9.5
kg/cm2 depending on turbine speed.
➢ Interlocks ofAOP
, EOP & JOP
➢ The standby AOP (SLC ON) will pick-up if discharge oil pressure < 4.8
kg/cm2 or the runningAOP is OFF
➢ DC Emergency Oil Pump will pick-up when SLC is ON and if lube oil
pressure is < 1.1 kg/cm2
➢ The standby JOP (SLC ON) will pick-up if running JOP trips.
Trip Speed rpm Pick-up Spee
rpm
i) Turning gear 240 210
ii) J.O.P. 540 510
iii) A.O.P. 2850 2800
Condensate & Feedwater Line Charging
Vacuum Pulling and Gland Sealing Checks
• Line-up the steam ejectors
• Ensure 220 V DC supply to the solenoid of vacuum breaker
valve and it is closed
• Ensure water sealing to glands of all the valves in vacuum
circuit
• CW system is established
• Condensate system is established
• Ensure gland steam cooler siphone is filled-up
• Ensure electrical supply to the motors of seal steam leak-off
controller and seal steam supply controller. Their oil pumps
are working on auto to maintain oil pressure of 60 kg/cm2
• Check that valve AS301 (CRH Steam to glands) is in closed
position
• The turbine is put on turning gear
Vacuum Pulling and Gland Sealing
Vacuum Pulling and Gland Sealing Operation
• Charge the gland steam header by opening AS 378 valve and build up
the pressure 6 –6. 5 kg/cm2. Set the pressure 6.5 kg/cm2 and put the
ejector steam pressure control on auto.
• Start vacuum pulling through starting ejector by first opening steam
valve and then the air valve.
• Start one exhauster fan of gland steam cooler
• After building up 0.2 kg/cm2 vacuum, open the gland seal steam supply
valve and charge the header at pressure 0.01 kg/cm2(g).
steam pressure control on auto.
• After opening the steam supply valve, the header drain valve MAL-81
will close on auto.
• After establishing the gland sealing, the condenser vacuum will improve
at a faster rate
• When vacuum builds-up to 0.7 kg/cm2, take one main ejector in to
service by opening first its steam valve (AS02 or AS03) and then the air
Put the gland
valve. Cut-off the starting ejector by closing air valve and then steam
valve.
• Note the final value of vacuum at which it stabilizes (0.92 kg/cm2) and
also note HPT/IPT & LPT differential expansions
Warming of Steam Piping
Checks :
➢Ensure all the drain valves M.S., CRH and HRH lines are open
➢M.S. line to be charged when drum pressure is raised to
10 kg/cm2 after blow-down
Operation :
❖ Charge the M.S. line by opening the boiler outlet bypass valves
(MS 301A/302A)
❖ Ensure that there is no hammering in M.S. pipeline
❖ Watch the temperature rise of ESV mid wall
❖ Rate of heating of steam pipelines should not exceed 25o to 30oC
per 5 min.
❖ During heating of M.S. & R.H. steam pipelines; the temperature
difference between LHS & RHS pipelines should not exceed
15oC. But this difference should not exceed 10oC when the set is
on load
HP-LP Bypass System Charging
Checks :
• Ensure that HP Bypass control oil pumps are running on auto and
maintaining the pressure oil pressure 110 kg/cm2 and oil tank level is
normal
• All the oil supply/return/leak-off Sulzer valves are open and there is no oil
leakage in the system
• ESV and IVs are closed
• Cooling water to HP BP valve gland from CEP is open
• Isolating spray valve before BD valve is open and BD valve is closed on
auto. Ensure that it is not passing.
• All controls of HP bypass are on manual mode and all valves are closed.
• Ensure power supply to HP BP panel is normal
• Ensure that control oil pressure to LP bypass station is > 5.5 kg/cm2
• All manually operated & auto injection water valves (V1, V2, V3, V4) of LP
bypass station are closed.
• All the drain valves of HP &LP bypass are open
• Ensure condenser vacuum is > 0.75 kg/cm2
• BFP & CEP are running and discharge header pressures are adequate
HP-LP Bypass System
HP-LP Bypass System Charging
Operation :
✓ Set the fixed pressure set point of LPBP at 3 kg/cm2
✓ Put the LP Bypass controller on “Auto”
✓ Make the automatic control interface "ON"
✓ Ensure drain valves of CRH, HRH and Warm-up valves are
open
✓ Open HPBP warm-up valves locally.
✓ Set the pressure master set point at 35 kg/cm2
✓ Put spray water control valves BPE1 & BPE2 of HPBP on
“Auto”
✓ After warming up for 15 min. open HPBP valves BP-1 and
BP-2 about 5%.
✓ Increase the BP1 & BP2 position manually in a step of 5%
✓ Check that LPBP valves and injection water valves open on
auto to maintain HRH pressure
HP-LP Bypass System Charging
Operation contd… :
✓ Close LPBP warm-up valve
✓ When LPBP position goes to 25% increase the oil-firing rate in
boiler by taking into service CD oil elevation pairs 1-3 & 2-4.
✓ When the controller demand of HP BP matches with BP1 and BP2
actual position, put BP1 and BP2 on auto to maintain M.S. pressure
as per the set point.
✓ Automatic control interface of LP bypass will increase the fixed
pressure set point value to 12 kg/cm2 and then it will be off.
✓ Check the following parameters :
✓ HRH pressure which maintains at 10 –12 kg/cm2
✓ CRH temperature after attemperation which should rise
✓ M.S./HRH temperature should rise
The steam parameters suitable to turbine condition are build-up
through this process to get the required steam temperature and
flow at preset pressure before rolling of turbine
0 1
0
0,S
O
O
O
S p e e d r p m
% 2 0 0 0
50
1000 S o a k in g •
6 0 0 r - - - - -
0 0
0
63 6
6 0 0
1
0
0
4 5 0 %
8 0
0
10 0
c
3 50
3 0 0
2$ 0
2 -0 0
H R H
3 4
3 0
M S
1 6 0
125
"10 0 P r
"24
"18
7 6
12 5 0
'25
6
0 0
K g t c m 2
M W
0
S T E A i .i T E L P E R A T V R E
-
-
- /
. /
-
-
- . .' . '
. .... "' --.--
.
.... . .. • T T T
T
T ,,,. T T T .. . .
6 0
40
6 0 12 0 2 4 0 3 0 0 4 2 0 4 8 0 5 4 0
S T E A M P R E SS U R E
H o t R e h e t S t e a r n
- - l -
l-
o
.4 4- '
4
-
- - - - -
-
1
-
.
.
.
.
.
,
,
,,
_
. _ lL -
l
-
- --l -+. ---t
5 0
0 2 4 0 3 0 0
S P E E O & L O A D
3 6 0 5 40
1 2 0
60 1 8 0
- - - - - S p e e d
L.o a<t
i
I
1
-
- I
/
,
- /
/
r
- H P C a s
i
n g T e m p ratPJre S e f " o r e S t a r t 3 6 . .C
t
t
- S o a k n g /
..- ---- L S y n c ._ronls ,e
#
I
,... J
•
I l
:
. 1 • • . . . . , . Ill • • . . . . . ..
6 0 1 2 0 2 4 0 4 2 0 6 4 0
3 0 0 3 6 0
18 0
C o ld S r a r t - u p C u r v e s f o r 2 1 0 M W K W U T u r b i n e
6 0 0
6 0 0
6 0 0
2
10 1
00
176
1
4-0 Load
o/
o
10
5 6
70
3
5
Turbine Start-up
Turbine is ready for start-up

More Related Content

Similar to Turbine Start Up.pptx

Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfMadan Karki
 
Gasturbinecourse 130129063149-phpapp02
Gasturbinecourse 130129063149-phpapp02Gasturbinecourse 130129063149-phpapp02
Gasturbinecourse 130129063149-phpapp02Naimat Khan
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Manohar Tatwawadi
 
Sop of turbine lubrication oil system
Sop of turbine lubrication oil systemSop of turbine lubrication oil system
Sop of turbine lubrication oil systemAjit Kumar
 
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfsuryanshsingh836763
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.pptssuser9e9be71
 
SUMMER TRAINING AT NTPC DADRI GAS SECTION
SUMMER TRAINING AT NTPC DADRI GAS SECTIONSUMMER TRAINING AT NTPC DADRI GAS SECTION
SUMMER TRAINING AT NTPC DADRI GAS SECTIONAMIT KUMAR
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdfyusuf699644
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdfMBouderbala
 
Hrsg startup proceudre
Hrsg startup proceudreHrsg startup proceudre
Hrsg startup proceudrekamaraprasad
 
SIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptSIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptMarcWorld
 
POWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEPOWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEManohar Tatwawadi
 
Mini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesMini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesjyotishmathi college
 
CHAP_4_AERO_ENGINE_MAINTENANCE_AND_REPAIR__1_.pptx
CHAP_4_AERO_ENGINE_MAINTENANCE_AND_REPAIR__1_.pptxCHAP_4_AERO_ENGINE_MAINTENANCE_AND_REPAIR__1_.pptx
CHAP_4_AERO_ENGINE_MAINTENANCE_AND_REPAIR__1_.pptxAshishPrabakaran
 
Governing and protection system
Governing and protection systemGoverning and protection system
Governing and protection systemSachin Pyasi
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 

Similar to Turbine Start Up.pptx (20)

Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdf
 
Gasturbinecourse 130129063149-phpapp02
Gasturbinecourse 130129063149-phpapp02Gasturbinecourse 130129063149-phpapp02
Gasturbinecourse 130129063149-phpapp02
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
 
Sop of turbine lubrication oil system
Sop of turbine lubrication oil systemSop of turbine lubrication oil system
Sop of turbine lubrication oil system
 
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
 
Boiler ppt
Boiler pptBoiler ppt
Boiler ppt
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
SUMMER TRAINING AT NTPC DADRI GAS SECTION
SUMMER TRAINING AT NTPC DADRI GAS SECTIONSUMMER TRAINING AT NTPC DADRI GAS SECTION
SUMMER TRAINING AT NTPC DADRI GAS SECTION
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
Hrsg startup proceudre
Hrsg startup proceudreHrsg startup proceudre
Hrsg startup proceudre
 
SIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptSIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.ppt
 
POWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEPOWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINE
 
Lmw turbine oprn. manual
Lmw turbine oprn. manualLmw turbine oprn. manual
Lmw turbine oprn. manual
 
Mini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesMini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliaries
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
CHAP_4_AERO_ENGINE_MAINTENANCE_AND_REPAIR__1_.pptx
CHAP_4_AERO_ENGINE_MAINTENANCE_AND_REPAIR__1_.pptxCHAP_4_AERO_ENGINE_MAINTENANCE_AND_REPAIR__1_.pptx
CHAP_4_AERO_ENGINE_MAINTENANCE_AND_REPAIR__1_.pptx
 
Governing and protection system
Governing and protection systemGoverning and protection system
Governing and protection system
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 

Recently uploaded

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

Turbine Start Up.pptx

  • 2. General Operation Philosophy ➢Achieving and maintaining the required output of the unit ➢Maintaining plant conditions at their optimum efficiency ➢Inspection for plant deterioration by studying the operation trends of main equipments and their auxiliaries (condition monitoring). The maintenance logs can be generated from this information. ➢T esting of stand-by plant auxiliaries, protective devices, alarms and automatic cut-in feature. ➢Changing over of auxiliaries depending on their running hours. ➢Generation of shift logs, event logs, post trip logs etc. ➢Readiness to respond to abnormal conditions.
  • 3. General Preparation for Start-up • It should be ensured that all the repair works on turbine system have been completed and all the permits are are healthy and in cancelled ensuring that equipments operative condition • First of all bring all the electrical equipments to a state of readiness i.e., switch-on the necessary switchgear for motors, valve actuators, controls protections and monitoring system • After this, carry out the necessary interlocks and protection checks feasible under stationary condition of turbine. Certain tests and checks require bypassing of certain interlocks. All such deliberate bypassing of interlocks must be prominently displayed in the control room during the test. After the test, all interlocks and protections should be brought to normal state
  • 4. General Preparation for Start-up • Various valves as per the scheme are to be kept in open or close position. It must be ensured that these valves are kept up in the required position. The isolating valves for all measuring control and protective device should be kept in fully open position • Turbine oil quality should be checked for viscosity, neutralization number, sludges etc. If required, the oil should be drained from MOT and topped up with fresh oil in order to restore the quality • Condenser tube leakage should be checked by charging the CW system and watching the increase in hot well level. If good amount of leakage is noticed, then action must be taken to plug the leaking tubes
  • 5. Turbine Start-up Requirements Turbine start-ups are classified as cold start-up, warm start-up and hot start-up depending on the HP turbine metal temperature as follows: If HPT metal temperature >350oC -Hot start-up If HPT metal temperature between 150 - 350oC -Warm start-up If HPT metal temperature < 150oC -Cold start-up The start-up procedure decides following aspects: • i) Steam parameters suitability viz. pressure and temperature & its raising rates. • ii) Soaking time for turbine and main valves • iii) Turbine speed raising, loading rates • iv) T otal time required reaching the full load.
  • 6. Turbine Start-up Requirements ❖ Generally absolute cold start-up of turbine takes 6 hours to reach the full load ❖ The turbine after two hours shutdown may require only half an hour to one hour to reach the full load (depending on boiler load) ❖ The rate of rise of steam parameters and turbine parameters, (speed, load) are specified by start-up curves for the regime. Operators should provide necessary time for proper soaking of turbine at specified speeds (600 and 3000 rpm), as shown by the curves, for permitting expansions at normal rate. This will give good temperature & load margins after synchronization
  • 7. Cold Start-up Steps 1. Pre-start checks and testing of supplies 2. Establishing lube oil and jacking oil system 3. Putting turbine on barring gear 4. Warming of main steam pipe lines (steam line drains and turbine SLC drains must be kept open) 5. Pulling-up vacuum in condenser by starting ejector 6. Establishing turbine gland sealing (at about 0.2 kg/cm2 vacuum) 7. Putting main ejector into service (at about 0.7 – 0.8 kg/cm2 vacuum) and withdrawing starting ejector. Normal vacuum of 0.91 kg/cm2 is obtained. 8. Charging of reheater through HP-LP Bypass system 9. Building of steam parameters suitable to turbine condition, viz. for cold start-up parameters are as follows:
  • 8. Cold Start-up Steps M.S. H.R.H. Pressure 30- 35 kg/cm2 T emperature 320o – 350oC Flow 95 –100 t/hr 10-12 kc/cm2 320o – 350oC 10. Warm-up of turbine stop valves (ESV & IV) to get the TSE margins >30oK & fulfillment of steam pressure and temperature criteria (X1, X2,X3) 11. Turbine trip resetting by bringing S.L.L.D. to zero position. 12.Opening of stop valves (ESV & IV) by raising the SLLD (starting device) to 42% and 56% respectively 13. Warming of HP control valves by opening warm-up control drains valves through warm-up controller
  • 9. Cold Start-up Steps 14. Fulfillment of steam temperature criteria with respect to mid wall temperature of turbine metal to ensure that main steam temperature is greater than turbine metal temperature & degree of superheat is > 50oC as recommended by criteria curves X4 and X5 respectively. TSE margins are ensured greater than 35oK 15. Preparing the electro-hydraulic governing system ready for operation by setting the speed & load controller reference values & keeping hydraulic governor as back-up by raising speeder gear position to 100% 16. Turbine rolling to 600 rpm through speed controller 17. Soaking of turbine at 600 rpm to fulfilled X6 criterion (approx. 1 hr), which ensures the proper warming of HP turbine with respect to main steam temperature. Turbine parameters monitoring 18. Speed raising to 3000 rpm by setting speed reference value at 3000 rpm without stopping in between
  • 10. X5 Criterion- M.S. Temperature
  • 11. X5 Criterion- H.R.H. Temperature
  • 12. Cold Start-up Steps 19.Soaking of turbine at 3000 rpm to fulfilled X7 criterion (approx. 45 min.), which ensures proper warming of IP turbine with respect to HRH temperature. Monitoring turbine expansion and shaft/bearing vibration trend 20.Ensuring TSE upper temperature margin of turbine greater than 35oK 21. Synchronization of generator to grid 22. Load raising to 10% (20MW) through speed reference setter. 23. Closing of all manual operated drains 24.Ensuring closure of HP-LP bypass valves by increasing pressure set point above M.S. pressure 25. Check that load controller becomes active at about 20 MW. 26. Raising the M.S. pr. to 50 kg/cm2 by taking coal mill into service and load is raised to 40 MW 27.Charging of LP heaters from steam side and putting the level controllers of LPH 2 & 3 on auto
  • 13. Cold Start-up Steps 28. T aking second coal mill into service and raising steam pressure. Ensure that HP bypass set point is kept at higher value than actual pressure 29.Raise the turbogenerator load to 100 MW. T ake HP heaters into service. 30.Establish second air cycle, second BFP , third coal mill and raise the steam parameters 31.Changing over the deaerator pegging steam supply from CRH to extraction-4 at about 55% load (when the NRVs release is obtained). 32.Raising the load to 150 MW 33. T aking the fourth coal mill into service. Put at least two mills on Auto. Stabilize the M.S. pressure at about 140 kg/cm2 34.Putting CMC in to service after adjusting the M.S. Pressure set point to match with actual pressure 35.Raising the turbogenerator load to 210 MW through unit target load set point at CMC 36.Monitoring of turbovisory parameters, viz. absolute expansion, differential expansions, axial shift, bearing & shaft vibrations, casing temperatures at admission and exhaust locations, bearing temperatures
  • 14. Turbine Oil System Check that: ➢ MOT level is normal ( 0+350 mm ) and basket strainers are cleaned ➢ Fire protection shut-off valve is closed and solenoid is reset at turbine floor and in MOT room. ➢ Readiness of Lube oil pumps and JOPs ➢ Sub-group control of oil system "Auto-ON" ➢ Ensure one of the lube oil coolers is in service from oil side and water side.
  • 17. Turbine Oil System Operation : • AOP and JOP can be started manually from PCR or on auto through “SLC-ON” or through SGC "Auto-ON" • T ake the standby trial of AOP , EOP and JOP • Watch drop in MOT level after AOP is started (280 mm). • Put temperature controller SLC "ON" • Watch the oil temperature at oil cooler outlet and ensure that it is maintains between 40o – 45oC by temperature controller Watch following parameters : -Discharge pressure of AOP : 6.5 kg/cm2 i) ii) iii) -Oil Pressure before cooler -Oil pressure after cooler : : 5.4 kg/cm2 4.8 kg/cm2 -MOT level -Jacking Oil Pressure : : + 25 mm 120 kg/cm2
  • 18. Turbine Oil System When the turbine is running, check the bearing drain oil temperature and babbit temperatures : • Bearing drain oil temperature : • Journal bearing babbit temperature : • Thrust bearing babbit temperature : • • • • • • • • • • • < 60oC < 90oC < 110oC Permissives for starting turning gear : Seal oil to H2 DP Seal oil pressure TE & EE H2 gas pressure H2 purity Liquid in generator : : : : : > 1 kg/cm2 > 4.4 kg/cm2 > 3.3 kg/cm2 > 97% Not present Turning gear can be started by opening gate valve either manually or through SLC. Observe that turbine speed on turning gear is as follows : When no vacuum in condenser At normal vacuum condition : : 110 – 120 rpm 150 – 160 rpm
  • 19. Turbine Oil System After turning gear is ON,AOP amperes will increase to 125Afrom 105A. AOP , JOP and turning gear trip and pick-up speeds are as follows : ➢ When MOP takes over, the discharge oil pressure will be 8.5 – 9.5 kg/cm2 depending on turbine speed. ➢ Interlocks ofAOP , EOP & JOP ➢ The standby AOP (SLC ON) will pick-up if discharge oil pressure < 4.8 kg/cm2 or the runningAOP is OFF ➢ DC Emergency Oil Pump will pick-up when SLC is ON and if lube oil pressure is < 1.1 kg/cm2 ➢ The standby JOP (SLC ON) will pick-up if running JOP trips. Trip Speed rpm Pick-up Spee rpm i) Turning gear 240 210 ii) J.O.P. 540 510 iii) A.O.P. 2850 2800
  • 20. Condensate & Feedwater Line Charging
  • 21. Vacuum Pulling and Gland Sealing Checks • Line-up the steam ejectors • Ensure 220 V DC supply to the solenoid of vacuum breaker valve and it is closed • Ensure water sealing to glands of all the valves in vacuum circuit • CW system is established • Condensate system is established • Ensure gland steam cooler siphone is filled-up • Ensure electrical supply to the motors of seal steam leak-off controller and seal steam supply controller. Their oil pumps are working on auto to maintain oil pressure of 60 kg/cm2 • Check that valve AS301 (CRH Steam to glands) is in closed position • The turbine is put on turning gear
  • 22. Vacuum Pulling and Gland Sealing
  • 23. Vacuum Pulling and Gland Sealing Operation • Charge the gland steam header by opening AS 378 valve and build up the pressure 6 –6. 5 kg/cm2. Set the pressure 6.5 kg/cm2 and put the ejector steam pressure control on auto. • Start vacuum pulling through starting ejector by first opening steam valve and then the air valve. • Start one exhauster fan of gland steam cooler • After building up 0.2 kg/cm2 vacuum, open the gland seal steam supply valve and charge the header at pressure 0.01 kg/cm2(g). steam pressure control on auto. • After opening the steam supply valve, the header drain valve MAL-81 will close on auto. • After establishing the gland sealing, the condenser vacuum will improve at a faster rate • When vacuum builds-up to 0.7 kg/cm2, take one main ejector in to service by opening first its steam valve (AS02 or AS03) and then the air Put the gland valve. Cut-off the starting ejector by closing air valve and then steam valve. • Note the final value of vacuum at which it stabilizes (0.92 kg/cm2) and also note HPT/IPT & LPT differential expansions
  • 24. Warming of Steam Piping Checks : ➢Ensure all the drain valves M.S., CRH and HRH lines are open ➢M.S. line to be charged when drum pressure is raised to 10 kg/cm2 after blow-down Operation : ❖ Charge the M.S. line by opening the boiler outlet bypass valves (MS 301A/302A) ❖ Ensure that there is no hammering in M.S. pipeline ❖ Watch the temperature rise of ESV mid wall ❖ Rate of heating of steam pipelines should not exceed 25o to 30oC per 5 min. ❖ During heating of M.S. & R.H. steam pipelines; the temperature difference between LHS & RHS pipelines should not exceed 15oC. But this difference should not exceed 10oC when the set is on load
  • 25. HP-LP Bypass System Charging Checks : • Ensure that HP Bypass control oil pumps are running on auto and maintaining the pressure oil pressure 110 kg/cm2 and oil tank level is normal • All the oil supply/return/leak-off Sulzer valves are open and there is no oil leakage in the system • ESV and IVs are closed • Cooling water to HP BP valve gland from CEP is open • Isolating spray valve before BD valve is open and BD valve is closed on auto. Ensure that it is not passing. • All controls of HP bypass are on manual mode and all valves are closed. • Ensure power supply to HP BP panel is normal • Ensure that control oil pressure to LP bypass station is > 5.5 kg/cm2 • All manually operated & auto injection water valves (V1, V2, V3, V4) of LP bypass station are closed. • All the drain valves of HP &LP bypass are open • Ensure condenser vacuum is > 0.75 kg/cm2 • BFP & CEP are running and discharge header pressures are adequate
  • 27. HP-LP Bypass System Charging Operation : ✓ Set the fixed pressure set point of LPBP at 3 kg/cm2 ✓ Put the LP Bypass controller on “Auto” ✓ Make the automatic control interface "ON" ✓ Ensure drain valves of CRH, HRH and Warm-up valves are open ✓ Open HPBP warm-up valves locally. ✓ Set the pressure master set point at 35 kg/cm2 ✓ Put spray water control valves BPE1 & BPE2 of HPBP on “Auto” ✓ After warming up for 15 min. open HPBP valves BP-1 and BP-2 about 5%. ✓ Increase the BP1 & BP2 position manually in a step of 5% ✓ Check that LPBP valves and injection water valves open on auto to maintain HRH pressure
  • 28. HP-LP Bypass System Charging Operation contd… : ✓ Close LPBP warm-up valve ✓ When LPBP position goes to 25% increase the oil-firing rate in boiler by taking into service CD oil elevation pairs 1-3 & 2-4. ✓ When the controller demand of HP BP matches with BP1 and BP2 actual position, put BP1 and BP2 on auto to maintain M.S. pressure as per the set point. ✓ Automatic control interface of LP bypass will increase the fixed pressure set point value to 12 kg/cm2 and then it will be off. ✓ Check the following parameters : ✓ HRH pressure which maintains at 10 –12 kg/cm2 ✓ CRH temperature after attemperation which should rise ✓ M.S./HRH temperature should rise The steam parameters suitable to turbine condition are build-up through this process to get the required steam temperature and flow at preset pressure before rolling of turbine
  • 29. 0 1 0 0,S O O O S p e e d r p m % 2 0 0 0 50 1000 S o a k in g • 6 0 0 r - - - - - 0 0 0 63 6 6 0 0 1 0 0 4 5 0 % 8 0 0 10 0 c 3 50 3 0 0 2$ 0 2 -0 0 H R H 3 4 3 0 M S 1 6 0 125 "10 0 P r "24 "18 7 6 12 5 0 '25 6 0 0 K g t c m 2 M W 0 S T E A i .i T E L P E R A T V R E - - - / . / - - - . .' . ' . .... "' --.-- . .... . .. • T T T T T ,,,. T T T .. . . 6 0 40 6 0 12 0 2 4 0 3 0 0 4 2 0 4 8 0 5 4 0 S T E A M P R E SS U R E H o t R e h e t S t e a r n - - l - l- o .4 4- ' 4 - - - - - - - 1 - . . . . . , , ,, _ . _ lL - l - - --l -+. ---t 5 0 0 2 4 0 3 0 0 S P E E O & L O A D 3 6 0 5 40 1 2 0 60 1 8 0 - - - - - S p e e d L.o a<t i I 1 - - I / , - / / r - H P C a s i n g T e m p ratPJre S e f " o r e S t a r t 3 6 . .C t t - S o a k n g / ..- ---- L S y n c ._ronls ,e # I ,... J • I l : . 1 • • . . . . , . Ill • • . . . . . .. 6 0 1 2 0 2 4 0 4 2 0 6 4 0 3 0 0 3 6 0 18 0 C o ld S r a r t - u p C u r v e s f o r 2 1 0 M W K W U T u r b i n e 6 0 0 6 0 0 6 0 0 2 10 1 00 176 1 4-0 Load o/ o 10 5 6 70 3 5
  • 30. Turbine Start-up Turbine is ready for start-up