SlideShare a Scribd company logo
Energy | Environment | Chemical www.thermaxglobal.com
Presented by –:
Mr. Akshay kunakekar
shift- incharge
Energy | Environment | Chemical www.thermaxglobal.com
Introduction
Operation of steam turbine is a complex process. Before starting the rolling of a
turbine, auxiliary systems, are to be properly put in service. Special care is required
to be taken for starting of Turbine.
Normally for start up of a turbine some sequence of operation is
followed. We will discuss the operation of different systems as per sequence.
NOTE-:
Don’t do any field activities without informing to control room
Energy | Environment | Chemical www.thermaxglobal.com
Block diagram
Open all
drains
Steam
line
charge
cooling
water
operation
Condensa
te steam
operation
Oil
System
Barring
gear
operation
Vacuum
build-up
Gland
steam
charge
Rolling of
turbine
Synchroni
zation
clearance
Close all
drains
cooling water operation
Energy | Environment | Chemical www.thermaxglobal.com
Energy | Environment | Chemical www.thermaxglobal.com
Operation of steam line charge.
1. First of all drains are should be in open condition before start the steam line charging.
2. Open the warm up went to charge the Turbine inlet steam line as per OEM suggested
parameters.
3. Give clearance to control room for open the MSSV Bypass .
4. Throttle the steam line drain after removing of condensate.
5. After steam line in operation close the main drain and traps to be taken in line.
Energy | Environment | Chemical www.thermaxglobal.com
Before Steam Charging
Following Drains should be in open condition.
1. Main steam line drain.
2. Warm-up vent open.
3. Throttle valve drain.
4. ESV drain.
5. Casing drain.
6. Wheel case drain.
7. Extraction line drain.
8. PRDS line drain.
Energy | Environment | Chemical www.thermaxglobal.com
Casing drain ESV Drain
Energy | Environment | Chemical www.thermaxglobal.com
QCNRV before & after drain Wheel chamber drain
Energy | Environment | Chemical www.thermaxglobal.com
Throttle valve drain. Main steam line drain.
Energy | Environment | Chemical www.thermaxglobal.com
Operation of cooling water system
To circulate cooling water in the condenser, cooling water pumps are to be started.
Following steps are followed to circulate cooling water in the condenser.
1. Ensure level of the cooling tower basin is normal.
2. Keep suction valve of the pump in open condition and discharge valve in closed
condition.
3 Ensure inlet and outlet cooling water valves of condenser and hot water distributor
valves of cooling tower are in open condition.
4. Do the priming & Start the pump. If there is variable speed drive then start the pump
at lower speed and gradually increase the speed.
5. Open the discharge valve.
6. Observe cooling water is falling on the cooling tower.
7. Increase speed or Start other pump to get required amount of cooling water flow at
the condenser. –
8.Observe all the cooling water pumps are sharing load.
Energy | Environment | Chemical www.thermaxglobal.com
Inlet and outlet cooling water valves
of condenser
level of the cooling tower basin
Energy | Environment | Chemical www.thermaxglobal.com
Condensate steam operation
1.Ensure condenser hot well level is adequate. Otherwise maintain the hot well with
make up DM water.
2. Open suction of the pump. Start the pump. Open discharge valve and Ensure
Differential pressure of the strainer is normal.
3. Open condensate inlet and outlet valves of GVC, ejector condenser.
Energy | Environment | Chemical www.thermaxglobal.com
Condensate extraction pump
Energy | Environment | Chemical www.thermaxglobal.com
Operation of oil system
1. Ensure the all work permit is closed.
2. Ensure Proper supply is available
3. Ensure emergency push button is release from field.
4. Ensure Main oil tank level is normal.
5. Valves provided at oil line at oil filter and oil cooler are in open condition.
6. Cooling water outlet valve of oil cooler is in close condition .
7. Start oil pump.
8. Check oil filter differential pressure. If it is high, change the filter cartridge or change the
filter.
9. Maintain oil temperature by adjusting cooling water outlet valve of oil cooler.
10. Keep the standby oil pump and Emergency oil pump in Auto mode.
11. Ensure overhead tank is full.
Energy | Environment | Chemical www.thermaxglobal.com
Oil system
Energy | Environment | Chemical www.thermaxglobal.com
Overhead tank overflow indication EOP mode selection
Energy | Environment | Chemical www.thermaxglobal.com
Operation of barring gear
Before rolling, turbine is required to be kept on barring operation at least 8
hours before. To put the turbine on barring operation.
1. Ensure lube oil system(AOP PUMP) is in service and oil is circulating at
all the bearings and oil pressure is at desired level.i.e.1.8-2kg/cm2.
2. Ensure emergency release button from local.
3. Start barring gear motor.
4. Observe rotor is rotating at barring speed without increase in bearing
vibration and temperature and there is no abnormal sound.
NOTE-:
when DC supply failed then Put BGM in manual mode and local
emergency push button of BGM should be pushed.
Energy | Environment | Chemical www.thermaxglobal.com
Vacuum build up
Ejector/
hogger
Vacuum
pump
Energy | Environment | Chemical www.thermaxglobal.com
Vacuum build up
1.Ensure auxiliary steam at desired pressure and temperature is available.
2. Ensure the vacuum break valve of the condenser is closed.
3. Ensure cooling water is circulating in the condenser and turbine gland is charged
fully.
4. Open steam valve of the hogger.
5. Observe steam is vented to atmosphere.
6. Open hogger air valve.
7. Observe vacuum inside condenser is increasing slowly
8. After normalization of plant take ejector in line.
Energy | Environment | Chemical www.thermaxglobal.com
Ejector & Hogger system
Steam valve Air valve
Energy | Environment | Chemical www.thermaxglobal.com
vacuum pump
Energy | Environment | Chemical www.thermaxglobal.com
Operation of gland steam charging
1.ensure auxiliary steam is available from PRDS at desired pressure and
temperature i.e. 10 kg /cm2 & 250 deg.c
2. Ensure GVC is in running condition.
3.Open gland steam header and gland drains.
4.Open HP side valve slowly. (1)
5.Open LP side valve slowly.(2)
1 2
Energy | Environment | Chemical www.thermaxglobal.com
Rolling of turbine
1. Ensure lube oil and control oil is available, cooling water is flowing in
condenser, turbine is on barring, gland is properly charged and vacuum is
available.
2. Steam pressure and temperature are within limit.
3. All the turbine tripping interlocks are healthy.
4. .Ensure ESV is in closed position .
5. Acknowledge the Alarm on DCS as well TCP
6. Alarm rest on DCS as well TCP
7. Turbine Trip reset
8. LP reset. On DCS if not reset do on field.
9. SOV reset from panel.
10. ESV open command.
11. Woodward 505 press “RESET” button.
12. Woodward 505 press “RUN” button.
13. observe bearing temperature, lube oil pressure at bearings, bearing
vibration, any abnormal sound during start-up.
Energy | Environment | Chemical www.thermaxglobal.com
14. Ensure barring device is disengaged.
15.Maintain lube oil temperature by adjusting cooling water at oil cooler.
16. At critical speed zone the speed to be raised faster and bearing vibrations should
be within limit.
17. Once turbine reaches full speed check all the parameters.
18.if the main oil pump is mechanically coupled with turbine rotor then stop AOP and
check oil pressure.
19. Give clearance to electrical dept. for synchronization.
20. After taking load on TG close the warm up went & all drains of turbine
Energy | Environment | Chemical www.thermaxglobal.com
Turbine Alarm Rest page
Energy | Environment | Chemical www.thermaxglobal.com
LP Reset
Energy | Environment | Chemical www.thermaxglobal.com
SOV Reset ESV Open command
Energy | Environment | Chemical www.thermaxglobal.com
Woodward 505
Energy | Environment | Chemical www.thermaxglobal.com
Thank you ……

More Related Content

What's hot

Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)
Billa ParameswaraRao
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
Ashish Kumar Jain
 
Turbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & WorkingTurbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & Working
Tahoor Alam Khan
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
Ashvani Shukla
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
Jaypee power ventures limited
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
Ashvani Shukla
 
Lmw turbine oprn. manual
Lmw turbine oprn. manualLmw turbine oprn. manual
Lmw turbine oprn. manual
Kattukolu Kishorereddy
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
Manohar Tatwawadi
 
Condensate system
Condensate systemCondensate system
Condensate system
RAVI PAL SINGH
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
VEERABHADRA SWAMY
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
VEERABHADRA SWAMY
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
Gaurav Kaushik
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
Ashish Kumar Jain
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
Manohar Tatwawadi
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)
Jigyasa Singh
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Manohar Tatwawadi
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
Vundavilli Gautham
 
POWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEPOWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINE
Manohar Tatwawadi
 

What's hot (20)

Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
 
Turbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & WorkingTurbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & Working
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
Lmw turbine oprn. manual
Lmw turbine oprn. manualLmw turbine oprn. manual
Lmw turbine oprn. manual
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
Condensate system
Condensate systemCondensate system
Condensate system
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
POWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEPOWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINE
 

Similar to Final Turbine rolling ppt Akshay.pptx

Turbine operation.pptx
Turbine operation.pptxTurbine operation.pptx
Turbine operation.pptx
DhananjayaTripathy1
 
49539990 burner-management-system
49539990 burner-management-system49539990 burner-management-system
49539990 burner-management-systemMowaten Masry
 
Turbine Start Up.pptx
Turbine Start Up.pptxTurbine Start Up.pptx
Turbine Start Up.pptx
ssuser0cdaa1
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
ssuser9e9be71
 
Competency Training Evidence for Panel Operator Answers
Competency Training Evidence for Panel Operator AnswersCompetency Training Evidence for Panel Operator Answers
Competency Training Evidence for Panel Operator Answersmark robertson
 
Curso refrigeración comercial y domestica
Curso refrigeración comercial y domesticaCurso refrigeración comercial y domestica
Curso refrigeración comercial y domestica
Percy Alfredo Huanca Chambi
 
Plant Air & Inst Air.ppt
Plant Air & Inst Air.pptPlant Air & Inst Air.ppt
Plant Air & Inst Air.ppt
MeherabHossainJihad
 
Hrsg startup proceudre
Hrsg startup proceudreHrsg startup proceudre
Hrsg startup proceudre
kamaraprasad
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
MBouderbala
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
yusuf699644
 
THERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSTHERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONS
Manohar Tatwawadi
 
hydroelectric power plant_overview.ppt
hydroelectric power plant_overview.ppthydroelectric power plant_overview.ppt
hydroelectric power plant_overview.ppt
AnonymousYoutuber2
 
Sabardairy Training Report
Sabardairy Training ReportSabardairy Training Report
Sabardairy Training Report
NiravDesai66
 
A guide for firetube boiler testes
A guide for firetube boiler   testesA guide for firetube boiler   testes
A guide for firetube boiler testes
ederpitapeva
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
Manohar Tatwawadi
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
ssuser8006c7
 
B737 NG Air Systems
B737 NG Air SystemsB737 NG Air Systems
B737 NG Air Systems
theoryce
 
Main air compressors PPT.pptx
Main air compressors PPT.pptxMain air compressors PPT.pptx
Main air compressors PPT.pptx
deepu501949
 
Gas Turbine Power Plant.pdf
Gas Turbine Power Plant.pdfGas Turbine Power Plant.pdf
Gas Turbine Power Plant.pdf
KIET Group of Institutions
 
Archive for the ‘refrigerator commissioning’ tag
Archive for the ‘refrigerator commissioning’ tagArchive for the ‘refrigerator commissioning’ tag
Archive for the ‘refrigerator commissioning’ tag
Muhammad Awais
 

Similar to Final Turbine rolling ppt Akshay.pptx (20)

Turbine operation.pptx
Turbine operation.pptxTurbine operation.pptx
Turbine operation.pptx
 
49539990 burner-management-system
49539990 burner-management-system49539990 burner-management-system
49539990 burner-management-system
 
Turbine Start Up.pptx
Turbine Start Up.pptxTurbine Start Up.pptx
Turbine Start Up.pptx
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
Competency Training Evidence for Panel Operator Answers
Competency Training Evidence for Panel Operator AnswersCompetency Training Evidence for Panel Operator Answers
Competency Training Evidence for Panel Operator Answers
 
Curso refrigeración comercial y domestica
Curso refrigeración comercial y domesticaCurso refrigeración comercial y domestica
Curso refrigeración comercial y domestica
 
Plant Air & Inst Air.ppt
Plant Air & Inst Air.pptPlant Air & Inst Air.ppt
Plant Air & Inst Air.ppt
 
Hrsg startup proceudre
Hrsg startup proceudreHrsg startup proceudre
Hrsg startup proceudre
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
THERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSTHERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONS
 
hydroelectric power plant_overview.ppt
hydroelectric power plant_overview.ppthydroelectric power plant_overview.ppt
hydroelectric power plant_overview.ppt
 
Sabardairy Training Report
Sabardairy Training ReportSabardairy Training Report
Sabardairy Training Report
 
A guide for firetube boiler testes
A guide for firetube boiler   testesA guide for firetube boiler   testes
A guide for firetube boiler testes
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
 
B737 NG Air Systems
B737 NG Air SystemsB737 NG Air Systems
B737 NG Air Systems
 
Main air compressors PPT.pptx
Main air compressors PPT.pptxMain air compressors PPT.pptx
Main air compressors PPT.pptx
 
Gas Turbine Power Plant.pdf
Gas Turbine Power Plant.pdfGas Turbine Power Plant.pdf
Gas Turbine Power Plant.pdf
 
Archive for the ‘refrigerator commissioning’ tag
Archive for the ‘refrigerator commissioning’ tagArchive for the ‘refrigerator commissioning’ tag
Archive for the ‘refrigerator commissioning’ tag
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 

Final Turbine rolling ppt Akshay.pptx

  • 1. Energy | Environment | Chemical www.thermaxglobal.com Presented by –: Mr. Akshay kunakekar shift- incharge
  • 2. Energy | Environment | Chemical www.thermaxglobal.com Introduction Operation of steam turbine is a complex process. Before starting the rolling of a turbine, auxiliary systems, are to be properly put in service. Special care is required to be taken for starting of Turbine. Normally for start up of a turbine some sequence of operation is followed. We will discuss the operation of different systems as per sequence. NOTE-: Don’t do any field activities without informing to control room
  • 3. Energy | Environment | Chemical www.thermaxglobal.com Block diagram Open all drains Steam line charge cooling water operation Condensa te steam operation Oil System Barring gear operation Vacuum build-up Gland steam charge Rolling of turbine Synchroni zation clearance Close all drains cooling water operation
  • 4. Energy | Environment | Chemical www.thermaxglobal.com
  • 5. Energy | Environment | Chemical www.thermaxglobal.com Operation of steam line charge. 1. First of all drains are should be in open condition before start the steam line charging. 2. Open the warm up went to charge the Turbine inlet steam line as per OEM suggested parameters. 3. Give clearance to control room for open the MSSV Bypass . 4. Throttle the steam line drain after removing of condensate. 5. After steam line in operation close the main drain and traps to be taken in line.
  • 6. Energy | Environment | Chemical www.thermaxglobal.com Before Steam Charging Following Drains should be in open condition. 1. Main steam line drain. 2. Warm-up vent open. 3. Throttle valve drain. 4. ESV drain. 5. Casing drain. 6. Wheel case drain. 7. Extraction line drain. 8. PRDS line drain.
  • 7. Energy | Environment | Chemical www.thermaxglobal.com Casing drain ESV Drain
  • 8. Energy | Environment | Chemical www.thermaxglobal.com QCNRV before & after drain Wheel chamber drain
  • 9. Energy | Environment | Chemical www.thermaxglobal.com Throttle valve drain. Main steam line drain.
  • 10. Energy | Environment | Chemical www.thermaxglobal.com Operation of cooling water system To circulate cooling water in the condenser, cooling water pumps are to be started. Following steps are followed to circulate cooling water in the condenser. 1. Ensure level of the cooling tower basin is normal. 2. Keep suction valve of the pump in open condition and discharge valve in closed condition. 3 Ensure inlet and outlet cooling water valves of condenser and hot water distributor valves of cooling tower are in open condition. 4. Do the priming & Start the pump. If there is variable speed drive then start the pump at lower speed and gradually increase the speed. 5. Open the discharge valve. 6. Observe cooling water is falling on the cooling tower. 7. Increase speed or Start other pump to get required amount of cooling water flow at the condenser. – 8.Observe all the cooling water pumps are sharing load.
  • 11. Energy | Environment | Chemical www.thermaxglobal.com Inlet and outlet cooling water valves of condenser level of the cooling tower basin
  • 12. Energy | Environment | Chemical www.thermaxglobal.com Condensate steam operation 1.Ensure condenser hot well level is adequate. Otherwise maintain the hot well with make up DM water. 2. Open suction of the pump. Start the pump. Open discharge valve and Ensure Differential pressure of the strainer is normal. 3. Open condensate inlet and outlet valves of GVC, ejector condenser.
  • 13. Energy | Environment | Chemical www.thermaxglobal.com Condensate extraction pump
  • 14. Energy | Environment | Chemical www.thermaxglobal.com Operation of oil system 1. Ensure the all work permit is closed. 2. Ensure Proper supply is available 3. Ensure emergency push button is release from field. 4. Ensure Main oil tank level is normal. 5. Valves provided at oil line at oil filter and oil cooler are in open condition. 6. Cooling water outlet valve of oil cooler is in close condition . 7. Start oil pump. 8. Check oil filter differential pressure. If it is high, change the filter cartridge or change the filter. 9. Maintain oil temperature by adjusting cooling water outlet valve of oil cooler. 10. Keep the standby oil pump and Emergency oil pump in Auto mode. 11. Ensure overhead tank is full.
  • 15. Energy | Environment | Chemical www.thermaxglobal.com Oil system
  • 16. Energy | Environment | Chemical www.thermaxglobal.com Overhead tank overflow indication EOP mode selection
  • 17. Energy | Environment | Chemical www.thermaxglobal.com Operation of barring gear Before rolling, turbine is required to be kept on barring operation at least 8 hours before. To put the turbine on barring operation. 1. Ensure lube oil system(AOP PUMP) is in service and oil is circulating at all the bearings and oil pressure is at desired level.i.e.1.8-2kg/cm2. 2. Ensure emergency release button from local. 3. Start barring gear motor. 4. Observe rotor is rotating at barring speed without increase in bearing vibration and temperature and there is no abnormal sound. NOTE-: when DC supply failed then Put BGM in manual mode and local emergency push button of BGM should be pushed.
  • 18. Energy | Environment | Chemical www.thermaxglobal.com Vacuum build up Ejector/ hogger Vacuum pump
  • 19. Energy | Environment | Chemical www.thermaxglobal.com Vacuum build up 1.Ensure auxiliary steam at desired pressure and temperature is available. 2. Ensure the vacuum break valve of the condenser is closed. 3. Ensure cooling water is circulating in the condenser and turbine gland is charged fully. 4. Open steam valve of the hogger. 5. Observe steam is vented to atmosphere. 6. Open hogger air valve. 7. Observe vacuum inside condenser is increasing slowly 8. After normalization of plant take ejector in line.
  • 20. Energy | Environment | Chemical www.thermaxglobal.com Ejector & Hogger system Steam valve Air valve
  • 21. Energy | Environment | Chemical www.thermaxglobal.com vacuum pump
  • 22. Energy | Environment | Chemical www.thermaxglobal.com Operation of gland steam charging 1.ensure auxiliary steam is available from PRDS at desired pressure and temperature i.e. 10 kg /cm2 & 250 deg.c 2. Ensure GVC is in running condition. 3.Open gland steam header and gland drains. 4.Open HP side valve slowly. (1) 5.Open LP side valve slowly.(2) 1 2
  • 23. Energy | Environment | Chemical www.thermaxglobal.com Rolling of turbine 1. Ensure lube oil and control oil is available, cooling water is flowing in condenser, turbine is on barring, gland is properly charged and vacuum is available. 2. Steam pressure and temperature are within limit. 3. All the turbine tripping interlocks are healthy. 4. .Ensure ESV is in closed position . 5. Acknowledge the Alarm on DCS as well TCP 6. Alarm rest on DCS as well TCP 7. Turbine Trip reset 8. LP reset. On DCS if not reset do on field. 9. SOV reset from panel. 10. ESV open command. 11. Woodward 505 press “RESET” button. 12. Woodward 505 press “RUN” button. 13. observe bearing temperature, lube oil pressure at bearings, bearing vibration, any abnormal sound during start-up.
  • 24. Energy | Environment | Chemical www.thermaxglobal.com 14. Ensure barring device is disengaged. 15.Maintain lube oil temperature by adjusting cooling water at oil cooler. 16. At critical speed zone the speed to be raised faster and bearing vibrations should be within limit. 17. Once turbine reaches full speed check all the parameters. 18.if the main oil pump is mechanically coupled with turbine rotor then stop AOP and check oil pressure. 19. Give clearance to electrical dept. for synchronization. 20. After taking load on TG close the warm up went & all drains of turbine
  • 25. Energy | Environment | Chemical www.thermaxglobal.com Turbine Alarm Rest page
  • 26. Energy | Environment | Chemical www.thermaxglobal.com LP Reset
  • 27. Energy | Environment | Chemical www.thermaxglobal.com SOV Reset ESV Open command
  • 28. Energy | Environment | Chemical www.thermaxglobal.com Woodward 505
  • 29. Energy | Environment | Chemical www.thermaxglobal.com Thank you ……