The Untold Story
of
Konkan Railway
Background











19th July’ 1990 – 26th January’ 1998
760 Km railway line connecting Bombay(Roha) to Managalore
(Thokur)
1,998 bridges(179 Major & 1,819 Minor)
93 tunnels with aggregating length of 83.5 Km
Dream project of Mr.George Fernandez
 Konkan Railway
 Chithoni & Bogha railway bridge
States – Maharashtra, Goa, Karnataka & Kerala
Bombay to Mangalore – 2,041 Km (41 hours)
Bombay to Mangalore – 914 Km (15 hours)
CMD – Mr. E Sreedharan
Q1. In the case study given identity the success or failure of
the following processes – Project conception, Project
definition, Project planning, Project launch & execution?


Project conception
 Concept of Roll on Roll off (RORO)
 Truck drivers find it extremely difficult to drive loaded
trucks through Ghats, undulating surfaces, narrow roads
and poor road and weather conditions
 Saving of fuels, decrease in wear and tear of Lorries
(trucks), relief to drivers of driving in extreme conditions,
can reach faster to destination which leads to saving in
travel time and money
 Project will boost to the economy of country
Q1. In the case study given identity the success or failure of
the following processes – Project conception, Project
definition, Project planning, Project launch & execution?


Project definition
 Four state governments have joined hands with the
central government to begin a project of this size.
 Konkan Railway project is a highly viable project,
financially very attractive, because it reduces distance
between Bombay & Mangalore considerably. The normal
haulage distance between Bombay & Mangalore was
2041 km. After the construction of this project, it would
be 914 km
 The project cost, initially estimated at Rs.860 crore, has
increased by over four times. The project cost has been
estimated at Rs.2,780 crore, with the funding cost alone
being Rs.550 crore
Q1. In the case study given identity the success or failure of
the following processes – Project conception, Project
definition, Project planning, Project launch & execution?


Project planning
 take approval from Planning Commission, central
government and the beneficiary state Government
(Maharashtra, Goa, Karnataka, and Kerala).
 The whole project was decided to complete in five years’
time.
 They planned that the whole railway line would be
divided into 7 zones, each zone concurrent with a
revenue district, and a Chief Engineer was posted for each
zone.
 They selected contractors only from the pre-qualified list
Q1. In the case study given identity the success or failure of
the following processes – Project conception, Project
definition, Project planning, Project launch & execution?


Project launch & execution
 The project was estimated to complete in 5 years’ time,
ultimately took 7 years for completion
 The main reason one was government’s own action. There
was controversy regard to the Goa government and the
work was stopped by the government. The second was
finance
 Three-fourths of the project funds had to be raised in the
market. The expectations were that we could raise the
money from the internal market through bonds, either
tax-free bonds or taxable bonds
 Unexpected adverse geological conditions in some of the
tunnels
Q2. Identify all the important stakeholders?







Central Govt.
 Planning commission
 Finance ministry
 Railway ministry
State Govt.
 Maharashtra
 Goa
 Karnataka
 Kerala
Landowners, Contractors, Investors, Engineers
Chief secretary & Transport secretary of Bangalore & Kerala

All the above stakeholders were important for making Konkan Rail project
successful, especially contractors, landowners & consent of all higher
government authorities of all four states. Without stakeholders,
project wouldn’t be successful. In every project whether it is smaller or
big, project stakeholder play a very important role.
Q3. The success of a project depends largely on the success of
the contractor. What steps were taken to ensure the success of
the contractor?









Contractors were selected from pre-qualified list
Decision making by the contractors had to be approved by the
higher authority.
Payment made to contractors
Mobilization of advances
There need to be a good communication between the
contractors and superiors
Fuel availability on site
Import of sophisticated equipment
Incentives of completion of work
Q4. What do you think were the areas of risk? How were the
risks managed / mismanaged?
Risk

Managed / Mismanaged

Disapproval/resistance from
beneficiary state govt.

This risk was managed by Mr. George Fernandes & Mr. E
Sreedharan by taking serious talks to the heads of the
state and making them believe the benefits that can be
derived from this project. Bureaucratic approach was
taken to solve this problem.

Budget for the project

The budget derived to railway project in India was around
Rs.250 to Rs.300 crores and already 20 – 25 new railway
projects were on going. This was a serious problem
because then it would take 25-30 years for completion of
the project. The govt. also issued tax free bonds but it was
a failure due to share market scam. At last only choice
was External Commercial Borrowing (ECB) through which
the govt. was able to raise Rs.400 crore.

Janata Dal party collapsed

Konkan Railway project was undertaken under Janata Dal
party. Within a week after Mr. E Sreedharan was
appointed as CMD, the party fell and Mr. George
Fernandez was no more the railway minister.
Q4. What do you think were the areas of risk? How were the
risks managed / mismanaged?
Difficulty in acquiring land

For the project, the govt. had to acquire land from 40,000 landowners.
This was a major problem as people would resist from selling their
land. A new strategy was developed to tackle this problem.
Landowners were given compensation for the land as well as rental
charges for 1 to 1 ½ years till they are ready with their new house.

Difficulty in making 760 Km line

Constructing 760 Km railway line would take many years and huge
cost. But this was reduced by adopting a new strategy where in
Konkan line was divided in 7 zones and construction was started at
each zone at the same time. By this the time as well as cost of the
project was reduced.
Many times in construction project, the risk of incomplete work from
the side of contractor is very high. This risk was managed by giving
contract only to recognized, pre-qualified contractors who have
adequate cash flow.
In a cross state construction project, many times there is government
interference. This problem aroused when GOI stopped work in Goa
sector for 9 months. There was no solution to this had a terrible effect
on the rest of the project.

Risk of contractors

Political Interference
Q4. What do you think were the areas of risk? How were the
risks managed / mismanaged?
Difficult geological conditions

The project only had 5 years’ time. In this time, all kinds of survey,
clearance, and geological inspection had to be done. Tunnels needed
geo-technical investigations, but there was no time. Accidents took
place while excavating tunnels in mountains. This delayed the project.

Environment impact

While some people thought that the project was economically
beneficial, some environmental groups raised questions towards its
impact to ecology in the konkan area. These groups stated that the
project would cause destruction of ecology, damage to historical sites
and disrupt the lifestyles of people in densely populated coastal
region.
Q5. Identify the areas of good communication or the lack of it?








It was very important for the people who are involved in this
project to communicate with each other for the completion of
the project.
Hired DOT lines and then established a good communication
network with the headquarters of each of the Chief Engineers.
They were all given FAX machines, they were all given
computers. A computer networking was done, so that
everybody can have any information he wants from anywhere
and message can be passed on time.
Mr. E Sreedharan would sit with the contractors and concerned
engineers and used to see the problems faced by the team and
on the spot used to sort out the problems. So that there is no
difficulty at all for the progress of the work.
Every Monday, Mr. E Sreedharan had a meeting with the Head
of Departments, where all the problems connected with the
whole project were discussed
Q7. What were the new technologies used in Konkan Railway
project?
Optical fibre cable
First time in the history of Indian Railway, Optical fibre cable was
used in Tele-communication network. At that time it was a new
technology which sensed a lot of opposition but today optical
fibre cable is a common thing. Today in the Indian railway
system, the konkan railway has the longest stretch of optical
fibre cable.

Q7. What were the new technologies used in Konkan Railway
project?
Incremental launching method
This is a new technology used for the 1 st time in India (same
technology was used in Delhi Metro). Incremental launch is a
method of building a complete bridge deck from one end to
other end.

Q7. What were the new technologies used in Konkan Railway
project?
Ballast less track
A disadvantage of traditional track structures is heavy demand
for maintenance which leads to heavy maintenance cost.
This can be overcome by using ballastless track.

Q7. What were the new technologies used in Konkan Railway
project?
Gas pressure welding
A new technology of gas pressure welding came from foreign
countries was used. People were trained for this technology
in Japan. The advantage of gas pressure welding is that it
can be done at the site itself. Traditional welding methods
can only be done in welding shops. And it was a problem to
get the welded railing to the site again.


More Related Content

What's hot

Stakeholder analysis of Delhi Metro
Stakeholder analysis of Delhi MetroStakeholder analysis of Delhi Metro
Stakeholder analysis of Delhi Metrojerry christo
 
Delhi metro case solution by nitin bana
Delhi metro case solution by nitin banaDelhi metro case solution by nitin bana
Delhi metro case solution by nitin bana
Nitin Bana
 
The delhi-metro-project
The delhi-metro-projectThe delhi-metro-project
The delhi-metro-projectVikas Saini
 
PM Gatishakti scheme
PM Gatishakti schemePM Gatishakti scheme
PM Gatishakti scheme
shrikrishna kesharwani
 
Ambuja cement
Ambuja cementAmbuja cement
Ambuja cement
sumit_gaurav
 
Hindustan Construction Company (HCC)
Hindustan Construction Company (HCC)Hindustan Construction Company (HCC)
Hindustan Construction Company (HCC)
Sk Md Nayar
 
Delhi Metro: A comprehensive analysis
Delhi Metro: A comprehensive analysisDelhi Metro: A comprehensive analysis
Delhi Metro: A comprehensive analysis
Piyusha Rustagi
 
Delhi metro case study
Delhi metro case studyDelhi metro case study
Delhi metro case study
Shubham Chaudhari
 
Plachimada coca cola case study - Corporate Ethics
Plachimada coca cola case study - Corporate Ethics Plachimada coca cola case study - Corporate Ethics
Plachimada coca cola case study - Corporate Ethics
Harison Xavier
 
Bandra Worli Sea Link
Bandra Worli Sea LinkBandra Worli Sea Link
Bandra Worli Sea Link
Sri Ram Srinivas Dudala
 
Delhi metro - Project Finance
Delhi metro - Project FinanceDelhi metro - Project Finance
Delhi metro - Project Finance
Prashant Dabhade
 
Reserach study on Delhi Metro project
Reserach study on Delhi Metro projectReserach study on Delhi Metro project
Reserach study on Delhi Metro projectSAKSHI AGHI
 
indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)
Gurjit Kaur Kaler
 
Bandra - Worli sea link
Bandra - Worli sea linkBandra - Worli sea link
Bandra - Worli sea link
Ankita Pal
 
Kochi Metro Rail Project.doc
Kochi Metro Rail Project.docKochi Metro Rail Project.doc
Kochi Metro Rail Project.doc
Suryadev Maity
 
CSR ACTIVITY BY LARSEN & TOUBRO
CSR ACTIVITY BY LARSEN & TOUBROCSR ACTIVITY BY LARSEN & TOUBRO
CSR ACTIVITY BY LARSEN & TOUBRO
Bidyut Bikash
 
“Gujarat Metro Rail Project”
“Gujarat Metro Rail Project”“Gujarat Metro Rail Project”
“Gujarat Metro Rail Project”
Vatsal Patel
 
Delhi metro project
Delhi metro projectDelhi metro project
Delhi metro project
Vinay Bardia
 

What's hot (20)

Stakeholder analysis of Delhi Metro
Stakeholder analysis of Delhi MetroStakeholder analysis of Delhi Metro
Stakeholder analysis of Delhi Metro
 
Delhi metro case solution by nitin bana
Delhi metro case solution by nitin banaDelhi metro case solution by nitin bana
Delhi metro case solution by nitin bana
 
The delhi-metro-project
The delhi-metro-projectThe delhi-metro-project
The delhi-metro-project
 
PM Gatishakti scheme
PM Gatishakti schemePM Gatishakti scheme
PM Gatishakti scheme
 
Ambuja cement
Ambuja cementAmbuja cement
Ambuja cement
 
Hindustan Construction Company (HCC)
Hindustan Construction Company (HCC)Hindustan Construction Company (HCC)
Hindustan Construction Company (HCC)
 
Delhi Metro: A comprehensive analysis
Delhi Metro: A comprehensive analysisDelhi Metro: A comprehensive analysis
Delhi Metro: A comprehensive analysis
 
Hyderabad Metro Rail Project
Hyderabad Metro Rail ProjectHyderabad Metro Rail Project
Hyderabad Metro Rail Project
 
Delhi metro case study
Delhi metro case studyDelhi metro case study
Delhi metro case study
 
Plachimada coca cola case study - Corporate Ethics
Plachimada coca cola case study - Corporate Ethics Plachimada coca cola case study - Corporate Ethics
Plachimada coca cola case study - Corporate Ethics
 
Bandra Worli Sea Link
Bandra Worli Sea LinkBandra Worli Sea Link
Bandra Worli Sea Link
 
Delhi metro - Project Finance
Delhi metro - Project FinanceDelhi metro - Project Finance
Delhi metro - Project Finance
 
Reserach study on Delhi Metro project
Reserach study on Delhi Metro projectReserach study on Delhi Metro project
Reserach study on Delhi Metro project
 
indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)
 
Bandra - Worli sea link
Bandra - Worli sea linkBandra - Worli sea link
Bandra - Worli sea link
 
Kochi Metro Rail Project.doc
Kochi Metro Rail Project.docKochi Metro Rail Project.doc
Kochi Metro Rail Project.doc
 
CSR ACTIVITY BY LARSEN & TOUBRO
CSR ACTIVITY BY LARSEN & TOUBROCSR ACTIVITY BY LARSEN & TOUBRO
CSR ACTIVITY BY LARSEN & TOUBRO
 
“Gujarat Metro Rail Project”
“Gujarat Metro Rail Project”“Gujarat Metro Rail Project”
“Gujarat Metro Rail Project”
 
Delhi metro project
Delhi metro projectDelhi metro project
Delhi metro project
 
LARSEN AND TOUBRO
 LARSEN AND TOUBRO LARSEN AND TOUBRO
LARSEN AND TOUBRO
 

Viewers also liked

Indian Railways ppt.
Indian Railways ppt.Indian Railways ppt.
Indian Railways ppt.
vinaybidarimath
 
Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
GAURAV. H .TANDON
 
0877 Civil Society Involvement in SRI
0877 Civil Society Involvement in SRI0877 Civil Society Involvement in SRI
Chapter 8 section 1 (erosion by gravity)
Chapter 8 section 1 (erosion by gravity)Chapter 8 section 1 (erosion by gravity)
Chapter 8 section 1 (erosion by gravity)Mr. Motuk
 
Quantitative Verification of Some Standard Support Patterns in Japanese Tunne...
Quantitative Verification of Some Standard Support Patterns in Japanese Tunne...Quantitative Verification of Some Standard Support Patterns in Japanese Tunne...
Quantitative Verification of Some Standard Support Patterns in Japanese Tunne...
Desh Sonyok
 
Products consumables
Products consumablesProducts consumables
Engr. Syed shahbaz Shah
Engr. Syed shahbaz ShahEngr. Syed shahbaz Shah
Engr. Syed shahbaz Shah
shahbaz sayed
 
Efforts Of Singapore In Controlling Traffic Congestion & Pollution
Efforts Of Singapore In Controlling Traffic Congestion & PollutionEfforts Of Singapore In Controlling Traffic Congestion & Pollution
Efforts Of Singapore In Controlling Traffic Congestion & PollutionANAND G
 
Leadership Dr. E Sreedharan Arun.Vi
Leadership Dr. E Sreedharan   Arun.ViLeadership Dr. E Sreedharan   Arun.Vi
Leadership Dr. E Sreedharan Arun.Vi
Arun VI
 
Nanotechnology in civil engineering
Nanotechnology in civil engineeringNanotechnology in civil engineering
Nanotechnology in civil engineering
Lakshmi K Suresh
 
36551105 delhi-metro
36551105 delhi-metro36551105 delhi-metro
36551105 delhi-metro
Shreyanand Patel
 
Foundation design of burj khalifa (deep foundation<piles>)
Foundation design of burj khalifa (deep foundation<piles>)Foundation design of burj khalifa (deep foundation<piles>)
Foundation design of burj khalifa (deep foundation<piles>)
sumitvikram
 
Foundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj KhalifaFoundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj Khalifaastoria104
 
Underwater Tunnels
Underwater TunnelsUnderwater Tunnels
Underwater Tunnels
Ishan Parekh
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
Sadek Abdelraheem
 
Burj Khalifa Dubai
Burj Khalifa DubaiBurj Khalifa Dubai
Burj Khalifa Dubai
The Legendary Hero
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
MD DANIYAL
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
jagadish chintu
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
Adil Shaikh
 

Viewers also liked (20)

Indian Railways ppt.
Indian Railways ppt.Indian Railways ppt.
Indian Railways ppt.
 
Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
 
0877 Civil Society Involvement in SRI
0877 Civil Society Involvement in SRI0877 Civil Society Involvement in SRI
0877 Civil Society Involvement in SRI
 
Chapter 8 section 1 (erosion by gravity)
Chapter 8 section 1 (erosion by gravity)Chapter 8 section 1 (erosion by gravity)
Chapter 8 section 1 (erosion by gravity)
 
Quantitative Verification of Some Standard Support Patterns in Japanese Tunne...
Quantitative Verification of Some Standard Support Patterns in Japanese Tunne...Quantitative Verification of Some Standard Support Patterns in Japanese Tunne...
Quantitative Verification of Some Standard Support Patterns in Japanese Tunne...
 
Products consumables
Products consumablesProducts consumables
Products consumables
 
CHENAB BRIDGE
CHENAB BRIDGECHENAB BRIDGE
CHENAB BRIDGE
 
Engr. Syed shahbaz Shah
Engr. Syed shahbaz ShahEngr. Syed shahbaz Shah
Engr. Syed shahbaz Shah
 
Efforts Of Singapore In Controlling Traffic Congestion & Pollution
Efforts Of Singapore In Controlling Traffic Congestion & PollutionEfforts Of Singapore In Controlling Traffic Congestion & Pollution
Efforts Of Singapore In Controlling Traffic Congestion & Pollution
 
Leadership Dr. E Sreedharan Arun.Vi
Leadership Dr. E Sreedharan   Arun.ViLeadership Dr. E Sreedharan   Arun.Vi
Leadership Dr. E Sreedharan Arun.Vi
 
Nanotechnology in civil engineering
Nanotechnology in civil engineeringNanotechnology in civil engineering
Nanotechnology in civil engineering
 
36551105 delhi-metro
36551105 delhi-metro36551105 delhi-metro
36551105 delhi-metro
 
Foundation design of burj khalifa (deep foundation<piles>)
Foundation design of burj khalifa (deep foundation<piles>)Foundation design of burj khalifa (deep foundation<piles>)
Foundation design of burj khalifa (deep foundation<piles>)
 
Foundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj KhalifaFoundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj Khalifa
 
Underwater Tunnels
Underwater TunnelsUnderwater Tunnels
Underwater Tunnels
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
Burj Khalifa Dubai
Burj Khalifa DubaiBurj Khalifa Dubai
Burj Khalifa Dubai
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 

Similar to The Untold Story of Konkan Railway

CV - B.SRIKANTH
CV - B.SRIKANTH CV - B.SRIKANTH
CV - B.SRIKANTH b_kanthi1
 
Cv b.srikanth
Cv   b.srikanth Cv   b.srikanth
Cv b.srikanth
b_kanthi1
 
PM Project group 4.pptx
PM Project group 4.pptxPM Project group 4.pptx
PM Project group 4.pptx
KumarAnand99
 
Padma Brige Project 2017
Padma Brige Project 2017Padma Brige Project 2017
Padma Brige Project 2017
RJ Sajeeb
 
Fatimanagar to mamnoor bridge construction
Fatimanagar to mamnoor bridge constructionFatimanagar to mamnoor bridge construction
Fatimanagar to mamnoor bridge construction
smatijay
 
Internship Report
Internship ReportInternship Report
Internship Reportprathagarg
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arunKartikeya Pandey
 
Jamuna bridge denar_final_19_feb20
Jamuna bridge denar_final_19_feb20Jamuna bridge denar_final_19_feb20
Jamuna bridge denar_final_19_feb20
Morshed Denar Alam Manna
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
oyepuneeta
 
Delhi Metro
Delhi MetroDelhi Metro
Delhi Metro
sarang shah
 
E. Sreedharan as Project manager
E. Sreedharan as Project managerE. Sreedharan as Project manager
E. Sreedharan as Project manager
Yogesh Vijay
 
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdfSPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
Adina Levin
 
CV Vinod Kumar Technip
CV Vinod Kumar TechnipCV Vinod Kumar Technip
CV Vinod Kumar TechnipVINOD KUMAR
 

Similar to The Untold Story of Konkan Railway (20)

CV - B.SRIKANTH
CV - B.SRIKANTH CV - B.SRIKANTH
CV - B.SRIKANTH
 
Cv b.srikanth
Cv   b.srikanth Cv   b.srikanth
Cv b.srikanth
 
PM Project group 4.pptx
PM Project group 4.pptxPM Project group 4.pptx
PM Project group 4.pptx
 
CV Sriinivas 1i doc
CV Sriinivas 1i docCV Sriinivas 1i doc
CV Sriinivas 1i doc
 
Padma Brige Project 2017
Padma Brige Project 2017Padma Brige Project 2017
Padma Brige Project 2017
 
Fatimanagar to mamnoor bridge construction
Fatimanagar to mamnoor bridge constructionFatimanagar to mamnoor bridge construction
Fatimanagar to mamnoor bridge construction
 
CV_Gursharan Choudhary
CV_Gursharan ChoudharyCV_Gursharan Choudhary
CV_Gursharan Choudhary
 
resume_AK2
resume_AK2resume_AK2
resume_AK2
 
CV PMG
CV PMGCV PMG
CV PMG
 
PK_Thakore_New_CV
PK_Thakore_New_CVPK_Thakore_New_CV
PK_Thakore_New_CV
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arun
 
Jamuna bridge denar_final_19_feb20
Jamuna bridge denar_final_19_feb20Jamuna bridge denar_final_19_feb20
Jamuna bridge denar_final_19_feb20
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
 
Delhi Metro
Delhi MetroDelhi Metro
Delhi Metro
 
E. Sreedharan as Project manager
E. Sreedharan as Project managerE. Sreedharan as Project manager
E. Sreedharan as Project manager
 
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdfSPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
 
CV Vinod Kumar Technip
CV Vinod Kumar TechnipCV Vinod Kumar Technip
CV Vinod Kumar Technip
 
RESUME-1
RESUME-1RESUME-1
RESUME-1
 
bs cv latest16.8
bs cv latest16.8bs cv latest16.8
bs cv latest16.8
 

More from Rohit Dhoundiyal

Interviewing tips
Interviewing tipsInterviewing tips
Interviewing tips
Rohit Dhoundiyal
 
Tata Tea & Tetley acquisition
Tata Tea & Tetley acquisitionTata Tea & Tetley acquisition
Tata Tea & Tetley acquisition
Rohit Dhoundiyal
 
Tata Motors & JLR Merger
Tata Motors & JLR MergerTata Motors & JLR Merger
Tata Motors & JLR Merger
Rohit Dhoundiyal
 
Quantitative Easing
Quantitative EasingQuantitative Easing
Quantitative Easing
Rohit Dhoundiyal
 
Nokia - Selling & Negotiation
Nokia -  Selling & NegotiationNokia -  Selling & Negotiation
Nokia - Selling & NegotiationRohit Dhoundiyal
 
Mittal Steel and the global steel industry
Mittal Steel and the global steel industryMittal Steel and the global steel industry
Mittal Steel and the global steel industryRohit Dhoundiyal
 
Incorporation of a company
Incorporation of a companyIncorporation of a company
Incorporation of a companyRohit Dhoundiyal
 
Fixing Fevicol - Case Study
Fixing Fevicol - Case StudyFixing Fevicol - Case Study
Fixing Fevicol - Case StudyRohit Dhoundiyal
 

More from Rohit Dhoundiyal (13)

Interviewing tips
Interviewing tipsInterviewing tips
Interviewing tips
 
Tata Tea & Tetley acquisition
Tata Tea & Tetley acquisitionTata Tea & Tetley acquisition
Tata Tea & Tetley acquisition
 
Tata Motors & JLR Merger
Tata Motors & JLR MergerTata Motors & JLR Merger
Tata Motors & JLR Merger
 
Sale of Goods Act
Sale of Goods ActSale of Goods Act
Sale of Goods Act
 
Quantitative Easing
Quantitative EasingQuantitative Easing
Quantitative Easing
 
Nokia - Selling & Negotiation
Nokia -  Selling & NegotiationNokia -  Selling & Negotiation
Nokia - Selling & Negotiation
 
Mittal Steel and the global steel industry
Mittal Steel and the global steel industryMittal Steel and the global steel industry
Mittal Steel and the global steel industry
 
Leadership ravi shankar
Leadership   ravi shankarLeadership   ravi shankar
Leadership ravi shankar
 
Incorporation of a company
Incorporation of a companyIncorporation of a company
Incorporation of a company
 
Fixing Fevicol - Case Study
Fixing Fevicol - Case StudyFixing Fevicol - Case Study
Fixing Fevicol - Case Study
 
Clocky - Case Study
Clocky - Case StudyClocky - Case Study
Clocky - Case Study
 
Capital One - Fairbank
Capital One - FairbankCapital One - Fairbank
Capital One - Fairbank
 
Ashok Leyland
Ashok LeylandAshok Leyland
Ashok Leyland
 

Recently uploaded

Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
An introduction to the cryptocurrency investment platform Binance Savings.
An introduction to the cryptocurrency investment platform Binance Savings.An introduction to the cryptocurrency investment platform Binance Savings.
An introduction to the cryptocurrency investment platform Binance Savings.
Any kyc Account
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
Training my puppy and implementation in this story
Training my puppy and implementation in this storyTraining my puppy and implementation in this story
Training my puppy and implementation in this story
WilliamRodrigues148
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
Corey Perlman, Social Media Speaker and Consultant
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Recruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media MasterclassRecruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media Masterclass
LuanWise
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
Corey Perlman, Social Media Speaker and Consultant
 
Auditing study material for b.com final year students
Auditing study material for b.com final year  studentsAuditing study material for b.com final year  students
Auditing study material for b.com final year students
narasimhamurthyh4
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Lviv Startup Club
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Holger Mueller
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 

Recently uploaded (20)

Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
An introduction to the cryptocurrency investment platform Binance Savings.
An introduction to the cryptocurrency investment platform Binance Savings.An introduction to the cryptocurrency investment platform Binance Savings.
An introduction to the cryptocurrency investment platform Binance Savings.
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
Training my puppy and implementation in this story
Training my puppy and implementation in this storyTraining my puppy and implementation in this story
Training my puppy and implementation in this story
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Recruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media MasterclassRecruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media Masterclass
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
 
Auditing study material for b.com final year students
Auditing study material for b.com final year  studentsAuditing study material for b.com final year  students
Auditing study material for b.com final year students
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 

The Untold Story of Konkan Railway

  • 2. Background          19th July’ 1990 – 26th January’ 1998 760 Km railway line connecting Bombay(Roha) to Managalore (Thokur) 1,998 bridges(179 Major & 1,819 Minor) 93 tunnels with aggregating length of 83.5 Km Dream project of Mr.George Fernandez  Konkan Railway  Chithoni & Bogha railway bridge States – Maharashtra, Goa, Karnataka & Kerala Bombay to Mangalore – 2,041 Km (41 hours) Bombay to Mangalore – 914 Km (15 hours) CMD – Mr. E Sreedharan
  • 3. Q1. In the case study given identity the success or failure of the following processes – Project conception, Project definition, Project planning, Project launch & execution?  Project conception  Concept of Roll on Roll off (RORO)  Truck drivers find it extremely difficult to drive loaded trucks through Ghats, undulating surfaces, narrow roads and poor road and weather conditions  Saving of fuels, decrease in wear and tear of Lorries (trucks), relief to drivers of driving in extreme conditions, can reach faster to destination which leads to saving in travel time and money  Project will boost to the economy of country
  • 4. Q1. In the case study given identity the success or failure of the following processes – Project conception, Project definition, Project planning, Project launch & execution?  Project definition  Four state governments have joined hands with the central government to begin a project of this size.  Konkan Railway project is a highly viable project, financially very attractive, because it reduces distance between Bombay & Mangalore considerably. The normal haulage distance between Bombay & Mangalore was 2041 km. After the construction of this project, it would be 914 km  The project cost, initially estimated at Rs.860 crore, has increased by over four times. The project cost has been estimated at Rs.2,780 crore, with the funding cost alone being Rs.550 crore
  • 5. Q1. In the case study given identity the success or failure of the following processes – Project conception, Project definition, Project planning, Project launch & execution?  Project planning  take approval from Planning Commission, central government and the beneficiary state Government (Maharashtra, Goa, Karnataka, and Kerala).  The whole project was decided to complete in five years’ time.  They planned that the whole railway line would be divided into 7 zones, each zone concurrent with a revenue district, and a Chief Engineer was posted for each zone.  They selected contractors only from the pre-qualified list
  • 6. Q1. In the case study given identity the success or failure of the following processes – Project conception, Project definition, Project planning, Project launch & execution?  Project launch & execution  The project was estimated to complete in 5 years’ time, ultimately took 7 years for completion  The main reason one was government’s own action. There was controversy regard to the Goa government and the work was stopped by the government. The second was finance  Three-fourths of the project funds had to be raised in the market. The expectations were that we could raise the money from the internal market through bonds, either tax-free bonds or taxable bonds  Unexpected adverse geological conditions in some of the tunnels
  • 7. Q2. Identify all the important stakeholders?     Central Govt.  Planning commission  Finance ministry  Railway ministry State Govt.  Maharashtra  Goa  Karnataka  Kerala Landowners, Contractors, Investors, Engineers Chief secretary & Transport secretary of Bangalore & Kerala All the above stakeholders were important for making Konkan Rail project successful, especially contractors, landowners & consent of all higher government authorities of all four states. Without stakeholders, project wouldn’t be successful. In every project whether it is smaller or big, project stakeholder play a very important role.
  • 8. Q3. The success of a project depends largely on the success of the contractor. What steps were taken to ensure the success of the contractor?         Contractors were selected from pre-qualified list Decision making by the contractors had to be approved by the higher authority. Payment made to contractors Mobilization of advances There need to be a good communication between the contractors and superiors Fuel availability on site Import of sophisticated equipment Incentives of completion of work
  • 9. Q4. What do you think were the areas of risk? How were the risks managed / mismanaged? Risk Managed / Mismanaged Disapproval/resistance from beneficiary state govt. This risk was managed by Mr. George Fernandes & Mr. E Sreedharan by taking serious talks to the heads of the state and making them believe the benefits that can be derived from this project. Bureaucratic approach was taken to solve this problem. Budget for the project The budget derived to railway project in India was around Rs.250 to Rs.300 crores and already 20 – 25 new railway projects were on going. This was a serious problem because then it would take 25-30 years for completion of the project. The govt. also issued tax free bonds but it was a failure due to share market scam. At last only choice was External Commercial Borrowing (ECB) through which the govt. was able to raise Rs.400 crore. Janata Dal party collapsed Konkan Railway project was undertaken under Janata Dal party. Within a week after Mr. E Sreedharan was appointed as CMD, the party fell and Mr. George Fernandez was no more the railway minister.
  • 10. Q4. What do you think were the areas of risk? How were the risks managed / mismanaged? Difficulty in acquiring land For the project, the govt. had to acquire land from 40,000 landowners. This was a major problem as people would resist from selling their land. A new strategy was developed to tackle this problem. Landowners were given compensation for the land as well as rental charges for 1 to 1 ½ years till they are ready with their new house. Difficulty in making 760 Km line Constructing 760 Km railway line would take many years and huge cost. But this was reduced by adopting a new strategy where in Konkan line was divided in 7 zones and construction was started at each zone at the same time. By this the time as well as cost of the project was reduced. Many times in construction project, the risk of incomplete work from the side of contractor is very high. This risk was managed by giving contract only to recognized, pre-qualified contractors who have adequate cash flow. In a cross state construction project, many times there is government interference. This problem aroused when GOI stopped work in Goa sector for 9 months. There was no solution to this had a terrible effect on the rest of the project. Risk of contractors Political Interference
  • 11. Q4. What do you think were the areas of risk? How were the risks managed / mismanaged? Difficult geological conditions The project only had 5 years’ time. In this time, all kinds of survey, clearance, and geological inspection had to be done. Tunnels needed geo-technical investigations, but there was no time. Accidents took place while excavating tunnels in mountains. This delayed the project. Environment impact While some people thought that the project was economically beneficial, some environmental groups raised questions towards its impact to ecology in the konkan area. These groups stated that the project would cause destruction of ecology, damage to historical sites and disrupt the lifestyles of people in densely populated coastal region.
  • 12. Q5. Identify the areas of good communication or the lack of it?     It was very important for the people who are involved in this project to communicate with each other for the completion of the project. Hired DOT lines and then established a good communication network with the headquarters of each of the Chief Engineers. They were all given FAX machines, they were all given computers. A computer networking was done, so that everybody can have any information he wants from anywhere and message can be passed on time. Mr. E Sreedharan would sit with the contractors and concerned engineers and used to see the problems faced by the team and on the spot used to sort out the problems. So that there is no difficulty at all for the progress of the work. Every Monday, Mr. E Sreedharan had a meeting with the Head of Departments, where all the problems connected with the whole project were discussed
  • 13. Q7. What were the new technologies used in Konkan Railway project? Optical fibre cable First time in the history of Indian Railway, Optical fibre cable was used in Tele-communication network. At that time it was a new technology which sensed a lot of opposition but today optical fibre cable is a common thing. Today in the Indian railway system, the konkan railway has the longest stretch of optical fibre cable. 
  • 14. Q7. What were the new technologies used in Konkan Railway project? Incremental launching method This is a new technology used for the 1 st time in India (same technology was used in Delhi Metro). Incremental launch is a method of building a complete bridge deck from one end to other end. 
  • 15. Q7. What were the new technologies used in Konkan Railway project? Ballast less track A disadvantage of traditional track structures is heavy demand for maintenance which leads to heavy maintenance cost. This can be overcome by using ballastless track. 
  • 16. Q7. What were the new technologies used in Konkan Railway project? Gas pressure welding A new technology of gas pressure welding came from foreign countries was used. People were trained for this technology in Japan. The advantage of gas pressure welding is that it can be done at the site itself. Traditional welding methods can only be done in welding shops. And it was a problem to get the welded railing to the site again. 