SlideShare a Scribd company logo
Hyderabad Metro Rail Project
- A case study
Topics
• Metro Network
• FinancialAspects
• Sub-structure
- Foundation
• Super structure
- Piers, Bearings, Pre-Cast Segments
• Station Concept
• Rolling Stock
• AutomaticTrain Operation (ATO)
• Summary
Metro Network
MIYAPUR
L B NAGAR
FALAKNUMA
JBS
NAGOLE
SHILPARAMAM
CORRIDOR I - RED
CORRIDOR II - GREEN
CORRIDOR III - BLUE
Financial Aspects
Total cost of Project Rs.14,320 Cr.
Central GOVT 10% of Total cost
L&T Metro Rail Hyderabad limited Remaining Total cost
State GOVT (Telangana) Ready to bear the extra cost
State GOVT (Andhra Pradesh) 0%
• Initially allotted to MAYTAS, but, was cancelled
due to delay in Financial closure.
• Allotted to L&T in PPP mode, DBFOT basis.
Structure - Overview
Foundation
• Soil Investigation
• Shifting of Services and Amenities
• Foundation
• Open foundation
• Pile foundation
Concrete/
Rock Breaker
Vibrator
Compactor
Pile driving equipment
Piers
Boom Placer
Transit Mixer
Shuttering
• Inner surface of Formwork coated with ‘Mould
Releasing Agent’; to prevent adhesion of
Concrete to the Formwork.
Security
Barricade
Piers (Contd.)
Piers
Total distance covered 72 KM
Total no. of piers 2748
Piers in corridor – I 1109
Piers in corridor – II 588
Piers in corridor – III 1051
Piers completed till now 1635
Piers
Bearings
• Bearings are used for resisting the rotatory loads
Pre-Fabrication
• Piers hold the viaduct, this is done by stringing and sticking the Segments together.
Segments
Gantry andTravel for Lifting and
Loading Segments in theYard
Pre-Cast Segments
• In gen, 10 Segments between 2 Piers, each Segment about 40Tons.
• PlacingViaduct Segments with the help of Launching Gantry.
Launching Gantry
Viaduct Segments
under-slung during
Sticking and
Stitching process
Slings for holding
Viaduct Segments
Traveler
For Lifting
And Shifting
Segments
VIADUCT
VIADUCT
P
I
E
R
Pre-Cast Segments (Contd.)
Sticking the Pre-Cast Segments
Application of
Epoxy on surface
of Segment
Pre-Cast Segments (Contd.)
Stringing of Pre-Cast Segments
Stringing
Cable
Duct in
Pre-Cast
Segment
Station Concept
• The Stations, being windows to the Metro Service, are tastefully designed
reflecting local culture.
Uppal stationInterior view of station
Station Concept (Contd.)
Station Design
• Stations are covered by an overlapping
roofing system, open at sides, covering
the platform
• Staircases & Escalators designed based
on
• Architectural Elements
• Functional Aspects.
Rolling Stock
• LTHMR has given Rolling Stock contract to
Hyundai Rotem Company (South Korea).
• Total 57Three-CarTrain Sets.
Measurement of car 21.7 X 2.9 X 3.8 (meters)
Material of car Stainless steel
Gauge length 1435 mm
Max. Design Speed 90 Km/h
Signal System ATO/ATP
Capacity (per train set) 126 seats
Power supply 25 KV AC
Rolling Stock
AutomaticTrain Operation (ATO)
Train
controls
Interior view
• LTHMR has given the Communication Based Train Control (CBTC) system
to TheThales Company .
• Thales will Design, Build, Deliver and Manage the installation of the fully
automatedCBTC.
Summary
• Faster :
- JourneyTime  Reduced
• Greater traffic capacity equivalent to:
• 7 lanes of BusTraffic (or)
• 24 lanes of CarTraffic
• Low Energy Consumption per Passenger Km:
• 20% only  in comparison to Road-based Systems.
• Eco-Friendly :
• Air Pollution  Nil
• Sound Pollution  Negligible
Development never ENDS
Thank u !!!!!!!!!!

More Related Content

What's hot

Ahmedabad Metro Project
Ahmedabad Metro ProjectAhmedabad Metro Project
Ahmedabad Metro Project
ASHISH SINGH
 
Mumbai metro - Planning
Mumbai metro - PlanningMumbai metro - Planning
Mumbai metro - Planning
RADHIKASARDA8
 
karunamoyee metro station thesis B.Arch
karunamoyee metro station thesis B.Archkarunamoyee metro station thesis B.Arch
karunamoyee metro station thesis B.Arch
Tuhina Chatterjee
 
Mass transit system
Mass transit systemMass transit system
Mass transit system
Sagar Kaptan
 
BRTS
BRTSBRTS
metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)
A.U Architecture Alumni Association
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
Nikita James
 
ELEVATOR SYSTEM IN DELHI METRO STATIONS
ELEVATOR SYSTEM IN DELHI METRO STATIONSELEVATOR SYSTEM IN DELHI METRO STATIONS
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
Akhilesh Shukla
 
Diiferent types of road
Diiferent types of roadDiiferent types of road
Diiferent types of road
Abhishek Dixit
 
Construction of joka majherhat phase-i metro corridor considering the requir...
Construction of joka  majherhat phase-i metro corridor considering the requir...Construction of joka  majherhat phase-i metro corridor considering the requir...
Construction of joka majherhat phase-i metro corridor considering the requir...Rajesh Prasad
 
Metro Rail and the City
Metro Rail and the CityMetro Rail and the City
Metro Rail and the City
Centre for Public Policy Research
 
Bangalore Metro Project
Bangalore Metro ProjectBangalore Metro Project
Bangalore Metro Project
Pradeep Srinivas
 
On street and off street parking
On street and off street parkingOn street and off street parking
On street and off street parking
Sagar Vekariya
 
jaipur metro rail presentation
jaipur metro rail presentationjaipur metro rail presentation
jaipur metro rail presentationtushar garg
 
Pune Metro plan & 4 FSI proposal - Presentation on Issues & Impacts (Sept 201...
Pune Metro plan & 4 FSI proposal - Presentation on Issues & Impacts (Sept 201...Pune Metro plan & 4 FSI proposal - Presentation on Issues & Impacts (Sept 201...
Pune Metro plan & 4 FSI proposal - Presentation on Issues & Impacts (Sept 201...
Prashant Inamdar
 
RAILWAY ENGINEERING
RAILWAY ENGINEERINGRAILWAY ENGINEERING
RAILWAY ENGINEERING
fye7884
 
1. classification of urban roads 28 jun
1. classification of urban roads 28 jun1. classification of urban roads 28 jun
1. classification of urban roads 28 jun
Prathamesh Kulkarni
 
Statue of unity case study
Statue of unity case studyStatue of unity case study
Statue of unity case study
bhagyashreekandoi
 
Need for MRTS
Need for MRTSNeed for MRTS
Need for MRTS
Ambuj Mishra
 

What's hot (20)

Ahmedabad Metro Project
Ahmedabad Metro ProjectAhmedabad Metro Project
Ahmedabad Metro Project
 
Mumbai metro - Planning
Mumbai metro - PlanningMumbai metro - Planning
Mumbai metro - Planning
 
karunamoyee metro station thesis B.Arch
karunamoyee metro station thesis B.Archkarunamoyee metro station thesis B.Arch
karunamoyee metro station thesis B.Arch
 
Mass transit system
Mass transit systemMass transit system
Mass transit system
 
BRTS
BRTSBRTS
BRTS
 
metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
 
ELEVATOR SYSTEM IN DELHI METRO STATIONS
ELEVATOR SYSTEM IN DELHI METRO STATIONSELEVATOR SYSTEM IN DELHI METRO STATIONS
ELEVATOR SYSTEM IN DELHI METRO STATIONS
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
Diiferent types of road
Diiferent types of roadDiiferent types of road
Diiferent types of road
 
Construction of joka majherhat phase-i metro corridor considering the requir...
Construction of joka  majherhat phase-i metro corridor considering the requir...Construction of joka  majherhat phase-i metro corridor considering the requir...
Construction of joka majherhat phase-i metro corridor considering the requir...
 
Metro Rail and the City
Metro Rail and the CityMetro Rail and the City
Metro Rail and the City
 
Bangalore Metro Project
Bangalore Metro ProjectBangalore Metro Project
Bangalore Metro Project
 
On street and off street parking
On street and off street parkingOn street and off street parking
On street and off street parking
 
jaipur metro rail presentation
jaipur metro rail presentationjaipur metro rail presentation
jaipur metro rail presentation
 
Pune Metro plan & 4 FSI proposal - Presentation on Issues & Impacts (Sept 201...
Pune Metro plan & 4 FSI proposal - Presentation on Issues & Impacts (Sept 201...Pune Metro plan & 4 FSI proposal - Presentation on Issues & Impacts (Sept 201...
Pune Metro plan & 4 FSI proposal - Presentation on Issues & Impacts (Sept 201...
 
RAILWAY ENGINEERING
RAILWAY ENGINEERINGRAILWAY ENGINEERING
RAILWAY ENGINEERING
 
1. classification of urban roads 28 jun
1. classification of urban roads 28 jun1. classification of urban roads 28 jun
1. classification of urban roads 28 jun
 
Statue of unity case study
Statue of unity case studyStatue of unity case study
Statue of unity case study
 
Need for MRTS
Need for MRTSNeed for MRTS
Need for MRTS
 

Viewers also liked

Hyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedureHyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedure
Aravind Samala
 
Feasibility Report of Hyd Metro
Feasibility Report of Hyd MetroFeasibility Report of Hyd Metro
Feasibility Report of Hyd Metro
Raghavendra Rachamadugu
 
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyHyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
IPPAI
 
Hyderabad metro rail reducing the negative impact on city environment - env...
Hyderabad metro rail   reducing the negative impact on city environment - env...Hyderabad metro rail   reducing the negative impact on city environment - env...
Hyderabad metro rail reducing the negative impact on city environment - env...
Umamaheswara Rao
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
Joseph Jincy
 
Delhi metro rail corporation project
Delhi metro rail corporation projectDelhi metro rail corporation project
Delhi metro rail corporation projectVimal Maurya
 
Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Aashna Sharma
 
The delhi-metro-project
The delhi-metro-projectThe delhi-metro-project
The delhi-metro-projectVikas Saini
 
Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over view
R K DHIMAN
 
Hyderabad Metro Rail Project team sets benchmark-6657
Hyderabad Metro Rail Project team sets benchmark-6657Hyderabad Metro Rail Project team sets benchmark-6657
Hyderabad Metro Rail Project team sets benchmark-6657MOHAN PRADEEP Y
 
DELHI-METRO-ADVERTISING-METRO-TRAINS-7-15
DELHI-METRO-ADVERTISING-METRO-TRAINS-7-15DELHI-METRO-ADVERTISING-METRO-TRAINS-7-15
DELHI-METRO-ADVERTISING-METRO-TRAINS-7-15Manish Kumar
 
Branding at Delhi Metro; TDI, Delhi Metro Advertising
Branding at Delhi Metro; TDI, Delhi Metro AdvertisingBranding at Delhi Metro; TDI, Delhi Metro Advertising
Branding at Delhi Metro; TDI, Delhi Metro Advertising
guestda02173
 
Railway Station Advertising Chennai - Chennai MRTS (Suburban) Railway Station...
Railway Station Advertising Chennai - Chennai MRTS (Suburban) Railway Station...Railway Station Advertising Chennai - Chennai MRTS (Suburban) Railway Station...
Railway Station Advertising Chennai - Chennai MRTS (Suburban) Railway Station...
Organized Outdoor Options
 
Traffic Analysis of The Culver Road and East Main Street Intersection
Traffic Analysis of The Culver Road and East Main Street IntersectionTraffic Analysis of The Culver Road and East Main Street Intersection
Traffic Analysis of The Culver Road and East Main Street Intersection
Nicholas Yager
 
Outdoor Advertising Options in Bangalore - OOH Outdoor Advertising Bangalore ...
Outdoor Advertising Options in Bangalore - OOH Outdoor Advertising Bangalore ...Outdoor Advertising Options in Bangalore - OOH Outdoor Advertising Bangalore ...
Outdoor Advertising Options in Bangalore - OOH Outdoor Advertising Bangalore ...
Organized Outdoor Options
 
Metro Rail Advertising Across India - Metro Train Branding
Metro Rail Advertising Across India - Metro Train BrandingMetro Rail Advertising Across India - Metro Train Branding
Metro Rail Advertising Across India - Metro Train Branding
Organized Outdoor Options
 
National geographic abu dhabi
National geographic abu dhabiNational geographic abu dhabi
National geographic abu dhabimrvanarsdale
 
L & T Metro Rail Impact Assessment Study - Stage 3
L & T Metro Rail Impact Assessment Study - Stage 3L & T Metro Rail Impact Assessment Study - Stage 3
L & T Metro Rail Impact Assessment Study - Stage 3
Ramesh Satyam
 

Viewers also liked (20)

Hyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedureHyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedure
 
Feasibility Report of Hyd Metro
Feasibility Report of Hyd MetroFeasibility Report of Hyd Metro
Feasibility Report of Hyd Metro
 
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyHyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
 
Hyderabad metro rail reducing the negative impact on city environment - env...
Hyderabad metro rail   reducing the negative impact on city environment - env...Hyderabad metro rail   reducing the negative impact on city environment - env...
Hyderabad metro rail reducing the negative impact on city environment - env...
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
 
Delhi metro rail corporation project
Delhi metro rail corporation projectDelhi metro rail corporation project
Delhi metro rail corporation project
 
Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)
 
The delhi-metro-project
The delhi-metro-projectThe delhi-metro-project
The delhi-metro-project
 
REPORT
REPORTREPORT
REPORT
 
Action plan
Action planAction plan
Action plan
 
Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over view
 
Hyderabad Metro Rail Project team sets benchmark-6657
Hyderabad Metro Rail Project team sets benchmark-6657Hyderabad Metro Rail Project team sets benchmark-6657
Hyderabad Metro Rail Project team sets benchmark-6657
 
DELHI-METRO-ADVERTISING-METRO-TRAINS-7-15
DELHI-METRO-ADVERTISING-METRO-TRAINS-7-15DELHI-METRO-ADVERTISING-METRO-TRAINS-7-15
DELHI-METRO-ADVERTISING-METRO-TRAINS-7-15
 
Branding at Delhi Metro; TDI, Delhi Metro Advertising
Branding at Delhi Metro; TDI, Delhi Metro AdvertisingBranding at Delhi Metro; TDI, Delhi Metro Advertising
Branding at Delhi Metro; TDI, Delhi Metro Advertising
 
Railway Station Advertising Chennai - Chennai MRTS (Suburban) Railway Station...
Railway Station Advertising Chennai - Chennai MRTS (Suburban) Railway Station...Railway Station Advertising Chennai - Chennai MRTS (Suburban) Railway Station...
Railway Station Advertising Chennai - Chennai MRTS (Suburban) Railway Station...
 
Traffic Analysis of The Culver Road and East Main Street Intersection
Traffic Analysis of The Culver Road and East Main Street IntersectionTraffic Analysis of The Culver Road and East Main Street Intersection
Traffic Analysis of The Culver Road and East Main Street Intersection
 
Outdoor Advertising Options in Bangalore - OOH Outdoor Advertising Bangalore ...
Outdoor Advertising Options in Bangalore - OOH Outdoor Advertising Bangalore ...Outdoor Advertising Options in Bangalore - OOH Outdoor Advertising Bangalore ...
Outdoor Advertising Options in Bangalore - OOH Outdoor Advertising Bangalore ...
 
Metro Rail Advertising Across India - Metro Train Branding
Metro Rail Advertising Across India - Metro Train BrandingMetro Rail Advertising Across India - Metro Train Branding
Metro Rail Advertising Across India - Metro Train Branding
 
National geographic abu dhabi
National geographic abu dhabiNational geographic abu dhabi
National geographic abu dhabi
 
L & T Metro Rail Impact Assessment Study - Stage 3
L & T Metro Rail Impact Assessment Study - Stage 3L & T Metro Rail Impact Assessment Study - Stage 3
L & T Metro Rail Impact Assessment Study - Stage 3
 

Similar to Hyderabad Metro Rail Project

Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
IRJET Journal
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metrosatish choudhari
 
Sarita Vihar Depot, Delhi Metro training report
Sarita Vihar Depot, Delhi Metro training reportSarita Vihar Depot, Delhi Metro training report
Sarita Vihar Depot, Delhi Metro training report
GAURAV KUMAR CHAUBEY
 
Rong Vo Catia V5 Projects And Fea And Msc Adams Simulations
Rong Vo Catia V5 Projects And Fea And Msc Adams SimulationsRong Vo Catia V5 Projects And Fea And Msc Adams Simulations
Rong Vo Catia V5 Projects And Fea And Msc Adams SimulationsRong Vo
 
West Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online ConsultationWest Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online Consultation
Crosstown TO
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Roland_Nikles
 
Eglinton Park
Eglinton ParkEglinton Park
Eglinton Park
Crosstown TO
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
Roshani Shahi
 
Achieving Exemplary Walking and Cycling Outcomes in a Major Road Project
Achieving Exemplary Walking and Cycling Outcomes in a Major Road Project Achieving Exemplary Walking and Cycling Outcomes in a Major Road Project
Achieving Exemplary Walking and Cycling Outcomes in a Major Road Project
JumpingJaq
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
Er. Bam Bhandari
 
108 barreras&accesos función justificaciónseleccióncomportamiento puerto...
108  barreras&accesos función justificaciónseleccióncomportamiento puerto...108  barreras&accesos función justificaciónseleccióncomportamiento puerto...
108 barreras&accesos función justificaciónseleccióncomportamiento puerto...
Sierra Francisco Justo
 
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
RAKESHPANDEY754083
 
Metro Work
Metro WorkMetro Work
Metro Work
Rajendra Kumar
 
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3Bruce Brymer
 
Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15Chandan Singh
 
highway development in india
highway development in indiahighway development in india
highway development in india
Prathi Baa
 
Battery Powered and Hybrid Drive Opportunities in Heavy Duty, Large Capacity,...
Battery Powered and Hybrid Drive Opportunities in Heavy Duty, Large Capacity,...Battery Powered and Hybrid Drive Opportunities in Heavy Duty, Large Capacity,...
Battery Powered and Hybrid Drive Opportunities in Heavy Duty, Large Capacity,...
Newton Montano
 
Refining pavement management strategies to enhance financial sustainability
Refining pavement management strategies to enhance financial sustainabilityRefining pavement management strategies to enhance financial sustainability
Refining pavement management strategies to enhance financial sustainability
Ashish Shah
 
Capacity management in large projects
Capacity management in large projectsCapacity management in large projects
Capacity management in large projects
Tristan Wiggill
 

Similar to Hyderabad Metro Rail Project (20)

Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
 
Sarita Vihar Depot, Delhi Metro training report
Sarita Vihar Depot, Delhi Metro training reportSarita Vihar Depot, Delhi Metro training report
Sarita Vihar Depot, Delhi Metro training report
 
Rong Vo Catia V5 Projects And Fea And Msc Adams Simulations
Rong Vo Catia V5 Projects And Fea And Msc Adams SimulationsRong Vo Catia V5 Projects And Fea And Msc Adams Simulations
Rong Vo Catia V5 Projects And Fea And Msc Adams Simulations
 
West Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online ConsultationWest Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online Consultation
 
TRB Managed Lane Design Build
TRB Managed Lane Design BuildTRB Managed Lane Design Build
TRB Managed Lane Design Build
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
 
Eglinton Park
Eglinton ParkEglinton Park
Eglinton Park
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
 
Achieving Exemplary Walking and Cycling Outcomes in a Major Road Project
Achieving Exemplary Walking and Cycling Outcomes in a Major Road Project Achieving Exemplary Walking and Cycling Outcomes in a Major Road Project
Achieving Exemplary Walking and Cycling Outcomes in a Major Road Project
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
 
108 barreras&accesos función justificaciónseleccióncomportamiento puerto...
108  barreras&accesos función justificaciónseleccióncomportamiento puerto...108  barreras&accesos función justificaciónseleccióncomportamiento puerto...
108 barreras&accesos función justificaciónseleccióncomportamiento puerto...
 
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
 
Metro Work
Metro WorkMetro Work
Metro Work
 
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
 
Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Battery Powered and Hybrid Drive Opportunities in Heavy Duty, Large Capacity,...
Battery Powered and Hybrid Drive Opportunities in Heavy Duty, Large Capacity,...Battery Powered and Hybrid Drive Opportunities in Heavy Duty, Large Capacity,...
Battery Powered and Hybrid Drive Opportunities in Heavy Duty, Large Capacity,...
 
Refining pavement management strategies to enhance financial sustainability
Refining pavement management strategies to enhance financial sustainabilityRefining pavement management strategies to enhance financial sustainability
Refining pavement management strategies to enhance financial sustainability
 
Capacity management in large projects
Capacity management in large projectsCapacity management in large projects
Capacity management in large projects
 

Hyderabad Metro Rail Project

  • 1. Hyderabad Metro Rail Project - A case study
  • 2. Topics • Metro Network • FinancialAspects • Sub-structure - Foundation • Super structure - Piers, Bearings, Pre-Cast Segments • Station Concept • Rolling Stock • AutomaticTrain Operation (ATO) • Summary
  • 3. Metro Network MIYAPUR L B NAGAR FALAKNUMA JBS NAGOLE SHILPARAMAM CORRIDOR I - RED CORRIDOR II - GREEN CORRIDOR III - BLUE
  • 4. Financial Aspects Total cost of Project Rs.14,320 Cr. Central GOVT 10% of Total cost L&T Metro Rail Hyderabad limited Remaining Total cost State GOVT (Telangana) Ready to bear the extra cost State GOVT (Andhra Pradesh) 0% • Initially allotted to MAYTAS, but, was cancelled due to delay in Financial closure. • Allotted to L&T in PPP mode, DBFOT basis.
  • 6. Foundation • Soil Investigation • Shifting of Services and Amenities • Foundation • Open foundation • Pile foundation Concrete/ Rock Breaker Vibrator Compactor
  • 8. Piers Boom Placer Transit Mixer Shuttering • Inner surface of Formwork coated with ‘Mould Releasing Agent’; to prevent adhesion of Concrete to the Formwork. Security Barricade
  • 9. Piers (Contd.) Piers Total distance covered 72 KM Total no. of piers 2748 Piers in corridor – I 1109 Piers in corridor – II 588 Piers in corridor – III 1051 Piers completed till now 1635 Piers
  • 10. Bearings • Bearings are used for resisting the rotatory loads
  • 11. Pre-Fabrication • Piers hold the viaduct, this is done by stringing and sticking the Segments together. Segments Gantry andTravel for Lifting and Loading Segments in theYard
  • 12. Pre-Cast Segments • In gen, 10 Segments between 2 Piers, each Segment about 40Tons. • PlacingViaduct Segments with the help of Launching Gantry. Launching Gantry Viaduct Segments under-slung during Sticking and Stitching process Slings for holding Viaduct Segments Traveler For Lifting And Shifting Segments VIADUCT VIADUCT P I E R
  • 13. Pre-Cast Segments (Contd.) Sticking the Pre-Cast Segments Application of Epoxy on surface of Segment
  • 14. Pre-Cast Segments (Contd.) Stringing of Pre-Cast Segments Stringing Cable Duct in Pre-Cast Segment
  • 15. Station Concept • The Stations, being windows to the Metro Service, are tastefully designed reflecting local culture. Uppal stationInterior view of station
  • 16. Station Concept (Contd.) Station Design • Stations are covered by an overlapping roofing system, open at sides, covering the platform • Staircases & Escalators designed based on • Architectural Elements • Functional Aspects.
  • 17. Rolling Stock • LTHMR has given Rolling Stock contract to Hyundai Rotem Company (South Korea). • Total 57Three-CarTrain Sets. Measurement of car 21.7 X 2.9 X 3.8 (meters) Material of car Stainless steel Gauge length 1435 mm Max. Design Speed 90 Km/h Signal System ATO/ATP Capacity (per train set) 126 seats Power supply 25 KV AC Rolling Stock
  • 18. AutomaticTrain Operation (ATO) Train controls Interior view • LTHMR has given the Communication Based Train Control (CBTC) system to TheThales Company . • Thales will Design, Build, Deliver and Manage the installation of the fully automatedCBTC.
  • 19. Summary • Faster : - JourneyTime  Reduced • Greater traffic capacity equivalent to: • 7 lanes of BusTraffic (or) • 24 lanes of CarTraffic • Low Energy Consumption per Passenger Km: • 20% only  in comparison to Road-based Systems. • Eco-Friendly : • Air Pollution  Nil • Sound Pollution  Negligible