PROJECT MANAGEMENT GROUP ASSIGNMENT
ON
KOCHI METRO RAIL CORPORATION
Presented by (Group 4)
Ankit Kumar – 140006
Kumar Anand – 140019
Ruby Ruchi – 140031
Supriya Jaiswal – 140042
ABOUT PROJECT
Kochi Metro is a proposed rapid transit system for the
city of Kochi in Kerala, India. The 25.65km metro line
will run from Aluva to Petta and will include 22
stations.
The $950m project will be operated by Kochi Metro
Rail Ltd. (KMRL), a joint venture between the Central
and State governments of India.
COST OF PROJECT
• The total cost of Kochi metro project is Rs. 5,181.79 crore (US$
943.09 million)
• Central government – Rs. 1,002.23 crore (US$ 182.41 million)
• State government – Rs. 1,772.23 crore (US$ 322.55 million)
• Japan international cooperation agency (JICA) – Rs. 2,174 crore
(US$ 395.67 million)
• JICA has agreed to offer loan at 1.50% interest rate
• Cost Allocated For Construction of Stations Is 220Cr. ( way side
civil A )
PROJECT TIMELINES
Sr No. Items of work Completion date
1 Obtain central government clearance 30/11/2011
2 Finalization of major contracts 29/02/2012
3 Execution of works and procurement of
equipment's, coaches and installations
01/04/2012 – 31/12/2015
4 Testing and Commissioning 01/01/2016 – 31/03/2016
5 Revenue Operation 31/03/2016
WORK BREAKDOWN STRUCTURE
• Main steps involves in station construction project are
• 1. Road winding, barricading and temporary street lighting.
• 2. Piling
• 3. Pile caps
• 4. Construction of main column (stage1)
• 5. Longitudinal and precast beam
• 6. Construction of main column (stage2)
• 7. Construction of Transvers Beam
• 8. RCC work for Track Slab
• 9. Construction of Outer Column up to Platform Beam
• 10. Erection of Roof
• 11. Finishing.
Project Plan
Risk associated with project
• Timing delays
• Weather risk
• Grid connection delays
• Staff and equipment availability
• Transportation
• Ground conditions
• Environmental or health and safety incidents
• Public protests
• Covid-19 Pandemic
• Political Agenda – Due to differences between the ruling party of
state and Centre there is an obvious delay in the project.
• Unavailability of Fund – The project requires very high funding of RS
63000 cr. and due to the delays, the investors are getting cold feet
some have even withdrawn from the project.
Recommendations
• It is recommended to construct Metro Stations Near
Beaches so it would be benefitted for tourist also.
• A series of meetings/discussions/presentations
happened with Railways and GOK authorities.
• Government should keep in check regarding
environmental effect.
• The concerned department must speed up the work
of as the more delay will cost more.
Conclusion
• According to the DPR and our study, the building of the
25.65 km long Metro Rail corridor is technically and
economically viable.
• This plan is a cost-effective transportation option for the
state of Kerala that would provide significant advantages
to the people.
• This Project will result in overall rapid development of
the State's economy due to the synergistic development
of all communities en-route.
• All of this, however, is only possible if the phase 2 and 3
is finished within the projected time and cost.
THANK YOU

More Related Content

Similar to PM Project group 4.pptx

Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocationJatin Mandhyan
 
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLift Events
 
BC Sir John A. MacDonald BC In A Pet.
BC Sir John A. MacDonald BC In A Pet.BC Sir John A. MacDonald BC In A Pet.
BC Sir John A. MacDonald BC In A Pet.
P. Anna Paddon
 
mumbai metro PPP model.pptx
mumbai metro PPP model.pptxmumbai metro PPP model.pptx
mumbai metro PPP model.pptx
TwinkleVincent2
 
The Untold Story of Konkan Railway
The Untold Story of Konkan RailwayThe Untold Story of Konkan Railway
The Untold Story of Konkan Railway
Rohit Dhoundiyal
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Oswar Mungkasa
 
summer training report in L&T construction
summer training report in L&T construction summer training report in L&T construction
summer training report in L&T construction
Manish Barwal
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
Joseph Jincy
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam
JunaidAshraf31
 
Infrastructure development in india
Infrastructure development in indiaInfrastructure development in india
Infrastructure development in indiaMukesh Khinchi
 
36551105 delhi-metro
36551105 delhi-metro36551105 delhi-metro
36551105 delhi-metro
Shreyanand Patel
 
Padma Brige Project 2017
Padma Brige Project 2017Padma Brige Project 2017
Padma Brige Project 2017
RJ Sajeeb
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiShobhit Acharya
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
Karan Shah
 
monorail system implication in Sri Lanka
monorail system implication in Sri Lankamonorail system implication in Sri Lanka
monorail system implication in Sri Lanka
University of Moratuwa, Sri Lanka
 
Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13
iain_cameron
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arunKartikeya Pandey
 

Similar to PM Project group 4.pptx (20)

Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocation
 
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
 
BC Sir John A. MacDonald BC In A Pet.
BC Sir John A. MacDonald BC In A Pet.BC Sir John A. MacDonald BC In A Pet.
BC Sir John A. MacDonald BC In A Pet.
 
mumbai metro PPP model.pptx
mumbai metro PPP model.pptxmumbai metro PPP model.pptx
mumbai metro PPP model.pptx
 
The Untold Story of Konkan Railway
The Untold Story of Konkan RailwayThe Untold Story of Konkan Railway
The Untold Story of Konkan Railway
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
 
summer training report in L&T construction
summer training report in L&T construction summer training report in L&T construction
summer training report in L&T construction
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam
 
Infrastructure development in india
Infrastructure development in indiaInfrastructure development in india
Infrastructure development in india
 
36551105 delhi-metro
36551105 delhi-metro36551105 delhi-metro
36551105 delhi-metro
 
Padma Brige Project 2017
Padma Brige Project 2017Padma Brige Project 2017
Padma Brige Project 2017
 
Project LlifeCycle
Project LlifeCycleProject LlifeCycle
Project LlifeCycle
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
 
wdfcil
wdfcilwdfcil
wdfcil
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
 
monorail system implication in Sri Lanka
monorail system implication in Sri Lankamonorail system implication in Sri Lanka
monorail system implication in Sri Lanka
 
ToR
ToRToR
ToR
 
Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arun
 

More from KumarAnand99

DM1_3.pdf
DM1_3.pdfDM1_3.pdf
DM1_3.pdf
KumarAnand99
 
ART & ARTIQUES.pdf
ART & ARTIQUES.pdfART & ARTIQUES.pdf
ART & ARTIQUES.pdf
KumarAnand99
 
SIP BVM.pptx
SIP BVM.pptxSIP BVM.pptx
SIP BVM.pptx
KumarAnand99
 
Ingersoll Rand.pptx
Ingersoll Rand.pptxIngersoll Rand.pptx
Ingersoll Rand.pptx
KumarAnand99
 
SCM_Solectron_G6.pptx
SCM_Solectron_G6.pptxSCM_Solectron_G6.pptx
SCM_Solectron_G6.pptx
KumarAnand99
 
group 3 scm.pptx
group 3 scm.pptxgroup 3 scm.pptx
group 3 scm.pptx
KumarAnand99
 
Wolfgang_Kohler.pptx
Wolfgang_Kohler.pptxWolfgang_Kohler.pptx
Wolfgang_Kohler.pptx
KumarAnand99
 
ACFrOgAsXX07Hpg-HY2djXIwyrkp9ScWwDAWCKBJPXU45x-d0N8a9ul4Rg41gvTiA_fKj7rc4tEj6...
ACFrOgAsXX07Hpg-HY2djXIwyrkp9ScWwDAWCKBJPXU45x-d0N8a9ul4Rg41gvTiA_fKj7rc4tEj6...ACFrOgAsXX07Hpg-HY2djXIwyrkp9ScWwDAWCKBJPXU45x-d0N8a9ul4Rg41gvTiA_fKj7rc4tEj6...
ACFrOgAsXX07Hpg-HY2djXIwyrkp9ScWwDAWCKBJPXU45x-d0N8a9ul4Rg41gvTiA_fKj7rc4tEj6...
KumarAnand99
 
624b3a5378d51.docx
624b3a5378d51.docx624b3a5378d51.docx
624b3a5378d51.docx
KumarAnand99
 
Jessica · SlidesCarnival.pptx
Jessica · SlidesCarnival.pptxJessica · SlidesCarnival.pptx
Jessica · SlidesCarnival.pptx
KumarAnand99
 
tsk_bbs-converted.docx
tsk_bbs-converted.docxtsk_bbs-converted.docx
tsk_bbs-converted.docx
KumarAnand99
 
bank-loan-66631035.pptx
bank-loan-66631035.pptxbank-loan-66631035.pptx
bank-loan-66631035.pptx
KumarAnand99
 

More from KumarAnand99 (12)

DM1_3.pdf
DM1_3.pdfDM1_3.pdf
DM1_3.pdf
 
ART & ARTIQUES.pdf
ART & ARTIQUES.pdfART & ARTIQUES.pdf
ART & ARTIQUES.pdf
 
SIP BVM.pptx
SIP BVM.pptxSIP BVM.pptx
SIP BVM.pptx
 
Ingersoll Rand.pptx
Ingersoll Rand.pptxIngersoll Rand.pptx
Ingersoll Rand.pptx
 
SCM_Solectron_G6.pptx
SCM_Solectron_G6.pptxSCM_Solectron_G6.pptx
SCM_Solectron_G6.pptx
 
group 3 scm.pptx
group 3 scm.pptxgroup 3 scm.pptx
group 3 scm.pptx
 
Wolfgang_Kohler.pptx
Wolfgang_Kohler.pptxWolfgang_Kohler.pptx
Wolfgang_Kohler.pptx
 
ACFrOgAsXX07Hpg-HY2djXIwyrkp9ScWwDAWCKBJPXU45x-d0N8a9ul4Rg41gvTiA_fKj7rc4tEj6...
ACFrOgAsXX07Hpg-HY2djXIwyrkp9ScWwDAWCKBJPXU45x-d0N8a9ul4Rg41gvTiA_fKj7rc4tEj6...ACFrOgAsXX07Hpg-HY2djXIwyrkp9ScWwDAWCKBJPXU45x-d0N8a9ul4Rg41gvTiA_fKj7rc4tEj6...
ACFrOgAsXX07Hpg-HY2djXIwyrkp9ScWwDAWCKBJPXU45x-d0N8a9ul4Rg41gvTiA_fKj7rc4tEj6...
 
624b3a5378d51.docx
624b3a5378d51.docx624b3a5378d51.docx
624b3a5378d51.docx
 
Jessica · SlidesCarnival.pptx
Jessica · SlidesCarnival.pptxJessica · SlidesCarnival.pptx
Jessica · SlidesCarnival.pptx
 
tsk_bbs-converted.docx
tsk_bbs-converted.docxtsk_bbs-converted.docx
tsk_bbs-converted.docx
 
bank-loan-66631035.pptx
bank-loan-66631035.pptxbank-loan-66631035.pptx
bank-loan-66631035.pptx
 

Recently uploaded

Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 

Recently uploaded (20)

Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 

PM Project group 4.pptx

  • 1. PROJECT MANAGEMENT GROUP ASSIGNMENT ON KOCHI METRO RAIL CORPORATION Presented by (Group 4) Ankit Kumar – 140006 Kumar Anand – 140019 Ruby Ruchi – 140031 Supriya Jaiswal – 140042
  • 2.
  • 3. ABOUT PROJECT Kochi Metro is a proposed rapid transit system for the city of Kochi in Kerala, India. The 25.65km metro line will run from Aluva to Petta and will include 22 stations. The $950m project will be operated by Kochi Metro Rail Ltd. (KMRL), a joint venture between the Central and State governments of India.
  • 4. COST OF PROJECT • The total cost of Kochi metro project is Rs. 5,181.79 crore (US$ 943.09 million) • Central government – Rs. 1,002.23 crore (US$ 182.41 million) • State government – Rs. 1,772.23 crore (US$ 322.55 million) • Japan international cooperation agency (JICA) – Rs. 2,174 crore (US$ 395.67 million) • JICA has agreed to offer loan at 1.50% interest rate • Cost Allocated For Construction of Stations Is 220Cr. ( way side civil A )
  • 5. PROJECT TIMELINES Sr No. Items of work Completion date 1 Obtain central government clearance 30/11/2011 2 Finalization of major contracts 29/02/2012 3 Execution of works and procurement of equipment's, coaches and installations 01/04/2012 – 31/12/2015 4 Testing and Commissioning 01/01/2016 – 31/03/2016 5 Revenue Operation 31/03/2016
  • 6.
  • 7. WORK BREAKDOWN STRUCTURE • Main steps involves in station construction project are • 1. Road winding, barricading and temporary street lighting. • 2. Piling • 3. Pile caps • 4. Construction of main column (stage1) • 5. Longitudinal and precast beam • 6. Construction of main column (stage2) • 7. Construction of Transvers Beam • 8. RCC work for Track Slab • 9. Construction of Outer Column up to Platform Beam • 10. Erection of Roof • 11. Finishing.
  • 9. Risk associated with project • Timing delays • Weather risk • Grid connection delays • Staff and equipment availability • Transportation • Ground conditions • Environmental or health and safety incidents • Public protests • Covid-19 Pandemic • Political Agenda – Due to differences between the ruling party of state and Centre there is an obvious delay in the project. • Unavailability of Fund – The project requires very high funding of RS 63000 cr. and due to the delays, the investors are getting cold feet some have even withdrawn from the project.
  • 10. Recommendations • It is recommended to construct Metro Stations Near Beaches so it would be benefitted for tourist also. • A series of meetings/discussions/presentations happened with Railways and GOK authorities. • Government should keep in check regarding environmental effect. • The concerned department must speed up the work of as the more delay will cost more.
  • 11. Conclusion • According to the DPR and our study, the building of the 25.65 km long Metro Rail corridor is technically and economically viable. • This plan is a cost-effective transportation option for the state of Kerala that would provide significant advantages to the people. • This Project will result in overall rapid development of the State's economy due to the synergistic development of all communities en-route. • All of this, however, is only possible if the phase 2 and 3 is finished within the projected time and cost.