BANDRA WORLI SEA-LINKBANDRA WORLI SEA LINK
Presented By
TE ( CIVIL)
Ankita Pal
SSJCET
INTRODUCTION
 Officially known as Rajiv Gandhi Sea Link.
 Cable-stayed bridge with pre-stressed concrete-steel viaducts.
 Links the Bandra (Western suburb) and Worli ( South Mumbai).
 Inaugurated on June 30 , 2009.
 Among the most complex & advanced construction projects
ever in India.
 Designed By : Sheshadri Srinivasan
(Structural engineer ,
Working in Lebanese Engineering Firm
Dar-Al-Handshah )
 Commissioned By : Maharashtra State Road Development Corporation
 Constructed By : Hindustan Construction company , India ( HCC)
HISTORY
 Mahim Causeway was the only link connecting westernsuburbs to island
city of Mumbai, making it highlycongested during the peak hours .
 Vehicular traffic admeasuring about 120,000 PCUtravels on the Mahim
causeway everyday and during peak hours and it takes about forty minutes to
travelfrom Mahim causeway to Worli, a distance of about 8km.
LOCATION
BASIC INFO
Official Name “ Rajiv Gandhi Setu ”
Carries 8 Lanes of Traffic
Owner MSRDC
Design Cable-stayed, Concrete-Steel precast viaducts
Total length 5.6 Km ( 3.5 miles )
Width 2 × 20 m ( 66 ft )
Highest Point 126 m ( 413 ft )
Longest Span 2 × 250 m ( 820 ft )
Vertical Clearance 20 m ( below bridge for transportation )
Foundation Type Pile Foundation
Toll System Automated 16-Lane Toll Plaza
Time Frame
 Estimated Time Frame : 5 years
Construction begin : June 1995
Construction end : March 2003
 Actual Time Frame : 11 years
Construction begin : October 2000
Construction End : 24 March 2010
Opened : 30 June 2009
BUDGET
 Estimated Cost : ₹ 665.81 Cr
 Actual Cost : ₹ 1653.25 Cr
 The Increament in project cost was due to payments of escalation ₹ 213
Cr on account of inordinate delay in completion (61 months ) .
New technical changes in the bridge at the behest of new consultant₹70 Cr
.
Contractor for delay in award of work ₹ 125 Cr .
Interest liability due to delayed completion ₹ 230 Cr .
 PIERS :
 The span between the piers is 50 maters .
 This distance arrived by considering optimization between foundation cost
Vs. superstructure cost .
 If the piers are wide apart then foundation cost comes down , but the
superstructure becomes heavier and its cost goes up .
 Moreover, more number of piers provide better wind resistance .
 CABLE WIRE
 Are also known as ‘ Parallel Wire Stay Cables ’.
 Manufactured by “Shanghai Pujiang Cable Co. Ltd” China .
 Each cable consists a group of steel wires ( 6 wires ) .
 Each steel wire has a diameter 7mm with a breaking limit of 6.28
Tones.
 Group of these wires was packed in two layers of HDPE (High
Density Poly Ethylene) material .
 Highly uneven and variable foundation bed
even for plane area of one pile .
 The maritime Board does not allow marine
traffic in monsoon season . Thus work was
halted Mid-May only to re-commence in
October . Effectively reducing the work
schedule to only seven month in a year .
 Needed for extra steel trusses , further
experts .
 Delay due to change in design of stray Cable
.
BENEFITS
 Considerable savings in travel time from 40
min to 8 min
 Estimated savings in fuel and vehicle
operating cost is around $ 16.2 million .
 Stress free driving .
 Reduced accidents and noise pollution .
 Reduction in air pollution .
Bandra - Worli sea link
Bandra - Worli sea link

More Related Content

What's hot

Bandra worli sea link case study
Bandra worli sea link  case studyBandra worli sea link  case study
Bandra worli sea link case study
AKSHAY CHATURVEDI
 
Presentation On Bandra Worli Sealink
Presentation On Bandra Worli SealinkPresentation On Bandra Worli Sealink
Presentation On Bandra Worli Sealinkpriyank123
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metrosatish choudhari
 
my project on chenab bridge
my project on chenab bridge my project on chenab bridge
my project on chenab bridge
Taseem mir
 
Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.
Axay Sharma
 
Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge Hakkim Shajahan
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
Ppt Creater
 
Internship Report on metro project
Internship Report on metro projectInternship Report on metro project
Internship Report on metro project
AkshathaBhandary
 
Chenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway TechnologyChenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway Technology
Pradeep Kumar
 
report
reportreport
report
Ravi Panchal
 
10 longest bridge of india
10 longest bridge of india10 longest bridge of india
10 longest bridge of india
gajjardhiren
 
Chenab bridge ppt
Chenab bridge pptChenab bridge ppt
Chenab bridge ppt
Ravi Panchal
 
Potential Economic Impact of The Padma Bridge
Potential Economic Impact of The Padma Bridge Potential Economic Impact of The Padma Bridge
Potential Economic Impact of The Padma Bridge
Shahriar Ferdous
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in indiaSourav Paul
 
Metro Work
Metro WorkMetro Work
Metro Work
Rajendra Kumar
 
Presentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir KhanPresentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir Khan
Aamir Rajput Khan
 
Jaipur metro rail project
Jaipur metro rail projectJaipur metro rail project
Jaipur metro rail projectDocumentStory
 
Trasnportation system of mumbai
Trasnportation system of  mumbaiTrasnportation system of  mumbai
Trasnportation system of mumbai
Yash Kotgirwar
 
Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)Gurparvesh kaur
 

What's hot (20)

Bandra worli sea link case study
Bandra worli sea link  case studyBandra worli sea link  case study
Bandra worli sea link case study
 
Presentation On Bandra Worli Sealink
Presentation On Bandra Worli SealinkPresentation On Bandra Worli Sealink
Presentation On Bandra Worli Sealink
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
 
my project on chenab bridge
my project on chenab bridge my project on chenab bridge
my project on chenab bridge
 
Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.
 
Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 
Internship Report on metro project
Internship Report on metro projectInternship Report on metro project
Internship Report on metro project
 
Chenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway TechnologyChenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway Technology
 
report
reportreport
report
 
10 longest bridge of india
10 longest bridge of india10 longest bridge of india
10 longest bridge of india
 
Chenab bridge ppt
Chenab bridge pptChenab bridge ppt
Chenab bridge ppt
 
Potential Economic Impact of The Padma Bridge
Potential Economic Impact of The Padma Bridge Potential Economic Impact of The Padma Bridge
Potential Economic Impact of The Padma Bridge
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in india
 
Metro Work
Metro WorkMetro Work
Metro Work
 
Presentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir KhanPresentation on chenab bridge by Aamir Khan
Presentation on chenab bridge by Aamir Khan
 
Jaipur metro rail project
Jaipur metro rail projectJaipur metro rail project
Jaipur metro rail project
 
Trasnportation system of mumbai
Trasnportation system of  mumbaiTrasnportation system of  mumbai
Trasnportation system of mumbai
 
Chenab Bridge
Chenab BridgeChenab Bridge
Chenab Bridge
 
Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)
 

Viewers also liked

Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
Yousuf Captain
 
Bandra Worli Bridge
Bandra Worli BridgeBandra Worli Bridge
Bandra Worli Bridge
derebail2008
 
Bandra Worli Sea Link #BWSL
Bandra Worli Sea Link #BWSLBandra Worli Sea Link #BWSL
Bandra Worli Sea Link #BWSL
Priyanka Dalal
 
Mumbai
MumbaiMumbai
B w sealink
B w sealinkB w sealink
B w sealink
Tejas Chandurkar
 
Mmmodified copy
Mmmodified   copyMmmodified   copy
Mmmodified copy
Shikha Verma
 
PPT ON GREEN CONCRETE BY TANMAY KUMAR
PPT ON GREEN CONCRETE BY TANMAY KUMARPPT ON GREEN CONCRETE BY TANMAY KUMAR
PPT ON GREEN CONCRETE BY TANMAY KUMAR
Tanmay Kumar
 
PPT on Green concrete by Pankaj Kumar
PPT on Green concrete by Pankaj KumarPPT on Green concrete by Pankaj Kumar
PPT on Green concrete by Pankaj Kumar
Pankaj Kumar
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
SlideShare
 
Mirage - Rohan Lifescapes
Mirage - Rohan LifescapesMirage - Rohan Lifescapes
Mirage - Rohan Lifescapes
Rohan Lifescapes
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
SlideShare
 
Hanging bridge kota
Hanging bridge kotaHanging bridge kota
Hanging bridge kota
Ñåwàb KĦâñ
 
Bruj khalifa
Bruj khalifaBruj khalifa
Bruj khalifa
Monik Hirpara
 
Cost effective construction materials
Cost effective construction materialsCost effective construction materials
Cost effective construction materials
RAMSIDDARTHAN .
 
Paresh
PareshParesh
Paresh
Niraj Dhande
 
GPC PROJECT audit 2 Final
GPC PROJECT audit 2 Final GPC PROJECT audit 2 Final
GPC PROJECT audit 2 Final Prithvi Raj
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli SealinkDesignTeja
 
DABHOL POWER COMPANY, INDIA
DABHOL POWER COMPANY,  INDIADABHOL POWER COMPANY,  INDIA
DABHOL POWER COMPANY, INDIA
Ankit Kumar Gupta
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
NR Computer Learning Center
 
Hydraulics
HydraulicsHydraulics
Hydraulics
HITESH PODDAR
 

Viewers also liked (20)

Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Bandra Worli Bridge
Bandra Worli BridgeBandra Worli Bridge
Bandra Worli Bridge
 
Bandra Worli Sea Link #BWSL
Bandra Worli Sea Link #BWSLBandra Worli Sea Link #BWSL
Bandra Worli Sea Link #BWSL
 
Mumbai
MumbaiMumbai
Mumbai
 
B w sealink
B w sealinkB w sealink
B w sealink
 
Mmmodified copy
Mmmodified   copyMmmodified   copy
Mmmodified copy
 
PPT ON GREEN CONCRETE BY TANMAY KUMAR
PPT ON GREEN CONCRETE BY TANMAY KUMARPPT ON GREEN CONCRETE BY TANMAY KUMAR
PPT ON GREEN CONCRETE BY TANMAY KUMAR
 
PPT on Green concrete by Pankaj Kumar
PPT on Green concrete by Pankaj KumarPPT on Green concrete by Pankaj Kumar
PPT on Green concrete by Pankaj Kumar
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 
Mirage - Rohan Lifescapes
Mirage - Rohan LifescapesMirage - Rohan Lifescapes
Mirage - Rohan Lifescapes
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
 
Hanging bridge kota
Hanging bridge kotaHanging bridge kota
Hanging bridge kota
 
Bruj khalifa
Bruj khalifaBruj khalifa
Bruj khalifa
 
Cost effective construction materials
Cost effective construction materialsCost effective construction materials
Cost effective construction materials
 
Paresh
PareshParesh
Paresh
 
GPC PROJECT audit 2 Final
GPC PROJECT audit 2 Final GPC PROJECT audit 2 Final
GPC PROJECT audit 2 Final
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
DABHOL POWER COMPANY, INDIA
DABHOL POWER COMPANY,  INDIADABHOL POWER COMPANY,  INDIA
DABHOL POWER COMPANY, INDIA
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Hydraulics
HydraulicsHydraulics
Hydraulics
 

Similar to Bandra - Worli sea link

Bridges construction
Bridges constructionBridges construction
Bridges construction
Shivam Mahajan
 
Bogibeel Rail cum Road Bridge.pptx
Bogibeel Rail cum Road Bridge.pptxBogibeel Rail cum Road Bridge.pptx
Bogibeel Rail cum Road Bridge.pptx
ANURAGSWAIN12
 
Report CHENAB BRIDGE 46,47,48,49 ....pdf
Report CHENAB BRIDGE 46,47,48,49 ....pdfReport CHENAB BRIDGE 46,47,48,49 ....pdf
Report CHENAB BRIDGE 46,47,48,49 ....pdf
GarimaSharma754550
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yard
Rajesh Prasad
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
KAVYA H
 
Bandra worli sealink
Bandra worli sealinkBandra worli sealink
Bandra worli sealinkAmit Kumar
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealinkpeepkya
 
Case Study on Mumbai Trans Harbor link
Case Study on Mumbai Trans Harbor linkCase Study on Mumbai Trans Harbor link
Case Study on Mumbai Trans Harbor link
AbhijeetTambade3
 
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
IRJET Journal
 
Mahatma gandhi setu Bihar
Mahatma gandhi setu BiharMahatma gandhi setu Bihar
Mahatma gandhi setu Biharchauhansunny
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...
Rajesh Prasad
 
Padma bridge
Padma bridgePadma bridge
Padma bridge
msnsela
 
Presentation about Padma Bridge.pptx
Presentation about Padma Bridge.pptxPresentation about Padma Bridge.pptx
Presentation about Padma Bridge.pptx
MdAbiAbdullah1
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Dr.Subramanian Narayanan
 
IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET Journal
 
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaSoutheast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
T.Y. Lin International
 
THE EFFECT OF LATERAL CONFIGURATION ON STATIC AND DYNAMIC BEHAVIOUR OF LONG S...
THE EFFECT OF LATERAL CONFIGURATION ON STATIC AND DYNAMIC BEHAVIOUR OF LONG S...THE EFFECT OF LATERAL CONFIGURATION ON STATIC AND DYNAMIC BEHAVIOUR OF LONG S...
THE EFFECT OF LATERAL CONFIGURATION ON STATIC AND DYNAMIC BEHAVIOUR OF LONG S...
IAEME Publication
 

Similar to Bandra - Worli sea link (20)

Bridges construction
Bridges constructionBridges construction
Bridges construction
 
Bogibeel Rail cum Road Bridge.pptx
Bogibeel Rail cum Road Bridge.pptxBogibeel Rail cum Road Bridge.pptx
Bogibeel Rail cum Road Bridge.pptx
 
Report CHENAB BRIDGE 46,47,48,49 ....pdf
Report CHENAB BRIDGE 46,47,48,49 ....pdfReport CHENAB BRIDGE 46,47,48,49 ....pdf
Report CHENAB BRIDGE 46,47,48,49 ....pdf
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yard
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Bandra worli sealink
Bandra worli sealinkBandra worli sealink
Bandra worli sealink
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Case Study on Mumbai Trans Harbor link
Case Study on Mumbai Trans Harbor linkCase Study on Mumbai Trans Harbor link
Case Study on Mumbai Trans Harbor link
 
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
 
Mahatma gandhi setu Bihar
Mahatma gandhi setu BiharMahatma gandhi setu Bihar
Mahatma gandhi setu Bihar
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...
 
Padma bridge
Padma bridgePadma bridge
Padma bridge
 
Presentation about Padma Bridge.pptx
Presentation about Padma Bridge.pptxPresentation about Padma Bridge.pptx
Presentation about Padma Bridge.pptx
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
 
CHENAB BRIDGE
CHENAB BRIDGECHENAB BRIDGE
CHENAB BRIDGE
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)
 
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, ChinaSoutheast Asia Construction - Qianximen Bridge, Chongqing, China
Southeast Asia Construction - Qianximen Bridge, Chongqing, China
 
THE EFFECT OF LATERAL CONFIGURATION ON STATIC AND DYNAMIC BEHAVIOUR OF LONG S...
THE EFFECT OF LATERAL CONFIGURATION ON STATIC AND DYNAMIC BEHAVIOUR OF LONG S...THE EFFECT OF LATERAL CONFIGURATION ON STATIC AND DYNAMIC BEHAVIOUR OF LONG S...
THE EFFECT OF LATERAL CONFIGURATION ON STATIC AND DYNAMIC BEHAVIOUR OF LONG S...
 

Recently uploaded

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 

Recently uploaded (20)

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 

Bandra - Worli sea link

  • 1.
  • 2. BANDRA WORLI SEA-LINKBANDRA WORLI SEA LINK Presented By TE ( CIVIL) Ankita Pal SSJCET
  • 3. INTRODUCTION  Officially known as Rajiv Gandhi Sea Link.  Cable-stayed bridge with pre-stressed concrete-steel viaducts.  Links the Bandra (Western suburb) and Worli ( South Mumbai).  Inaugurated on June 30 , 2009.  Among the most complex & advanced construction projects ever in India.
  • 4.  Designed By : Sheshadri Srinivasan (Structural engineer , Working in Lebanese Engineering Firm Dar-Al-Handshah )  Commissioned By : Maharashtra State Road Development Corporation  Constructed By : Hindustan Construction company , India ( HCC)
  • 5. HISTORY  Mahim Causeway was the only link connecting westernsuburbs to island city of Mumbai, making it highlycongested during the peak hours .  Vehicular traffic admeasuring about 120,000 PCUtravels on the Mahim causeway everyday and during peak hours and it takes about forty minutes to travelfrom Mahim causeway to Worli, a distance of about 8km.
  • 7. BASIC INFO Official Name “ Rajiv Gandhi Setu ” Carries 8 Lanes of Traffic Owner MSRDC Design Cable-stayed, Concrete-Steel precast viaducts Total length 5.6 Km ( 3.5 miles ) Width 2 × 20 m ( 66 ft ) Highest Point 126 m ( 413 ft ) Longest Span 2 × 250 m ( 820 ft ) Vertical Clearance 20 m ( below bridge for transportation ) Foundation Type Pile Foundation Toll System Automated 16-Lane Toll Plaza
  • 8. Time Frame  Estimated Time Frame : 5 years Construction begin : June 1995 Construction end : March 2003  Actual Time Frame : 11 years Construction begin : October 2000 Construction End : 24 March 2010 Opened : 30 June 2009
  • 9. BUDGET  Estimated Cost : ₹ 665.81 Cr  Actual Cost : ₹ 1653.25 Cr  The Increament in project cost was due to payments of escalation ₹ 213 Cr on account of inordinate delay in completion (61 months ) . New technical changes in the bridge at the behest of new consultant₹70 Cr . Contractor for delay in award of work ₹ 125 Cr . Interest liability due to delayed completion ₹ 230 Cr .
  • 10.  PIERS :  The span between the piers is 50 maters .  This distance arrived by considering optimization between foundation cost Vs. superstructure cost .  If the piers are wide apart then foundation cost comes down , but the superstructure becomes heavier and its cost goes up .  Moreover, more number of piers provide better wind resistance .
  • 11.
  • 12.  CABLE WIRE  Are also known as ‘ Parallel Wire Stay Cables ’.  Manufactured by “Shanghai Pujiang Cable Co. Ltd” China .  Each cable consists a group of steel wires ( 6 wires ) .  Each steel wire has a diameter 7mm with a breaking limit of 6.28 Tones.  Group of these wires was packed in two layers of HDPE (High Density Poly Ethylene) material .
  • 13.
  • 14.  Highly uneven and variable foundation bed even for plane area of one pile .  The maritime Board does not allow marine traffic in monsoon season . Thus work was halted Mid-May only to re-commence in October . Effectively reducing the work schedule to only seven month in a year .  Needed for extra steel trusses , further experts .  Delay due to change in design of stray Cable .
  • 15. BENEFITS  Considerable savings in travel time from 40 min to 8 min  Estimated savings in fuel and vehicle operating cost is around $ 16.2 million .  Stress free driving .  Reduced accidents and noise pollution .  Reduction in air pollution .