Career Summary :
A post graduate in civil engineering with over 25 years’ experience in Handling civil engineering of EPC projects of Oil and Gas
sector, Power plants, fertilizer plant etc. in India and abroad , I have extensive senior management experience in large organizations with
operations around the globe, especially with EPC approach. My strengths lie in strategy, leading, improving efficiency of operations,
motivating, training, mentoring and relationship-building.
Types of projects handled:
Oil & Gas, refinery, LNG Re-gasification, Fertilizer, Caustic Soda, Material Handling, Power Plants and Sponge iron plants . Project
size more than 100k man-hours spread over about 14 months. Civil works cost up to $ 150 Million
Software Handled: Frameworks+, Tekla, Staad pro, PDS, PDMS
Certification: IPMA certified project manager Level “C”
Current position: Dy. General Manager
Skills and Abilities
Management and leadership: Over 25 years of working in designing and engineering at a senior level have given me excellent
interpersonal, management and leadership skills. I am able to take responsibility and lead a wide range of projects with full accountability.
Strategy and team management: High-level problem-solving and decision-making, combined with techno-economic considerations, value
engineering and continual improvement.
Establishing / organizing / reorganizing the civil department: Implementation of quality procedures, Interdepartmental work
methodologies, integration of organizational procedures in to the department, leading the department, organize the department with the
hierarchy within the department based on organization norms, and setting up departmental reporting system
Civil design procedures, technical standards: This includes upgrading company technical standards based on current development,
adding standards. Development of soft library of details.
Design software centralization: Harmonizing the worksheets used in various projects, protecting them from getting unauthorized
modification / unauthorized duplication within or outside the company. By this to large extent protecting intellectual property rights.
Technical trainings: This would include facilitation of technical trainings.
Project databank: Development databank of ongoing and completed projects in oracle by providing the functional requirement to develop
web based applications.
2. Prashant M.Gujar
+91 9819126841
Pra.gujar@gmail.com
2
Education and Professional Development
Post Graduate in Civil Engineering with structural engineering specialization from V.J.T.I Mumbai in 1988.
Graduation in Civil Engineering from SDM College of engineering Dharwad.in 1984
Trained for various Software handling as well as for leadership skills
IPMA certified Project manager – Level C in 2014.
Employment History
1. From Aug 2002 till date with Tecnimont ICB Pvt. Ltd.
Responsibilities: Leading Civil engineering team / task force, mentoring, training etc.
In this period I grew from area lead to lead engineer; Lead engineer to Mentor; and at present I am looking
after technical issues of all ongoing projects, conduct independent design reviews, technical audits,
facilitating internal trainings and training the graduate engineer trainees as an additional responsibility.
Projects Handled during this period:
Project Client Description Location Role Specific Achievements
Al Dabbiya
facilities
ADCO
Abu Dhabi Company for onshore oil
operations -surface facility Al
Dabbiya phase III (more than 175 k
civil manhours proj cost $2.2 Billion) ,
Abu Dhabi
Technical
Advisor
Making software compatible to OLD
BS codes as client was firm on either
using old codes OR manual
calculations.
Punta
Catalina
CNO /
Dominican
Republic
2 X 365 Mw Coal Fired Power Plant
In Dominican Republic ($ 2 Billion)
Domnican
Republic South
America
Mentor
Most optimum suggestion for
discharge channel which was grossly
underestimated while bidding.
Tempa
Rossa
Totalgaz
Joint Venture with Total Gaz for
setting up Refinery (Euro 567 Million)
South Italy Mentor
Adverse geotechnical conditions
surfaced during the project, organized
review of critical foundations.
Habshan -5
Process
Plant
Gasco
Lstk Contract With Joint Venture
Between JGC & Tecnimont. (GAS
treatment) (Tecnimont $2.2 Billion)
Abu Dhabi,
UAE
Technical
Advisor
Structural steel connections
optimized standards developed. This
saved time as well as the material of
connections
New Boiler -
Substation
10
GPIC
Supply And Erection Of Boiler ($ 28
Million)
Kindom Of
Bahrain
Project
Leader /
Mentor
The plant was constructed at 300mm
lower level by survey mistake.
Challenge was to provide drains
without pumping. Drainage system
was successfully implemented.
J3 LDPE Reliance
Reliance Jamnagar J3 LDPE
Approx. 55k Civil Manhours)
Jamnagar
India
Technical
Advisor
Implementation of past LDPE project
Lessons learnt, especially for blow
down reactor, Being purely engineering
project, past project references used
for optimum manhour usage
AGRP
Knpc Maa
Refinary
Acid Gas Recovery / Sulphur
Recovery From Gas. Inclluding
Revamp Activities ($ 400 Million)
Kuwait Mentor
Challenge was to engineer the
foundations with partial knowledge of
existing underground facilities, This
was successfully developed and
implemented with many to and fro
communications with site.
3. Prashant M.Gujar
+91 9819126841
Pra.gujar@gmail.com
3
Project Client Description Location Role Specific Achievements
Etileno XXI-
LDPE Plant Etileno XXI
New Ldpe Plant Located In
Coatzacoalcos, Vera Cruz, Mexico
300 KTPA Euro 147 Million
Coatzacoalcos,
Mexico
Mentor
Challenges – High seismicity, Local
norms too stringent, tough
consortium partner. With all these
project was successfully completed
within permissible deviations
3 X 360 MW
Coal Fired
Power Plant
Geracao De
Energia
LSTK Contract In Joint Venture
Consortium Between Maire,Alusa,BC
Projectos And Efacec (MABE).
Pecem, State
Of Ceara.
(Brazil)
Mentor
- Schedule recovery:
Three projects were being executed
simultaneously; there was delay
attributable to inputs and delay in
handover. The delay was recovered
by extra efforts, sharing the
resources competence, making use
of other project information, etc. in
spite of input changes. ALSO
underground engineering with large
complexity was handled for the first
time in these projects.
1 X 360 MW
Coal Fired
Power Plant
Itaqui, State Of
Maranhao
LSTK Contract In Joint Venture
Consortium Between Maire, Alusa,
Bc Projectos And Efacec (MABE).
Itaqui, State Of
Maranhao
Mentor
370 MW
Coal Fired
Power Plant
Endesa, Chile
LSTK Contract In Joint Venture
Consortium Between Maire And Ses.
The Contract Is On LSTK Basis
Including Basic Engineering, Detail
Engineering
Bocamina,
Coronel, Chile
Mentor
PE, NAO
(350KMTA)
Chevron-
Philips
Tech.
Q-Chem
Petrochemicals
EPC-LSTK project (JV Between
TCM & Daewoo Engg. &
Construction Co.Ltd. Korea) For
HDPE And NAO Plants With Offsite
Facilities. The Plant Capacities Are:
HDPE Plant –
350 KMTA And NAO Plant – 350
KMTA.
Mesaieed
Industrial City,
Qatar
Mentor / Field
Engineer
Established the root cause of
excessive deflection of the pipe
bridges in the construction stage
under self-weight only. The reason
(i.e. poor detailing) was
substantiated by calculations.
Further the same was rectified at site
under my guidance with minimum
efforts, and time.
Borealis
Ldpe 5 Plant
Sweden
Borealis
EPC project, Polyolefins Unit
(PE/PP), Product Handling &
Marine Works. The Plant Capacities
Are: (PE) Plant - 540,000 Tons/Yr. &
(PP) Plant 2 Units Of
400,000 Tons/Yr.Each.
Stenungsund
Dy. Lead
Engineer
The project was given to Mumbai
office to recover huge delay by
engineering sub-contractor. More
than 30% of manhour and schedule
were consumed without any output
by subcontractor. The schedule was
recovered with most of the team-
members being new joinees, with
little manhour over-run.
LNG FOS
(FR) EPC
FRANCE
GAZ DE
FRANCE
LSTK contract in joint venture
between SOFREGAZ, SN
TECHNIGAZ and SAIPEM SA for
LNG Re-Gassification
FOS CAVAOU
France
Lead
Engineer
First overseas regasification project
where detailed engineering was in
the scope. Worked closely with the
sister concern – Sofregaz. Worked
on site and led Civil team, developed
cryogenic pipe support alternative
design to cater for huge thermal
forces.
LNG
TERMINAL
PM/CS
HAZIRA
Shell
LSTK project for LNG regassification:
PLANT CAPACITY IS 2,000,000
TONS/YEAR.
HAZIRA,
GUJARAT
India
Lead
Engineer/
Field
Engineer
The First LNG plant in India. SHELL
DEP were used for the first time, so
also carrying out cryogenic
requirements. Headed Field
engineering team at site for nearly
one year. During this many site
issues were resolved.
4. Prashant M.Gujar
+91 9819126841
Pra.gujar@gmail.com
4
Major Achievements during this period:
Successful timely completion of engineering of many of the projects with very little cost deviation, Recovered the
schedule in case of taking over from external party. Post engineering, providing solutions the site for many
construction related issues. Heading civil team of field engineering on Indian and overseas sites. Saved cost
by Value engineering, mentoring, and solved site issues – both design related and construction related issues.
I have conducted technical trainings for new joinees as well as other colleagues as an additional responsibility.
Conducted Technical Audits and built lessons learnt databank, and spread the technical awareness in the
department.
Centralization of the in-house development of software in Excel, MathCAD by converting the same in DOT NET
2. From Feb 2002 to Aug 2001 with Technet (I) Pvt. Ltd.
Responsibilities: Leading shop drawing team / co-ordination with parent office in USA. I was working for
subsidiary of US based company. Main function of the company was to make fabrication drawings for
various US based projects. I joined the company as a technical head, next to the head of the company. The
software used for the detailing was SDS2. One of my responsibilities was to communicate with Parent office
for day-to-day matters and solve the technical issues.
Projects Handled during this period:
Project Client Description Location Role
St. Baptist church RMM Global
Structural steel detailing
(approx.. 25 drawings)
TEXAS,
USA
Technical manager
Dangerfield school RMM Global
Structural steel detailing
(approx.. 35 drawings)
NC USA Technical manager
Murphy school RMM Global
Structural steel detailing in
SDS2 Test project(approx..
35 drawings)
OHIO, USA Technical manager
Major Achievements during this period:
Streamlined the communication between Mumbai office and USA office.
Explored the additional capabilities of SDS2 software.
Checklist for accuracy in “Advance Bill of Material” was developed and implemented. I also developed Qbasic
software for point to point bolts.
5. Prashant M.Gujar
+91 9819126841
Pra.gujar@gmail.com
5
3. From Nov 1996 to Feb 2002 with Jacobs Engineering.
Responsibilities: Leading Civil engineering team /supporting sister offices / Implementing 3D modeling. My
main function was lead engineer, however in the absence of projects, I was looking after some proposals and
partly off-loaded projects from other cost centers. The lean period was utilized for development of PDMS
capabilities and I was chosen to head civil engineering team. Generic models were developed during this
period after getting trained for the same.
Projects Handled during this period:
Project Client Description Location Role Specific Achievements
QABICO MIDREX
STEEL PLANT DETAING IN PDMS
(1000 TPA)
Qatar
Lead
engineer
Achieved target of modeling
Reduction furnace, reformer structure,
Analyzed for seismic loads, extracted
drawing and got approval from
MIDREXMESABI
NUGGET
REVAMP
MIDREX(COBE
STEEL)
PDMS DETAILING OF STEEL
PLANT
(upgraded to 1000 TPA)
USA
Lead
engineer
ST. GOBAIN
GLASS
PLANT
CHENNAI
ST. GOBAIN
(SGGI)
GLASS PLANT , 1200 TPD glass
production
Chennai ,
India
Dy. Lead
Engineer
Furnace building: engineering
completed within schedule
Pipe rack cable tray deflection
problem at site was solved.
Warehouse drainage backflow
problem resolved.
SHAKTI
PAINTS
ICI
Design and detailing of PAINT
PLANT
MOHALI,
PUNJAB
Dy. Lead
Engineer
-
SIP
HITACHI-
ZOSEN
Substation design and detailing JAWA
Design
Engineer
-
LLDPE/HDPE
IPCL (THRO'
SAMSUNG)
Control building modifications
Nagothane,
India
Design
Engineer
-
PTTI
(INDOTHAMA)
STONE &
WEBSTER
WASTE WATER TREATMENT
(PROJECT ABONDONES AFTER
ECONOMIC SETBACK OF
INDONETIA)
Indonesia
Dy. Lead
Engineer
Underground Basins – I was
instrumental in evolving most
economic system for large buoyancy
during detailed engineering
Major Achievements during this period:
I Successfully implemented of PDMS, a 3D modeling software. I was part of the team to evaluate and implement
PDMS. I was instrumental in evolving most economical arrangement for underground basins subjected to significant
buoyancy.
6. Prashant M.Gujar
+91 9819126841
Pra.gujar@gmail.com
6
4. From Apr 1990 to Nov 1996 with ICB / TICB
Responsibilities:
Worked at various levels - Design engineer to lead engineer. During this period, my growth took place from
design engineer level to lead engineer. This was the period when the reputed companies shifted from
manual drafting to computerized and computer aided design. I was chosen to facilitate the implementation
the new system.
Projects Handled during this period:
Project Client Description Location Role Specific Achievements
Al Jubail,
Saudi Arabia,
Caustic Soda
NAMA, KSA PRILLING PLANT AL-JUBAIL
Lead
Engineer
Economical structural system
developed and implemented
Caustic Soda
MARDIA
CHEMICALS
Detailed engineering of caustic
soda plant
MARDIA
NAGAR,
India
Lead
engineer
Salt handling new structural system
was implemented
Coal Handling
Project
COAL INDIA
LTD.
Design of various structures as
trestlels, conveyor gallaries,
crusher house, Roads etc.
PIPARWAR,
India
Dy. Lead
engineer
-
Poly-
Prophylene
Plant
INDIAN
PETROCHEMI
CALS
CORPN.LTD
Design of extrusion building and
blast resistant control building
BARODA,
India
Dy. Lead
engineer
First blast resistant building was
designed
Formic Acid
Plant
RASHTRIYA
CHEMICALS &
FERTILIZER
Design of tank farms, Ammonia
vessel foundations.
THAL,
MAHARASH
TRA, India
Design
engibeer
-
Bagging Plant
And Wagon
Loading
Platform
CHAMBAL
FERTILIZERS
LTD.
BAGGING PLANT, WAGON
LOADING PLATFORM.
GADAPEN,
India
Design
Engineer
-
Wagon
Loading
platform
ZUARI AGRO
CHEMICALS
LTD.
Wagon Loading platform for
bagged fertilizer
Goa, India
Design
engineer
-
Soaps &
Detergents
TATA
VASHISHTI
DETERGENTS
Design and detailing plant buildings' Khed, India
Design
engineer
-
Major Achievements during this period:
Successful implementation of computer aided drafting both in Microstation and AutoCAD.
Harmonization of Technimont systems and ICB system during take-over.
Design of blast resistant buildings.
Handled Part of PP plant for IPCL - the first Oil and Gas project in ICB
Designed most economical structural system for pilling plant in Saudi Arabia, which was vetted by Head of the
department.
7. Prashant M.Gujar
+91 9819126841
Pra.gujar@gmail.com
7
5. From Sep 1988 to Apr 1990 with Dubon Project Engineering Pvt. Ltd.
During this period, I designed multi-storied buildings, Aircraft Hangers, Glindia Pharma project in Ankaleshwar,
Theatres design Etc.
6. From Sep 1987 to Sep 1988 with A. B. Yeri and Associte
Worked as an associate, Design mainly Residential buildings and worked on some off-loaded industrial projects
like Capro-lactum warehouses, Sulphuric acid plant etc.
7. Worked as a lecturer in Civil department for an year after graduation and before post-
graduation
Trainings imparted
During my career I attended various trainings – software operating, technical, non-technical, In-house – external,
Management – quality Assurance, Current developments, leadership- corporate, etc.
Technical:
PDMS software
Dynamics
Outstanding structures around
Cathodic protection
Behavioral:
Corporate etiquettes and finesse
Communication and presentation skills
Personal effectiveness
Leadership and team building
System:
ISO 9001awareness
OHSAS 18001 and ISO 14001
ISO 29001
8. Prashant M.Gujar
+91 9819126841
Pra.gujar@gmail.com
8
References:
1. Mr. M. Stephen
Vice President (Mechanical Design)
Tecnimont ICB Pvt Ltd
+91 9920912295
2. Mr. V.V.S. Murthy
Asst. Vice President
Reliance Industries Ltd.
+91 7710008287
Hobbies:
Reading, Running completed half marathon twice in 2 Hr. 43 min and 2 Hr. 47 Min