1. DEPARTMENT OF CIVIL
ENGINEERING, SR UNIVERSITY
Under the Guidance of
Sri L Rajam
District R&B Officer Hanamkonda
An Industrial Project Review-2 on
Submitted By:
Name: B. Jayakar
Hall ticket No: 2005A11019
Fatimanagar to Mamnoor
Bridge Construction
2. OVERVIEW OF INDUSTRIAL PROJECT
2
• The Fatimanagar to Mamnoor Bridge project aims to enhance transportation
infrastructure in Hanamkonda by connecting two important locations.
• The ongoing construction at the R&B Department Hanamkonda is aimed to meet
the important needs of the region. Both sides of the proposed bridge are 126.6
meters long and designed as a steel girder bridge. Its capital is Rs.68-crore’s,
which includes not only the bridge but also service facilities and CC sewers,
represents a major investment in supporting transport.
• The structure, using rods of different sizes (8 mm, 10 mm, 12 mm, 16 mm, 25 mm
and 32 mm), complies with strict standards. The project has a broader objective
beyond its physical aspect: to facilitate transportation of vehicles and provide seamless
connectivity between Fatimanagar and Mamnoor.
3. • As a collaboration between government agencies and construction experts, this
• Initiative life and supporting business growth in the region. The structure, using rods of
different sizes (8 mm, 10 mm, 12 mm, 16 mm, 25 mm
• and 32 mm), complies with strict standards. The project has a broader objective beyond
its physical
• pect: to facilitate transportation of vehicles and provide seamless connectivity between
Fatimanagar and Mamnoor.
• As a collaboration between government agencies and construction experts, this initiative
and supporting business growth in the region.
4. 4
• Name of the project : Fatimanagar to Mamnoor Bridge Construction
• Company Name : Roads & Buildings Department Hanamkonda
• Complete Address of the company : 2-6_58, Circuit House Rd, KLN Reddy
Colony, Nakkala Gutta, Hanamkonda.
• Industrial Project location : Fatimanagar Area back side of NIT Warangal
• Project Guidance : Sri L Rajam (District R&B Officer)
• Duration of the project : The duration is projected to be 6 Months.
5. OBJECTIVE
• Hanamkonda, Telangana.
• The aim is to provide a direct and efficient route between Fatimanagar and Mannoor, thereby reducing
travel time, improving accessibility for residents and businesses, and encouraging business growth.
• Additionally, the project focuses on environmentally sustainable practices to reduce the project's impact
on the environment and preserve natural resources. Through careful planning, design and
implementation, the aim is to provide safe, durable, efficient models that meet customers' needs while
also supporting development to fix the entire transportation of the region.
5
In order to improve regional connectivity and reduce traffic congestion, a bridge
Has been proposed to be constructed from Fatimanagar to Mamnoor,
6. NEED OF THE PROJECT
6
• The construction of the Fatimanagar to Mamnoor Bridge is crucial for our community because it
helps solve big problems with traffic and makes it easier for everyone to get around. Right now,
there's too much traffic in Hanamkonda, and it's making things slow and hard for people to reach
where they need to go. By building this bridge, we're creating a direct path between Fatimanagar
and Mamnoor, which means less time stuck in traffic and more time for important things like work,
school, and spending time with family.
• It is not just about making things easier for us it is also about helping businesses grow and
making sure everyone has access to important services like hospitals and schools
8. DESIGN ESTIMATION
8
• Fatimanagar to Mamnoor Bridge Construction at R&B
Hanamkonda .
• The length of the bridge is projected to be 126.6m
long on both the sides.
• It is a Girder Bridge.
• The Budget of the construction is 68 Crore.
• Iron roods of 8mm-32mm are being used in the
construction.
• The depth of the footings is 4.5m depth.
• The construction utilized M25 grade concrete for the
project.
9. CONCLUSION
9
• In our Review 2, we are happy to report the significant progress made in the construction of the
Fathianagar to Mamnoor bridge. Since our last inspection our work has progressed from finishing
the foundation to constructing the hammer head bearing blocks. This is an important step towards
achieving our project goals.
• Going forward, we are committed to seizing this opportunity and delivering the best bridge designs
that improve connectivity and support business growth. With the completion of the hammerhead
foundation bed, we are now ready to move on to the next phase of construction with renewed
determination and enthusiasm. We remain committed to completing this critical infrastructure
project for the benefit of everyone.
10. FUTURE WORK
10
• Going forward, we will focus on completing the next phase of bridge construction. Along with the
work on developing the superstructure, our next step involves the complete installation of the beams
and girders that will support the deck, followed by the location of the deck. Railings will then be
installed for additional safety and finishing the surface like protective layers will ensure the long
life of the bridge. Strict controls will be followed throughout this process in accordance with safety
and quality standards.
• Detailed reports will be maintained providing detailed information about our progress. By pursuing
these responsibilities and goals, we aim to complete bridge construction, build relationships for our
community, and support regional economic growth.
11. OUTCOME OF THE PROJECT/ KEY DELIVERABLES
11
• The outcome of the project is a completed bridge stretching from Fatimanagar to Mamnoor in
Hanamkonda. making it easier for people and goods to move between these places. This bridge
improves how connected Fatimanagar and Mamnoor are, cutting down on travel time and helping
businesses grow. It also helps with traffic jams in Hanamkonda, making travel smoother for
everyone.
• By building the bridge, we're making life better for the community, creating jobs, and protecting
the environment. The bridge is built safely and meets all the rules and standards, ensuring that
people can use it without worry. We've talked with the community throughout the project to make
sure everyone's happy with the results, and we've kept good records of everything for future
reference. Overall, this project brings big benefits to our area, making it easier to get around and
improving the quality of life for everyone.