Metro Route 2020 Dubai – Construction $2.9bn
Included
Route, Programme Graphic
Tunnelling, Stations & Viaduct
Details
Lengths
Viaduct 10.5 km
Tunnel 4 km
Stations
Underground 2 Nr.
Elevated 5 Nr.
Capacity 46,000 passengers per hour.
Maximum wait time will be 100 seconds and there
will be 15 trains
Tunnels & Underground Stations
Viaduct
3D image to show Sequence, Method & Plant.
David H Moloney
21st July 2016
ⓒ David H Moloney
Project Execution Plan. Details how the Metro will be
constructed, and how the progress, safety and quality will be
monitored and controlled. Also the measures to ensure that
the site is environmentally friendly
Contents
Work Categories as per CESMM
Introduction
Metro Route 2020
Red Line Green Line
Route
ⓒ David H Moloney
Route Animation
Green
Community
Dubai
Investment
Park
Jebel Ali Port
Palm Jebel Ali u/c
Ibn
Battuta
Mall
Harbour &
Tower Station
Tunnel
ⓒ David H Moloney
Programme Time Chainage
The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types
Programme Visualisation
Tunnel
Viaduct
Viaduct
ⓒ David H Moloney
Schematic longitudinal Profile
Principal Quantities
Schematic Longitudinal Section ⓒ David H Moloney
Cost Comparisons of various Metro Projects
Dubai Route
2020
UAE
(To Start)
Red Line North
Doha
Qatar
(In Progress)
Red Line South
Doha
Qatar
( In Progress)
Metro North
Dublin
(Proposed)
Dart
Underground
Dublin
(Proposed)
Overall Cost €2,450 million €1,803 million €1,500 million €2,400 million
Cost per km €158 million /k m €140 million / km €108 million / km €134 million / km
Overall Length 15.5 km 13 km 14m 18 km 5 km
Tunnel 4 km
Single Tunnel
11.6 km
Twin Tunnels
14 km
Twin Tunnels
7.5 km
Twin Tunnels
5 km
Twin Tunnel
Cut & Cover 0 2.7 km 0
Elevated 10.5 km 2.2 km 0
Road Level 0 5.5 0
Stations 7 Nr. 7 Nr. 5 Nr. 14 Nr. 3 Nr.
Capacity 13,000 Passengers
per hour
19,800 Passengers per
hour
?
ⓒ David H Moloney
Advantages of Light Rail Systems Benefits of Metro to commuters
1. Time saving for commuters 4. Reduction in accident
2. Reliable and safe journey 5. Reduced fuel consumption
3. Reduction in atmospheric pollution 6. Reduced traffic congestion
Contractor’s General Items
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
Quarry & Aggregate Production
ⓒ David H Moloney
Brief Description
Rock is blasted free from the quarry
face and fragmented so it will fit into
the primary crusher. Any oversized
rock is broken with a excavator and
hydraulic Rockbreaker.
At the Crushing and screening yard
the fragmented rock is crushed and
screened into various size ranges.
Concrete Batching Plant David H Moloney
Concrete batching plant comprises -
concrete mixer, control cabin, silos for
cement and fly ash, aggregate bins and
conveyor belt system to feed the mixer.
Also aggregate storage bays and water
storage tanks.
The mixing is computer controlled and has
a dynamic screen display, showing the
process. Material storage capacity to
match two days concrete production
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Site Hoarding examples
ⓒ David H Moloney
GeneralItems
Weighbridge & Sheeting Access
ⓒ David H Moloney
GeneralItems
Wheel Wash Drive-through
ⓒ David H Moloney
GeneralItems
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
Dewatering
ⓒ David H Moloney
GeneralItems
Dewatering by Wellpoints
ⓒ David H Moloney
GeneralItems
Dust Suppression
ⓒ David H Moloney
GeneralItems
Traffic Management
ⓒ David H Moloney
GeneralItems
Brief Description
Traffic management plans are
necessary when working on or beside
roads
Traffic Management – Work on Median
ⓒ David H Moloney
GeneralItems
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
GeneralItems
Welfare Facilities
ⓒ David H Moloney
GeneralItems
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
HSE
Existing Underground Utilities
ⓒ David H Moloney
Earthworks
Brief Description
Before digging
establish the location
and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Earthworks
Trench - Safety Measures
Health,Safety&Environment
Trench - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Safety Precautions
Environmentally Friendly Site Air, Noise, Water & Soil Pollution
Segregation of WasteHealth,Safety&Environment
Segregation of waste for proper disposal and
recycling. Less waste goes to landfill and
hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
Water Pollution PreventionGeneralItems
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Emergency Phone Numbers & Response
Geotechnical
Diaphragm Wall Construction - Sequence, Plant & Methods
Diaphragm Wall Grab
ⓒ David H Moloney
Brief Description
Shown is the Sequence,
methods and plant to construct a
diaphragm slurry underground
wall.
Diaphragm Wall Construction - Sequence, Plant & Methods
ⓒ David H Moloney
Earthworks
Tunnels & Underground Stations
3D image to show Sequence, Method & Plant.
David H Moloney
ⓒ David H Moloney
Underground Station Excavation
Underground Station Construction
Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
Concrete
Concrete Full Scale Trial Castings of Pier
ⓒ David H Moloney
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
BIM 3D Model Shutter Fibreglass
Concrete Full Scale Trial Castings of Bridge Deck
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
Fresh Concrete Properties Tests
Air Content, Consistence, Density, Initial and Final Setting Time, Temperature
and Bleeding
Chloride Ion Content
Hardening and Hardened Concrete Properties Tests:
Density and Compressive Strength for 1, 3, 7, 14 and 28 Days
Concrete Core Compressive Strength
Tensile Splitting Strength
Modulus of Elasticity
Heat Development
Chloride Migration Coefficient (28 Days)
Reinforcement Cover Measurement Survey
Trial for Waterproofing to Bridge Deck
ⓒ David H Moloney
Brief Description
. The trial for the deck waterproofing
shall demonstrate/document that all
requirements to the waterproofing and
the execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
Trial for Waterproofing to Bridge Deck - Tests
Concrete
Vibrating Concrete
ⓒ David H Moloney
Concrete
Tunnel Wall Segments Casting
Clean Mould
Lift Precast Segment out of mould
after 18 hours.
Reinforcement
fabricate
Reinforcement
into Mould
Concreting
Segment Storage
Cycle Time
24 hrs
ⓒ David H Moloney
Tunnel Precast Segments
Precast Yard for Tunnel Segments
Viaduct Construction David H Moloney
ⓒ David H Moloney
Viaduct Construction David H Moloney
ⓒ David H Moloney
Viaduct Construction David H Moloney
ⓒ David H Moloney
Viaduct Segments Casting David H Moloney
Casting Method
The concrete segments are manufactured
using the short-line, match-casting method.
Match-casting is when sequential segments are
poured against the previous cast segment, this
ensures that the segments will fit perfectly on
site.
ⓒ David H Moloney
Viaduct Segments – Short-line, Match Casting Method David H Moloney
Precast Yard for Viaduct Segments
Viaduct Segments Launching
ⓒ David H Moloney
Bridge Construction Sequence
David H Moloney
Bridge Construction Sequence
David H Moloney
Piling Surcharge Abutments
Remove Surcharge Abutments
Deck centre
Post-tensioning Fascia & Waterproof deck Complete Bridge
PiersOverview
Deck Ends
Images with Schematic 3D view, Photos & Timeline
ⓒ David H Moloney
Post-tensioning Bridge Deck David H Moloney
Falsework & Shuttering for Insitu Ramp David H Moloney
Large Floor Concrete Pour
Reinforced Wall Construction Sequence David H Moloney
ⓒ David H Moloney
Reinforced Structure Construction Sequence David H Moloney
ⓒ David H Moloney
Going Underground
ⓒ David H Moloney
Cut & Cover Tunnel Construction
Sequence -Traffic and utilities are diverted, excavate trench, construct & backfill to bury.
To prevent the faces of the excavation from collapsing, different measures are used –
batter the faces, diaphragm walls, secant piles or a combination of soil nailing and
shotcreting.
Ramp Construction
Sequence -Traffic and utilities are diverted, excavate, construct and backfill to sides.
To prevent the faces of the excavation from collapsing, different measures are used – batter
faces, diaphragm walls, secant piles or a combination of soil nailing and shotcreting.
ⓒ David H Moloney
Structural Steel
Elevated Stations
Elevated Stations
Elevated Stations
ⓒ David H Moloney
Elevated Stations
ⓒ David H Moloney
Inside Stations
ⓒ David H Moloney
Passenger Bridge
Roof Covering
Roof Covering
Roof Covering
View of Metro from Burg Khalifa
ⓒ David H Moloney
Piling
Piling Construction - Plant & Methods
Brief Description
Piling Plant, Equipment and Material;
Crawler Crane, Piling Hammer, Temporary Casing,
Piling Rig, Concrete Pump, Concrete Mixer Trucks,
Tremie Pipe and Reinforcement Cage
Piling
Piling Construction - Plant, Methods & SequencePiling
Piling Construction - Plant & MethodsPiling
Piling Construction - Vertical PilesPiling
Pile Load Test
ⓒ David H Moloney
Piling
Brief Description
A jack is used to load the pile in steps and
gauges measure any settlement.
Secant Pile Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
Brief Description
Shown is the Sequence,
methods and plant to construct a
secant pile underground wall.
Secant Pile Construction - Sequence, Plant & Methods
Sheet Pile Shaft Temporary to Support Excavation
Drive Sheet Piles Excavate & install bracing
Construct Concrete Structure Backfill, remove bracing & sheet piles
ⓒ David H Moloney
Sheet Pile Shaft Temporary to Support Excavation
ⓒ David H Moloney
Roads & Paving
Asphalt Batching Yard
Roads&Pavings
Road Construction Sequence Animation
Railway
Tunnel Fit-out Rail, Electricals, Ventilation
Tunnel Fit-out
Install Sleepers & Rails
Concrete Batching Train for Floor Slab
Drilling Machine for Utilities Brackets
Commissioning, Testing, Handover & Opening
Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.
ⓒ David H Moloney
Commissioning, Testing, Handover & Opening
Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.
ⓒ David H Moloney
Tunnel
Tunnel Boring Machine (TBM)
Tunnel Boring Machine (TBM)
HERRENKNECHY AG
Tunnel Boring Machine (TBM)
Tunnel Boring Machine (TBM)
Tunnel Boring Machine (TBM)
Cutting Head rotates to Dig
Excavated material removed
by conveyor belt
Lifting muck to surface
with skip
Placing Concrete
Segments
Tunnel Boring Machine (TBM)
Cutting Head rotates
7 nr. Precast segments
form rings that line the
tunnel Excavated material removed
by conveyor belt
ⓒ David H Moloney
Miscellaneous Works
Fencing
ⓒ David H Moloney
Sequence of Construction
Clear Scrub & Grade ground
Fix Corner & Strainer Posts
Fix Intermediate Posts
Fix Line Wire, Chain-link & Razer wire
Concrete ground beam
Administrative
Progress Monthly, Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current
progress and historical trends
Histogram Charts for Resources & Outputs
Concrete, Manpower, TBM,
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Quality Assurance
Quality Assurance Dashboard Dashboard is a single page, graphical representation of
current statistics and historical trends
Setting out & Surveying
Setting out & Surveying
Setting out & Surveying
Pavement Art
Production by David H Moloney
See my YouTube channel for further details
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
ⓒ David H Moloney

Route 2020 Metro Dubai Construction Details