SlideShare a Scribd company logo
1 of 6
Download to read offline
SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref -
SE-CTJ-01CW-MST-00417
Project - ABC Works By - ABC Ltd Date – 01/01/01
Page 1 of 6
Nr. HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
General Airside Working
1 Lack of Airside
safety awareness
• Cause damage &
Injury
• Impact negatively on
airport operations
6 6 36 • Staff to receive airside safety training.
• Risk Assessments & Method of Work Plan to
be briefed to all affected workers.
• Airside induction
• Pre start-up and regular site meetings
should be held to ensure safety
requirements are met.
• Promotion of safety awareness through
training.
6 2 12 Adequately
Controlled
Risk
2 Construction that
impacts on the safe
operation of airport
• Cause damage and
injury
6 6 36 • Method of Work Plans to be submitted and
approved by stakeholders prior to any work
starting
• Notams to be issued where necessary.
• A close working relationship between the
contractor, airport operator and
stakeholders will enhance safety at the
airport
• Ensure clean and tidy storage and proper
disposal of materials and waste
6 2 12 Adequately
Controlled
Risk
SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref -
SE-CTJ-01CW-MST-00417
Project - ABC Works By - ABC Ltd Date – 01/01/01
Page 2 of 6
Nr. HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
3 Unauthored
Persons
• Security breach 8 4 32 • All those entering airside to have a pass and
to be checked by security.
8 2 16 Adequately
Controlled
Risk
4 Collision with
aircraft in flight
• Severe damage
• Fatalities
• Public outcry
10 4 40 • Fan corridor height restrictions briefed to all
site teams
• Works in the fan corridor will be controlled by
Restricted Area Access Work Permits
• Height markers ( such as goal posts ) shall be
constructed as applicable to advise of height
limits
• All plant equipment shall be selected on basis
of maximum operating heights so as to not
interfere with airport operations
• Supervision at all times.
• Any plant operating at heights must not
infringe the protected surfaces, inside or
outside the airport property limits
• Crane operating heights should be checked
to ensure no protected surfaces are
infringed.
10 2 20 Adequately
Controlled
Risk
5 Lighting for night
working
• Distracts, dazzle and
blind pilots and ATC
8 4 32 • Lights shall be shielded so direct light does not
shine above the horizon.
8 2 16 Adequately
Controlled
Risk
6 FOD- Foreign
Object Debris
• Damage to aircraft
tyres, engines
• Injury
4 6 24 • Continuously remove waste or loose
materials
• Vehicles entering or exiting the worksite
may need to be cleaned to prevent mud or
debris being deposited in the airside area
4 2 8 Negligible
Risk
SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref -
SE-CTJ-01CW-MST-00417
Project - ABC Works By - ABC Ltd Date – 01/01/01
Page 3 of 6
Nr. HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
• Ensuring the workforce are committed to
active FOD prevention
• Maintaining good housekeeping practice
•Suitable site fencing should be installed to
protect from jet blast and to ensure FOD is
contained within the site
•Staff should remove and dispose of any
FOD found
7 Bird Strikes • Damage to aircrafts
• injury
4 4 16 • Don’t attract birds by feeding them.
• Dispose of waste food properly using bins
4 2 8 Negligible
Risk
8 Equipment or
material near
NAVAIDs
Navigational Aids
• Degrade or impair
radiated signals
• Injury
4 4 16 • Keep area in front of localiser and glide slope
free.
• Know the ILS sensitive areas
• Providing warning signs, markings or
lights at the edge of the sensitive area to
prevent accidental intrusion into the
sensitive areas
4 2 8 Negligible
Risk
9 Failure to control
dust.
•Obscures or
diminishes the
visibility of areas
•Injury
6 4 24 • Use dust suppression by wetting surface.
• Use sheeting on trucks transporting fine
materials
• Sweep up dust
6 2 12 Adequately
Controlled
Risk
10 Inappropriate or
poorly maintained
fencing
•inadequate to
separate
construction areas
•Injury
4 4 16 • Ensure fencing is adequate
• Maintain fencing
4 2 12 Adequately
Controlled
Risk
SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref -
SE-CTJ-01CW-MST-00417
Project - ABC Works By - ABC Ltd Date – 01/01/01
Page 4 of 6
Nr. HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
11 Jet Blast •Injury 6 6 36 • Protect construction workers from jet blast
• Ground crews are to ensure areas behind
the aircraft are clear, and that the aircraft is
positioned in such a way as to avoid
concentrating break-away blast at
buildings, parked or taxiing aircraft or
persons on the apron
6 2 12 Adequately
Controlled
Risk
12 Driving Airside • Accidents
• Injury
6 6 36 • All contractor drivers must be escorted by
a qualified vehicle operator or undergo
airside driver training and testing Access
routes should be agreed to and clearly
identified to minimize interference with the
operation on the airport
6 2 12 Negligible
Risk
13 Fire • Damage
• Injury
• Smoking restrictions should be described,
monitored and enforced
• Hot works restrictions (possibly involving
a separate hot works permit) should be
described, monitored and enforced
• Mobile phones should be switched off
when refueling plant so as not to ignite
fumes.
• No smoking.
• Fire extinguishers to be provided
14 Spillage of fuel,
oil, substances
• Injury by trips and
falls
•Provide spill kits
•Deal with spills straight away
•Spills should be thoroughly cleaned and
dried.
SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref -
SE-CTJ-01CW-MST-00417
Project - ABC Works By - ABC Ltd Date – 01/01/01
Page 5 of 6
Note - The Control Measures are used to reduce the Likelihood and thereby the Residual Risk
A Hazard is the potential to cause harm. A Risk is the likelihood of harm taking place.
Table
Value Severity Value Likelihood Residual Risk - Ratings & Actions
10 Multiple Fatalities 10 Certain
Risk valve is obtained by multiplying the likelihood
value by the severity value. The severity value
remained the same, without or with controls, it is
the likelihood valve that the controls will reduce
8 Single Fatality or Permanent Disability 8 Very Likely 60 - 100 Intolerable Risk
6 Major Injury loss of time >3 days 6 Likely 32 - 48 Moderately Controlled Risk
4 Minor or Serious Injury 4 May Happen 12 - 24 Adequately Controlled Risk
2 Slight injury 2 Unlikely 0 - 8 Negligible Risk
Aim of Risk Assessment - To find solutions that would eliminate, mitigate, or manage the risks to an acceptable level.
Risk Assessment Matrix
Severity Likelihood
Certain
Value =10
Very Likely
Value = 8
Likely
Value = 6
May Happen
Value = 4
Unlikely
Value = 2
Multiple Fatalities Value = 10 100 80 60 40 20
Single Fatality or Permanent
Disability
Value = 8 80 64 42 32 16
Major Injury loss of time >3 days Value = 6 60 49 36 24 12
Minor or Serious Injury Value = 4 40 32 24 16 8
Slight injury Value = 2 20 16 12 8 4
Green
Amber
Red
No further action required
The current residual risk requires a review of available options and action
The current residual risk requires further action to reduce it.
SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref -
SE-CTJ-01CW-MST-00417
Project - ABC Works By - ABC Ltd Date – 01/01/01
Page 6 of 6
Images

More Related Content

What's hot

history of airport security
history of airport security               history of airport security
history of airport security Hasin Raheel
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTERDavid H Moloney
 
General Aviation Security
General Aviation SecurityGeneral Aviation Security
General Aviation SecurityERAUWebinars
 
273372884-Permit-To-Work.pptx
273372884-Permit-To-Work.pptx273372884-Permit-To-Work.pptx
273372884-Permit-To-Work.pptxHafizYunus6
 
Safe Push back Procedure.
Safe Push back Procedure.Safe Push back Procedure.
Safe Push back Procedure.Andrew Louis
 
Job safety analysis
Job safety analysis Job safety analysis
Job safety analysis soumenmakar
 
AVIATION SECURITY PRESENTATION
AVIATION SECURITY PRESENTATIONAVIATION SECURITY PRESENTATION
AVIATION SECURITY PRESENTATIONPaul Mears Phd.
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slidesMaffino
 
Airport Operations & Traffic Pattern Operations
Airport Operations & Traffic Pattern OperationsAirport Operations & Traffic Pattern Operations
Airport Operations & Traffic Pattern OperationsEdwin Pitty Sanchez
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Procedure for Safe Ground Handling Practices - (Sample for Edition)
Procedure for Safe Ground Handling Practices - (Sample for Edition)Procedure for Safe Ground Handling Practices - (Sample for Edition)
Procedure for Safe Ground Handling Practices - (Sample for Edition)Andrew Louis
 
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Risk assessment for soil investigation at towers 5,6,7,8  rev01  a.doganiRisk assessment for soil investigation at towers 5,6,7,8  rev01  a.dogani
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.doganiArber Dogani
 
airside operation 3
airside operation 3airside operation 3
airside operation 3AiDY
 
Method of Working Plan - Unit Project
Method of Working Plan - Unit ProjectMethod of Working Plan - Unit Project
Method of Working Plan - Unit ProjectDyne Candido
 
Confined space entry natt7029
Confined space entry   natt7029Confined space entry   natt7029
Confined space entry natt7029Piyushjauhari3
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranesAzmeel Contracting Company
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptssuser0ebdc3
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pagesDavid H Moloney
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2Sergio Augusto Esteves
 

What's hot (20)

history of airport security
history of airport security               history of airport security
history of airport security
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTER
 
General Aviation Security
General Aviation SecurityGeneral Aviation Security
General Aviation Security
 
273372884-Permit-To-Work.pptx
273372884-Permit-To-Work.pptx273372884-Permit-To-Work.pptx
273372884-Permit-To-Work.pptx
 
Safe Push back Procedure.
Safe Push back Procedure.Safe Push back Procedure.
Safe Push back Procedure.
 
Job safety analysis
Job safety analysis Job safety analysis
Job safety analysis
 
AVIATION SECURITY PRESENTATION
AVIATION SECURITY PRESENTATIONAVIATION SECURITY PRESENTATION
AVIATION SECURITY PRESENTATION
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slides
 
Airport Operations & Traffic Pattern Operations
Airport Operations & Traffic Pattern OperationsAirport Operations & Traffic Pattern Operations
Airport Operations & Traffic Pattern Operations
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 
Procedure for Safe Ground Handling Practices - (Sample for Edition)
Procedure for Safe Ground Handling Practices - (Sample for Edition)Procedure for Safe Ground Handling Practices - (Sample for Edition)
Procedure for Safe Ground Handling Practices - (Sample for Edition)
 
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Risk assessment for soil investigation at towers 5,6,7,8  rev01  a.doganiRisk assessment for soil investigation at towers 5,6,7,8  rev01  a.dogani
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
 
airside operation 3
airside operation 3airside operation 3
airside operation 3
 
Method of Working Plan - Unit Project
Method of Working Plan - Unit ProjectMethod of Working Plan - Unit Project
Method of Working Plan - Unit Project
 
Confined space entry natt7029
Confined space entry   natt7029Confined space entry   natt7029
Confined space entry natt7029
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.ppt
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
 

Similar to Risk Assessments for Airside Construction

18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docxDwarika Bhushan Sharma
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...MohammedAliQazi
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docxDwarika Bhushan Sharma
 
HSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputHSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputGaurav Singh Rajput
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templatesDwarika Bhushan Sharma
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templatesDwarika Bhushan Sharma
 
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01Andrew Louis
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docxDwarika Bhushan Sharma
 
IR_Safety orientation.pdf TRAINING PRESENTATION
IR_Safety orientation.pdf TRAINING PRESENTATIONIR_Safety orientation.pdf TRAINING PRESENTATION
IR_Safety orientation.pdf TRAINING PRESENTATIONSINOPECHSEDEPARTMENT
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
 
DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxAamirAbbas75
 

Similar to Risk Assessments for Airside Construction (20)

18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
HSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputHSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh Rajput
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
HIRARC FORM (skylift).pdf
HIRARC FORM (skylift).pdfHIRARC FORM (skylift).pdf
HIRARC FORM (skylift).pdf
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
Safety plan
Safety planSafety plan
Safety plan
 
Safety_induction
Safety_inductionSafety_induction
Safety_induction
 
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
 
IR_Safety orientation.pdf TRAINING PRESENTATION
IR_Safety orientation.pdf TRAINING PRESENTATIONIR_Safety orientation.pdf TRAINING PRESENTATION
IR_Safety orientation.pdf TRAINING PRESENTATION
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 
DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptx
 

More from David H Moloney

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 David H Moloney
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824David H Moloney
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionDavid H Moloney
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures ConstructionDavid H Moloney
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport ConstructionDavid H Moloney
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019David H Moloney
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanDavid H Moloney
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionDavid H Moloney
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanDavid H Moloney
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution PlanDavid H Moloney
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionDavid H Moloney
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 kmDavid H Moloney
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction TechniquesDavid H Moloney
 

More from David H Moloney (20)

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway Reconstruction
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution Plan
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 km
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
 

Recently uploaded

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Risk Assessments for Airside Construction

  • 1. SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref - SE-CTJ-01CW-MST-00417 Project - ABC Works By - ABC Ltd Date – 01/01/01 Page 1 of 6 Nr. HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk General Airside Working 1 Lack of Airside safety awareness • Cause damage & Injury • Impact negatively on airport operations 6 6 36 • Staff to receive airside safety training. • Risk Assessments & Method of Work Plan to be briefed to all affected workers. • Airside induction • Pre start-up and regular site meetings should be held to ensure safety requirements are met. • Promotion of safety awareness through training. 6 2 12 Adequately Controlled Risk 2 Construction that impacts on the safe operation of airport • Cause damage and injury 6 6 36 • Method of Work Plans to be submitted and approved by stakeholders prior to any work starting • Notams to be issued where necessary. • A close working relationship between the contractor, airport operator and stakeholders will enhance safety at the airport • Ensure clean and tidy storage and proper disposal of materials and waste 6 2 12 Adequately Controlled Risk
  • 2. SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref - SE-CTJ-01CW-MST-00417 Project - ABC Works By - ABC Ltd Date – 01/01/01 Page 2 of 6 Nr. HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 3 Unauthored Persons • Security breach 8 4 32 • All those entering airside to have a pass and to be checked by security. 8 2 16 Adequately Controlled Risk 4 Collision with aircraft in flight • Severe damage • Fatalities • Public outcry 10 4 40 • Fan corridor height restrictions briefed to all site teams • Works in the fan corridor will be controlled by Restricted Area Access Work Permits • Height markers ( such as goal posts ) shall be constructed as applicable to advise of height limits • All plant equipment shall be selected on basis of maximum operating heights so as to not interfere with airport operations • Supervision at all times. • Any plant operating at heights must not infringe the protected surfaces, inside or outside the airport property limits • Crane operating heights should be checked to ensure no protected surfaces are infringed. 10 2 20 Adequately Controlled Risk 5 Lighting for night working • Distracts, dazzle and blind pilots and ATC 8 4 32 • Lights shall be shielded so direct light does not shine above the horizon. 8 2 16 Adequately Controlled Risk 6 FOD- Foreign Object Debris • Damage to aircraft tyres, engines • Injury 4 6 24 • Continuously remove waste or loose materials • Vehicles entering or exiting the worksite may need to be cleaned to prevent mud or debris being deposited in the airside area 4 2 8 Negligible Risk
  • 3. SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref - SE-CTJ-01CW-MST-00417 Project - ABC Works By - ABC Ltd Date – 01/01/01 Page 3 of 6 Nr. HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk • Ensuring the workforce are committed to active FOD prevention • Maintaining good housekeeping practice •Suitable site fencing should be installed to protect from jet blast and to ensure FOD is contained within the site •Staff should remove and dispose of any FOD found 7 Bird Strikes • Damage to aircrafts • injury 4 4 16 • Don’t attract birds by feeding them. • Dispose of waste food properly using bins 4 2 8 Negligible Risk 8 Equipment or material near NAVAIDs Navigational Aids • Degrade or impair radiated signals • Injury 4 4 16 • Keep area in front of localiser and glide slope free. • Know the ILS sensitive areas • Providing warning signs, markings or lights at the edge of the sensitive area to prevent accidental intrusion into the sensitive areas 4 2 8 Negligible Risk 9 Failure to control dust. •Obscures or diminishes the visibility of areas •Injury 6 4 24 • Use dust suppression by wetting surface. • Use sheeting on trucks transporting fine materials • Sweep up dust 6 2 12 Adequately Controlled Risk 10 Inappropriate or poorly maintained fencing •inadequate to separate construction areas •Injury 4 4 16 • Ensure fencing is adequate • Maintain fencing 4 2 12 Adequately Controlled Risk
  • 4. SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref - SE-CTJ-01CW-MST-00417 Project - ABC Works By - ABC Ltd Date – 01/01/01 Page 4 of 6 Nr. HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 11 Jet Blast •Injury 6 6 36 • Protect construction workers from jet blast • Ground crews are to ensure areas behind the aircraft are clear, and that the aircraft is positioned in such a way as to avoid concentrating break-away blast at buildings, parked or taxiing aircraft or persons on the apron 6 2 12 Adequately Controlled Risk 12 Driving Airside • Accidents • Injury 6 6 36 • All contractor drivers must be escorted by a qualified vehicle operator or undergo airside driver training and testing Access routes should be agreed to and clearly identified to minimize interference with the operation on the airport 6 2 12 Negligible Risk 13 Fire • Damage • Injury • Smoking restrictions should be described, monitored and enforced • Hot works restrictions (possibly involving a separate hot works permit) should be described, monitored and enforced • Mobile phones should be switched off when refueling plant so as not to ignite fumes. • No smoking. • Fire extinguishers to be provided 14 Spillage of fuel, oil, substances • Injury by trips and falls •Provide spill kits •Deal with spills straight away •Spills should be thoroughly cleaned and dried.
  • 5. SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref - SE-CTJ-01CW-MST-00417 Project - ABC Works By - ABC Ltd Date – 01/01/01 Page 5 of 6 Note - The Control Measures are used to reduce the Likelihood and thereby the Residual Risk A Hazard is the potential to cause harm. A Risk is the likelihood of harm taking place. Table Value Severity Value Likelihood Residual Risk - Ratings & Actions 10 Multiple Fatalities 10 Certain Risk valve is obtained by multiplying the likelihood value by the severity value. The severity value remained the same, without or with controls, it is the likelihood valve that the controls will reduce 8 Single Fatality or Permanent Disability 8 Very Likely 60 - 100 Intolerable Risk 6 Major Injury loss of time >3 days 6 Likely 32 - 48 Moderately Controlled Risk 4 Minor or Serious Injury 4 May Happen 12 - 24 Adequately Controlled Risk 2 Slight injury 2 Unlikely 0 - 8 Negligible Risk Aim of Risk Assessment - To find solutions that would eliminate, mitigate, or manage the risks to an acceptable level. Risk Assessment Matrix Severity Likelihood Certain Value =10 Very Likely Value = 8 Likely Value = 6 May Happen Value = 4 Unlikely Value = 2 Multiple Fatalities Value = 10 100 80 60 40 20 Single Fatality or Permanent Disability Value = 8 80 64 42 32 16 Major Injury loss of time >3 days Value = 6 60 49 36 24 12 Minor or Serious Injury Value = 4 40 32 24 16 8 Slight injury Value = 2 20 16 12 8 4 Green Amber Red No further action required The current residual risk requires a review of available options and action The current residual risk requires further action to reduce it.
  • 6. SAFETY RISK ASSESSMENTS for Airside Construction Doc Ref - SE-CTJ-01CW-MST-00417 Project - ABC Works By - ABC Ltd Date – 01/01/01 Page 6 of 6 Images