Presentation on U-Girder casting
By
RAVINDER SINGH
Noida Metro Rail Project
CEC-SAM-JV.
Project Route Map
Casting Yard
Scope U-girder
Scope of Work
Sl no Package Nos of Girder 27 m standard span Non standard span Concrete Qty Steel Qty.
1 NC-01 656 460 196 38376 6667.58
2 NC-02 704 532 172 41184 7155.46
Total 1360 992 368 79560 13823
U-GIRDER MIX DESIGN
Grade of Concrete:M55
Ingredients Source/Brand Qty/M3
Cement(Kg) Ultratech OPC-53 450
Microsilica(Kg) Elkem/Comiche 25
20mm Aggregate(Kg) Kotputli 577
10mm Aggregate(Kg) Kotputli 532
Fine aggregate(Sand)(Kg) Bajpur 765
Free Water(Kg) Batching plant 141.66
Admixture(Kg) Don super flow PC-250 4.037
Slump after 2 hours retension(mm) 140
7days strength(Mpa) 61.55
28 days strength(Mpa) 74.61
W/C Ratio 0.31
U-GIRDER MIX DESIGN
CASTING YARD INFRASTRUCTURE
1. Total No of BAY-4.
2.U-girder bay-03 nos
3.Pier cap Bay-1
4. No of U-girder bed 36 (6 bed in each row).
5. Pier cap mould-16.
6. 100 MT capacity gantry 02 nos in each u-girder bay.
7. T ime cycle is 10 days FOR U-girder casting.
8. Peak Max production 6*6*3=108 nos u-girder per month
STACKING CAPACITY
1. Bay-1 28*2= 56
2.Bay-2 28*2 56
3.Bay-3 23*2 46
Total 158
Casting Bed Preparation
PCC for casting bed
Casting Bed preparation
Rebar fixing
C/Bed Wall
Casting Bed Wall
Longitudional Wall
300*1100
2800mm
RCC Wall 1100*300 mm
Shutter Making
Outer
Shutter
Bottom
Shutter
Outer
Shutter
Lifting hole
Lifting hole
5050mm
3800mm
1850 mm
Lifting hole
Lifting hole
Inner shutter
Inner Shutter
Outer shutter
support
Outer Shutter
Outer shutter
Bottom shutter
Outer form
Buffing of Shutter
Buffing/cleaning
of shutter
Applying shuttering
oil(Reebol)
Girder Mould
Automatic bar cutting & Bending M/c
Automatic bar cutting & Bending M/c
Capacity 100 MT/Day
Automatic bar cutting & Bending M/c
Format Line 12
12mm dia rebar coil
Format line 16
Bending upto 32mm
Bending upto 32mm
Re-bar zig
Rebar zig
Re bar cage placing
Rebar zig.
Rebar cage
Pre Fab Rebar
Pre Fab Rebar
Rebar zig.
Cage lifter
Wt. of cage 10.2
MT
Cage Lifting
Cage Placing
Cage Placing
Cage Lifter
Cage Lifter
Cage Lifting
U-girder cage 27
mts long
wt.10.12 MT
Cage lifting from zig.
Outer Shutter
2500mm c/c
Turn buckle
Shutter vibrator
Shutter vibrator
Shutter vibrator
Shutter vibrator
Rebar cage Placing
Rebar cage
Bulk Head
Shear Key Box
Cage Placing
Re bar is coated with inhibitor
solution for corrosion protection
HT Coil despenser
HT Coil despenser
HT coil
HTS CABLE
Cross section 140 mm2
Cable Threading
HT Cable
Bulk head
Cable Threading
Bulk head
Floating Beam
15.2mm dia . 7 ply
LRPC Class-2
Stressing end
75mm dia Macalloy bar
Wedge & Barrel
Grip for cable
15.2 mm
cable grip
wedge 3
segmental
Barrel
15.2mm dia HT cable
Prestressing
300MT Capacity hyd. Jack
600mm stroke
Prestressing
1. HT cable 15.2mm
dia
2. Load in each
cable 195.5
KN/19.92 MT
3. Total load
1434.24 MT
4. Ram area of jack
529.2 sq.cm
5. Required
pressure 460.55
kg/cm2
6. Modified
elongation
1179mm
Hydraulic hose
700 bar.
Stressing operation
Power pack 10 HP motor
Stressing line
Return line
700 bar cap. Hyd
.hose
Washer plate
75mm dia
macalloy nut
Hollow device
Stressing jack
Washer plate
Nut
75mm dia Macalloy
bar
Stressing Mechanism
300MT cap. 600mm stroke
Prestressing
Piston
Nut
Washer
Stressing line
Return Line
Dead End
Reaction wall
6500*1450*1200 mm Cable grip
Cable Threading
Drainage
spout
Debonding
tube
Debonding
tube 20 mm id
HDPE pipe
Debonded length 2175 mm both side
Debonded tube
Stressing End
Floating
Beam
Anchorage/Grip
HT strand
Bulk head
Stressing End
Washer plate & Nut. 75mm dia.
Macalloy bar.
Concreteing by Boom placer
Grade of conc. M55 with micro silica
Cement content 450 kg.
W/c Ratio 0.31
Admixture Don super flow PC-250
4.037 Kg/m3.
Conc. Qty per girder 60m3
Concrete placing
Boom Placer
Boom Placer
Concreting
Transit Mixture
Concreting
Load Transfer
Load Transfer criteria
After 3 days of
concreting with a
minimum
compresshive
strength of conc.
35 Mpa.
Load Transfer To Concrete
Pre cast pier cap cage
Precast pier cap cae
Pier cap
Anchor cone
19T15
Anchor cone 12T15
Cross Arm
Anchor cone
Anchor cone
Rebar for Bearing
pedestal Rebar for seismic
restrainer
Cross Arm
Jack fixing
Stressing Jack
Stressing operation
Bearing plate
Anchor cone
Grout vent
Seathing pipe
Anchorage arrangement
Stressing
Multipull stressing jack
Girder Lifting
Girder lifting &
shifting
Girder Lifting From Bed
Lifter 02 nos
40 mm dia
Macalloy bar 4
nos
Girder Lifting
Lifting hole
Girder Lifting
Washer plate
40 mm dia Macalloy
nut
Girder Lifter
Girder Lifter
40mm Dia. Macalloy Bar
Girder Lifting from Bed
Double layer Stacking
Stacking
Girder Stacking
Girder stacking
Girder Lifting
Girder wt 150 MT
100 MT
Capacity EOT
Cable cutting by Mechanical cutter
Cable cutting
Recess Filling with
conbextra GP-2.
Recess Filling with conbextra
GP-2
Recess Filling
Double layer stacking
Stacking stool
Curing
Curing period 21 days from
DOC
Girder Lifting & Stacking
Girder stacking
TIME CYCLE FOR U-GIRDER
Sl no Activity Day Duration in
hours
Total Hours Remarks
1 Cleaning of bed and shuttering oil applying
1
12 12
2 Fixing of outer shutter 10 22
3 Fixing of bulkhead & cage placing. 2 12 34
4 Threading of HT strand.
3
24 58
5 Initial prestressing 6 64
6 Final Prestressing 6 70
7 Sealing of debonding tubes
4
3 73
8 Inner shutter placing 5 78
9 Inner shutter Alignment 9 87
10 Inspection by Client. 4 91
11 Pouring of concrete 5 48 139
12 Curing 6,7,&8 72 211
13 Load transfer 9 6 217
14 Lifting of girder for stacking. 10 24 241
10.04167
Note: Time cycle for 6 U-girder casting 10 Days.
Time cycle U-girder
Loading for Launching
200 MT Capacity Trailor
Loading For Launching
Loading for launching
Loading For Launching
Tieing with 04 nos Belt
Ready for Despatch
Positioning gor lifting
Lifting From Trailor
Lifting for launching
Neoprene Bearing.
Denka chloroprene
Denka chloroprene
section of Neoprene Bearing.
Steel Neoprene
Wedge plate
Steel wedge plate
350 MT Capacity tyre
mounted crane.
400 MT Capacity
crane
Position of crane during
lifting
Behing pier cap
Beside pier cap
Lifting for launching
Straight lifting above pier cap
Lifting for launching
350 MT cap.
crane
400 MT Capacity
crane
Swing for proper position
Lowering on bearing
pedestal
Lowering on bearing
pedestal
Lowering on pedestal
Position of crane during
final lowering
Final position
Launching view
Launching
400 MT Capacity crane
02 nos
Thank you