Technology for Infrastructure Construction
Guided by,
Dr. Debasis Sarkar
Associate Professor
PDEU
Submitted by,
ABHISHEK PARMAR (20MCL001)
AXAY SHARMA (20MCL002)
CASE STUDY OF SEGMENT CASTING AND TRANSPORTATION
FOR ELEVATED CORRIDOR METRO RAIL PROJECT
1
Concrete pump
• Concrete pumps are mainly used to transfer wet concrete into the
building formwork.
• The pump delivers high volume of premixed concrete within a short
time.
• They are ideal for large construction projects or numerous
construction are required within a short period.
Pumping of concrete
• Pumping is used for both transporting and placing of concrete-Combines both
vertical and horizontal transport in one.
• it can place concrete in congested sites with little access .Small or large quantities
of concrete can be placed in the form, continuously at a very fast rate.
• Pumping of concrete requires use of mix having special properties suited to
pumping itself.
• Pumping rates ranges from 10 to 75 cubic meter/hour.
• Concrete can be pumped to a distance of 90--300 m horizontally.––Concrete can
be pumped from 30 to 90 m vertically.
Types of pumps
• Main pumps:
• Boom pump
• Line pump
• Pneumatic pump
• Squeeze pump
• There are two main configurations of concrete pumping equipment:
(1) pump with a separate pipeline
(2) a pump and boom combination
• third, less common configuration, used mostly in high-rise construction, the
pump and pipeline with a separate, tower-mounted boom.
Different type of pump
Stationary pump.
• The pump is mounted on a steel frame and stationed in a fixed location
throughout construction. This configuration is suitable for limited-area sites
with large and frequent concreting operations.
Trailer pump.
• The pump is mounted on a one- or two-axle trailer to enable easy on-site
relocation as well as movement between sites.
• It is suitable mainly for spread-out sites. One pump can also serve several
adjacent sites, as it can be moved between them according to concreting
schedule.
Truck pump
• Truck-mounted pump and boom combination, this quick setup pump is
moved between sites and operated on a standard truck chassis.
• It is commonly used for one-time concrete operations (such as in small-scale
repair or renovation projects, or on a regular construction project prior to
setup of the main concrete transportation equipment) when a reach greater
than that provided by a pump-truck boom is needed.
Advantages of concrete pumping
• Faster concrete placement
• Less labour
• Improved concrete
• Concrete pouring accuracy
• convenience
SEGMENT CASTING
METHODS OF SEGMENT CASTING
1. LONG LINE METHOD
2. SHORT LINE METHOD
1. LONG LINE METHOD
• All segments of a span are manufactured on a fixed bed with the formwork
moving along the bed for successive casting operation.
• All segments are cast on a soffit which is a full span upto coupling section
in a span by span method.
 Advantage
• The obvious advantage is that all the geometry control is done when
constructing the soffit thus simplifying this process during segment
production and avoiding errors in geometry control in finished structure.
Disadvantage
• It requires a large area.
• The soffit can not be used for new project.
• The soffit can be made for only one casting curve.
2. SHORT LINE METHOD
• It is a match casting process.
• Stationary forms are used next to the previously cast segment in order to get a
homogeneous perfect fitting match-cast joint.
Advantage
• Space requirements are much less compared to the long line method.
• The entire manufacturing process is centralized.
• The system is extremely adaptable to geometry variations such as horizontal and
vertical curvature and super elevation transition which are obtained without
increase in costs.
• The forms are reusable for other projects.
STANDARD LAYOUT OF CASTING YARD
Cross Section of Single cell box girder bridge deck
Reinforcement Cage
Casting Form
Batching and mixing of concrete
• Raw material Cement (OPC grade 53)
• Fly Ash (Maximum 30% of cement)
• Water (between 0.1 & 0.4)
• Admixture (SP-430, SP-432)
• Fine aggregate Coarse aggregates of 10mm & 20mm size
Batching procedure
• Batching plant may be of manually operated type or may be operated with the
help of computer aided software.
• The quantities are filled in the computer and start key is pressed, the sensors
provided near the gates get into action and according to the load scale value, that
much quantity of sand, 10mm aggregates, & 20mm aggregates are filled in a
bucket.
• When the required quantity of the aggregates is filled the gates get closed
automatically and the bucket is pulled up.
• As the bucket reaches the top,
its contents are put into a mixing
pan, where it gets mixed with
the cement, water & admixtures
from their separate hoppers.
Mixing tank
QUALITY CONTROL
• Initial Set Up Survey - Required for formwork setting and getting the match cast
segment in “rough” position.
• Final Set Up Survey - Required for final adjustments of the match cast segment
and small adjustments to the formwork once the forms have been closed up to
final position.
• As Cast Survey - Required to obtain “as cast” data on the segment used to
determine the positioning of the segment in the “match cast” position.
• Inputting Data - Required for geometry control for the for the next segment to
be cast.
Ranjit Buildcon Casting Yard
• India has taken a giant leap in the field of construction over the past 15-20 years. And infrastructure
development is feather to the cap. A large number of cities are constructing metro projects. Similarly, an
average of about 35 km of road is constructed every day in the country, which perhaps is the most rapid
expansion in the world. In most urban habitats, it becomes inevitable to go for long elevated viaducts, as
effective means of transport. These elevated viaducts easily clear the congested roads and other
inhabitations, at ground level leaving them unhindered. However, certain difficulties may be faced in locating
the substructures and foundations caused due to underground/ elevated utilities, land encroachments,
important establishments etc. Once the difficulties are surmounted, the elevated viaducts tend to provide
seamless connectivity. Needless to mention that they create additional movement area, without jeopardizing
the existing ground level network.
• Several such elevated viaducts have been constructed in the country, and some are in different phases of
construction. To name a few, 3 phases of Delhi Metro, over 60 km of Bangalore Metro, 30 km long Noida-
Greater Noida Metro, Bangalore Hosur Elevated Expressway, Delhi Gurgaon Expressway, Barapulla Nallah
Elevated Road, Badarpur Elevated Corridor etc.
• It is understood and agreed by masses that Metro Rail is the best means of transporting large set of
commuters, especially in mega cities. Like any developing/developed country, Delhi also started planning of
Metro project in the year 1995. About 60 km was constructed in Phase-1, 130 km in Phase-2 and another 110
km is now nearing completion in Phase-3. Essential ingredients of structures of a Metro Rail are i) Viaduct, ii)
Elevated Station, iii) Tunnel, iv) Underground Station, v) Workshop-cum-Depot etc. Similary, other major cities
where metro is under construction are Bangalore, Chennai, Kochi, Kolkata, Lucknow, Meerut, Agra, Bhopal,
Indore, Nagpur, Pune, Mumbai, Jaipur etc.
• a large number of long elevated viaducts are in various phases of construction. These include 26 km long
Delhi-Gurgaon Toll Raod, 10 km long Bangalore-Hosur Elevated Toll Expressway, 4 km long Barapullah Elevated
Viaduct, 4 km long Badarpur Elevated Expressway etc. All these viaducts are servicing their intended purpose
efficiently. In fact, it is difficult to imagine life without these metro & road viaducts.
Elevated Corridors For - Metro & Road Connectivity
Vinay Gupta, Director & CEO, Tandon Consultants Pvt. Ltd. New Delhi
It was decided to provide an Incrementally Launched bridge over the river, so as to avoid any
requirements of ground supported staging or launching girder. In an incrementally launched bridge,
casting is done at one of the two banks, which gives factory quality concrete. In this case 552m long
bridge comprises 12 spans of 46m each. At every typical stage, 23m long length of box girder is cast and
pushed forwarded. Figs 1,2,3 &4 depict the system of incrementally launched bridge. Figs 5 & 6 depict
the system of pushing the superstructure using strands and multi-pull Jacks (400 T capacity each, in this
case) Figs 7 & 8 indicate the side guides required for lateral alignment control of superstructure and
launching nose, respectively. Fig 9 depicts the system of sag control of the launching nose.
Incrementally Launched Bridge over River Yamuna
Fig 1. Incremental launching: Construction stages Fig 2. Incremental launching: construction stages
Fig 3. View showing launching nose with superstructure Fig 4. Yamuna bridge for DMRC Construcetd by incremental launching
Fig 5. Soffit view during launching
• Fig 6. Cross beam attachment for pulling
Fig 8. Lateral guide for launching nose
Fig 7. Lateral Guide for box girder
Fig 9. Temporary bearing over pier,
Teflon pad slides over temporary
bearing.
Transportation and Erection
Erection of these girders was facilitated in two ways. In case of shorter stretches, two type
mounted cranes worked in tandem and in case of longer stretches, parallel tracks were laid to
move two Goliath Cranes to move with the girder in tandem.
Transferring segments through trucks
Erection Methodology
• Precast Segmental – Span-by-Span
• Erection with Launching Gantry
• Erection with Cranes
• On Falsework
• Erection with Lifting Frames
• Precast Segmental – Full Span
• Erection with Launching Gantry
• Erection with Launching Gantry or Heavy Lift
Erection with Launching Gantry
Erection with Cranes
On Falsework
Erection with Lifting Frames
References
• https://www.zaubacorp.com/company/RANJIT-BUILDCON-
LIMITED/U45206GJ2006PLC049570
• https://www.nbmcw.com/articles-reports/building-construction-
material/precast-construction/elevated-corridors-for-metro-road-
connectivity.html
• https://www.tcpl.com/
• https://www.youtube.com/watch?v=7rIDv7Q_Cy4
THANK YOU

More Related Content

What's hot

pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
Rahul bhatnagar
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
PrasannaRaniB
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
Akhilesh Shukla
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
Durgesh Kumar Yadav
 
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
Akanksha Priya
 
Unit 1 anchorage systems
Unit 1   anchorage systemsUnit 1   anchorage systems
Unit 1 anchorage systems
Haripriya Kumar
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
TVijayaGowri
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
Chockalingam T
 
Metro Work
Metro WorkMetro Work
Metro Work
Rajendra Kumar
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
jamali husain
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
RAMPRASAD KUMAWAT
 
Pumping of concrete
Pumping of concretePumping of concrete
Pumping of concrete
Yaswanth Reddy
 
Canal Fall
Canal FallCanal Fall
Canal Fall
GAURAV. H .TANDON
 
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdfMETHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
Er Adil Khan
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
ShuBham RaNa
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
AyushHajare
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
VATSAL PATEL
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
Bhavya Jaiswal
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
Aaquib ansari
 

What's hot (20)

pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
 
Unit 1 anchorage systems
Unit 1   anchorage systemsUnit 1   anchorage systems
Unit 1 anchorage systems
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Metro Work
Metro WorkMetro Work
Metro Work
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Pumping of concrete
Pumping of concretePumping of concrete
Pumping of concrete
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdfMETHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 

Similar to Metro rail segments

Presentation2 constructioin equipments.pptx
Presentation2 constructioin equipments.pptxPresentation2 constructioin equipments.pptx
Presentation2 constructioin equipments.pptx
Ayushsharma131736
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Prerak Ka.Patel
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentation
ATUL SHUKLA
 
JMRC TRAINING FINAL REPORT
JMRC TRAINING FINAL   REPORT JMRC TRAINING FINAL   REPORT
JMRC TRAINING FINAL REPORT
Rohit kumar nagar
 
Transporting and handling of concrete (construction planning and management)
Transporting and handling of concrete (construction planning and management)Transporting and handling of concrete (construction planning and management)
Transporting and handling of concrete (construction planning and management)
Sumit Nandan
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
srinivas cnu
 
Batching plant ppt
Batching plant pptBatching plant ppt
Batching plant ppt
dip17
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLYTOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
Vj NiroSh
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
KriShna Sharma
 
Building construction report
Building construction  reportBuilding construction  report
Building construction report
Aprajeeta Singh
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction
ajinkyaraj
 
1. railway track gauge
1. railway track gauge1. railway track gauge
1. railway track gauge
Gaurav Jagad
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
Jeelkumar Patel
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
3 hayzi.pptx
3 hayzi.pptx3 hayzi.pptx
3 hayzi.pptx
sol zem
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
Kamesh Tripathi
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
Darshit
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
2018kumaranurag
 

Similar to Metro rail segments (20)

Presentation2 constructioin equipments.pptx
Presentation2 constructioin equipments.pptxPresentation2 constructioin equipments.pptx
Presentation2 constructioin equipments.pptx
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentation
 
JMRC TRAINING FINAL REPORT
JMRC TRAINING FINAL   REPORT JMRC TRAINING FINAL   REPORT
JMRC TRAINING FINAL REPORT
 
Transporting and handling of concrete (construction planning and management)
Transporting and handling of concrete (construction planning and management)Transporting and handling of concrete (construction planning and management)
Transporting and handling of concrete (construction planning and management)
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Batching plant ppt
Batching plant pptBatching plant ppt
Batching plant ppt
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLYTOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
Building construction report
Building construction  reportBuilding construction  report
Building construction report
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction
 
1. railway track gauge
1. railway track gauge1. railway track gauge
1. railway track gauge
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
3 hayzi.pptx
3 hayzi.pptx3 hayzi.pptx
3 hayzi.pptx
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 

More from Axay Sharma

A case study on GIS application
A case study on GIS applicationA case study on GIS application
A case study on GIS application
Axay Sharma
 
Renewable Energy
Renewable EnergyRenewable Energy
Renewable Energy
Axay Sharma
 
Smart solid waste management-surat city.
Smart solid waste management-surat city.Smart solid waste management-surat city.
Smart solid waste management-surat city.
Axay Sharma
 
Bolt(build own lease transfer) model
Bolt(build own lease transfer) modelBolt(build own lease transfer) model
Bolt(build own lease transfer) model
Axay Sharma
 
Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.
Axay Sharma
 
Project on brts(ahmedabad)
Project on brts(ahmedabad)Project on brts(ahmedabad)
Project on brts(ahmedabad)
Axay Sharma
 
Flyover Bridge construction project
Flyover Bridge construction projectFlyover Bridge construction project
Flyover Bridge construction project
Axay Sharma
 
Classification of Organization
Classification of OrganizationClassification of Organization
Classification of Organization
Axay Sharma
 
Crawler Mounted crane
Crawler Mounted craneCrawler Mounted crane
Crawler Mounted crane
Axay Sharma
 
Presentation on Modern construction materials
Presentation on Modern construction materialsPresentation on Modern construction materials
Presentation on Modern construction materials
Axay Sharma
 
3D Printing
3D Printing3D Printing
3D Printing
Axay Sharma
 

More from Axay Sharma (11)

A case study on GIS application
A case study on GIS applicationA case study on GIS application
A case study on GIS application
 
Renewable Energy
Renewable EnergyRenewable Energy
Renewable Energy
 
Smart solid waste management-surat city.
Smart solid waste management-surat city.Smart solid waste management-surat city.
Smart solid waste management-surat city.
 
Bolt(build own lease transfer) model
Bolt(build own lease transfer) modelBolt(build own lease transfer) model
Bolt(build own lease transfer) model
 
Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.
 
Project on brts(ahmedabad)
Project on brts(ahmedabad)Project on brts(ahmedabad)
Project on brts(ahmedabad)
 
Flyover Bridge construction project
Flyover Bridge construction projectFlyover Bridge construction project
Flyover Bridge construction project
 
Classification of Organization
Classification of OrganizationClassification of Organization
Classification of Organization
 
Crawler Mounted crane
Crawler Mounted craneCrawler Mounted crane
Crawler Mounted crane
 
Presentation on Modern construction materials
Presentation on Modern construction materialsPresentation on Modern construction materials
Presentation on Modern construction materials
 
3D Printing
3D Printing3D Printing
3D Printing
 

Recently uploaded

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 

Recently uploaded (20)

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 

Metro rail segments

  • 1. Technology for Infrastructure Construction Guided by, Dr. Debasis Sarkar Associate Professor PDEU Submitted by, ABHISHEK PARMAR (20MCL001) AXAY SHARMA (20MCL002) CASE STUDY OF SEGMENT CASTING AND TRANSPORTATION FOR ELEVATED CORRIDOR METRO RAIL PROJECT 1
  • 2. Concrete pump • Concrete pumps are mainly used to transfer wet concrete into the building formwork. • The pump delivers high volume of premixed concrete within a short time. • They are ideal for large construction projects or numerous construction are required within a short period.
  • 3. Pumping of concrete • Pumping is used for both transporting and placing of concrete-Combines both vertical and horizontal transport in one. • it can place concrete in congested sites with little access .Small or large quantities of concrete can be placed in the form, continuously at a very fast rate. • Pumping of concrete requires use of mix having special properties suited to pumping itself. • Pumping rates ranges from 10 to 75 cubic meter/hour. • Concrete can be pumped to a distance of 90--300 m horizontally.––Concrete can be pumped from 30 to 90 m vertically.
  • 4. Types of pumps • Main pumps: • Boom pump • Line pump • Pneumatic pump • Squeeze pump
  • 5. • There are two main configurations of concrete pumping equipment: (1) pump with a separate pipeline (2) a pump and boom combination • third, less common configuration, used mostly in high-rise construction, the pump and pipeline with a separate, tower-mounted boom.
  • 6. Different type of pump Stationary pump. • The pump is mounted on a steel frame and stationed in a fixed location throughout construction. This configuration is suitable for limited-area sites with large and frequent concreting operations. Trailer pump. • The pump is mounted on a one- or two-axle trailer to enable easy on-site relocation as well as movement between sites. • It is suitable mainly for spread-out sites. One pump can also serve several adjacent sites, as it can be moved between them according to concreting schedule.
  • 7. Truck pump • Truck-mounted pump and boom combination, this quick setup pump is moved between sites and operated on a standard truck chassis. • It is commonly used for one-time concrete operations (such as in small-scale repair or renovation projects, or on a regular construction project prior to setup of the main concrete transportation equipment) when a reach greater than that provided by a pump-truck boom is needed.
  • 8.
  • 9.
  • 10. Advantages of concrete pumping • Faster concrete placement • Less labour • Improved concrete • Concrete pouring accuracy • convenience
  • 12. METHODS OF SEGMENT CASTING 1. LONG LINE METHOD 2. SHORT LINE METHOD
  • 13. 1. LONG LINE METHOD • All segments of a span are manufactured on a fixed bed with the formwork moving along the bed for successive casting operation. • All segments are cast on a soffit which is a full span upto coupling section in a span by span method.  Advantage • The obvious advantage is that all the geometry control is done when constructing the soffit thus simplifying this process during segment production and avoiding errors in geometry control in finished structure.
  • 14. Disadvantage • It requires a large area. • The soffit can not be used for new project. • The soffit can be made for only one casting curve.
  • 15. 2. SHORT LINE METHOD • It is a match casting process. • Stationary forms are used next to the previously cast segment in order to get a homogeneous perfect fitting match-cast joint.
  • 16.
  • 17. Advantage • Space requirements are much less compared to the long line method. • The entire manufacturing process is centralized. • The system is extremely adaptable to geometry variations such as horizontal and vertical curvature and super elevation transition which are obtained without increase in costs. • The forms are reusable for other projects.
  • 18. STANDARD LAYOUT OF CASTING YARD
  • 19. Cross Section of Single cell box girder bridge deck
  • 20.
  • 23. Batching and mixing of concrete • Raw material Cement (OPC grade 53) • Fly Ash (Maximum 30% of cement) • Water (between 0.1 & 0.4) • Admixture (SP-430, SP-432) • Fine aggregate Coarse aggregates of 10mm & 20mm size
  • 24. Batching procedure • Batching plant may be of manually operated type or may be operated with the help of computer aided software. • The quantities are filled in the computer and start key is pressed, the sensors provided near the gates get into action and according to the load scale value, that much quantity of sand, 10mm aggregates, & 20mm aggregates are filled in a bucket. • When the required quantity of the aggregates is filled the gates get closed automatically and the bucket is pulled up.
  • 25.
  • 26. • As the bucket reaches the top, its contents are put into a mixing pan, where it gets mixed with the cement, water & admixtures from their separate hoppers. Mixing tank
  • 27. QUALITY CONTROL • Initial Set Up Survey - Required for formwork setting and getting the match cast segment in “rough” position. • Final Set Up Survey - Required for final adjustments of the match cast segment and small adjustments to the formwork once the forms have been closed up to final position. • As Cast Survey - Required to obtain “as cast” data on the segment used to determine the positioning of the segment in the “match cast” position. • Inputting Data - Required for geometry control for the for the next segment to be cast.
  • 29.
  • 30.
  • 31. • India has taken a giant leap in the field of construction over the past 15-20 years. And infrastructure development is feather to the cap. A large number of cities are constructing metro projects. Similarly, an average of about 35 km of road is constructed every day in the country, which perhaps is the most rapid expansion in the world. In most urban habitats, it becomes inevitable to go for long elevated viaducts, as effective means of transport. These elevated viaducts easily clear the congested roads and other inhabitations, at ground level leaving them unhindered. However, certain difficulties may be faced in locating the substructures and foundations caused due to underground/ elevated utilities, land encroachments, important establishments etc. Once the difficulties are surmounted, the elevated viaducts tend to provide seamless connectivity. Needless to mention that they create additional movement area, without jeopardizing the existing ground level network. • Several such elevated viaducts have been constructed in the country, and some are in different phases of construction. To name a few, 3 phases of Delhi Metro, over 60 km of Bangalore Metro, 30 km long Noida- Greater Noida Metro, Bangalore Hosur Elevated Expressway, Delhi Gurgaon Expressway, Barapulla Nallah Elevated Road, Badarpur Elevated Corridor etc.
  • 32. • It is understood and agreed by masses that Metro Rail is the best means of transporting large set of commuters, especially in mega cities. Like any developing/developed country, Delhi also started planning of Metro project in the year 1995. About 60 km was constructed in Phase-1, 130 km in Phase-2 and another 110 km is now nearing completion in Phase-3. Essential ingredients of structures of a Metro Rail are i) Viaduct, ii) Elevated Station, iii) Tunnel, iv) Underground Station, v) Workshop-cum-Depot etc. Similary, other major cities where metro is under construction are Bangalore, Chennai, Kochi, Kolkata, Lucknow, Meerut, Agra, Bhopal, Indore, Nagpur, Pune, Mumbai, Jaipur etc. • a large number of long elevated viaducts are in various phases of construction. These include 26 km long Delhi-Gurgaon Toll Raod, 10 km long Bangalore-Hosur Elevated Toll Expressway, 4 km long Barapullah Elevated Viaduct, 4 km long Badarpur Elevated Expressway etc. All these viaducts are servicing their intended purpose efficiently. In fact, it is difficult to imagine life without these metro & road viaducts.
  • 33. Elevated Corridors For - Metro & Road Connectivity Vinay Gupta, Director & CEO, Tandon Consultants Pvt. Ltd. New Delhi
  • 34. It was decided to provide an Incrementally Launched bridge over the river, so as to avoid any requirements of ground supported staging or launching girder. In an incrementally launched bridge, casting is done at one of the two banks, which gives factory quality concrete. In this case 552m long bridge comprises 12 spans of 46m each. At every typical stage, 23m long length of box girder is cast and pushed forwarded. Figs 1,2,3 &4 depict the system of incrementally launched bridge. Figs 5 & 6 depict the system of pushing the superstructure using strands and multi-pull Jacks (400 T capacity each, in this case) Figs 7 & 8 indicate the side guides required for lateral alignment control of superstructure and launching nose, respectively. Fig 9 depicts the system of sag control of the launching nose. Incrementally Launched Bridge over River Yamuna
  • 35. Fig 1. Incremental launching: Construction stages Fig 2. Incremental launching: construction stages
  • 36. Fig 3. View showing launching nose with superstructure Fig 4. Yamuna bridge for DMRC Construcetd by incremental launching
  • 37. Fig 5. Soffit view during launching • Fig 6. Cross beam attachment for pulling
  • 38. Fig 8. Lateral guide for launching nose Fig 7. Lateral Guide for box girder Fig 9. Temporary bearing over pier, Teflon pad slides over temporary bearing.
  • 39. Transportation and Erection Erection of these girders was facilitated in two ways. In case of shorter stretches, two type mounted cranes worked in tandem and in case of longer stretches, parallel tracks were laid to move two Goliath Cranes to move with the girder in tandem.
  • 41. Erection Methodology • Precast Segmental – Span-by-Span • Erection with Launching Gantry • Erection with Cranes • On Falsework • Erection with Lifting Frames • Precast Segmental – Full Span • Erection with Launching Gantry • Erection with Launching Gantry or Heavy Lift
  • 46.