SlideShare a Scribd company logo
Introduction of METRO RAIL in INDIA
Rapid transits in India consist of Metro, Monorails and light rail system
How it Began
India’s 1st and Asia’s 5th Metro rail was introduced in Kolkata in 1984
Delhi Metro was India's first modern metro which began its operation in 2002.
Rapid Metro Rail Gurgaon, which started operations in November 2013, is India's first privately owned & operated metro.
Why is it Needed ?
Unprecedented growth of personal Vehicle
Growing Traffic Congestion
Air pollution and traffic accidents has become a major concern
To avoid congestion at Peak hour
Time saving and Reduced fuel consumption
METRO RAIL in INDIA
Unprecedented growth of personal Vehicle
Growing Traffic Congestion
Air pollution and traffic accidents has become a major concern
To avoid congestion at Peak hour
Time saving and Reduced fuel consumption
METRO RAIL in INDIA
Existing Metro Rail in INDIA
1) Delhi Metro
2) Kolkata Metro
3) Mumbai Metro
4) Chennai Metro
5) Bangalore Metro
6) Jaipur Metro
7) Lucknow Metro
8) Hyderabad Metro
9) Kochi Metro
10) Noida Metro
Under construction and proposed Metro Rail in India
1) Ahmedabad Metro
2) Pune Metro
3) Nagpur Metro
4) Indore Metro
5) Bhopal Metro
5) Kanpur Metro
Type of metro
Type of Metro
1) Elevated Metro
2) Underground Metro
3) On Grade
ELEVATED METRO
Basic Sequence of Activities For Elevated Metro (Viaduct)
Obtain site
acquired by the
Client
Preliminary
Survey Works
Barricading Utilities
Identification
Shifting of Utilities
Test Pile Casting &
Testing (Vertical &
Lateral Load Tests)
Pile FoundationPile CapPiersPier Cap
Erection of
Segments
Pre stressing of
Span & Grouting
Alignment, &
Bearing
Parapet Erection
Cable Trough
Erection
Fixing of vertical
bearing & Shear
key Bar
Handing Over
Casting of
superstructure
Segments &
parapet
Stacking and
Transportatio
n of segments
Casting Yard Set
Up
Basic Sequence of Activities For Elevated Metro (Station)
Obtain site
acquired by the
Client
Preliminary Survey
Works
Barricading
Utilities
Identification Shifting of Utilities
Test Pile Casting &
Testing (Vertical &
Lateral Load Tests
Pile FoundationPile Cap
Pier up to CL
Beam Bottom
Pier Arm/Portal
Beams at CL
Pier up to PL
Beam Bottom
Pier Heads at PL &
TL
Girder Launching Deck Slab at CL, PL
& TL
Deck Slab PL & TL Entry & Exit
Roofing works at
PL
Finishing Works
MEP & FFTG
Works
General
Development &
Road Works
Handing Over
Casting of
superstructure I -
Girder
Stacking and
Transportation of
segments
Casting Yard Set Up
P nP n+1
Span Length Number of
Segments
37 m 13
34 m 12
31 m 11
28 m 10
25 m 9
22 m 8
S7C
3000
S6D
3000
S6U
3000
S5D
3000
S4D
3000
S3D
3000
S2D
3000
S5U
3000
S4U
3000
S3U
3000
S2U
3000
S1U
1975
S1D
1975
Segment Codes
Standard
Span
Length
S1U
S2U
S3U
S4U
S5U
S6U
S7C
S6D
S5D
S4D
S3D
S2D
S1D
37 √ √ √ √ √ √ √ √ √ √ √ √ √
34 √ √ √ √ √ √ x √ √ √ √ √ √
31 √ √ √ √ √ x √ x √ √ √ √ √
28 √ √ √ √ √ x x x √ √ √ √ √
25 √ √ √ √ x x √ x x √ √ √ √
22 √ √ √ √ x x x x x √ √ √ √
Casting Yard – Segment Details
Preparation
of
Reinforcem
ent Cage
(3 days)
Placing of
cage,
Profiling
Shuttering
(18 Hrs.)
Concreting
(4 Hrs.)
Deshutteri
ng
(5 Hrs.)
Lifting and
stacking in
C.Y
(3 Hrs.)
Curing will
be done for
14 days and
after 28
days ,
Ready for
Launching Average 15 Days will be
required to cast segments
for 37m span.
Casting
Sequence
Segment
Id
Average Cummulative
days
1 S7C 1
2 S1U 2
3 S6U 4
4 S6D 5
5 S2U 6
6 S5U 7
7 S5D 8
8 S4U 9
9 S1D 10
10 S4D 11
11 S2D 12
12 S3U 14
13 S3D 15
Match Casting Activity
Short bed
Long bed
Pier
Pile
Pile Cap
Crash Barrier
Pier Cap
Upstand/Pedestal
Segments (Span)
Sub Structure
Super Structure
Seismic arrester of span
Details of Structure
Pile
3 4
12
Average Time
Required for
Casting of one
Pile will be
12hrs.
Pile
Boring
(5 hrs )
Transportati
on of Caging
(1Hr)
Cage
placing
(3 hrs)
Pile
concrete
(3hrs)
Casing
removal
(1 hr)
Average Time take to cast
pile group will be 5 Days.
Piling Sequence
Piling Activity
P - 1 P – 2 P -3 P -4
Pile cap
shutter 1
Pile cap
shutter 2
Pile Cap
Reinforcement
(3 Days)
Average Time take
to cast pile cap will
be 12 Days.
After 1 day
Resources movement
Pile Cap
Pile
Pile cap Activity
P -1 P -2 P -3 P -4
Piershutter1
Pier
shutter 1
Piershutter2
Piershutter3
Piershutter1
Piershutter2
Piershutter3
Pier
shutter 2
Pier
shutter 3
Pier
Pile Cap
Pile
Pier
reinforcement
(2 days)
Pier
starter
(6 Hrs)
Pier
shutter
(2 Days)
Pier
concreting
(6 Hrs)
Pier
Deshuttering
(12 Hrs)
After 24 Hrs.
After 1 day
Pier Activity
Resources movement
Average Time
Cycle for Pier
5 days
Pier
P -5 P -6
Pier Cap
Preparation of
reinforcement
Cage
(3 Days)
Pedestal And
shear key
Casting
(18 Hrs)
After 21 day
Average Time
cycle for pier
cap is 8 days
Pier Cap Activity
dry matching (8 hrs) and
wet matching (10 hrs)
including cutting and
treading and lowering of
span.
Launching Sequence Activity
DETAILS OF LAUNCHING GIRDER
COMPONENTS OF LAUNCHING GIRDER
 MAIN BOX GIRDER
 FRONT SUPOORT
 MIDDLE SUPPORT
 REAR SUPPORT
 REAR TROLLEY
 SLIDER BEAM
 COUNTER WEIGHT
 FIXED MOUNTED HOIST
 PLATFORM/ WALK WAYS
Maximum height of Front support : 6220mm
Minimum height of Front support : 4230mm
FRONT SUPPORT
TOP BEAM
TOP VERTICAL LEG
BOTTOM
BEAM
TELESCOPIC LEG
GENERAL ARRANGEMENT OF FRONT SUPPORT
TYPICAL ISOMETRIC VIEW OF FRONT SUPPORT
MIDDLE SUPPORT
Main beam
Bracket of main
beam
Launching bearing
Longitudinal
side bearing
Knuckle bearing
Cradle
TYPICAL ISOMETRIC VIEW OF MIDDLE SUPPORT
Rear support is more or
less same replica of
middle support accept
longitudinal pushing
assembly is not provided
in this support.
REAR SUPPORT
TYPICAL ISOMETRIC VIEW OF REAR SUPPORT
REAR TROLLEY
TYPICAL ISOMETRIC VIEW OF REAR TROLLEY
 REAR TROLLEY IS POSITIONED AT
4500MM FROM THE REAR END OF
THE MAIN GIRDER S8 AND PROVIDES
SUPPORTS DURING LONGITUDINAL
AUTO LAUNCHING.
SLIDER BEAMS
TYPICAL FRONT VIEW OF SLIDER BEAM TYPICAL ISOMETRIC VIEW OF SLIDER BEAM
 SLIDER BEAMS ARE INDEPENDENT ASSEMBLY OF TWO BUILT UP I SECTIONS CONNECTED TOGETHER WITH STEEL DIAPHRAGMS
SCHEME FOR AUTO-LAUNCHING
FOR SPANs UPTO 37m Span
Step:1 Erect all the segments of the span and do final pre-stressing as per specification in drawing.
Step:2 Ensure that erection of all span is completed in all aspects. Release all suspenders from erected span and lower the span
on temporary bearing placed on pier cap.
Step:3 Bring all the sliders to the rear end.
Step:4 Release the middle support from the span and with the help of slider beam shift the middle support nearer to the front
support on segment S1 as shown in drawing.
Step:5 Activate the jacks of middle support on segment S1 and anchor with the span.
Step:6 Release the Rear support from the span and with the help of slider beam shift the rear support to the erected span of
segment S1.
Step:7 Activate the jacks of rear support on segment S1 and anchor with the span.
Step:8 Now move both the sliders back to the rear trolley.
Step:9 Ensure that middle and rear support are firmly anchored with the span. Now close the telescopic leg of front support so
that all load transferred to the middle and rear support.
Step:10 Ensure all the supports firmly anchored with the span and make sure that rear trolley free from anchorage from the
span.
Step:11 Ensure that all supports firmly anchored with super structure. Start Auto-launching and auto launch the launching
girder by 1200mm. Check that all supports are firmly anchored or not.
Step:12 Now again start auto launching until rear trolley come nearer to the rear support.
Step:13 With the help of slider beam move rear support near to the middle support and anchored it with the span.
Step:14 Continue auto-launching till front support reaches next pier cap location..
Step:15 Open the telescopic leg of front support and activate it. Anchor firmly with pier cap.
Step: 1 Make sure that launching Girder is ready for erection of new span and lifting of segments. Now move the sliding
towards the next span to be erected near front support as shown.
Step:2 Move the trailer below the lifting hoist.
Step:3 Pull down the lifting beam.
Step:4 Fix the lifting beam and temporary pre-stressing beam on segment S1. Now lift the pier segment S1 with the help of
lifting hoist. Now move the slider in position to lift the S1 segment.
Step:5 Connect the S1 with the slider beam and move it nearer to the middle support.
Step:7 Move S2 nearer to the segment S1.
Step:8 Move S3 nearer to the segment S2.
Step:9 Move S4 nearer to the segment S3.
Step:10 Move S5 nearer to the segment S4.
Step:11 Move S6 nearer to the segment S5.
Step:11 Move S7 nearer to the segment S6.
Step:11 Move all the sliders towards Segment S7.
Step:11 Move all the sliders towards Segment S7.
Step:11 Now lift the segment S3 upwards then other segments for adjustment of all the segments in fixed length.
Step:11 Now lift the segment S3 upwards then other segments for adjustment of all the segments for dry matching.
Step:11 Now move remaining sliders towards segment S3.
Step:11 Now move remaining sliders towards segment S3.
Step: Lift the segment S5 and move it near the segment S6.Now same do same procedure for segment S4.
Step:17 Now do dry/wet matching and temporary pre-stressing and follow the procedure for final pre-stressing as per
specification given in drawing.
Concourse Level
Track Level
Platform Level
Road Level
CANTILEVER TYPE STATION
Bored Cast-in situ Piles
Pile Cap
Pier
Crash Barrier
Pier Head at CL
Staircase
Precast I-girders
Deck slab at CL
Pier Heads at PL & TL
Pre-cast I-girders
PEB Roofing
Deck Slab at PL & TL
61
Concourse Level
Track Level
Platform Level
Road Level
PORTAL TYPE STATION
Bored Cast-in situ Piles
Pile Cap
Pier
Crash Barrier
Portal Beam at CL
Staircase
Precast I-girders
Deck slab at CL
Pier Heads at PL & TL
Pre-cast I-girders
PEB Roofing
Deck Slab at PL & TL
62
Underground Metro
Tunnel
• Cut and Cover
• Bored Tunnel
Station
• Top –Down
• Bottom-up
Stage – 03.
Stop End inserted in both end
of the trench.
Stop End
Stop End Installation
Stage – 05.
Concrete placing through
tremie pipe as polymer
slurry is displaced.
Panel Concreting
`
DIAPHRAGM WALL CONSTRUCTION METHODOLOGY.
Excavation Methods
Bottom Up Method:
Slabs will be laid from Bottom to Top
such that Base slab will be
constructed first
Base slab
Concourse Slab
Roof Slab
GLGL
D-wall
Top Down Method:
Slabs will be laid from Top to Bottom
such that Top slab will be constructed
first
 Top slab
 Concourse Slab
 Base Slab
GLGL
D-wall
65
1) Completion of all D wall Works
2) Start excavation for 1st layer
D wall
King Post
Bottom Up Method : Launching shaft Construction (Stage 1)
1) Excavation upto 1 m Below Temporary Sturt -1 From one side
D wall
King Post
Bottom Up Method : Launching shaft Construction (Stage 1)
50 T Gantry
D Wall
Road
Waler
1) Start Fixing brackets form one side
2) Start Fixing of Waler form one side
Bottom Up Method : Launching shaft Construction (Stage 2)
50 T Gantry
D Wall
Waler
Road
Erection of Diagonal
Strut
1) Start Fixing Diagonal Strut
2) Start Fixing of Waler for Straight Strut
Bottom Up Method : Launching shaft Construction (Stage 2)
1) Start Fixing Straight Strut
2) Start Fixing of Waler for Diagonal Strut
50 T Gantry
D Wall
Diagonal Strut
Road
Erection of Straight Strut
Erection of Waler for Diagonal strut
Bottom Up Method : Launching shaft Construction (Stage 2)
1) Completion of Strut erection Start on 1st Layer
2) Excavation for 2nd layer
Diagonal Strut
Road
Straight Strut
Erection of Diagonal strut
D Wall
50 T Gantry
Bottom Up Method : Launching shaft Construction (Stage 2)
1) Erection of 2nd Strut Layer
2) Excavation upto 1 m Below Temporary Sturt -2 From one side
D wall
King Post
Bottom Up Method : Launching shaft Construction (Stage 3)
1) Start Fixing of Brackets from One side
2) Start Fixing of Waler from One side
3) Erection of 2nd Strut Layer
4) Excavation upto 1 m Below Temporary Sturt – 3 From one side
King Post
D wall
Bottom Up Method : Launching shaft Construction (Stage 4)
1) Start Fixing of Brackets from One side
2) Start Fixing of Waler from One side
3) Erection of 3rd Strut Layer
4) Excavation upto 1 m Below Temporary Sturt – 4 From one side
King Post
D wall
Bottom Up Method : Launching shaft Construction (Stage 5)
1) Start Fixing of Brackets from One side
2) Start Fixing of Waler from One side
3) Erection of 4th Strut Layer
4) Excavation upto Base Slab Level From one side
King Post
D wall
Bottom Up Method : Launching shaft Construction (Stage 6)
1) Excavation upto Base Slab Level
2) Levelling Surface for Base slab construction
King Post
D wall
Bottom Up Method : Launching shaft Construction (Stage 7)
1) Casting of Base Slab
2) Attain required strength for Base slab
3) Removal of 4th Level strut
4) Cast reaction Frame support for Pedestal
5) Handover the shaft to TBM operations
Base Slab
King Post
D wall
Bottom Up Method : Launching shaft Construction (Stage 8)
Station Construction
Top – Down Method
Top Down Method : Station Construction (Stage 1)- Excavation still Roof Slab
Top Down Method : Station Construction (Stage 2)- Casting of Roof Slab and Excavation till Roof Slab
Top Down Method : Station Construction (Stage 3)-Excavation for Concourse Slab
Top Down Method : Station Construction (Stage 4)-Excavation for Concourse Slab and Completion of Roof Slab
Top Down Method : Station Construction (Stage 5)- Casting Concourse Slab
Top Down Method : Station Construction (Stage 6)- Excavation of Base slab and Casting of Concourse Slab
Top Down Method : Station Construction (Stage 7)- Completion of concourse and Casting of Base Slab
Top Down Method : Station Construction (Stage 8)- Casting of Base Slab
Station Construction
Bottom – Up Method
Bottom UP Method : Station Construction (Stage 1)- Excavation still Roof Slab and Fixing of Strut
Bottom UP Method : Station Construction (Stage 2)- Excavation still Concourse
Slab and Fixing of Strut
Bottom UP Method : Station Construction (Stage 3)- Excavation still Base
Slab and Casting of Base Slab
Bottom UP Method : Station Construction (Stage 4)- Casting of Concousre Slab
Bottom UP Method : Station Construction (Stage 5)- Casting of Roof Slab
Bottom UP Method : Station Construction (Stage 6)- Backfill
Cut and Cover Method
Tunnel Segment
TUNNEL SEGMENT CYCLE TIME
Sr.N
o
Activity Duration In Minutes Start Finish
1Mould Opening 30 0 30
2Cleaning of Mould 40 30 70
3Placing of reinforcement 20 70 90
4Insert Fixing 10 90 100
5Checking of reinforcement 20 100 120
6Concrete Pouring 20 120 140
7Steam Curing 420 140 560
8Removal of Segment 40 560 600
In Minutes 600
In Hours 10 Mould
Opening(3
0 min)
Cleaning
of Mould
(40 Min)
Placing of
Reinforce
ment(20
Min)
Insert
Fixing (10
min)
Checking
of
Reinforce
ment(20
Min)
Concreting
(20 Min)
Steam
Curing
(7 hrs
Removal
of
Segment(4
0 Min)
Average Time take
for 1 Tunnel
Segment will be
10 Hrs
TUNNEL SEGMENT CYCLE TIME (6 Nos of Mould)
Sr.No Activity Mould 1 Mould 2 Mould3 Mould 4 Mould 5 Mould 6
1 Mould Opening 30 30 30 30 30 30
Duration ( In Minutes) 0-30 30-60 60-90 0-30 30-60 60-90
2 Cleaning of Mould 40 40 40 40 40 40
Duration ( In Minutes) 30-70 70-110 110-150 30-70 70-110 110-150
3 Placing of reinforcement 20 20 20 20 20 20
Duration ( In Minutes) 70-90 110-130 150-170 70-90 110-130 150-170
4 Insert Fixing 10 10 10 10 10 10
Duration ( In Minutes) 90-100 130-140 170-180 90-100 130-140 170-180
5 Checking of reinforcement 20 20 20 20 20 20
Duration ( In Minutes) 100-120 140-160 180-200 100-120 140-160 180-200
6 Concrete Pouring 20 20 20 20 20 20
Duration ( In Minutes) 120-140 160-180 200-220 120-140 160-180 200-220
7 Steam Curing 420 420 420 420 420 420
Duration ( In Minutes) 140-560 180-600 240-640 140-560 180-600 240-640
8 Removal of Segment 40 40 40 40 40 40
Duration ( In Minutes) 560-600 600-640 640-680 560-600 600-640 640-680
Total Time for Casting ( For each
Mould)
600 Min 10 Hours
Total Time for casting (For 6 Mould) 680 Min 11.33 Hours
Total Repeatative Ring casting in 22
hours
22/11.33 1.94 Repition
No.Of working Days 26
Total no of casting by each mould
each month
50 Rings
Total Number of Casting 302 Rings
Average.Casting Per Day 12 Rings 10 Rings Consider in DWP
Lift Precast segment out of
Mould After 8 hours
Type of Tunnel Boring Machine
1) EPB Machine
2) Slurry Machine
3) EPB and Slurry Machine
Parts of TBM machine
Working of TBM
Ahmedabad Metro
PROJECT ALIGNMENT (UG2)
Package: UG2 – 4.102 Km (11620.302m  7518.161 m)
Shafts
Launching Shaft - Top Down (40 m length)
Stations
Ghee Kanta - Top Down (170 m length)
Shahpur - Top Down (260 m length)
Tunnel & Cross Passage
TBM Tunnel - 3300 m length × 2
Cross Passage - 13 Nos.
Ramp
West Ramp - Bottom Up (286 m length)
Entry & Exit
Entry / Exits - 07 Nos. (3 nos. – Ghee Kanta, 4 nos. – Shahpur)
SCOPE OF WORKS (UG2)
116
Description Launching Shaft Intermediate Shaft Ghee Kanta Shahpur Arrival Shaft
Construction Method Bottom Up Bottom Up Top Down Top Down Bottom Up
Length (Outer Length) 40 30 170 260 25
Width (C/C) 25 25 22 22 22
Depth (Base Slab) 20 21 19.5 18.5 18.5
No of Entrances -- -- 3 4 --
Ancillary Building -- -- 1 1 --
SCOPE OF WORKS (UG2) : GENERAL DETAIL
25 M 109 M 21 M 40 M
AS IMS
30-Mar-19
02-May-19
12-Apr-18
09-May-18
12-Feb-18
29-May-18
30-Aug-18
19-Aug-18TBM-1 Reach
TBM-2 Reach
TBM-1 Re-launch
TBM-2 Re-launch
Roof Slab
Concousre Slab 17-Sep-18
TBM-1 Reach
TBM-1
TBM-2
02-Mar-18
27-Mar-18
03-Mar-18
06-Apr-18
05-Apr-18
21-Jul-18
31-Dec-18
TBM -3 Completion
TBM -1 Completion
Roof Slab
Concousre Slab
Base Slab
TBM-1 Reach
TBM-2 Reach
TBM-3 Launch
TBM-1 Re-launch
05-Oct-18
02-Sep-18
CUT & COVER SHAHPUR STATION LAUNCHING
SHAFT
GHEE KANTA STATION
Base Slab
TUNNEL -1
TUNNEL-2
East West Corridor - UG2 PACKAGE LENTGH - 4.10 KMS (DWP Programme)
286 M 260 M 170 M 666 M1338 M1203 M
TBM1TBM2
TBM1TBM2
TBM1TBM2
TBM1TBM3
TBM PATH (UG2)
TBM 2TBM 1 TBM 3
Tunneling Configuration
1) Completion of all D wall Works
2) Start excavation for 1st layer1) Excavation upto 1 m Below Temporary Sturt -1
From one side
1) Start Fixing brackets form one side
2) Start Fixing of Waler form one side
THALTEJ GAM (WEST) VASTRAL GAM (EAST)
LAUNCHING SHAFT SEQUENCE
CONSTRUCTION SEQUENCE OF GHEEKANTA
Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity

More Related Content

What's hot

Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
Gaurang Kakadiya
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
Shanmugaraj M
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
Sameer Thaiyam
 
A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...
Prashant Shaurabh
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
Construction Tech. and Mgmt., VNIT Nagpur
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile FoundationSubham Kundu
 
metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)
A.U Architecture Alumni Association
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
Axay Sharma
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ssuser5fea8f
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
RAMPRASAD KUMAWAT
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
KHUSHBU SHAH
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Bridge
Bridge Bridge
Bridge illpa
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
mukul srivastava
 
Presentation on Railway STATION LAYOUT
Presentation on  Railway STATION LAYOUTPresentation on  Railway STATION LAYOUT
Presentation on Railway STATION LAYOUT
RONAK SUTARIYA
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
Vijai Krishnan V
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
Seminar Links
 

What's hot (20)

Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile Foundation
 
metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)
 
PPT OF LG
PPT OF LGPPT OF LG
PPT OF LG
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Bridge
Bridge Bridge
Bridge
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
 
Presentation on Railway STATION LAYOUT
Presentation on  Railway STATION LAYOUTPresentation on  Railway STATION LAYOUT
Presentation on Railway STATION LAYOUT
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 

Similar to Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity

Electricity generation using speed breaker
Electricity generation using speed breakerElectricity generation using speed breaker
Electricity generation using speed breaker
Raza Ishtiaq
 
Tool box talk power point 3
Tool box talk power point 3Tool box talk power point 3
Tool box talk power point 3
Larry Wleczyk
 
IRJET- 360 Degree Rotated Gearbox Trolley
IRJET-  	  360 Degree Rotated Gearbox TrolleyIRJET-  	  360 Degree Rotated Gearbox Trolley
IRJET- 360 Degree Rotated Gearbox Trolley
IRJET Journal
 
GENEVA CONVEYOR
GENEVA CONVEYORGENEVA CONVEYOR
GENEVA CONVEYOR
Nikhilesh Mane
 
Waste disposal system of railway wagon
Waste disposal system of railway wagonWaste disposal system of railway wagon
Waste disposal system of railway wagon
Rajeshvaliya
 
TBEA ENERGY (INDIA) PVT LTD
 TBEA   ENERGY (INDIA) PVT LTD TBEA   ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTD
Raviraj solanki
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
IRJET Journal
 
Product Presentation (2016-01-28).pptx
Product Presentation (2016-01-28).pptxProduct Presentation (2016-01-28).pptx
Product Presentation (2016-01-28).pptx
NoSelfie
 
Skidded helicopter tug design calculation
Skidded helicopter tug design calculationSkidded helicopter tug design calculation
Skidded helicopter tug design calculation
Lahiru Dilshan
 
Prashant patel
Prashant patelPrashant patel
Prashant patel
PRASHANT KUMAR PATEL
 
Tripping out automatic
Tripping out automaticTripping out automatic
Tripping out automatic
Ruba Alsoheil
 
Design and Fabrication of Multi Speed Centrifugal Pump
Design and Fabrication of Multi Speed Centrifugal PumpDesign and Fabrication of Multi Speed Centrifugal Pump
Design and Fabrication of Multi Speed Centrifugal Pump
Raushan Sah
 
inclined car parking lift mechanism system by 070 batch (IOE Pulchowk)
inclined car parking lift mechanism system by 070 batch (IOE Pulchowk)inclined car parking lift mechanism system by 070 batch (IOE Pulchowk)
inclined car parking lift mechanism system by 070 batch (IOE Pulchowk)
Dinesh Rawal
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2Ravi Mehta
 
Gearless power-transmission-project report
Gearless power-transmission-project reportGearless power-transmission-project report
Gearless power-transmission-project report
Erole technologies Pvt. Ltd
 
Heavy Lifts PPVC Lifting Frame & Anchor.pdf
Heavy Lifts PPVC Lifting Frame & Anchor.pdfHeavy Lifts PPVC Lifting Frame & Anchor.pdf
Heavy Lifts PPVC Lifting Frame & Anchor.pdf
VeeramuthuBalakrishn
 
Coates Hire Structural Propping & Support
Coates Hire Structural Propping & Support Coates Hire Structural Propping & Support
Coates Hire Structural Propping & Support
Rafi Tchopourian
 
Glass Lift report
Glass Lift reportGlass Lift report
Glass Lift report
Shao Xun Sean Thun
 

Similar to Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity (20)

Electricity generation using speed breaker
Electricity generation using speed breakerElectricity generation using speed breaker
Electricity generation using speed breaker
 
Tool box talk power point 3
Tool box talk power point 3Tool box talk power point 3
Tool box talk power point 3
 
IRJET- 360 Degree Rotated Gearbox Trolley
IRJET-  	  360 Degree Rotated Gearbox TrolleyIRJET-  	  360 Degree Rotated Gearbox Trolley
IRJET- 360 Degree Rotated Gearbox Trolley
 
GENEVA CONVEYOR
GENEVA CONVEYORGENEVA CONVEYOR
GENEVA CONVEYOR
 
Waste disposal system of railway wagon
Waste disposal system of railway wagonWaste disposal system of railway wagon
Waste disposal system of railway wagon
 
TBEA ENERGY (INDIA) PVT LTD
 TBEA   ENERGY (INDIA) PVT LTD TBEA   ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTD
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
Product Presentation (2016-01-28).pptx
Product Presentation (2016-01-28).pptxProduct Presentation (2016-01-28).pptx
Product Presentation (2016-01-28).pptx
 
Skidded helicopter tug design calculation
Skidded helicopter tug design calculationSkidded helicopter tug design calculation
Skidded helicopter tug design calculation
 
Prashant patel
Prashant patelPrashant patel
Prashant patel
 
Tripping out automatic
Tripping out automaticTripping out automatic
Tripping out automatic
 
Closure Report
Closure ReportClosure Report
Closure Report
 
Design and Fabrication of Multi Speed Centrifugal Pump
Design and Fabrication of Multi Speed Centrifugal PumpDesign and Fabrication of Multi Speed Centrifugal Pump
Design and Fabrication of Multi Speed Centrifugal Pump
 
inclined car parking lift mechanism system by 070 batch (IOE Pulchowk)
inclined car parking lift mechanism system by 070 batch (IOE Pulchowk)inclined car parking lift mechanism system by 070 batch (IOE Pulchowk)
inclined car parking lift mechanism system by 070 batch (IOE Pulchowk)
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2
 
Gearless power-transmission-project report
Gearless power-transmission-project reportGearless power-transmission-project report
Gearless power-transmission-project report
 
Heavy Lifts PPVC Lifting Frame & Anchor.pdf
Heavy Lifts PPVC Lifting Frame & Anchor.pdfHeavy Lifts PPVC Lifting Frame & Anchor.pdf
Heavy Lifts PPVC Lifting Frame & Anchor.pdf
 
Engineered Spring Supports V.2
Engineered Spring Supports V.2Engineered Spring Supports V.2
Engineered Spring Supports V.2
 
Coates Hire Structural Propping & Support
Coates Hire Structural Propping & Support Coates Hire Structural Propping & Support
Coates Hire Structural Propping & Support
 
Glass Lift report
Glass Lift reportGlass Lift report
Glass Lift report
 

Recently uploaded

Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 

Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity

  • 1. Introduction of METRO RAIL in INDIA Rapid transits in India consist of Metro, Monorails and light rail system How it Began India’s 1st and Asia’s 5th Metro rail was introduced in Kolkata in 1984 Delhi Metro was India's first modern metro which began its operation in 2002. Rapid Metro Rail Gurgaon, which started operations in November 2013, is India's first privately owned & operated metro.
  • 2. Why is it Needed ? Unprecedented growth of personal Vehicle Growing Traffic Congestion Air pollution and traffic accidents has become a major concern To avoid congestion at Peak hour Time saving and Reduced fuel consumption
  • 3. METRO RAIL in INDIA Unprecedented growth of personal Vehicle Growing Traffic Congestion Air pollution and traffic accidents has become a major concern To avoid congestion at Peak hour Time saving and Reduced fuel consumption
  • 4. METRO RAIL in INDIA Existing Metro Rail in INDIA 1) Delhi Metro 2) Kolkata Metro 3) Mumbai Metro 4) Chennai Metro 5) Bangalore Metro 6) Jaipur Metro 7) Lucknow Metro 8) Hyderabad Metro 9) Kochi Metro 10) Noida Metro Under construction and proposed Metro Rail in India 1) Ahmedabad Metro 2) Pune Metro 3) Nagpur Metro 4) Indore Metro 5) Bhopal Metro 5) Kanpur Metro
  • 5. Type of metro Type of Metro 1) Elevated Metro 2) Underground Metro 3) On Grade
  • 7. Basic Sequence of Activities For Elevated Metro (Viaduct) Obtain site acquired by the Client Preliminary Survey Works Barricading Utilities Identification Shifting of Utilities Test Pile Casting & Testing (Vertical & Lateral Load Tests) Pile FoundationPile CapPiersPier Cap Erection of Segments Pre stressing of Span & Grouting Alignment, & Bearing Parapet Erection Cable Trough Erection Fixing of vertical bearing & Shear key Bar Handing Over Casting of superstructure Segments & parapet Stacking and Transportatio n of segments Casting Yard Set Up
  • 8. Basic Sequence of Activities For Elevated Metro (Station) Obtain site acquired by the Client Preliminary Survey Works Barricading Utilities Identification Shifting of Utilities Test Pile Casting & Testing (Vertical & Lateral Load Tests Pile FoundationPile Cap Pier up to CL Beam Bottom Pier Arm/Portal Beams at CL Pier up to PL Beam Bottom Pier Heads at PL & TL Girder Launching Deck Slab at CL, PL & TL Deck Slab PL & TL Entry & Exit Roofing works at PL Finishing Works MEP & FFTG Works General Development & Road Works Handing Over Casting of superstructure I - Girder Stacking and Transportation of segments Casting Yard Set Up
  • 9. P nP n+1 Span Length Number of Segments 37 m 13 34 m 12 31 m 11 28 m 10 25 m 9 22 m 8 S7C 3000 S6D 3000 S6U 3000 S5D 3000 S4D 3000 S3D 3000 S2D 3000 S5U 3000 S4U 3000 S3U 3000 S2U 3000 S1U 1975 S1D 1975 Segment Codes Standard Span Length S1U S2U S3U S4U S5U S6U S7C S6D S5D S4D S3D S2D S1D 37 √ √ √ √ √ √ √ √ √ √ √ √ √ 34 √ √ √ √ √ √ x √ √ √ √ √ √ 31 √ √ √ √ √ x √ x √ √ √ √ √ 28 √ √ √ √ √ x x x √ √ √ √ √ 25 √ √ √ √ x x √ x x √ √ √ √ 22 √ √ √ √ x x x x x √ √ √ √ Casting Yard – Segment Details Preparation of Reinforcem ent Cage (3 days) Placing of cage, Profiling Shuttering (18 Hrs.) Concreting (4 Hrs.) Deshutteri ng (5 Hrs.) Lifting and stacking in C.Y (3 Hrs.) Curing will be done for 14 days and after 28 days , Ready for Launching Average 15 Days will be required to cast segments for 37m span.
  • 10. Casting Sequence Segment Id Average Cummulative days 1 S7C 1 2 S1U 2 3 S6U 4 4 S6D 5 5 S2U 6 6 S5U 7 7 S5D 8 8 S4U 9 9 S1D 10 10 S4D 11 11 S2D 12 12 S3U 14 13 S3D 15 Match Casting Activity Short bed Long bed
  • 11. Pier Pile Pile Cap Crash Barrier Pier Cap Upstand/Pedestal Segments (Span) Sub Structure Super Structure Seismic arrester of span Details of Structure
  • 12. Pile 3 4 12 Average Time Required for Casting of one Pile will be 12hrs. Pile Boring (5 hrs ) Transportati on of Caging (1Hr) Cage placing (3 hrs) Pile concrete (3hrs) Casing removal (1 hr) Average Time take to cast pile group will be 5 Days. Piling Sequence Piling Activity
  • 13. P - 1 P – 2 P -3 P -4 Pile cap shutter 1 Pile cap shutter 2 Pile Cap Reinforcement (3 Days) Average Time take to cast pile cap will be 12 Days. After 1 day Resources movement Pile Cap Pile Pile cap Activity
  • 14. P -1 P -2 P -3 P -4 Piershutter1 Pier shutter 1 Piershutter2 Piershutter3 Piershutter1 Piershutter2 Piershutter3 Pier shutter 2 Pier shutter 3 Pier Pile Cap Pile Pier reinforcement (2 days) Pier starter (6 Hrs) Pier shutter (2 Days) Pier concreting (6 Hrs) Pier Deshuttering (12 Hrs) After 24 Hrs. After 1 day Pier Activity Resources movement Average Time Cycle for Pier 5 days Pier P -5 P -6
  • 15. Pier Cap Preparation of reinforcement Cage (3 Days) Pedestal And shear key Casting (18 Hrs) After 21 day Average Time cycle for pier cap is 8 days Pier Cap Activity
  • 16. dry matching (8 hrs) and wet matching (10 hrs) including cutting and treading and lowering of span. Launching Sequence Activity
  • 18. COMPONENTS OF LAUNCHING GIRDER  MAIN BOX GIRDER  FRONT SUPOORT  MIDDLE SUPPORT  REAR SUPPORT  REAR TROLLEY  SLIDER BEAM  COUNTER WEIGHT  FIXED MOUNTED HOIST  PLATFORM/ WALK WAYS
  • 19. Maximum height of Front support : 6220mm Minimum height of Front support : 4230mm FRONT SUPPORT TOP BEAM TOP VERTICAL LEG BOTTOM BEAM TELESCOPIC LEG GENERAL ARRANGEMENT OF FRONT SUPPORT
  • 20. TYPICAL ISOMETRIC VIEW OF FRONT SUPPORT
  • 21. MIDDLE SUPPORT Main beam Bracket of main beam Launching bearing Longitudinal side bearing Knuckle bearing Cradle TYPICAL ISOMETRIC VIEW OF MIDDLE SUPPORT
  • 22. Rear support is more or less same replica of middle support accept longitudinal pushing assembly is not provided in this support. REAR SUPPORT TYPICAL ISOMETRIC VIEW OF REAR SUPPORT
  • 23. REAR TROLLEY TYPICAL ISOMETRIC VIEW OF REAR TROLLEY  REAR TROLLEY IS POSITIONED AT 4500MM FROM THE REAR END OF THE MAIN GIRDER S8 AND PROVIDES SUPPORTS DURING LONGITUDINAL AUTO LAUNCHING.
  • 24. SLIDER BEAMS TYPICAL FRONT VIEW OF SLIDER BEAM TYPICAL ISOMETRIC VIEW OF SLIDER BEAM  SLIDER BEAMS ARE INDEPENDENT ASSEMBLY OF TWO BUILT UP I SECTIONS CONNECTED TOGETHER WITH STEEL DIAPHRAGMS
  • 25. SCHEME FOR AUTO-LAUNCHING FOR SPANs UPTO 37m Span
  • 26. Step:1 Erect all the segments of the span and do final pre-stressing as per specification in drawing.
  • 27. Step:2 Ensure that erection of all span is completed in all aspects. Release all suspenders from erected span and lower the span on temporary bearing placed on pier cap.
  • 28. Step:3 Bring all the sliders to the rear end.
  • 29. Step:4 Release the middle support from the span and with the help of slider beam shift the middle support nearer to the front support on segment S1 as shown in drawing.
  • 30. Step:5 Activate the jacks of middle support on segment S1 and anchor with the span.
  • 31. Step:6 Release the Rear support from the span and with the help of slider beam shift the rear support to the erected span of segment S1.
  • 32. Step:7 Activate the jacks of rear support on segment S1 and anchor with the span.
  • 33. Step:8 Now move both the sliders back to the rear trolley.
  • 34. Step:9 Ensure that middle and rear support are firmly anchored with the span. Now close the telescopic leg of front support so that all load transferred to the middle and rear support.
  • 35. Step:10 Ensure all the supports firmly anchored with the span and make sure that rear trolley free from anchorage from the span.
  • 36. Step:11 Ensure that all supports firmly anchored with super structure. Start Auto-launching and auto launch the launching girder by 1200mm. Check that all supports are firmly anchored or not.
  • 37. Step:12 Now again start auto launching until rear trolley come nearer to the rear support.
  • 38. Step:13 With the help of slider beam move rear support near to the middle support and anchored it with the span.
  • 39. Step:14 Continue auto-launching till front support reaches next pier cap location..
  • 40. Step:15 Open the telescopic leg of front support and activate it. Anchor firmly with pier cap.
  • 41.
  • 42. Step: 1 Make sure that launching Girder is ready for erection of new span and lifting of segments. Now move the sliding towards the next span to be erected near front support as shown.
  • 43. Step:2 Move the trailer below the lifting hoist.
  • 44. Step:3 Pull down the lifting beam.
  • 45. Step:4 Fix the lifting beam and temporary pre-stressing beam on segment S1. Now lift the pier segment S1 with the help of lifting hoist. Now move the slider in position to lift the S1 segment.
  • 46. Step:5 Connect the S1 with the slider beam and move it nearer to the middle support.
  • 47. Step:7 Move S2 nearer to the segment S1.
  • 48. Step:8 Move S3 nearer to the segment S2.
  • 49. Step:9 Move S4 nearer to the segment S3.
  • 50. Step:10 Move S5 nearer to the segment S4.
  • 51. Step:11 Move S6 nearer to the segment S5.
  • 52. Step:11 Move S7 nearer to the segment S6.
  • 53. Step:11 Move all the sliders towards Segment S7.
  • 54. Step:11 Move all the sliders towards Segment S7.
  • 55. Step:11 Now lift the segment S3 upwards then other segments for adjustment of all the segments in fixed length.
  • 56. Step:11 Now lift the segment S3 upwards then other segments for adjustment of all the segments for dry matching.
  • 57. Step:11 Now move remaining sliders towards segment S3.
  • 58. Step:11 Now move remaining sliders towards segment S3.
  • 59. Step: Lift the segment S5 and move it near the segment S6.Now same do same procedure for segment S4.
  • 60. Step:17 Now do dry/wet matching and temporary pre-stressing and follow the procedure for final pre-stressing as per specification given in drawing.
  • 61. Concourse Level Track Level Platform Level Road Level CANTILEVER TYPE STATION Bored Cast-in situ Piles Pile Cap Pier Crash Barrier Pier Head at CL Staircase Precast I-girders Deck slab at CL Pier Heads at PL & TL Pre-cast I-girders PEB Roofing Deck Slab at PL & TL 61
  • 62. Concourse Level Track Level Platform Level Road Level PORTAL TYPE STATION Bored Cast-in situ Piles Pile Cap Pier Crash Barrier Portal Beam at CL Staircase Precast I-girders Deck slab at CL Pier Heads at PL & TL Pre-cast I-girders PEB Roofing Deck Slab at PL & TL 62
  • 63. Underground Metro Tunnel • Cut and Cover • Bored Tunnel Station • Top –Down • Bottom-up
  • 64. Stage – 03. Stop End inserted in both end of the trench. Stop End Stop End Installation Stage – 05. Concrete placing through tremie pipe as polymer slurry is displaced. Panel Concreting ` DIAPHRAGM WALL CONSTRUCTION METHODOLOGY.
  • 65. Excavation Methods Bottom Up Method: Slabs will be laid from Bottom to Top such that Base slab will be constructed first Base slab Concourse Slab Roof Slab GLGL D-wall Top Down Method: Slabs will be laid from Top to Bottom such that Top slab will be constructed first  Top slab  Concourse Slab  Base Slab GLGL D-wall 65
  • 66. 1) Completion of all D wall Works 2) Start excavation for 1st layer D wall King Post Bottom Up Method : Launching shaft Construction (Stage 1)
  • 67. 1) Excavation upto 1 m Below Temporary Sturt -1 From one side D wall King Post Bottom Up Method : Launching shaft Construction (Stage 1)
  • 68. 50 T Gantry D Wall Road Waler 1) Start Fixing brackets form one side 2) Start Fixing of Waler form one side Bottom Up Method : Launching shaft Construction (Stage 2)
  • 69. 50 T Gantry D Wall Waler Road Erection of Diagonal Strut 1) Start Fixing Diagonal Strut 2) Start Fixing of Waler for Straight Strut Bottom Up Method : Launching shaft Construction (Stage 2)
  • 70. 1) Start Fixing Straight Strut 2) Start Fixing of Waler for Diagonal Strut 50 T Gantry D Wall Diagonal Strut Road Erection of Straight Strut Erection of Waler for Diagonal strut Bottom Up Method : Launching shaft Construction (Stage 2)
  • 71. 1) Completion of Strut erection Start on 1st Layer 2) Excavation for 2nd layer Diagonal Strut Road Straight Strut Erection of Diagonal strut D Wall 50 T Gantry Bottom Up Method : Launching shaft Construction (Stage 2)
  • 72. 1) Erection of 2nd Strut Layer 2) Excavation upto 1 m Below Temporary Sturt -2 From one side D wall King Post Bottom Up Method : Launching shaft Construction (Stage 3)
  • 73. 1) Start Fixing of Brackets from One side 2) Start Fixing of Waler from One side 3) Erection of 2nd Strut Layer 4) Excavation upto 1 m Below Temporary Sturt – 3 From one side King Post D wall Bottom Up Method : Launching shaft Construction (Stage 4)
  • 74. 1) Start Fixing of Brackets from One side 2) Start Fixing of Waler from One side 3) Erection of 3rd Strut Layer 4) Excavation upto 1 m Below Temporary Sturt – 4 From one side King Post D wall Bottom Up Method : Launching shaft Construction (Stage 5)
  • 75. 1) Start Fixing of Brackets from One side 2) Start Fixing of Waler from One side 3) Erection of 4th Strut Layer 4) Excavation upto Base Slab Level From one side King Post D wall Bottom Up Method : Launching shaft Construction (Stage 6)
  • 76. 1) Excavation upto Base Slab Level 2) Levelling Surface for Base slab construction King Post D wall Bottom Up Method : Launching shaft Construction (Stage 7)
  • 77. 1) Casting of Base Slab 2) Attain required strength for Base slab 3) Removal of 4th Level strut 4) Cast reaction Frame support for Pedestal 5) Handover the shaft to TBM operations Base Slab King Post D wall Bottom Up Method : Launching shaft Construction (Stage 8)
  • 79. Top Down Method : Station Construction (Stage 1)- Excavation still Roof Slab
  • 80. Top Down Method : Station Construction (Stage 2)- Casting of Roof Slab and Excavation till Roof Slab
  • 81. Top Down Method : Station Construction (Stage 3)-Excavation for Concourse Slab
  • 82. Top Down Method : Station Construction (Stage 4)-Excavation for Concourse Slab and Completion of Roof Slab
  • 83. Top Down Method : Station Construction (Stage 5)- Casting Concourse Slab
  • 84. Top Down Method : Station Construction (Stage 6)- Excavation of Base slab and Casting of Concourse Slab
  • 85. Top Down Method : Station Construction (Stage 7)- Completion of concourse and Casting of Base Slab
  • 86. Top Down Method : Station Construction (Stage 8)- Casting of Base Slab
  • 88. Bottom UP Method : Station Construction (Stage 1)- Excavation still Roof Slab and Fixing of Strut
  • 89. Bottom UP Method : Station Construction (Stage 2)- Excavation still Concourse Slab and Fixing of Strut
  • 90. Bottom UP Method : Station Construction (Stage 3)- Excavation still Base Slab and Casting of Base Slab
  • 91. Bottom UP Method : Station Construction (Stage 4)- Casting of Concousre Slab
  • 92. Bottom UP Method : Station Construction (Stage 5)- Casting of Roof Slab
  • 93. Bottom UP Method : Station Construction (Stage 6)- Backfill
  • 94. Cut and Cover Method
  • 95.
  • 96.
  • 97.
  • 98.
  • 100. TUNNEL SEGMENT CYCLE TIME Sr.N o Activity Duration In Minutes Start Finish 1Mould Opening 30 0 30 2Cleaning of Mould 40 30 70 3Placing of reinforcement 20 70 90 4Insert Fixing 10 90 100 5Checking of reinforcement 20 100 120 6Concrete Pouring 20 120 140 7Steam Curing 420 140 560 8Removal of Segment 40 560 600 In Minutes 600 In Hours 10 Mould Opening(3 0 min) Cleaning of Mould (40 Min) Placing of Reinforce ment(20 Min) Insert Fixing (10 min) Checking of Reinforce ment(20 Min) Concreting (20 Min) Steam Curing (7 hrs Removal of Segment(4 0 Min) Average Time take for 1 Tunnel Segment will be 10 Hrs
  • 101. TUNNEL SEGMENT CYCLE TIME (6 Nos of Mould) Sr.No Activity Mould 1 Mould 2 Mould3 Mould 4 Mould 5 Mould 6 1 Mould Opening 30 30 30 30 30 30 Duration ( In Minutes) 0-30 30-60 60-90 0-30 30-60 60-90 2 Cleaning of Mould 40 40 40 40 40 40 Duration ( In Minutes) 30-70 70-110 110-150 30-70 70-110 110-150 3 Placing of reinforcement 20 20 20 20 20 20 Duration ( In Minutes) 70-90 110-130 150-170 70-90 110-130 150-170 4 Insert Fixing 10 10 10 10 10 10 Duration ( In Minutes) 90-100 130-140 170-180 90-100 130-140 170-180 5 Checking of reinforcement 20 20 20 20 20 20 Duration ( In Minutes) 100-120 140-160 180-200 100-120 140-160 180-200 6 Concrete Pouring 20 20 20 20 20 20 Duration ( In Minutes) 120-140 160-180 200-220 120-140 160-180 200-220 7 Steam Curing 420 420 420 420 420 420 Duration ( In Minutes) 140-560 180-600 240-640 140-560 180-600 240-640 8 Removal of Segment 40 40 40 40 40 40 Duration ( In Minutes) 560-600 600-640 640-680 560-600 600-640 640-680 Total Time for Casting ( For each Mould) 600 Min 10 Hours Total Time for casting (For 6 Mould) 680 Min 11.33 Hours Total Repeatative Ring casting in 22 hours 22/11.33 1.94 Repition No.Of working Days 26 Total no of casting by each mould each month 50 Rings Total Number of Casting 302 Rings Average.Casting Per Day 12 Rings 10 Rings Consider in DWP
  • 102. Lift Precast segment out of Mould After 8 hours
  • 103.
  • 104.
  • 105.
  • 106. Type of Tunnel Boring Machine 1) EPB Machine 2) Slurry Machine 3) EPB and Slurry Machine
  • 107.
  • 108. Parts of TBM machine
  • 109.
  • 111.
  • 112.
  • 114.
  • 116. Package: UG2 – 4.102 Km (11620.302m  7518.161 m) Shafts Launching Shaft - Top Down (40 m length) Stations Ghee Kanta - Top Down (170 m length) Shahpur - Top Down (260 m length) Tunnel & Cross Passage TBM Tunnel - 3300 m length × 2 Cross Passage - 13 Nos. Ramp West Ramp - Bottom Up (286 m length) Entry & Exit Entry / Exits - 07 Nos. (3 nos. – Ghee Kanta, 4 nos. – Shahpur) SCOPE OF WORKS (UG2) 116
  • 117. Description Launching Shaft Intermediate Shaft Ghee Kanta Shahpur Arrival Shaft Construction Method Bottom Up Bottom Up Top Down Top Down Bottom Up Length (Outer Length) 40 30 170 260 25 Width (C/C) 25 25 22 22 22 Depth (Base Slab) 20 21 19.5 18.5 18.5 No of Entrances -- -- 3 4 -- Ancillary Building -- -- 1 1 -- SCOPE OF WORKS (UG2) : GENERAL DETAIL
  • 118. 25 M 109 M 21 M 40 M AS IMS 30-Mar-19 02-May-19 12-Apr-18 09-May-18 12-Feb-18 29-May-18 30-Aug-18 19-Aug-18TBM-1 Reach TBM-2 Reach TBM-1 Re-launch TBM-2 Re-launch Roof Slab Concousre Slab 17-Sep-18 TBM-1 Reach TBM-1 TBM-2 02-Mar-18 27-Mar-18 03-Mar-18 06-Apr-18 05-Apr-18 21-Jul-18 31-Dec-18 TBM -3 Completion TBM -1 Completion Roof Slab Concousre Slab Base Slab TBM-1 Reach TBM-2 Reach TBM-3 Launch TBM-1 Re-launch 05-Oct-18 02-Sep-18 CUT & COVER SHAHPUR STATION LAUNCHING SHAFT GHEE KANTA STATION Base Slab TUNNEL -1 TUNNEL-2 East West Corridor - UG2 PACKAGE LENTGH - 4.10 KMS (DWP Programme) 286 M 260 M 170 M 666 M1338 M1203 M TBM1TBM2 TBM1TBM2 TBM1TBM2 TBM1TBM3 TBM PATH (UG2) TBM 2TBM 1 TBM 3 Tunneling Configuration
  • 119. 1) Completion of all D wall Works 2) Start excavation for 1st layer1) Excavation upto 1 m Below Temporary Sturt -1 From one side 1) Start Fixing brackets form one side 2) Start Fixing of Waler form one side THALTEJ GAM (WEST) VASTRAL GAM (EAST) LAUNCHING SHAFT SEQUENCE