SlideShare a Scribd company logo
1 of 97
Download to read offline
Metro North Dublin Ireland, Proposed – Construction €2.4bn
Included
Route
Programme Graphic
Tunnelling Construction
Stations Construction
Cost
Details
Lengths
Overall 18 km
Tunnel 7.5 km
Cut & Cover 2.7 km
Viaduct 2.25 km
Road Level 5.5 km
Stations 15 Nr.
Underground 9 Nr.
Road Level 6 Nr.
Tunnels & Underground Stations
Route
3D image to show Sequence, Method & Plant.
David H Moloney
29th June 2017
Purpose of presentation to give the Public, Stakeholders and Politicians
an understanding of the Construction, Cost and Timeline
ⓒ David H Moloney
Schematic Longitudinal Profile
Project Execution Plan
Details of how a Metro is constructed, and how the progress, safety
and quality will be monitored and controlled.
Table of Contents
Overview
Route of Metro North
ⓒ David H Moloney
Schematic with Principal Quantities
David H Moloney
Schematic Longitudinal Profile
ⓒ David H Moloney
Programme - Time Chainage Diagram
ⓒ David H Moloney
Tunnels & Underground Stations
TBM TBM
Tunnel Tunnel
TunnelViaduct Along Street
Programme Animation
ⓒ David H Moloney
Schematic Longitudinal Profile
Cost Comparisons of Metro Projects
Dubai Route
2020
UAE
(To Start)
Red Line North
Doha
Qatar
(In Progress)
Red Line South
Doha
Qatar
( In Progress)
Metro North
Dublin
(Proposed)
Dart
Underground
Dublin
(Proposed)
Port Tunnel
Dublin
(2005)
Overall Cost €2,450 million €1,803 million €1,500 million €2,400 million €2,000 million ? €752 million
Cost per km €158 million /k m €140 million / km €108 million / km €134 million / km €400 million / km ? €134 million / km
Overall Length 15.5 km 13 km 14m 18 km 5 km 5.6 km
Tunnel 4 km
Single Tunnel
11.6 km
Twin Tunnels
14 km
Twin Tunnels
7.5 km
Twin Tunnels
5 km
Twin Tunnel
4.5 km
Road Tunnel x 2
Cut & Cover 0 2.7 km 0
Elevated 10.5 km 2.2 km 0 Not applicable
Road Level 0 5.5 km 0
Stations 7 Nr. 7 Nr. 5 Nr. 14 Nr. 3 Nr. Not applicable
Capacity 13,000 Passengers per
hour
19,800 Passengers per
hour
? Not applicable
ⓒ David H Moloney
Advantages of Rail Benefits of Metro to commuters
1. Time saving for commuters 4. Reduction in accident
2. Reliable and safe journey 5. Reduced fuel consumption
3. Reduction in atmospheric pollution 6. Reduced traffic congestion
Contractor’s General Items
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
Brief Description
Contractors Site facilities comprise:
Offices, Canteens, Toilets, Drying Rooms,
Stores, Plant Yard, generators and
Workshops.
GeneralItems
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises -
concrete mixer, control cabin, silos for
cement and fly ash, aggregate bins and
conveyor belt system to feed the mixer.
Also aggregate storage bays and water
storage tanks.
The mixing is computer controlled and has
a dynamic screen display, showing the
process. Material storage capacity to
match two days concrete production
Quarry & Aggregate Production
3D image to show Sequence, Method & Plant.
ⓒ David H Moloney
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Site Hoarding examples
ⓒ David H Moloney
GeneralItems
Wheel Wash Drive-throughGeneralItems
Weighbridge & Sheeting Access
ⓒ David H Moloney
GeneralItems
Sheet Pile Temporary Shaft
ⓒ David H Moloney
GeneralItems
Brief Description
Sheet Pile Temporary shaft is used to enable an
excavation for a deep structure.
The construction sequence is:
Install sheet-piles.
Excavate and install bracing.
Excavate to final level.
Construct concrete structure.
Backfill, remove bracing and sheet-piles
Sheet Pile Temporary Shaft
ⓒ David H Moloney
GeneralItems
3D Animation to show Sequence
FalseworkGeneralItems
Brief Description
Falsework to support Bridge deck formwork
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
Dewatering
ⓒ David H Moloney
GeneralItems
Dewatering by Wellpoints
ⓒ David H Moloney
GeneralItems
Dust Suppression
ⓒ David H Moloney
GeneralItems
Temporary Fence type 2
ⓒ David H Moloney
GeneralItems
Brief Description
Temporary fence on precast beam for airport.
Traffic Management
ⓒ David H Moloney
GeneralItems
Brief Description
Traffic management plans are
necessary when working on or beside
roads
Traffic Management - Realign Motorway under new Bridges
ⓒ David H Moloney
GeneralItems
Health, Safety & Environmental
Existing Underground Utilities
ⓒ David H Moloney
Earthworks
Brief Description
Before digging
establish the location
and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Earthworks
Safety Precautions
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Environmentally Friendly Site Air, Noise, Water & Soil Pollution
Water Pollution PreventionGeneralItems
Geotechnical
Diaphragm Wall Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
Earthworks
Tunnels & Underground Stations
3D image to show Sequence, Method & Plant.
David H Moloney
ⓒ David H Moloney
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance
using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes
Earthworks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
Underground Station Excavation
Underground Station Construction
Rock Excavation Underground
Excavate with Roadheader
Drill & Fit Rock Bolts
Spray Mortar as Lining
Excavators with Rock Breaker
& Rock Rotary Cutter
Roadheader
ⓒ David H Moloney
Using Mining Techniques
Bed Rock - Type & Depth
Ground Conditions
The limestone bedrock is between 5 and 25 metres below ground level. The overlying deposits are generally boulder clay with thin layers of sand and gravel. The water table is
between 2 and 4 metres below ground level.
The Bedrock Geology Map of Ireland, gives the rock as limestone and mudstone, along the tunnel route.
Rock - Excavability
Brief Description
The excavability of rock depends
mainly on the rock strength and the
layer thickness. This diagram shows
excavation methods for rock of
various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
Earthworks
Station Excavation - Soil on Rock Situation
Rock Nailing, Rock breaking & Excavation
ⓒ David H Moloney
Concrete
Tunnel Wall Segments Casting
Clean Mould
Lift Precast Segment out of mould
after 18 hours.
Reinforcement
fabricate
Reinforcement
into Mould
Concreting
Segment Storage
Casting Cycle Time 24 hrs
ⓒ David H Moloney
Tunnel Precast Segments
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Reinforced Structure Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The general sequence to construct a reinforced concrete tank
is as follows-
1. Construct the floor and wall panels in a hit and miss pattern.
2. Construct the floor and wall corners and T shape panels.
3. Construct the roof working outwards from the back.
Reinforced Structure Construction Sequence David H Moloney
ⓒ David H Moloney
Bridge & Post-tensioning
Concrete
Brief Description
The sequence to post-tension a bridge
deck is as follows;
Fix the ducts and anchorages.
Install the stressing strand.
Concrete the deck.
Stress the strands and lock at
anchorages.
Grout the ducts.
Bridge & Post-tensioning
Concrete
Bridge & Post-tensioning
Concrete
Bridge Construction Sequence
David H Moloney
Piling Surcharge Abutments
Remove Surcharge Abutments
Deck centre
Post-tensioning Fascia & Waterproof deck Complete Bridge
PiersOverview
Deck Ends
Images with Schematic 3D view, Photos & Timeline
ⓒ David H Moloney
Post-tensioning Bridge Deck David H Moloney
Waterproofing Spray on System
Miscellaneous
Waterproofing Spray on Tests
Miscellaneous
Underground Stations David H Moloney
ⓒ David H Moloney
Large Floor Concrete Pour
Rail Viaduct
Concrete
Brief Description
Shown is the construction of a light rail viaduct where
an overhead gantry was used to lift and place the
precast concrete viaduct segments.
Viaduct Construction
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
David H Moloney
ⓒ David H Moloney
Viaduct Construction David H Moloney
ⓒ David H Moloney
Viaduct Segments Launching
ⓒ David H Moloney
Viaduct Segments Casting David H Moloney
Casting Method
The concrete segments are manufactured
using the short-line, match-casting method.
Match-casting is when sequential segments are
poured against the previous cast segment, this
ensures that the segments will fit perfectly on
site.
Horizontal and vertical curves are achieved by
setting the cast segment at a rotation in either or
both axis to the mould used to cast the next
segment.
ⓒ David H Moloney
Viaduct Segments – Short-line, Match Casting Method
David H MoloneyMatch-casting is when sequential segments are poured against the previous
cast segment, this ensures that the segments will fit perfectly on site.
Cycle Time 24 hrs
Piling
Piling Construction - Plant & Methods
Brief Description
Piling Plant, Equipment and Material;
Crawler Crane, Piling Hammer, Temporary Casing,
Piling Rig, Concrete Pump, Concrete Mixer Trucks,
Tremie Pipe and Reinforcement Cage
Piling
Piling Construction - Plant, Methods & SequencePiling
Piling Construction - Plant & MethodsPiling
Piling Construction - Vertical PilesPiling
Piling Construction - Raking PilesPiling
Piling Construction - Raking PilesPiling
Pile Load Test
ⓒ David H Moloney
Piling
Brief Description
A jack is used to load the pile in steps and
gauges measure any settlement.
Secant Pile Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
Roads & Paving
Asphalt Batching Yard
Roads&Pavings
Road Construction Sequence Animation
Tunnel
Tunnel Design
Twin Tunnels single track with
Cross passages at 250m intervals
for emergency evacuation
Tunnels in rock to avoid ground &
building settlement.
Depth 25 metres on average
ⓒ David H Moloney
Cut & Cover Tunnel Construction
Sequence -Traffic and utilities are diverted, excavate trench, construct & backfill to bury.
To prevent the faces of the excavation from collapsing, different measures are used –
batter the faces, diaphragm walls, secant piles or a combination of soil nailing and
shotcreting.
Ramp Construction
Sequence -Traffic and utilities are diverted, excavate, construct and backfill to sides.
To prevent the faces of the excavation from collapsing, different measures are used – batter
faces, diaphragm walls, secant piles or a combination of soil nailing and shotcreting.
ⓒ David H Moloney
Tunnel Boring Machine (TBM)
Cutting Head rotates to Dig
Excavated material removed
by conveyor belt
Lifting muck to surface
with skip
Placing Concrete
Segments
Tunnel Boring Machine (TBM)
Cutting Head rotates
7 nr. Precast segments
form rings that line the
tunnel Excavated material removed
by conveyor belt
ⓒ David H Moloney
Tunnel Fit-out Rail, Electricals, Ventilation
Tunnel Fit-out
Install Sleepers & Rails
Concrete Batching Train for Floor Slab
Drilling Machine for Utilities Brackets
Commissioning, Testing, Handover & Opening
Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.
ⓒ David H Moloney
Miscellaneous Works
Fencing
ⓒ David H Moloney
Sequence of Construction
Clear Scrub & Grade ground
Fix Corner & Strainer Posts
Fix Intermediate Posts
Fix Line Wire, Chain-link & Razer wire
Concrete ground beam
Progress Monthly, Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current
progress and historical trends
Histogram Charts for Resources & Outputs
Concrete, Manpower, TBM,
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Other Projects
Luas – Dublin, Tram / Light Rail System Construction Sequence & Methods
Install Traffic Control Fencing & Welfare Facilities Divert Underground Utilities Excavate
Prepare Formation Reinforcement & Rails Paving
Paving Information Sign Trams in Operation Trams in Operation
Reinforcement & Rails
ⓒ David H Moloney
Production by David H Moloney
See my YouTube Video on Dublin Metro North
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
ⓒ David H Moloney

More Related Content

What's hot

Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution PlanDavid H Moloney
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionDavid H Moloney
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures ConstructionDavid H Moloney
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction TechniquesDavid H Moloney
 
Typical road structure cross section details
Typical road structure cross section detailsTypical road structure cross section details
Typical road structure cross section detailsAglaia Connect
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yardRavinder Singh
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 kmDavid H Moloney
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian uitm pulau pinang
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc roaddeepak athwal
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineeringKHUSHBU SHAH
 
A Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesA Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesSubham Kundu
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
project final year civil
project final year civilproject final year civil
project final year civilAlankar jaiswal
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction MethodsDavid H Moloney
 
Hill roads and Drainage
Hill roads and DrainageHill roads and Drainage
Hill roads and Drainageholegajendra
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1KhangWei Chin
 

What's hot (20)

Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution Plan
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Site Survey Report
Site Survey ReportSite Survey Report
Site Survey Report
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
 
Typical road structure cross section details
Typical road structure cross section detailsTypical road structure cross section details
Typical road structure cross section details
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yard
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 km
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
A Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesA Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ Piles
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
project final year civil
project final year civilproject final year civil
project final year civil
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
 
Hill roads and Drainage
Hill roads and DrainageHill roads and Drainage
Hill roads and Drainage
 
PPT OF LG
PPT OF LGPPT OF LG
PPT OF LG
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
 

Viewers also liked

Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationDavid H Moloney
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionDavid H Moloney
 
Current Long Span Bridges 16
Current Long Span Bridges 16Current Long Span Bridges 16
Current Long Span Bridges 16David Collings
 
Multi span suspension bridges
Multi span suspension bridgesMulti span suspension bridges
Multi span suspension bridgesDavid Collings
 
Lec 7 pile foundation
Lec 7 pile foundationLec 7 pile foundation
Lec 7 pile foundationGhulam Yasin
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanDavid H Moloney
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Delhi metro rail corporation project
Delhi metro rail corporation projectDelhi metro rail corporation project
Delhi metro rail corporation projectVimal Maurya
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Aashna Sharma
 
Summer training DMRC ppt
Summer training DMRC pptSummer training DMRC ppt
Summer training DMRC pptVimal Maurya
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineeringAdil Shaikh
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 

Viewers also liked (20)

Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D Visualisation
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
Metro presentation
Metro presentationMetro presentation
Metro presentation
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
 
Current Long Span Bridges 16
Current Long Span Bridges 16Current Long Span Bridges 16
Current Long Span Bridges 16
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Multi span suspension bridges
Multi span suspension bridgesMulti span suspension bridges
Multi span suspension bridges
 
Long Span Bridges
Long Span BridgesLong Span Bridges
Long Span Bridges
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Lec 7 pile foundation
Lec 7 pile foundationLec 7 pile foundation
Lec 7 pile foundation
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Delhi metro rail corporation project
Delhi metro rail corporation projectDelhi metro rail corporation project
Delhi metro rail corporation project
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)
 
Summer training DMRC ppt
Summer training DMRC pptSummer training DMRC ppt
Summer training DMRC ppt
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 

Similar to Metro North, Dublin - Construction Explained

Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Emma Attwood
 
PS-1 SUMMARY NHAI
PS-1 SUMMARY NHAIPS-1 SUMMARY NHAI
PS-1 SUMMARY NHAIStudent
 
rajeev kumar.pptx
rajeev kumar.pptxrajeev kumar.pptx
rajeev kumar.pptxlovish34
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaStephen McKnight
 
Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.SHWETABH SINHA
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)Adib Ramli
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
PROJECT 1 (BUILDING CONSTRUCTION 1)
PROJECT 1 (BUILDING CONSTRUCTION 1)PROJECT 1 (BUILDING CONSTRUCTION 1)
PROJECT 1 (BUILDING CONSTRUCTION 1)Crysmond Goh
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCXMekonnenAyal
 
1255 - Roy Hill Port Landside
1255 - Roy Hill Port Landside1255 - Roy Hill Port Landside
1255 - Roy Hill Port LandsideAnthony Jones
 
Site visit report
Site visit reportSite visit report
Site visit reportJıa Yıı
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh PrasadRajesh Prasad
 
Demery and assoc madison and yount street community presentation 3 4-14
Demery and assoc madison and yount street community presentation 3 4-14Demery and assoc madison and yount street community presentation 3 4-14
Demery and assoc madison and yount street community presentation 3 4-14kristinemassey
 

Similar to Metro North, Dublin - Construction Explained (20)

Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
 
PS-1 SUMMARY NHAI
PS-1 SUMMARY NHAIPS-1 SUMMARY NHAI
PS-1 SUMMARY NHAI
 
Grouting
Grouting Grouting
Grouting
 
rajeev kumar.pptx
rajeev kumar.pptxrajeev kumar.pptx
rajeev kumar.pptx
 
YAWAR HUSSAIN.pptx
YAWAR HUSSAIN.pptxYAWAR HUSSAIN.pptx
YAWAR HUSSAIN.pptx
 
ZAHEER ABASS.pptx
ZAHEER ABASS.pptxZAHEER ABASS.pptx
ZAHEER ABASS.pptx
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
 
Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
PROJECT 1 (BUILDING CONSTRUCTION 1)
PROJECT 1 (BUILDING CONSTRUCTION 1)PROJECT 1 (BUILDING CONSTRUCTION 1)
PROJECT 1 (BUILDING CONSTRUCTION 1)
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
 
1255 - Roy Hill Port Landside
1255 - Roy Hill Port Landside1255 - Roy Hill Port Landside
1255 - Roy Hill Port Landside
 
Cv Presentation
Cv PresentationCv Presentation
Cv Presentation
 
Site visit report
Site visit reportSite visit report
Site visit report
 
C V-OSAMA-Revised 2014(PDF)
C V-OSAMA-Revised 2014(PDF)C V-OSAMA-Revised 2014(PDF)
C V-OSAMA-Revised 2014(PDF)
 
VCS Resume_May 2015
VCS Resume_May 2015VCS Resume_May 2015
VCS Resume_May 2015
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh Prasad
 
Demery and assoc madison and yount street community presentation 3 4-14
Demery and assoc madison and yount street community presentation 3 4-14Demery and assoc madison and yount street community presentation 3 4-14
Demery and assoc madison and yount street community presentation 3 4-14
 

More from David H Moloney

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 David H Moloney
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824David H Moloney
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pagesDavid H Moloney
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pagesDavid H Moloney
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionDavid H Moloney
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside ConstructionDavid H Moloney
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTERDavid H Moloney
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageDavid H Moloney
 

More from David H Moloney (9)

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pages
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway Reconstruction
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside Construction
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTER
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulage
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Metro North, Dublin - Construction Explained

  • 1. Metro North Dublin Ireland, Proposed – Construction €2.4bn Included Route Programme Graphic Tunnelling Construction Stations Construction Cost Details Lengths Overall 18 km Tunnel 7.5 km Cut & Cover 2.7 km Viaduct 2.25 km Road Level 5.5 km Stations 15 Nr. Underground 9 Nr. Road Level 6 Nr. Tunnels & Underground Stations Route 3D image to show Sequence, Method & Plant. David H Moloney 29th June 2017 Purpose of presentation to give the Public, Stakeholders and Politicians an understanding of the Construction, Cost and Timeline ⓒ David H Moloney Schematic Longitudinal Profile Project Execution Plan Details of how a Metro is constructed, and how the progress, safety and quality will be monitored and controlled.
  • 4. Route of Metro North ⓒ David H Moloney
  • 5. Schematic with Principal Quantities David H Moloney Schematic Longitudinal Profile ⓒ David H Moloney
  • 6. Programme - Time Chainage Diagram ⓒ David H Moloney
  • 7. Tunnels & Underground Stations TBM TBM Tunnel Tunnel TunnelViaduct Along Street Programme Animation ⓒ David H Moloney Schematic Longitudinal Profile
  • 8. Cost Comparisons of Metro Projects Dubai Route 2020 UAE (To Start) Red Line North Doha Qatar (In Progress) Red Line South Doha Qatar ( In Progress) Metro North Dublin (Proposed) Dart Underground Dublin (Proposed) Port Tunnel Dublin (2005) Overall Cost €2,450 million €1,803 million €1,500 million €2,400 million €2,000 million ? €752 million Cost per km €158 million /k m €140 million / km €108 million / km €134 million / km €400 million / km ? €134 million / km Overall Length 15.5 km 13 km 14m 18 km 5 km 5.6 km Tunnel 4 km Single Tunnel 11.6 km Twin Tunnels 14 km Twin Tunnels 7.5 km Twin Tunnels 5 km Twin Tunnel 4.5 km Road Tunnel x 2 Cut & Cover 0 2.7 km 0 Elevated 10.5 km 2.2 km 0 Not applicable Road Level 0 5.5 km 0 Stations 7 Nr. 7 Nr. 5 Nr. 14 Nr. 3 Nr. Not applicable Capacity 13,000 Passengers per hour 19,800 Passengers per hour ? Not applicable ⓒ David H Moloney
  • 9. Advantages of Rail Benefits of Metro to commuters 1. Time saving for commuters 4. Reduction in accident 2. Reliable and safe journey 5. Reduced fuel consumption 3. Reduction in atmospheric pollution 6. Reduced traffic congestion
  • 11. Contractor’s Temporary Site Facilities ⓒ David H Moloney Brief Description Contractors Site facilities comprise: Offices, Canteens, Toilets, Drying Rooms, Stores, Plant Yard, generators and Workshops. GeneralItems
  • 12. Concrete Batching Plant David H Moloney ⓒ David H Moloney Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production
  • 13. Quarry & Aggregate Production 3D image to show Sequence, Method & Plant. ⓒ David H Moloney
  • 14. Reinforcement Cutting & Bending Yard David H Moloney ⓒ David H Moloney Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
  • 15. Site Hoarding examples ⓒ David H Moloney GeneralItems
  • 17. Weighbridge & Sheeting Access ⓒ David H Moloney GeneralItems
  • 18. Sheet Pile Temporary Shaft ⓒ David H Moloney GeneralItems Brief Description Sheet Pile Temporary shaft is used to enable an excavation for a deep structure. The construction sequence is: Install sheet-piles. Excavate and install bracing. Excavate to final level. Construct concrete structure. Backfill, remove bracing and sheet-piles
  • 19. Sheet Pile Temporary Shaft ⓒ David H Moloney GeneralItems 3D Animation to show Sequence
  • 21. Dewatering ⓒ David H Moloney GeneralItems Brief Description Construction dewatering is the removal or drainage of groundwater and or surface / rain water usually by pumping to keep the works dry.
  • 22. Dewatering ⓒ David H Moloney GeneralItems
  • 23. Dewatering by Wellpoints ⓒ David H Moloney GeneralItems
  • 24. Dust Suppression ⓒ David H Moloney GeneralItems
  • 25. Temporary Fence type 2 ⓒ David H Moloney GeneralItems Brief Description Temporary fence on precast beam for airport.
  • 26. Traffic Management ⓒ David H Moloney GeneralItems Brief Description Traffic management plans are necessary when working on or beside roads
  • 27. Traffic Management - Realign Motorway under new Bridges ⓒ David H Moloney GeneralItems
  • 28. Health, Safety & Environmental
  • 29. Existing Underground Utilities ⓒ David H Moloney Earthworks Brief Description Before digging establish the location and route of underground utilities. Locator to find Utilities Spray Paint to mark pavement
  • 30. Existing Underground Utilities & Overhead Cables - Safety Measures ⓒ David H Moloney Earthworks
  • 32. HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of current HSE Issues and historical trends
  • 33. Environmentally Friendly Site Air, Noise, Water & Soil Pollution
  • 36. Diaphragm Wall Construction - Sequence, Plant & Methods 3D image to show Sequence, Method & Plant. For construction details see my YouTube Channel ⓒ David H Moloney
  • 38. Tunnels & Underground Stations 3D image to show Sequence, Method & Plant. David H Moloney ⓒ David H Moloney
  • 39. Excavate & Load, Cart, Tip & Return Brief Description Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes Earthworks 7 minutes 14 minutes 3 minutes 14 minutes 7 km 7 km
  • 42. Rock Excavation Underground Excavate with Roadheader Drill & Fit Rock Bolts Spray Mortar as Lining Excavators with Rock Breaker & Rock Rotary Cutter Roadheader ⓒ David H Moloney Using Mining Techniques
  • 43. Bed Rock - Type & Depth Ground Conditions The limestone bedrock is between 5 and 25 metres below ground level. The overlying deposits are generally boulder clay with thin layers of sand and gravel. The water table is between 2 and 4 metres below ground level. The Bedrock Geology Map of Ireland, gives the rock as limestone and mudstone, along the tunnel route.
  • 44. Rock - Excavability Brief Description The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face. ⓒ David H Moloney Earthworks
  • 45. Station Excavation - Soil on Rock Situation Rock Nailing, Rock breaking & Excavation ⓒ David H Moloney
  • 47. Tunnel Wall Segments Casting Clean Mould Lift Precast Segment out of mould after 18 hours. Reinforcement fabricate Reinforcement into Mould Concreting Segment Storage Casting Cycle Time 24 hrs ⓒ David H Moloney
  • 49. Reinforced Wall Construction Sequence ⓒ David H Moloney Concrete Brief Description The sequence to construct a reinforced concrete wall is as follows: Tie the reinforcement. Erect stop-ends and the wall shutters. Pour and vibrate the concrete mix. Remove the shutters after the concrete has hardened. . Cycle Time Pour per Day
  • 50. Reinforced Wall Construction Sequence ⓒ David H Moloney Concrete
  • 51. Reinforced Structure Construction Sequence ⓒ David H Moloney Concrete Brief Description The general sequence to construct a reinforced concrete tank is as follows- 1. Construct the floor and wall panels in a hit and miss pattern. 2. Construct the floor and wall corners and T shape panels. 3. Construct the roof working outwards from the back.
  • 52. Reinforced Structure Construction Sequence David H Moloney ⓒ David H Moloney
  • 53. Bridge & Post-tensioning Concrete Brief Description The sequence to post-tension a bridge deck is as follows; Fix the ducts and anchorages. Install the stressing strand. Concrete the deck. Stress the strands and lock at anchorages. Grout the ducts.
  • 56. Bridge Construction Sequence David H Moloney Piling Surcharge Abutments Remove Surcharge Abutments Deck centre Post-tensioning Fascia & Waterproof deck Complete Bridge PiersOverview Deck Ends Images with Schematic 3D view, Photos & Timeline ⓒ David H Moloney
  • 57. Post-tensioning Bridge Deck David H Moloney
  • 58. Waterproofing Spray on System Miscellaneous
  • 59. Waterproofing Spray on Tests Miscellaneous
  • 60. Underground Stations David H Moloney ⓒ David H Moloney
  • 62. Rail Viaduct Concrete Brief Description Shown is the construction of a light rail viaduct where an overhead gantry was used to lift and place the precast concrete viaduct segments.
  • 63. Viaduct Construction 3D image to show Sequence, Method & Plant. For construction details see my YouTube Channel David H Moloney ⓒ David H Moloney
  • 64. Viaduct Construction David H Moloney ⓒ David H Moloney
  • 66. Viaduct Segments Casting David H Moloney Casting Method The concrete segments are manufactured using the short-line, match-casting method. Match-casting is when sequential segments are poured against the previous cast segment, this ensures that the segments will fit perfectly on site. Horizontal and vertical curves are achieved by setting the cast segment at a rotation in either or both axis to the mould used to cast the next segment. ⓒ David H Moloney
  • 67. Viaduct Segments – Short-line, Match Casting Method David H MoloneyMatch-casting is when sequential segments are poured against the previous cast segment, this ensures that the segments will fit perfectly on site. Cycle Time 24 hrs
  • 69. Piling Construction - Plant & Methods Brief Description Piling Plant, Equipment and Material; Crawler Crane, Piling Hammer, Temporary Casing, Piling Rig, Concrete Pump, Concrete Mixer Trucks, Tremie Pipe and Reinforcement Cage Piling
  • 70. Piling Construction - Plant, Methods & SequencePiling
  • 71. Piling Construction - Plant & MethodsPiling
  • 72. Piling Construction - Vertical PilesPiling
  • 73. Piling Construction - Raking PilesPiling
  • 74. Piling Construction - Raking PilesPiling
  • 75. Pile Load Test ⓒ David H Moloney Piling Brief Description A jack is used to load the pile in steps and gauges measure any settlement.
  • 76. Secant Pile Construction - Sequence, Plant & Methods 3D image to show Sequence, Method & Plant. For construction details see my YouTube Channel ⓒ David H Moloney
  • 81. Tunnel Design Twin Tunnels single track with Cross passages at 250m intervals for emergency evacuation Tunnels in rock to avoid ground & building settlement. Depth 25 metres on average ⓒ David H Moloney
  • 82. Cut & Cover Tunnel Construction Sequence -Traffic and utilities are diverted, excavate trench, construct & backfill to bury. To prevent the faces of the excavation from collapsing, different measures are used – batter the faces, diaphragm walls, secant piles or a combination of soil nailing and shotcreting.
  • 83. Ramp Construction Sequence -Traffic and utilities are diverted, excavate, construct and backfill to sides. To prevent the faces of the excavation from collapsing, different measures are used – batter faces, diaphragm walls, secant piles or a combination of soil nailing and shotcreting. ⓒ David H Moloney
  • 84. Tunnel Boring Machine (TBM) Cutting Head rotates to Dig Excavated material removed by conveyor belt Lifting muck to surface with skip Placing Concrete Segments
  • 85. Tunnel Boring Machine (TBM) Cutting Head rotates 7 nr. Precast segments form rings that line the tunnel Excavated material removed by conveyor belt ⓒ David H Moloney
  • 86. Tunnel Fit-out Rail, Electricals, Ventilation
  • 87. Tunnel Fit-out Install Sleepers & Rails Concrete Batching Train for Floor Slab Drilling Machine for Utilities Brackets
  • 88. Commissioning, Testing, Handover & Opening Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should. ⓒ David H Moloney
  • 90. Fencing ⓒ David H Moloney Sequence of Construction Clear Scrub & Grade ground Fix Corner & Strainer Posts Fix Intermediate Posts Fix Line Wire, Chain-link & Razer wire Concrete ground beam
  • 91. Progress Monthly, Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of current progress and historical trends
  • 92. Histogram Charts for Resources & Outputs Concrete, Manpower, TBM, Manpower per Discipline Concrete per Location Numbers for each month of the Project Quantity for each month of the Project ⓒ David H Moloney
  • 93. Plant & Equipment List & Worker’s Job Titles ⓒ David H Moloney
  • 94. Organogram Brief Description Shown are the line and lateral relationships between the various team members and their relative position in the site organisation.
  • 96. Luas – Dublin, Tram / Light Rail System Construction Sequence & Methods Install Traffic Control Fencing & Welfare Facilities Divert Underground Utilities Excavate Prepare Formation Reinforcement & Rails Paving Paving Information Sign Trams in Operation Trams in Operation Reinforcement & Rails ⓒ David H Moloney
  • 97. Production by David H Moloney See my YouTube Video on Dublin Metro North My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ ⓒ David H Moloney