SlideShare a Scribd company logo
Structural Design of bridge
and Culvert
SDE. Prabhat Kumar Jha
Department of Road
9841360244
Structural design of bridge:
• solid slab bridges, deck girder bridges, B.M. in slab
supported on four edges, distribution of live loads on
longitudinal beams, method of distribution
coefficients, Courbon’s method,
• design of a T- beam bridge, balanced cantilever bridge,
Design of box culvertDesign of box culvert
Solid Slab Bridge
Generally for Span <10m
The simplest form of R.C.C. bridges in which the deck
spans between the abutments as a simply supported
one-way slab.
Bending moments and shear force are determined
separately for dead load and live loads.
The design B.M, obtained by adding the B.M due to dead
loads and live load, governs the thickness of slab and
the area of main reinforcement.
• Solid Slab Bridge
The live load to be considered in the design of bridges
consists of concentrated wheel loads due to trains of
different types of heavy vehicles following each other
closely (viz, class AA, class A or class B loading).
The analysis of a slab spanning in one or two directions andThe analysis of a slab spanning in one or two directions and
carrying concentrated load may be carried out by any one of
the rational method like
(i)Pigeaud’s theory
(ii)Westergaurd’s method and
(iii)Effective width method.
• Solid Slab Bridge
7.5m1m W W
Dead Load Bending Moment = w l2 / 8
Live Load Bending Moment by Pigeaud’s theory/Curve
10m
Effective depth required :
d = Sqrt [BM / (R x b)]
Area of Reinforcement required
:
= M / (j x d x σst )
R = Moment of Resistance factor
= 0.5 (σcbc . j . K)
d = effective depth
j = lever arm factor = (1- k/3)
k = neutral axis factor = n/d
= (m. σcbc )/(m. σcbc + σst )
σst = 240 N/mm2 for fy = 500 N/mm2
Solid Slab Bridge
T-BEAM Bridge “Deck Girder Bridge”
Generally for Span >10m to 25m
The deck Slab is cast monolithically with Longitudinalmonolithically with Longitudinal
GirdersGirders
Design involves :
Design of Deck Slab : Pigeaud’s theory
Design of Longitudinal Girder : Courbon's Method for Live Load
Moment and Shear Force calculation
Design of Cross Girders : Simple Beam Analysis
BM for Slab Supported on four edge
Traffic Direction
Case I : Single Load Placed centrally
Case II : a) 2 Concentric Load placed on x-axis
x
y
L
B = Short Span
Case II : b) 2 Concentric Load placed on y-axis
BM for Slab Supported on four edge
B
b
W
u=W+2D
W
u
v
v= b+ 2D
X-X
L
b
Slab Depth ,D
b
BM for Slab Supported on four edge
Case I : Single Load Placed centrally
x
y
Using Pigeaud’s Graph :
Load Placing must be
symmetrical
k = Width of Slab/Effective
Length /
For given k, related u/B Vs v/L :-
m1 and m2 determined
. IF
. IF
k = Effective Length / Width of Slab
BM for Slab Supported on four edge
Case II : a) 2 Concentric Load placed on x-axis
x
2.(u1+x) v
=DBM
2x
v
BM for Slab Supported on four edge
Case II : b) 2 Concentric Load placed on y-axis
u
2.(v1 + y)
u
2y
=DBM
70R Live Load
Case III : Single Load Placed centrally
0.85m+
2D
4.57m+2D
Class A Live Load
Case IIb
1 2
0.5m+2D
1.2m
=DBM
3
Imaginary
(For Wheel 1,3 case )/2 + Wheel 2 case
1.2m
0.25m+2D
=DBM(For Wheel 1,3 case )/2 + Wheel 2 case
Longitudinal Analysis
Calculate BM / SF for Location
L/2
3L/8
L/4
L/8
At Support
Leff. 25m
P1 27KN X1varies
P2 27KN X2 1.1m
P3 114KN X3 3.2m
P4 114KN X4 1.2m
P5 68KN X5 4.3m
P6 68KN X6 3m
P7 68KN X7 3m
P8 68KN X8 3m
Calculate BM / SF for Location
L/2
3L/8
L/4
L/8
At Support
Leff. 25m
P1 80KN X1varies
P2 120KN X2 3.96m
P3 120KN X3 1.52m
P4 170KN X4 2.13m
P5 170KN X5 1.37m
P6 170KN X6 3.05m
P7 170KN X7 1.37m
Calculate BM / SF for Location
L/2
3L/8
L/4
L/8
At Support
COURBON'S METHOD FOR ESTIMATING DISTRIBUTION
COEFFICIENTS
Courbon's method :
According to Courbon's method,
The reaction Ri of the cross beam on any girder I of a typical
bridge consisting of multiple parallel beam is computed
assuming a linear variation of deflection in the transverseassuming a linear variation of deflection in the transverse
direction.
The deflection will be maximum on the exterior girder on the
side of the eccentric load or e.g. of loads if there is a system of
concentrated loads) and minimum of the other exterior girder.
Assumptions or Conditions for Applicability of Courbon's method :
• Simply put, this method for transverse load distribution
among the deck longitudinal is applicable mainly to beam and
slab type decks which are straight in plan (no skew and no
curve).
• The longitudinal beams must be interconnection by
symmetrically spaced, rigid cross beams that are at least five
in number (one above each support, and at least three
intermediate cross beams, equally spaced) ,such that they are
in number (one above each support, and at least three
intermediate cross beams, equally spaced) ,such that they are
not more than about 9 m apart.
• The cross beams should preferably be cast monolithically
with the longitudinal or should be cast at least before any
other gravity loads (besides the self weight of the main
beams) comes on. The stiffness of cross girders is much
greater than that of the longitudinal girders.
Assumptions or Conditions for Applicability of Courbon's
method :
• The ratio of span to width is greater than 2 but less than 4 i.e.
the bridge should be longish.
• spacing between main beams should be between 2 and 4.
• The cross girders extend to a depth of at least 0.75 of the
depth of the longitudinal girders. This is done so as to avoid
• The cross girders extend to a depth of at least 0.75 of the
depth of the longitudinal girders. This is done so as to avoid
anchoring of steel which may interfere with the main steel.
• The bridge structure may have longitudinal girders of same or
different moment of inertia and may have uniform or non -
uniform girder spacing.
• Under the effect of loading, the transverse profile of the
bridge deck maintains a straight geometry.
• These conditions are usually satisfied for majority of modern T-beams bridges.
IRC Class A
IRC Class A
P/2=114/2
P/2=114/2
P/2=114/2
P/2=114/2
IRC Class A
0.4 1.8 1.81.7
7.5
7.5/2
2P
e=0.7m
x2
Inner
Inner
Outer
Outer
x1
x2
1.63 1.93
7.5
7.5/2
e=1.155m
x2
70R
P/2
P/2
Inner
Inner
Outer
Outer
x1
x2
Sample
T-Beam Designed as Singly Reinforced Beam
Effective depth required :
d = Sqrt [BM / (R x b)]
Area of Reinforcement required :
= M / (j x d x σst )
R = Moment of Resistance factor
= 0.5 (σcbc . j . K)
d = effective depth
j = lever arm factor = (1- k/3)
k = neutral axis factor = n/d
= (m. σcbc )/(m. σcbc + σst )
σst = 240 N/mm2 for fy = 500 N/mm2
σcbc= fck /3
Moment of Resistance > Design BM
Balanced Cantilever Bridge
•Design of Box Culvert
It is RCC rigid frame box culverts with square or
rectangular opening.
If 4m Span limit and height max. 3m for economy
If Q is low and Bearing Capacity is also low : Box Culvert
is preferred rather than Slab Culvert
The Top of Box Section can be at road level or can be at a
depth below.
Box is structurally very strong, rigid and safe.
Box does not need any elaborate foundation and can
easily be placed over soft foundation by increasing base
slab projection to retain base pressure within safe
bearing capacity of ground soil.
Design of Box Culvert
• V1 = Uniform Vertical Load due to Slab, Wearing Coat and or Wt. of Soil above
• V2 = Reaction of V3 and or Weight of water
• V3 = Wt. of Wall
Design of Box Culvert
• V4 = Concentrated vertical Load of Wheel = V x I / e
P = Wheel load
I = Impact factor
e = effective width of dispersion
• H1 = Earth Pressure by Coloumb’s Theory
• H2 = Water Pressure inside box =  x H
• H3 = Live load surcharge = q x Ka x ( H + Free Board )
•Design of Box Culvert
Loading Case
Mainly three load cases govern the design. These are
given below :
a) Box empty, live load surcharge on top slab of box
and superimposed surcharge load on earth fill.
b) Box inside full with water, live load surcharge onb) Box inside full with water, live load surcharge on
top slab and superimposed surcharge load on earth
fill.
c) Box inside full with water, live load surcharge on
top slab and no superimposed surcharge on earth
fill.
Design of Box Culvert
The bending moment is obtained by
moment distribution considering all the cell
or cells together for different combination
of loading and design of section
accomplished for final bending momentsaccomplished for final bending moments
for that member.
EffectivedepthrequiredforWallorSlab
d=Sqrt[BM/(Rx1000)]mm
AreaofReinforcementrequiredforWallorSlab
=M/(jxdx
EffectivedepthrequiredforWallorSlab
d=Sqrt[BM/(Rx1000)]mm
AreaofReinforcementrequiredforWallorSlab
=M/(jxdxσst)

More Related Content

What's hot

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Pooja Lonare
 
52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girdersSaleem Malik
 
Watertank
WatertankWatertank
Watertank
Shawon Aziz
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
Penchala Vineeth
 
Box culvert
Box culvertBox culvert
Gravity Dam
Gravity DamGravity Dam
Design of rcc structures note
Design of rcc structures noteDesign of rcc structures note
Design of rcc structures note
Mahendra Poudel
 
Intze ppt
Intze pptIntze ppt
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
hatim ahmed
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdf
Gaurav Rawat
 
Limit state, working stress, ultimate load method - Detailed Concept
Limit state, working stress, ultimate load method - Detailed ConceptLimit state, working stress, ultimate load method - Detailed Concept
Limit state, working stress, ultimate load method - Detailed Concept
Civil Insider
 
Losses in prestressed concrete
Losses in prestressed concreteLosses in prestressed concrete
Losses in prestressed concrete
Shubham Singh [NITK]
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
sarhad university peshawer
 
Slope deflection method
Slope deflection methodSlope deflection method
Slope deflection methodAnik Mamun
 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000
PraveenKumar Shanmugam
 
Lined canal ppt
Lined canal ppt Lined canal ppt
Lined canal ppt
Anand Kumar
 
Bridge architecture and economic sapn 1
Bridge architecture and economic sapn 1Bridge architecture and economic sapn 1
Bridge architecture and economic sapn 1
SaadKhot1
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
Yash Patel
 

What's hot (20)

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders
 
Watertank
WatertankWatertank
Watertank
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Box culvert
Box culvertBox culvert
Box culvert
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
Design of rcc structures note
Design of rcc structures noteDesign of rcc structures note
Design of rcc structures note
 
Intze ppt
Intze pptIntze ppt
Intze ppt
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdf
 
Limit state, working stress, ultimate load method - Detailed Concept
Limit state, working stress, ultimate load method - Detailed ConceptLimit state, working stress, ultimate load method - Detailed Concept
Limit state, working stress, ultimate load method - Detailed Concept
 
Losses in prestressed concrete
Losses in prestressed concreteLosses in prestressed concrete
Losses in prestressed concrete
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
 
Slope deflection method
Slope deflection methodSlope deflection method
Slope deflection method
 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000
 
Lined canal ppt
Lined canal ppt Lined canal ppt
Lined canal ppt
 
Bridge architecture and economic sapn 1
Bridge architecture and economic sapn 1Bridge architecture and economic sapn 1
Bridge architecture and economic sapn 1
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
 

Similar to 1.5 class c,d,e

BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
srinivas cnu
 
about dam of archi that is cost effective
about dam of archi that is cost effectiveabout dam of archi that is cost effective
about dam of archi that is cost effective
FikaduDebiso
 
PRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptxPRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptx
kuba9
 
Presentation on Slab, Beam, Column, and Foundation/Footing
Presentation on Slab,  Beam, Column, and Foundation/FootingPresentation on Slab,  Beam, Column, and Foundation/Footing
Presentation on Slab, Beam, Column, and Foundation/Footing
Dhaka University of Engineering & Technology, Gazipur
 
any
anyany
Bridge
Bridge Bridge
Bridge illpa
 
Tony
TonyTony
Tony
TONY ROSE
 
boxculvert-191203173959.pdf
boxculvert-191203173959.pdfboxculvert-191203173959.pdf
boxculvert-191203173959.pdf
lancersphine
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
abdqadeer
 
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiUrsachi Răzvan
 
MULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKINGMULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKING
Manoj Navneeth
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
PranotiHunungare
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Hossam Shafiq II
 
Acm Space Frames
Acm Space FramesAcm Space Frames
Acm Space Frames
Aaqib Iqbal
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
Abhinav Pateriya
 
stress ribbon bridge by kaiser malik
stress ribbon bridge by kaiser  malikstress ribbon bridge by kaiser  malik
stress ribbon bridge by kaiser malik
junaid bashir
 
Prsesntation on Commercial building Project
Prsesntation on Commercial building ProjectPrsesntation on Commercial building Project
Prsesntation on Commercial building Project
MD AFROZ ALAM
 

Similar to 1.5 class c,d,e (20)

BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
10.01.03.160
10.01.03.16010.01.03.160
10.01.03.160
 
about dam of archi that is cost effective
about dam of archi that is cost effectiveabout dam of archi that is cost effective
about dam of archi that is cost effective
 
PRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptxPRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptx
 
Presentation on Slab, Beam, Column, and Foundation/Footing
Presentation on Slab,  Beam, Column, and Foundation/FootingPresentation on Slab,  Beam, Column, and Foundation/Footing
Presentation on Slab, Beam, Column, and Foundation/Footing
 
any
anyany
any
 
Reinforced slab
Reinforced slabReinforced slab
Reinforced slab
 
Bridge
Bridge Bridge
Bridge
 
Tony
TonyTony
Tony
 
Intze PPT
Intze PPTIntze PPT
Intze PPT
 
boxculvert-191203173959.pdf
boxculvert-191203173959.pdfboxculvert-191203173959.pdf
boxculvert-191203173959.pdf
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
 
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
 
MULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKINGMULTI-STOREY CAR PARKING
MULTI-STOREY CAR PARKING
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
 
Acm Space Frames
Acm Space FramesAcm Space Frames
Acm Space Frames
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 
stress ribbon bridge by kaiser malik
stress ribbon bridge by kaiser  malikstress ribbon bridge by kaiser  malik
stress ribbon bridge by kaiser malik
 
Prsesntation on Commercial building Project
Prsesntation on Commercial building ProjectPrsesntation on Commercial building Project
Prsesntation on Commercial building Project
 

More from Mani Das

201911121130435dca470798b5a1
201911121130435dca470798b5a1201911121130435dca470798b5a1
201911121130435dca470798b5a1
Mani Das
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
Mani Das
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067
Mani Das
 
Survey handsout question for sub er and asst
Survey handsout question for sub er and asstSurvey handsout question for sub er and asst
Survey handsout question for sub er and asst
Mani Das
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete note
Mani Das
 
Chapter 5 average
Chapter 5 averageChapter 5 average
Chapter 5 average
Mani Das
 
Chap 2 classification
Chap 2 classificationChap 2 classification
Chap 2 classification
Mani Das
 
Chap 1 table chart
Chap 1 table chartChap 1 table chart
Chap 1 table chart
Mani Das
 
Chap 1 arithmetical reasoning
Chap 1 arithmetical reasoningChap 1 arithmetical reasoning
Chap 1 arithmetical reasoning
Mani Das
 
Chap 1 analogy
Chap 1 analogyChap 1 analogy
Chap 1 analogy
Mani Das
 
Irrigation and hydrology
Irrigation and hydrologyIrrigation and hydrology
Irrigation and hydrology
Mani Das
 
High way
High wayHigh way
High way
Mani Das
 
Group c airport converted
Group c airport convertedGroup c airport converted
Group c airport converted
Mani Das
 
Group d converted
Group d convertedGroup d converted
Group d converted
Mani Das
 
9.epp
9.epp9.epp
9.epp
Mani Das
 
8.drawing technicue
8.drawing technicue8.drawing technicue
8.drawing technicue
Mani Das
 
7.surveying
7.surveying7.surveying
7.surveying
Mani Das
 
6.eastimating and costing
6.eastimating and costing6.eastimating and costing
6.eastimating and costing
Mani Das
 
5.economics
5.economics5.economics
5.economics
Mani Das
 
4. construction management
4. construction management4. construction management
4. construction management
Mani Das
 

More from Mani Das (20)

201911121130435dca470798b5a1
201911121130435dca470798b5a1201911121130435dca470798b5a1
201911121130435dca470798b5a1
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067
 
Survey handsout question for sub er and asst
Survey handsout question for sub er and asstSurvey handsout question for sub er and asst
Survey handsout question for sub er and asst
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete note
 
Chapter 5 average
Chapter 5 averageChapter 5 average
Chapter 5 average
 
Chap 2 classification
Chap 2 classificationChap 2 classification
Chap 2 classification
 
Chap 1 table chart
Chap 1 table chartChap 1 table chart
Chap 1 table chart
 
Chap 1 arithmetical reasoning
Chap 1 arithmetical reasoningChap 1 arithmetical reasoning
Chap 1 arithmetical reasoning
 
Chap 1 analogy
Chap 1 analogyChap 1 analogy
Chap 1 analogy
 
Irrigation and hydrology
Irrigation and hydrologyIrrigation and hydrology
Irrigation and hydrology
 
High way
High wayHigh way
High way
 
Group c airport converted
Group c airport convertedGroup c airport converted
Group c airport converted
 
Group d converted
Group d convertedGroup d converted
Group d converted
 
9.epp
9.epp9.epp
9.epp
 
8.drawing technicue
8.drawing technicue8.drawing technicue
8.drawing technicue
 
7.surveying
7.surveying7.surveying
7.surveying
 
6.eastimating and costing
6.eastimating and costing6.eastimating and costing
6.eastimating and costing
 
5.economics
5.economics5.economics
5.economics
 
4. construction management
4. construction management4. construction management
4. construction management
 

Recently uploaded

TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

1.5 class c,d,e

  • 1. Structural Design of bridge and Culvert SDE. Prabhat Kumar Jha Department of Road 9841360244
  • 2. Structural design of bridge: • solid slab bridges, deck girder bridges, B.M. in slab supported on four edges, distribution of live loads on longitudinal beams, method of distribution coefficients, Courbon’s method, • design of a T- beam bridge, balanced cantilever bridge, Design of box culvertDesign of box culvert
  • 3. Solid Slab Bridge Generally for Span <10m The simplest form of R.C.C. bridges in which the deck spans between the abutments as a simply supported one-way slab. Bending moments and shear force are determined separately for dead load and live loads. The design B.M, obtained by adding the B.M due to dead loads and live load, governs the thickness of slab and the area of main reinforcement.
  • 4. • Solid Slab Bridge The live load to be considered in the design of bridges consists of concentrated wheel loads due to trains of different types of heavy vehicles following each other closely (viz, class AA, class A or class B loading). The analysis of a slab spanning in one or two directions andThe analysis of a slab spanning in one or two directions and carrying concentrated load may be carried out by any one of the rational method like (i)Pigeaud’s theory (ii)Westergaurd’s method and (iii)Effective width method.
  • 5. • Solid Slab Bridge 7.5m1m W W Dead Load Bending Moment = w l2 / 8 Live Load Bending Moment by Pigeaud’s theory/Curve 10m Effective depth required : d = Sqrt [BM / (R x b)] Area of Reinforcement required : = M / (j x d x σst ) R = Moment of Resistance factor = 0.5 (σcbc . j . K) d = effective depth j = lever arm factor = (1- k/3) k = neutral axis factor = n/d = (m. σcbc )/(m. σcbc + σst ) σst = 240 N/mm2 for fy = 500 N/mm2
  • 7. T-BEAM Bridge “Deck Girder Bridge” Generally for Span >10m to 25m The deck Slab is cast monolithically with Longitudinalmonolithically with Longitudinal GirdersGirders Design involves : Design of Deck Slab : Pigeaud’s theory Design of Longitudinal Girder : Courbon's Method for Live Load Moment and Shear Force calculation Design of Cross Girders : Simple Beam Analysis
  • 8. BM for Slab Supported on four edge Traffic Direction Case I : Single Load Placed centrally Case II : a) 2 Concentric Load placed on x-axis x y L B = Short Span Case II : b) 2 Concentric Load placed on y-axis
  • 9. BM for Slab Supported on four edge B b W u=W+2D W u v v= b+ 2D X-X L b Slab Depth ,D b
  • 10. BM for Slab Supported on four edge Case I : Single Load Placed centrally x y Using Pigeaud’s Graph : Load Placing must be symmetrical k = Width of Slab/Effective Length / For given k, related u/B Vs v/L :- m1 and m2 determined . IF . IF
  • 11.
  • 12. k = Effective Length / Width of Slab
  • 13. BM for Slab Supported on four edge Case II : a) 2 Concentric Load placed on x-axis x 2.(u1+x) v =DBM 2x v
  • 14. BM for Slab Supported on four edge Case II : b) 2 Concentric Load placed on y-axis u 2.(v1 + y) u 2y =DBM
  • 15. 70R Live Load Case III : Single Load Placed centrally 0.85m+ 2D 4.57m+2D
  • 16. Class A Live Load Case IIb 1 2 0.5m+2D 1.2m =DBM 3 Imaginary (For Wheel 1,3 case )/2 + Wheel 2 case 1.2m 0.25m+2D =DBM(For Wheel 1,3 case )/2 + Wheel 2 case
  • 18. Calculate BM / SF for Location L/2 3L/8 L/4 L/8 At Support
  • 19. Leff. 25m P1 27KN X1varies P2 27KN X2 1.1m P3 114KN X3 3.2m P4 114KN X4 1.2m P5 68KN X5 4.3m P6 68KN X6 3m P7 68KN X7 3m P8 68KN X8 3m Calculate BM / SF for Location L/2 3L/8 L/4 L/8 At Support
  • 20. Leff. 25m P1 80KN X1varies P2 120KN X2 3.96m P3 120KN X3 1.52m P4 170KN X4 2.13m P5 170KN X5 1.37m P6 170KN X6 3.05m P7 170KN X7 1.37m Calculate BM / SF for Location L/2 3L/8 L/4 L/8 At Support
  • 21.
  • 22. COURBON'S METHOD FOR ESTIMATING DISTRIBUTION COEFFICIENTS Courbon's method : According to Courbon's method, The reaction Ri of the cross beam on any girder I of a typical bridge consisting of multiple parallel beam is computed assuming a linear variation of deflection in the transverseassuming a linear variation of deflection in the transverse direction. The deflection will be maximum on the exterior girder on the side of the eccentric load or e.g. of loads if there is a system of concentrated loads) and minimum of the other exterior girder.
  • 23. Assumptions or Conditions for Applicability of Courbon's method : • Simply put, this method for transverse load distribution among the deck longitudinal is applicable mainly to beam and slab type decks which are straight in plan (no skew and no curve). • The longitudinal beams must be interconnection by symmetrically spaced, rigid cross beams that are at least five in number (one above each support, and at least three intermediate cross beams, equally spaced) ,such that they are in number (one above each support, and at least three intermediate cross beams, equally spaced) ,such that they are not more than about 9 m apart. • The cross beams should preferably be cast monolithically with the longitudinal or should be cast at least before any other gravity loads (besides the self weight of the main beams) comes on. The stiffness of cross girders is much greater than that of the longitudinal girders.
  • 24. Assumptions or Conditions for Applicability of Courbon's method : • The ratio of span to width is greater than 2 but less than 4 i.e. the bridge should be longish. • spacing between main beams should be between 2 and 4. • The cross girders extend to a depth of at least 0.75 of the depth of the longitudinal girders. This is done so as to avoid • The cross girders extend to a depth of at least 0.75 of the depth of the longitudinal girders. This is done so as to avoid anchoring of steel which may interfere with the main steel. • The bridge structure may have longitudinal girders of same or different moment of inertia and may have uniform or non - uniform girder spacing. • Under the effect of loading, the transverse profile of the bridge deck maintains a straight geometry.
  • 25. • These conditions are usually satisfied for majority of modern T-beams bridges.
  • 26. IRC Class A IRC Class A P/2=114/2 P/2=114/2 P/2=114/2 P/2=114/2 IRC Class A 0.4 1.8 1.81.7 7.5 7.5/2 2P e=0.7m x2 Inner Inner Outer Outer x1 x2
  • 29. T-Beam Designed as Singly Reinforced Beam Effective depth required : d = Sqrt [BM / (R x b)] Area of Reinforcement required : = M / (j x d x σst ) R = Moment of Resistance factor = 0.5 (σcbc . j . K) d = effective depth j = lever arm factor = (1- k/3) k = neutral axis factor = n/d = (m. σcbc )/(m. σcbc + σst ) σst = 240 N/mm2 for fy = 500 N/mm2 σcbc= fck /3
  • 30.
  • 31. Moment of Resistance > Design BM
  • 33. •Design of Box Culvert It is RCC rigid frame box culverts with square or rectangular opening. If 4m Span limit and height max. 3m for economy If Q is low and Bearing Capacity is also low : Box Culvert is preferred rather than Slab Culvert The Top of Box Section can be at road level or can be at a depth below. Box is structurally very strong, rigid and safe. Box does not need any elaborate foundation and can easily be placed over soft foundation by increasing base slab projection to retain base pressure within safe bearing capacity of ground soil.
  • 34. Design of Box Culvert • V1 = Uniform Vertical Load due to Slab, Wearing Coat and or Wt. of Soil above • V2 = Reaction of V3 and or Weight of water • V3 = Wt. of Wall
  • 35. Design of Box Culvert • V4 = Concentrated vertical Load of Wheel = V x I / e P = Wheel load I = Impact factor e = effective width of dispersion • H1 = Earth Pressure by Coloumb’s Theory • H2 = Water Pressure inside box =  x H • H3 = Live load surcharge = q x Ka x ( H + Free Board )
  • 36. •Design of Box Culvert Loading Case Mainly three load cases govern the design. These are given below : a) Box empty, live load surcharge on top slab of box and superimposed surcharge load on earth fill. b) Box inside full with water, live load surcharge onb) Box inside full with water, live load surcharge on top slab and superimposed surcharge load on earth fill. c) Box inside full with water, live load surcharge on top slab and no superimposed surcharge on earth fill.
  • 37. Design of Box Culvert The bending moment is obtained by moment distribution considering all the cell or cells together for different combination of loading and design of section accomplished for final bending momentsaccomplished for final bending moments for that member.