Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an Airport.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Site Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.
High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD).
This Video Presentation is innovative and has many beneficial uses.
Can be used for Tender Presentations and to substantiate entitlement for additional payments.
Characteristics of good seaport and principles of seaport planning, size of seaport, site selection criteria and layout of seaport, Dry ports, Bulk cargo, Transshipment ports, Port of call, Surveys to be carried out for seaport planning, regional and intercontinental transportation development, forecasting cargo & passenger demand, regional connectivity, cargo handling capacity of port.
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity . For more details u can contact me on my mail id -shuklaakhilesh08@gmail.com
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an Airport.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Site Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.
High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD).
This Video Presentation is innovative and has many beneficial uses.
Can be used for Tender Presentations and to substantiate entitlement for additional payments.
Characteristics of good seaport and principles of seaport planning, size of seaport, site selection criteria and layout of seaport, Dry ports, Bulk cargo, Transshipment ports, Port of call, Surveys to be carried out for seaport planning, regional and intercontinental transportation development, forecasting cargo & passenger demand, regional connectivity, cargo handling capacity of port.
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity . For more details u can contact me on my mail id -shuklaakhilesh08@gmail.com
For innovation in construction, use video presentations with 3D animations to plan and communicate how a project will be carried out and the timeline. This presentation can be used to communicate with the Client, Stakeholders and Site Team.
Project Execution Plan for Bridge ConstructionDavid H Moloney
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an insitu concrete bridge.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)
This Presentation is innovative and has many beneficial uses.
Show how different projects were constructed, generally the construction methods, sequence and plant are included. The information is presented in a way that is easily understood and explained.
A Portfolio showing my career path Until 1/1/2020, It was demanded by an Hr manager from me and here it is just packed to her. I'm sharing it to everyone for the sake of sharing and also if anyone want to make a portfolio like this just contact me on whatsapp or my email
+201143346363
mahmoud3adel.aamer@gmail.com
t the end of this workshop participants will be able to:
Anticipate future traffic problems of a transportation network
Understand the use and limitations of various modes of transportation and learn a technique to design an efficient transportation system by combination of these
Understand the concept of Level of Service of the transport system and techniques to maintain those within acceptable limits
Obtain guidance in the traffic control systems and their use during special events as well as during construction
Develop an intelligent transportation system as well as efficient parking system
Be aware of and be able to evaluate the effects of any new development on the adjacent traffic network
Understanding the concepts of traffic calming, forecasts, traffic management systems
Acquire a basic knowledge of standards of transportation safety
Obtain sufficient knowledge to manage traffic in your small neighborhood/ complex/construction site
WHO SHOULD ATTEND?
Architects
Builders and developers
Civil engineers
Development control officers
Engineers and technicians in charge of a construction site
Town planners
Traffic control authorities of big events
http://www.idc-online.com/content/transportation-planning-and-management-27
Factors for success of a construction project_Construction Management (218061...A Makwana
As the construction projects involve high costs and use of millions of man hours, it becomes duty of the engineers to see that the project is successful and fulfils the intended purposes.
Harbour engineering - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
Definition of Basic Terms: Harbour, Port, Satellite Port, Docks, Waves and Tides – Planning and Design of Harbours: Harbour Layout and Terminal Facilities – Coastal Structures: Piers, Break waters, Wharves, Jetties, Quays, Spring Fenders, Dolphins and Floating Landing Stage – Inland Water Transport – Wave action on Coastal Structures and Coastal Protection Works – Coastal Regulation Zone, 2011
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
For innovation in construction, use video presentations with 3D animations to plan and communicate how a project will be carried out and the timeline. This presentation can be used to communicate with the Client, Stakeholders and Site Team.
Project Execution Plan for Bridge ConstructionDavid H Moloney
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an insitu concrete bridge.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)
This Presentation is innovative and has many beneficial uses.
Show how different projects were constructed, generally the construction methods, sequence and plant are included. The information is presented in a way that is easily understood and explained.
A Portfolio showing my career path Until 1/1/2020, It was demanded by an Hr manager from me and here it is just packed to her. I'm sharing it to everyone for the sake of sharing and also if anyone want to make a portfolio like this just contact me on whatsapp or my email
+201143346363
mahmoud3adel.aamer@gmail.com
t the end of this workshop participants will be able to:
Anticipate future traffic problems of a transportation network
Understand the use and limitations of various modes of transportation and learn a technique to design an efficient transportation system by combination of these
Understand the concept of Level of Service of the transport system and techniques to maintain those within acceptable limits
Obtain guidance in the traffic control systems and their use during special events as well as during construction
Develop an intelligent transportation system as well as efficient parking system
Be aware of and be able to evaluate the effects of any new development on the adjacent traffic network
Understanding the concepts of traffic calming, forecasts, traffic management systems
Acquire a basic knowledge of standards of transportation safety
Obtain sufficient knowledge to manage traffic in your small neighborhood/ complex/construction site
WHO SHOULD ATTEND?
Architects
Builders and developers
Civil engineers
Development control officers
Engineers and technicians in charge of a construction site
Town planners
Traffic control authorities of big events
http://www.idc-online.com/content/transportation-planning-and-management-27
Factors for success of a construction project_Construction Management (218061...A Makwana
As the construction projects involve high costs and use of millions of man hours, it becomes duty of the engineers to see that the project is successful and fulfils the intended purposes.
Harbour engineering - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
Definition of Basic Terms: Harbour, Port, Satellite Port, Docks, Waves and Tides – Planning and Design of Harbours: Harbour Layout and Terminal Facilities – Coastal Structures: Piers, Break waters, Wharves, Jetties, Quays, Spring Fenders, Dolphins and Floating Landing Stage – Inland Water Transport – Wave action on Coastal Structures and Coastal Protection Works – Coastal Regulation Zone, 2011
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
Project Execution Plan for High Rise BuildingDavid H Moloney
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a high-rise building.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
India has a coastline which is more than 7,517 km long, interspersed with more than 200 ports. Most cargo ships that sail between East Asia and America, Europe and Africa pass through Indian territorial waters.
There are 13 major and about 200 non-major ports in the country. The total cargo traffic in India stood at 911.5 million metric tonnes (MMT) during FY12 and is expected to touch 1,758 MMT by FY17. Port traffic at major and non-major ports in India is set to rise at a compound annual growth rate (CAGR) of 22 per cent and 5.5 per cent respectively over FY12-14.
The rising demand for port infrastructure, strong growth potential, favourable investment climate, and sops provided by state governments provide private players with an opportunity to enter the Indian ports sector to serve the spill-off demand from major ports. During FY13, 29 projects are scheduled to be executed adding capacity of 208 million tonnes per annum (MTPA) at the cost of US$ 8.8 billion. Non-major ports are also expected to benefit from strong growth in India's external trade.
The Government of India (GOI) has initiated National Maritime Development Programme (NMDP), an initiative to develop the maritime sector with an planned outlay of US$ 11.8 billion. The government has also allowed foreign direct investment (FDI) of up to 100 per cent under the automatic route for projects related to the construction and maintenance of ports and harbours and a 10-year tax holiday for enterprises engaged in ports.
The Azerbaijan Section of the Project’s Oil Pipeline including valve and pig trap stations, laying of Fiber Optic cable and tie-ins at pumping stations.
The Pipeline links the Caspian sea oil wells with the Mediterranean Sea ship tankers port.
The capacity is1 million barrels of crude oil flow per day
Hello readers,
In this presentation, i am sharing Concept & Construction of Palm Island.
The following parameters are discussed in the presentation:
Where?
Why?
When?
Construction Machinery
Construction Steps
Conclusion.
Route 2020 is a proposed extension to the existing Red Line of the Dubai Metro. The extension will be 14.5 km long, 4 km will be underground in a tunnel and the balance will be elevated on viaducts.
Presentation Typical Construction Methods & Sequence.
For the Stakeholders, Public & Politicians to get an understanding of how the works are carried out and the timeline.
Dart Underground, Dublin - Light Rail Network in TunnelsDavid H Moloney
The Dart Underground is a proposed underground rail system that will run under the city centre, and connect Heuston Station with Pearse Station a distance of 4 kilometres. At the proposed St Stephen’s Green interconnection Station, on the route, passengers will be able to transfer to the Metro North and go to the Airport.
We shall examine the various factors to be taken into consideration in the construction of seaports.
https://realestateandepc.wordpress.com/2023/12/11/how-are-sea-ports-constructed/
Project Planning Organising Tracking ConstructionDavid H Moloney
The aim of this book is to show construction information relevant to planning, organising and tracking progress, graphically, focusing on the essential facts that can be easily discussed, communicated and implemented.
Regarding the illustrations showing construction sequences (storyboards), the approach is to find the easiest, quickest and safest way to execute a project with maximum utilisation of the employed resources also ensuring that executed work is right first time.
Gantt type chart programmes show the sequence and durations. Storyboards can show the sequence, durations along with how to build an operation graphically in a way that all team members along with operatives on site can understand leading to a collaborative effort.
This book deals mainly with heavy Civils and structures, the details and outputs are for guidance, each case should be evaluated separately allowing for particular site conditions.
Rock excavability, drill & blast, marine & haulageDavid H Moloney
Infographics showing methods for excavation of Rock and its excavability.
Included is the dredging of rock in a marine situation by drilling and blasting.
Also are the loading and haulage outputs.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
ML for identifying fraud using open blockchain data.pptx
Sea Port Construction, Project Execution Plan
1. David H Moloney
14th August 2016
Sea Port Construction, Project Execution Plan
Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled.
Also the measures to ensure that the site is environmentally friendly.
http://www.slideshare.net/DavidHMoloney/sea-port-construction-project-execution-plan
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant
and Sequence to construct a Sea Port .
This presentation can be used to engage Stakeholders and to get the Site Teams
commitment to the programme. Also can be used for Induction Training and as a
way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and
controlled.
High in Educational Value and easily understood. Recommended for Continuing
Professional Development (CPD)
This Video Presentation is innovative and has many beneficial uses.
Video https://www.youtube.com/watch?v=6_Aco_GPO8I
5. Quay Wall
QuayWall
Brief Description
The quay wall is constructed using precast reinforced concrete hollow
blocks that weigh up to 160 tonnes. The blocks were cast in the on-site
precast yard and loaded onto barges at the temporary loading jetty that
had a 200 tonne capacity gantry crane.
A screeding frame that extended from the sea bet to above water was
used to place the bedding layer to the correct level.
Up to 22 blocks were placed per day using a barge with a crane.
Part of the coping beam was cast in-sit-u in sections using concrete pumps
positioned on the reclaimed land behind the quay wall.
14. Breakwater & Wavewall
Breakwater&Wavewall
Brief Description
The breakwater is constructed using core rock, rock armour, precast
armour units and geotextile.
The core rock is placed using split hopper barges in deep water and
by lorry tipping and dozers in shallow water where the risk of
slippage is minimal.
The precast armour units are placed using crawler cranes fitted with
a real-time visual aid system that enabled 70 placements per day.
The wave wall is cast in-sit-u in 6 metre long sections.
15. Sequence & Methods to Construct Breakwater & Wavewall
Breakwater&Wavewall
16. Breakwaters
ⓒ David H Moloney
Filling Barge with Rock – Temporary Jetty Placing Rock Fill
Breakwater under Construction Placing Rock Armour
26. Precast Yard & Loading Jetty
PrecastYard&LoadingJetty
Brief Description
Full-scale sample castings are constructed to demonstrate and
document that all the requirements of the concrete and the
execution of the work are fulfilled using the actual methods and
performed by personnel that will carry out the future castings. One
concrete component of each type is produced for approval. The
approved castings were retained in a dedicated area for quality
assurance purposes.
All works were inspected in accordance with the Inspection & Test
Plan on an ongoing basis, in accordance with the site Project Quality
Plan. The ITP set out in matrix form the sequence of inspection
steps, the governing document (specification, standards), the
standard to be achieved, the persons witnessing and the supporting
documents to be produced.
34. Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins
and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks.
The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage
capacity to match two days concrete production
36. Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
38. Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
40. Concrete MixGeneralItems
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
43. Dredging & Reclamation
Dredging&Reclamation
Brief Description
Dredgers are marine vessels used to excavate and fill under water.
Types
1. Cutter Suction Dredgers are used to dredge hard soils by cutting
and breaking up the soil using a rotating head at the end of a pipe
which is lowered onto the sea bed. The fragmented material is
sucked and pumped either into a hopper barge or through a floating
pipeline. During operation the dredger is anchored by a spud that
allows the cutting head to swing in an arc.
2. Trailing Suction Hopper Dredgers are used to dredge soft and
loose soils, gravels and silts. There are two suction drag heads
which are lowered onto the sea bed. These move with the dredger
along the sea bed. The dredged material is sucked and pumped
either into the hopper or through a floating pipeline to a discharge
area.
48. Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
50. Vibro Compaction - Fill behind Quay
Ground Improvement using deep vibro-compaction.
Purpose is to provide protection against liquefaction during a seismic
event. Also to provide a specified minimum ground bearing capacity.
Vibro-compaction was use to compact the Dubai man made islands
that were constructed from dredged sand.
Equipment.
Vibroflot with extension tube, hydraulic power pack mounted on crane,
diesel engine driven water jetting pumps, compressors, crawler cranes
60 tonne capacity, water tank, de-watering pump
51. Vibro Compaction - Fill behind Quay
3D image to show Sequence, Method & Plant.
David H Moloney
ⓒ David H Moloney
75. Personal Protective Equipment (PPE)
Health,Safety&Environment
Personal protective
equipment (PPE) is
protective clothing,
helmets, goggles, or other
garments or equipment
designed to protect the
wearer from injury or
infection
76. Safety Training on Site
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
85. Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
95. Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
96. Histogram Charts for Resources & Outputs
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
117. Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
My Port Construction YouTube link https://www.youtube.com/watch?v=6_Aco_GPO8I