SlideShare a Scribd company logo
PREPARING COST
ESTIMATION
Presented By,
Somashekar S M,
Asst Professor
Introduction
• Estimate costs is the process of developing an approximation of the monetary
resources needed to complete project activities.
• The key benefit of this process is that it determines the amount of cost required to
complete project work.
• Cost estimates should be reviewed and refined during the course of project to
reflect additional detail as it becomes available & assumptions are tested.
For ex: a project in the initiation phase may have rough order of magnitude
estimate in the range of +25% to +75%. Later the project has more information is
known, definitive estimates could narrow the range of accuracy -5% to +10%.
• The techniques for estimating the cost involved in performing each of the project
activities are the same as estimating the time required.
• When a project is formed under contract, care should be taken to distinguish cost
estimating from pricing.
• Cost estimating includes identifying and considering various costing alternatives.
Data Flow Diagram
Preparing Cost Estimation: Inputs
• Work breakdown structure: A WBS is a deliverable-oriented grouping of
project components that organizes and defines the total scope of the project;
work not in the WBS is outside of the project.
It is used to organize cost estimates and to ensure that all identified work
has been estimated.
• Resource requirements: The resource planning process is a description of
what types of resources are required and in what quantities for each element
at the lowest level of the WBS.
Resource requirements for higher levels within the WBS can be calculated
based on the lowest level values.
Preparing Cost Estimation: Inputs
• Resource rates: The individual or group preparing the estimates must know
the unit rates for each resource to calculate the project costs.
If actual rates are not known, the rates themselves may have to be estimated.
• Activity duration estimates: Activity duration estimating is the process of
taking information on project scope and resources and then developing
durations for input to schedules.
It will affect cost estimates on project, where the project budget includes
allowance for the cost of financing.
• Chart of accounts: A chart of accounts describes the coding structure used
by the performing organization to financial information in its general ledger.
Project cost estimates must be assigned to the correct accounting category.
Preparing Cost Estimation: Inputs
• Historical information: Information on the cost of many categories of
resources is often available from one or more of the following sources.
 Project files
 Commercial-cost estimating databases
 Project team knowledge
• Estimating publications: Commercially available data on cost estimating.
• Risks: The project team considers information on risks when procuring cost
estimates, since risks can have a significant impact on cost.
The project team considers the extent to which the effect risk is included
in the cost estimates for each activity.
Preparing Cost Estimation: Tools and Techniques
• Analogous estimating: Analogous estimating, means using the actual cost of
a previous, similar project as the basis for estimating the cost of the current
project.
It is frequently used to estimate total project costs when there is a limited
amount of detailed information about the project
Analogous estimating is generally less costly than other techniques, but it is
also generally less accurate.
It is most reliable when,
a) the previous projects are similar in fact and not just in appearance, and
b) the individuals or groups preparing the estimates have the needed
expertise.
Preparing Cost Estimation: Tools and Techniques
• Parametric modelling: Parametric modelling involves using project
characteristics (parameters) in a mathematical model to predict project
costs.
Models may be simple or complex.
Both the cost and accuracy of parametric models vary widely
They are most likely to be reliable when
a) the historical information used to develop the model was accurate,
b) the parameters
c) the model is scalable
Preparing Cost Estimation: Tools and Techniques
• Bottom-up estimating: It involves estimating the cost of individual
activities or work packages, then summarizing the individual estimates to get
a project total cost.
The cost and accuracy of bottom-up estimating is driven by the size and
complexity of the individual activity or work package.
• Computerized tools: Computerized tools, such as project management
software spreadsheets and simulation/statistical tools are widely used to
assist with cost estimating.
Such products can simplify the use of the tools and thereby facilitate rapid
consideration of many costing alternatives.
• Other cost estimating methods: For example, vendor bid analysis.
Preparing Cost Estimation: Outputs
• Cost estimates: Cost estimates are quantitative assessments of the likely costs of
the resources required to complete project activities. They may be presented in
summary or detail.
Costs must be estimated for all resources that will be charged to the project.
Cost estimates are generally expressed in units of currency (dollars, euros, yen
etc.) to facilitate comparisons both within and across projects.
In some cases, the estimator may use units of measure to estimate cost
Cost estimating generally include considering appropriate risk response
planning, such as contingency plans.
Cost estimated may benefit from being refined during the course of the project to
reflect the additional detail available.
The Association for the Advancement of Cost Engineering (AACE) International has
identified a progression five type estimates of construction costs during engineering
order magnitude, conceptual, preliminary, definitive, and control.
Preparing Cost Estimation: Outputs
• Supporting detail: Supporting detail for the cost estimates should include:
 A description of the scope of work estimated. This is often provided by a
reference to the WBS.
 Documentation of the basis for the estimate, i.e., how it as developed.
 Documentation of any assumptions made.
 An indication of the range of possible results; for example, Rs 10,000 ± Rs
1000 to indicate that item is expected to cost between Rs 9000 and Rs 11000.
• Cost management plan: The cost management plan describes how cost
variances will be managed.
A cost management plan may be formal or informal, highly detailed or
broadly framed, based on the needs of the project stake holders
PROJECT PROFITABILITY
EVALUATION
Presented By,
Somashekar S M
Asst Professor
Introduction
• Profit is an excess of revenues over associated expenses for an activity over a
period of time.
• Every business should earn sufficient profits to survive and grow over a long
period of time.
• Profitability means ability to make profit from all the business activities of
an organization, company, firm, or an enterprise.
• Profit refers to the total income earned by the enterprise during the specified
period of time, while profitability refers to the operating efficiency of the
enterprise.
• It shows how efficiently the management can make profit by using all the
resources available in the market.
• Profitability is an index of efficiency; and is regarded as a measure of
efficiency and management guide to greater efficiency.
Methods of profitability evaluation
1. Pay Back Period (PBP) Method
2. Average Annual Rate of Return (AARR)
3. Net Present Value (NPV)
4. Internal Rate of Return (ARR)
Payback Period
• The payback period method is concerned with the recoupment (return) of
the original investment made in a project.
• It lays emphasis on calculating the length of time it would take to recover the
original investment.
• It involves calculation of the cash flows which would arise from investment
in each year of the life of a project.
• These cash flows are accumulated year by year till the time they equal the
amount of the original investment made in the project.
• The length of time it takes to obtain the necessary cash flows equal to the
original investment, determines the payback period for the project.
• For example, if a project requires an annual investment of Rs. 25,000 crores
and is expected to generate an annual cash inflow of Rs. 5,000 crores for 10
years, the payback period can be calculated as under;
Solution: Pay Back Period (PBP) = Initial Investment/Annual, Cash Inflow
or P = C/A1
Where, P = Pay Back Period;
С = Initial Investment or the cost of capital project; and
A1 = Annual Cash Inflow
P = 25,000/5,000 = 5
Thus, the PBP of this project is 5 years
Payback Period: Acceptance/Rejectance
• PBP is used as a criterion to accept or reject an investment proposal.
• PBP calculated for a proposal is to be compared with some predetermined
target period.
• If PBP is less than the target period, the proposal may be accepted.
• If PBP is more than the target period, the proposal may be rejected.
• By this method, proposals may be ranked.
• The lower the PBP, the more profitable the projects proposal.
Average Annual Rate of Return (AARR):
• This method is based on the accounting concept of return on investment or
rate of return.
• It refers to the percentage of the annual net income earned on the average
funds invested in a project.
• The annual return of a project is the percentage of net investment in the
project.
Average Annual Rate of Return (AARR):
• Example: , if average annual return of a project is Rs. 10,000 while the initial
cost of project is Rs.1, 00, 000, the annual rate of return will be as under:
• Solution:
AARR= 10,000/1,00,000 x 100
Thus, the average rate of return is 10%.
Acceptance/Rejection: AARR is compared with the cut off or the pre-
determined rate of return. If AARR is more than the pre-determined rate of
return, the project will be accepted otherwise rejected.
Net Present Value Method (NPV)
• It is also called as present value method.
• Net present value is calculated by using an appropriate rate of interest which
is the capital cost of a firm.
• This is the minimum rate of expected return likely to be earned by the firm
on investment proposals.
• To find out the present value of cash flows expected in future periods, all the
cash outflows and cash inflows are discounted at the above rate.
• Net present value is the difference between total present value of cash
outflows and total present value of cash inflows occurring in periods over the
entire life of the project.
• When the net present value is positive, the investment proposal is profitable
and worth selecting.
Net Present Value Method (NPV)
• NPV = Present value of Gross Earnings – Net Cash Investment NPV can be
found out from the following formula:
NPV= A1/(1+ r)1 + A2/ (1 + r)2 + A3 (1 + r)3 + …..An/ (1+r)n – C
Where A1, A2, A3 etc. are the cash inflows at the end of first, second and third
year respectively
n = Expected life of investment proposals;
r = Rate of discount which is equal to the cost of capital;
С = Present value of costs.
• Thus, NPV = Sum of Discounted Gross Earnings – Sum of Discounted Value
of Cost
Net Present Value Method (NPV)
• For example, if the initial investment cost of a project is Rs.100 crores, cash inflow in
the coming years is Rs.125 crores and the market rate of interest is 10% p.a., NPV will
be as follows:
Solution: NPV = 125/ (1 + 0.10)1 – 100
= 125 x 10/11-100
= 113.64-100=13.64
• Accept or Rejectance:
The decision criterion relating to NPV may be as under:
(a) If NPV > 0, the project is profitable.
(b) If NPV < 0, the project will not be profitable.
(c) If NPV = 0, the project may or may not be started.
If the decision is to be taken between two projects, the project with high positive NPV
would be selected rather than the other
Preparing cost estimation
Preparing cost estimation

More Related Content

What's hot

SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
Rupesh Brahmankar
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
Dacanay Elmer
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and controlLaxmikant Deshmukh
 
Master Scheduling
Master SchedulingMaster Scheduling
Master Scheduling
pilly_leon
 
Production planning hierarchy
Production planning hierarchy Production planning hierarchy
Production planning hierarchy
Cher Dong Theng
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Capacity planning
Capacity planningCapacity planning
Capacity planning
Uday Pawar
 
Production Planning And Control
Production Planning And ControlProduction Planning And Control
Production Planning And Control
PVG's College of Engineering Nashik
 
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesOm lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesvideoaakash15
 
Production of Planning & control
Production of Planning & controlProduction of Planning & control
Production of Planning & control
Vishal Kanthali
 
Production Planning And Control
Production Planning And ControlProduction Planning And Control
Production Planning And ControlAvinash Verma
 
SCM2013_Vermeylen_CasestudySupplyChainSixSigma
SCM2013_Vermeylen_CasestudySupplyChainSixSigmaSCM2013_Vermeylen_CasestudySupplyChainSixSigma
SCM2013_Vermeylen_CasestudySupplyChainSixSigmaTerry Vermeylen
 
Production management
Production managementProduction management
Production management
Purnesh Aloni
 
Material resource planning
Material resource planningMaterial resource planning
Material resource planning
Nishant Agrawal
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
ejalgfer
 
Production planning hierarchy
Production planning hierarchyProduction planning hierarchy
Production planning hierarchy
Dr. Mahmoud Al-Naimi
 
small and effective ppt on master production schedule
small and effective ppt on master production schedulesmall and effective ppt on master production schedule
small and effective ppt on master production schedule
yashbhhardwaj260
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentation
Pankaj Kumar
 
Production mgt lecture_4
Production mgt lecture_4Production mgt lecture_4
Production mgt lecture_4Jyoti Yadav
 

What's hot (20)

SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
Ppc C1
Ppc C1Ppc C1
Ppc C1
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
Master Scheduling
Master SchedulingMaster Scheduling
Master Scheduling
 
Production planning hierarchy
Production planning hierarchy Production planning hierarchy
Production planning hierarchy
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Resource Requirement Planning
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Production Planning And Control
Production Planning And ControlProduction Planning And Control
Production Planning And Control
 
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesOm lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
 
Production of Planning & control
Production of Planning & controlProduction of Planning & control
Production of Planning & control
 
Production Planning And Control
Production Planning And ControlProduction Planning And Control
Production Planning And Control
 
SCM2013_Vermeylen_CasestudySupplyChainSixSigma
SCM2013_Vermeylen_CasestudySupplyChainSixSigmaSCM2013_Vermeylen_CasestudySupplyChainSixSigma
SCM2013_Vermeylen_CasestudySupplyChainSixSigma
 
Production management
Production managementProduction management
Production management
 
Material resource planning
Material resource planningMaterial resource planning
Material resource planning
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
 
Production planning hierarchy
Production planning hierarchyProduction planning hierarchy
Production planning hierarchy
 
small and effective ppt on master production schedule
small and effective ppt on master production schedulesmall and effective ppt on master production schedule
small and effective ppt on master production schedule
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentation
 
Production mgt lecture_4
Production mgt lecture_4Production mgt lecture_4
Production mgt lecture_4
 

Similar to Preparing cost estimation

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
Ir.Noor Iziddin,PMP, P.Eng,REEM,CCPM,TTT.
 
Introduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projectsIntroduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projects
Essam Lotffy, PMP®, CCP®
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
ssuser9d62d6
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
Dr. ABEER KHALID MANSOUR
 
2 b agile domains
2 b agile domains2 b agile domains
2 b agile domains
qtntpam
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
AHMED NADIM JILANI
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
Madhusha15
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg
adabotor7
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
ProfDrAnbalaganChinn
 
Project cost management
Project cost management Project cost management
Project cost management
PALLA NARASIMHUDU
 
L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
Pmp inititating process group
Pmp inititating process groupPmp inititating process group
Pmp inititating process group
Pradeep Patel, PMP®
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
BhuWan Khadka
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl90
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
Zaur Ahmadov, PMP
 
Unit 4 Capital Budgeting
Unit 4 Capital BudgetingUnit 4 Capital Budgeting
Unit 4 Capital Budgeting
Parrthipan B K
 

Similar to Preparing cost estimation (20)

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
Introduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projectsIntroduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projects
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
2 b agile domains
2 b agile domains2 b agile domains
2 b agile domains
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
Project cost management
Project cost management Project cost management
Project cost management
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
Pmp inititating process group
Pmp inititating process groupPmp inititating process group
Pmp inititating process group
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Unit 4 Capital Budgeting
Unit 4 Capital BudgetingUnit 4 Capital Budgeting
Unit 4 Capital Budgeting
 

More from Somashekar S.M

Teamcenter AWS Login Background image customization
Teamcenter AWS Login Background image customizationTeamcenter AWS Login Background image customization
Teamcenter AWS Login Background image customization
Somashekar S.M
 
Operations Management VTU BE Mechanical 2015 Solved paper
Operations Management VTU BE Mechanical 2015 Solved paperOperations Management VTU BE Mechanical 2015 Solved paper
Operations Management VTU BE Mechanical 2015 Solved paper
Somashekar S.M
 
Teamcenter Product Cost Management - Software Installation, Upload Master dat...
Teamcenter Product Cost Management - Software Installation, Upload Master dat...Teamcenter Product Cost Management - Software Installation, Upload Master dat...
Teamcenter Product Cost Management - Software Installation, Upload Master dat...
Somashekar S.M
 
NX_CAM_Sales_Enablement.pptx
NX_CAM_Sales_Enablement.pptxNX_CAM_Sales_Enablement.pptx
NX_CAM_Sales_Enablement.pptx
Somashekar S.M
 
Sheet metal design in Solid Edge.docx
Sheet metal design in Solid Edge.docxSheet metal design in Solid Edge.docx
Sheet metal design in Solid Edge.docx
Somashekar S.M
 
Digital Factory setup
Digital Factory setupDigital Factory setup
Digital Factory setup
Somashekar S.M
 
Capital software installation procedure
Capital software installation procedureCapital software installation procedure
Capital software installation procedure
Somashekar S.M
 
Inspire cast quiz
Inspire cast quizInspire cast quiz
Inspire cast quiz
Somashekar S.M
 
Operations management notes
Operations management notesOperations management notes
Operations management notes
Somashekar S.M
 
Understanding stakeholders
Understanding stakeholdersUnderstanding stakeholders
Understanding stakeholders
Somashekar S.M
 
Communications needs of global and virtual project teams
Communications needs of global and virtual project teamsCommunications needs of global and virtual project teams
Communications needs of global and virtual project teams
Somashekar S.M
 
Scope definition
Scope definitionScope definition
Scope definition
Somashekar S.M
 
Communication planning
Communication planningCommunication planning
Communication planning
Somashekar S.M
 
Hydraulic actuators and motors
Hydraulic actuators and motors Hydraulic actuators and motors
Hydraulic actuators and motors
Somashekar S.M
 
MRP-II
MRP-IIMRP-II
project management
 project management project management
project management
Somashekar S.M
 
Entrepreneurship
EntrepreneurshipEntrepreneurship
Entrepreneurship
Somashekar S.M
 
Project Planning and Estimation
Project Planning and EstimationProject Planning and Estimation
Project Planning and Estimation
Somashekar S.M
 
Decision making
Decision makingDecision making
Decision making
Somashekar S.M
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
Somashekar S.M
 

More from Somashekar S.M (20)

Teamcenter AWS Login Background image customization
Teamcenter AWS Login Background image customizationTeamcenter AWS Login Background image customization
Teamcenter AWS Login Background image customization
 
Operations Management VTU BE Mechanical 2015 Solved paper
Operations Management VTU BE Mechanical 2015 Solved paperOperations Management VTU BE Mechanical 2015 Solved paper
Operations Management VTU BE Mechanical 2015 Solved paper
 
Teamcenter Product Cost Management - Software Installation, Upload Master dat...
Teamcenter Product Cost Management - Software Installation, Upload Master dat...Teamcenter Product Cost Management - Software Installation, Upload Master dat...
Teamcenter Product Cost Management - Software Installation, Upload Master dat...
 
NX_CAM_Sales_Enablement.pptx
NX_CAM_Sales_Enablement.pptxNX_CAM_Sales_Enablement.pptx
NX_CAM_Sales_Enablement.pptx
 
Sheet metal design in Solid Edge.docx
Sheet metal design in Solid Edge.docxSheet metal design in Solid Edge.docx
Sheet metal design in Solid Edge.docx
 
Digital Factory setup
Digital Factory setupDigital Factory setup
Digital Factory setup
 
Capital software installation procedure
Capital software installation procedureCapital software installation procedure
Capital software installation procedure
 
Inspire cast quiz
Inspire cast quizInspire cast quiz
Inspire cast quiz
 
Operations management notes
Operations management notesOperations management notes
Operations management notes
 
Understanding stakeholders
Understanding stakeholdersUnderstanding stakeholders
Understanding stakeholders
 
Communications needs of global and virtual project teams
Communications needs of global and virtual project teamsCommunications needs of global and virtual project teams
Communications needs of global and virtual project teams
 
Scope definition
Scope definitionScope definition
Scope definition
 
Communication planning
Communication planningCommunication planning
Communication planning
 
Hydraulic actuators and motors
Hydraulic actuators and motors Hydraulic actuators and motors
Hydraulic actuators and motors
 
MRP-II
MRP-IIMRP-II
MRP-II
 
project management
 project management project management
project management
 
Entrepreneurship
EntrepreneurshipEntrepreneurship
Entrepreneurship
 
Project Planning and Estimation
Project Planning and EstimationProject Planning and Estimation
Project Planning and Estimation
 
Decision making
Decision makingDecision making
Decision making
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 

Recently uploaded

Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 

Recently uploaded (20)

Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 

Preparing cost estimation

  • 2. Introduction • Estimate costs is the process of developing an approximation of the monetary resources needed to complete project activities. • The key benefit of this process is that it determines the amount of cost required to complete project work. • Cost estimates should be reviewed and refined during the course of project to reflect additional detail as it becomes available & assumptions are tested. For ex: a project in the initiation phase may have rough order of magnitude estimate in the range of +25% to +75%. Later the project has more information is known, definitive estimates could narrow the range of accuracy -5% to +10%. • The techniques for estimating the cost involved in performing each of the project activities are the same as estimating the time required. • When a project is formed under contract, care should be taken to distinguish cost estimating from pricing. • Cost estimating includes identifying and considering various costing alternatives.
  • 4. Preparing Cost Estimation: Inputs • Work breakdown structure: A WBS is a deliverable-oriented grouping of project components that organizes and defines the total scope of the project; work not in the WBS is outside of the project. It is used to organize cost estimates and to ensure that all identified work has been estimated. • Resource requirements: The resource planning process is a description of what types of resources are required and in what quantities for each element at the lowest level of the WBS. Resource requirements for higher levels within the WBS can be calculated based on the lowest level values.
  • 5. Preparing Cost Estimation: Inputs • Resource rates: The individual or group preparing the estimates must know the unit rates for each resource to calculate the project costs. If actual rates are not known, the rates themselves may have to be estimated. • Activity duration estimates: Activity duration estimating is the process of taking information on project scope and resources and then developing durations for input to schedules. It will affect cost estimates on project, where the project budget includes allowance for the cost of financing. • Chart of accounts: A chart of accounts describes the coding structure used by the performing organization to financial information in its general ledger. Project cost estimates must be assigned to the correct accounting category.
  • 6. Preparing Cost Estimation: Inputs • Historical information: Information on the cost of many categories of resources is often available from one or more of the following sources.  Project files  Commercial-cost estimating databases  Project team knowledge • Estimating publications: Commercially available data on cost estimating. • Risks: The project team considers information on risks when procuring cost estimates, since risks can have a significant impact on cost. The project team considers the extent to which the effect risk is included in the cost estimates for each activity.
  • 7. Preparing Cost Estimation: Tools and Techniques • Analogous estimating: Analogous estimating, means using the actual cost of a previous, similar project as the basis for estimating the cost of the current project. It is frequently used to estimate total project costs when there is a limited amount of detailed information about the project Analogous estimating is generally less costly than other techniques, but it is also generally less accurate. It is most reliable when, a) the previous projects are similar in fact and not just in appearance, and b) the individuals or groups preparing the estimates have the needed expertise.
  • 8. Preparing Cost Estimation: Tools and Techniques • Parametric modelling: Parametric modelling involves using project characteristics (parameters) in a mathematical model to predict project costs. Models may be simple or complex. Both the cost and accuracy of parametric models vary widely They are most likely to be reliable when a) the historical information used to develop the model was accurate, b) the parameters c) the model is scalable
  • 9. Preparing Cost Estimation: Tools and Techniques • Bottom-up estimating: It involves estimating the cost of individual activities or work packages, then summarizing the individual estimates to get a project total cost. The cost and accuracy of bottom-up estimating is driven by the size and complexity of the individual activity or work package. • Computerized tools: Computerized tools, such as project management software spreadsheets and simulation/statistical tools are widely used to assist with cost estimating. Such products can simplify the use of the tools and thereby facilitate rapid consideration of many costing alternatives. • Other cost estimating methods: For example, vendor bid analysis.
  • 10. Preparing Cost Estimation: Outputs • Cost estimates: Cost estimates are quantitative assessments of the likely costs of the resources required to complete project activities. They may be presented in summary or detail. Costs must be estimated for all resources that will be charged to the project. Cost estimates are generally expressed in units of currency (dollars, euros, yen etc.) to facilitate comparisons both within and across projects. In some cases, the estimator may use units of measure to estimate cost Cost estimating generally include considering appropriate risk response planning, such as contingency plans. Cost estimated may benefit from being refined during the course of the project to reflect the additional detail available. The Association for the Advancement of Cost Engineering (AACE) International has identified a progression five type estimates of construction costs during engineering order magnitude, conceptual, preliminary, definitive, and control.
  • 11. Preparing Cost Estimation: Outputs • Supporting detail: Supporting detail for the cost estimates should include:  A description of the scope of work estimated. This is often provided by a reference to the WBS.  Documentation of the basis for the estimate, i.e., how it as developed.  Documentation of any assumptions made.  An indication of the range of possible results; for example, Rs 10,000 ± Rs 1000 to indicate that item is expected to cost between Rs 9000 and Rs 11000. • Cost management plan: The cost management plan describes how cost variances will be managed. A cost management plan may be formal or informal, highly detailed or broadly framed, based on the needs of the project stake holders
  • 13. Introduction • Profit is an excess of revenues over associated expenses for an activity over a period of time. • Every business should earn sufficient profits to survive and grow over a long period of time. • Profitability means ability to make profit from all the business activities of an organization, company, firm, or an enterprise. • Profit refers to the total income earned by the enterprise during the specified period of time, while profitability refers to the operating efficiency of the enterprise. • It shows how efficiently the management can make profit by using all the resources available in the market. • Profitability is an index of efficiency; and is regarded as a measure of efficiency and management guide to greater efficiency.
  • 14. Methods of profitability evaluation 1. Pay Back Period (PBP) Method 2. Average Annual Rate of Return (AARR) 3. Net Present Value (NPV) 4. Internal Rate of Return (ARR)
  • 15. Payback Period • The payback period method is concerned with the recoupment (return) of the original investment made in a project. • It lays emphasis on calculating the length of time it would take to recover the original investment. • It involves calculation of the cash flows which would arise from investment in each year of the life of a project. • These cash flows are accumulated year by year till the time they equal the amount of the original investment made in the project. • The length of time it takes to obtain the necessary cash flows equal to the original investment, determines the payback period for the project.
  • 16. • For example, if a project requires an annual investment of Rs. 25,000 crores and is expected to generate an annual cash inflow of Rs. 5,000 crores for 10 years, the payback period can be calculated as under; Solution: Pay Back Period (PBP) = Initial Investment/Annual, Cash Inflow or P = C/A1 Where, P = Pay Back Period; С = Initial Investment or the cost of capital project; and A1 = Annual Cash Inflow P = 25,000/5,000 = 5 Thus, the PBP of this project is 5 years
  • 17. Payback Period: Acceptance/Rejectance • PBP is used as a criterion to accept or reject an investment proposal. • PBP calculated for a proposal is to be compared with some predetermined target period. • If PBP is less than the target period, the proposal may be accepted. • If PBP is more than the target period, the proposal may be rejected. • By this method, proposals may be ranked. • The lower the PBP, the more profitable the projects proposal.
  • 18. Average Annual Rate of Return (AARR): • This method is based on the accounting concept of return on investment or rate of return. • It refers to the percentage of the annual net income earned on the average funds invested in a project. • The annual return of a project is the percentage of net investment in the project.
  • 19. Average Annual Rate of Return (AARR): • Example: , if average annual return of a project is Rs. 10,000 while the initial cost of project is Rs.1, 00, 000, the annual rate of return will be as under: • Solution: AARR= 10,000/1,00,000 x 100 Thus, the average rate of return is 10%. Acceptance/Rejection: AARR is compared with the cut off or the pre- determined rate of return. If AARR is more than the pre-determined rate of return, the project will be accepted otherwise rejected.
  • 20. Net Present Value Method (NPV) • It is also called as present value method. • Net present value is calculated by using an appropriate rate of interest which is the capital cost of a firm. • This is the minimum rate of expected return likely to be earned by the firm on investment proposals. • To find out the present value of cash flows expected in future periods, all the cash outflows and cash inflows are discounted at the above rate. • Net present value is the difference between total present value of cash outflows and total present value of cash inflows occurring in periods over the entire life of the project. • When the net present value is positive, the investment proposal is profitable and worth selecting.
  • 21. Net Present Value Method (NPV) • NPV = Present value of Gross Earnings – Net Cash Investment NPV can be found out from the following formula: NPV= A1/(1+ r)1 + A2/ (1 + r)2 + A3 (1 + r)3 + …..An/ (1+r)n – C Where A1, A2, A3 etc. are the cash inflows at the end of first, second and third year respectively n = Expected life of investment proposals; r = Rate of discount which is equal to the cost of capital; С = Present value of costs. • Thus, NPV = Sum of Discounted Gross Earnings – Sum of Discounted Value of Cost
  • 22. Net Present Value Method (NPV) • For example, if the initial investment cost of a project is Rs.100 crores, cash inflow in the coming years is Rs.125 crores and the market rate of interest is 10% p.a., NPV will be as follows: Solution: NPV = 125/ (1 + 0.10)1 – 100 = 125 x 10/11-100 = 113.64-100=13.64 • Accept or Rejectance: The decision criterion relating to NPV may be as under: (a) If NPV > 0, the project is profitable. (b) If NPV < 0, the project will not be profitable. (c) If NPV = 0, the project may or may not be started. If the decision is to be taken between two projects, the project with high positive NPV would be selected rather than the other