Project Cost Management
Apr 02, 2018
Project Cost Management
Types of Cost
▪ Direct Cost- Any cost that is identified specifically with a particular final
cost objective.
▪ Indirect Cost- Any cost not directly identified with a single, final cost
objective (more than one project)
▪ Fixed Cost - Periodic charge that does not vary with business volume
▪ Variable Cost - Cost that fluctuates based on the business volume
▪ Opportunity Cost: When there is a decision to be made between two
opportunities, the opportunity cost is the value / money forgone for the not
doing the project.
Types of Cost
• Lifecycle Costing: Takes into account cost of development of a project
and also the cost of supporting during the lifecycle.
• Sunk Cost - Cost already incurred which cannot be recovered regardless
of future events
Types of Cost
1. If you are constructing a road, the costs of excavators and bulldozers…?
2. Cost of Fuel, being used by equipment…?
3. Cost of Support Staff, providing services for project from Head office…?
4. Rent of Project Company Head office…?
5. Company has hired a freelancer to develop a website in .NET. After a month,
you decide that the freelancer isn’t doing a good job and reach out to another
freelancer. The second freelancer convinces you that .NET is not the way to go
and that your website project would be better off based on the Java platform.
The cost associated with the .NET freelancer would be treated as…?
Project Cost Management
Project Cost Management
Project Cost Management includes the processes involved in:
• estimating,
• budgeting, and
• controlling costs
so that the project can be completed within the approved budget
Process Process Group
Plan Cost Management Planning
Estimate Costs Planning
Determine Budget Planning
Control Costs Monitoring and Controlling
Plan Cost Management- Outputs
Cost Management Plan – is a component of the project management plan and
describes how the project costs will be planned, structured , and controlled. The cost
management plan can establish the following.
 Units of measure
 Level of precision
 Level of accuracy
 Control threshold
 Rules of performance measurement
Estimate Cost
Estimate cost is the process of developing an approximation of the
monetary resources needed to complete project activities.
The key benefit of this process is that it determines the amount of
cost required to complete project work.
Estimate Costs -Tools and Techniques
Estimate Costs -Tools and Techniques
Analogous Estimating
Estimate Costs -Tools and Techniques
Parametric estimating
Estimate Costs -Tools and Techniques
Analogous vs Parametric estimating
1. It costed $7,100 to develop a website a few months ago and you are responsible for
developing a new similar website, you estimate it to cost $7,100.
2. It took four days to excavate one acre of plant land last week and in order to excavate two
acres this week, it will take eight days.
3. Sue is currently estimating the cost of a deliverable based on a project with a similar
product 2 years ago. Sue puts down the estimate by copying directly from the actual cost
of the product found from project documents. Which estimation technique does Sue
make use of?
Estimate Costs -Tools and Techniques
• Three-point estimates concept originated with the program evaluation and
review technique (PERT). PERT uses three estimates to define an approximate
range for an activity’s cost:
• Beta Distribution
ESTIMATED COST = (Optimistic + 4*(Most Likely) + Pessimistic) / 6
• Bottom-up estimating produces a separate estimate for
each scheduled activity. The detailed cost is then
summarized or “rolled up” to higher levels for subsequent
reporting and tracking purposes. The cost and accuracy of
bottom-up cost estimating is typically influenced by the size
and complexity of the individual activity or work package.
Bottom up
estimating
Determine Budget
Determine Budget is the process of aggregating the estimated costs of
individual activities or work packages to establish an authorized cost
baseline.
This baseline includes all authorized budgets, but excludes
management reserves.
Determine Budget - Inputs
• Once the project has been divided into the WBS work packages, a code or
numbering system is assigned to every work package for cost monitoring, control,
reports, and forecasting purposes. These codes are usually called “Code of
accounts” or “Cost centers”
• Cost Aggregation involves aggregating the costs of individual activities to
work packages that are further aggregated to higher levels of WBS and finally
into the project cost
• Reserve Analysis include contingency reserve and management reserves for the
project. Contingency reserves are allowances for response plan strategized for the
identified risks. These are also known as “known unknowns”. Management
reserves are allowance for unplanned changes to thee project scope and cost. The
are also known as “unknown unknowns”. Reserves are not the part of the project
cost baseline.
Determine Budget – Tools and Techniques
• Budget within the cost baseline that is allocated for
identified & accepted risks
• Viewed to address the “known-unknowns”
• Provide for a specific activity/ whole project, or both
• Percentage of the estimated cost, a fixed number, or
may be developed by using quantitative analysis
methods
• As more precise information about the project becomes
available, the contingency reserve may be used,
reduced, or eliminated
• Contingency should be clearly identified in cost
documentation
• Contingency reserves are part of the cost baseline and
the overall funding requirements for the project
• Amount of the project budget withheld for
management control purposes and are reserved for
unforeseen work that is within scope of the project
• To address the “unknown unknowns” that can affect a
project
• Not included in the cost baseline but is part of the
overall project budget and funding requirements
• When an amount of management reserves is used to
fund unforeseen work, the amount of management
reserve used is added to the cost baseline, thus
requiring an approved change to the cost baseline
Project Budget Components
Project Budget Components
Determine Budget – Outputs
Cost performance baseline is an authorized time-phased budget at completion
(BAC) used to measure, monitor, and control overall cost performance on the project.
It is developed as a summation of the approved budgets by time period and is
typically displayed in the form of an S-curve, as is illustrated in Figure below:
Reference PMBOK 5th Edition
Determine Budget – Outputs
Reference PMBOK 5th Edition
Exercise: Determine Budget
Revise Tools to Determine Budget
Monika reads a newspaper article that says there has been sharp increase in steel
cost recently. She knows this was not in her contractor’s original plan and decidesto
put a few hundred dollars aside to deal with the price hike if it should happen. The
tool used by Monika is
• Parametric estimating
• Reserve analysis
• Cost aggregation
• Fund Limit Reconciliation
Control Costs
Control Costs is the process of monitoring the status of the project
to update the project budget and managing changes to the cost
baseline.
Control Costs – Tools and Techniques
Earned value management is used to measure the performance of the project, It
integrates project scope, cost and schedule measures to help the project management
team assess and measure project performance and progress.
1. Planned Value (PV) is the authorized budget assigned to the scheduled work to
be accomplished for a schedule activity or work breakdown structure component.
2. Earned Value (EV) is the value of work performed expressed in terms of
the approved budget assigned to that work for a schedule activity or a WBS
component.
3. Actual Cost (AC) is the total cost actually incurred and recorded in
accomplishing work performed for an activity or work breakdown structure
component.
Control Costs – Tools and Techniques
• Variance Analysis helps in analyzing the performance of the project vis-à-vis
cost and schedule baselines
• Schedule Variance (SV) is a measure of schedule performance on a project. It
is equal to the earned value (EV) minus the planned value (PV). SV= EV-PV.
• Cost variance (CV) is a measure of cost performance on a project. It is
equal to the earned value (EV) minus the actual costs (AC). CV = EV-AC
• Schedule performance Index (SPI) in addition to project status is used to
predict the completion date. SPI = EV/PV
• Cost Performance Index (CPI) measures the cost efficiency for the work
completed, it is the ration of EV to AC. CPI = EV/AC.
Control Costs – Tools and Techniques
Forecasting Techniques are used to calculate Estimate at completion (EAC) and
Estimate to complete (ETC).
EAC = AC + ETC
To-complete performance index (TCPI) is the calculated projection of cost
performance that must be achieved on the remaining work to meet a specified
management goal, such as the BAC or the EAC.
Performance reviews involves following three types of analysis
1.Variance Analysis compares actual project performance to planned or expected
performance. Cost and schedule variances are the most frequently analyzed.
2.Trend Analysis examines project performance over time to determine if
performance is improving or deteriorating.
3.Earned value management compares the baseline plan to actual schedule and
cost performance.
Control Costs – Outputs
• Work Performance Information includes the calculated CV, SV, CPI, and
SPI values for WBS components, in particular the work packages.
• Cost Forecasts includes a calculated EAC value or a bottom-up EAC value.
• Organizational Process Assets Updates include Causes of variances, Corrective
action chosen and the reasons, and Other types of lessons learned from project
cost control.
• Change Requests include change request to the cost performance baseline or
other components of the project management plan. Change requests can include
preventive or corrective actions and are processed for review and disposition
through the Perform Integrated Change Control process
Exercise : EVM
Your current project is an $800,000 software development effort, with two
teams of programmers that will work for six months, at a total of 10,000
hours.
According to the project schedule your team should be done with 38% of the
work. You find that the project is currently 40% complete. You have spent 50%
of the budget so far.
Calculate the following
1. BAC
2. EV, PV
3. SV, CV
4. SPI, CPI

More Related Content

What's hot

Project Time Management
Project Time ManagementProject Time Management
Project Time Management
dyaksa hanindito
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
Jawad Ahmad
 
Project Execution
Project ExecutionProject Execution
Project Execution
megat zainurul anuar
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
Agus Suhanto
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
BhuWan Khadka
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
BhuWan Khadka
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
PedadaSaikumar
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
PedadaSaikumar
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
Sunayana Miglani
 
Project cost management
Project cost managementProject cost management
Project cost management
Mohammad Ashraf Khan, PMP
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
Reetesh Gupta
 
Project Time Management
Project Time ManagementProject Time Management
Project Time ManagementSerdar Temiz
 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areas
Insaf Ali Soomro PMP
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
mohamed elashri
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
Wasis Witjaksono
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 

What's hot (20)

Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Project cost management
Project cost managementProject cost management
Project cost management
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areas
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 

Similar to A brief on project cost management

Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
ssuser9d62d6
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
Ala Ibrahim
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
Madhusha15
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
Somashekar S.M
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
ssusercf695b
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
VarunSubramanyam
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi
 
Tools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure ControlTools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure Control
Sheetal Wagh
 
Chapter 5 Project Cost Management.ppt
Chapter 5 Project Cost    Management.pptChapter 5 Project Cost    Management.ppt
Chapter 5 Project Cost Management.ppt
desalewminale
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
Peter Cholakis
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
NivethaSampath3
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
alvieramada23
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
Ir.Noor Iziddin,PMP, P.Eng,REEM,CCPM,TTT.
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
adabotor7
 

Similar to A brief on project cost management (20)

Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Tools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure ControlTools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure Control
 
Chapter 5 Project Cost Management.ppt
Chapter 5 Project Cost    Management.pptChapter 5 Project Cost    Management.ppt
Chapter 5 Project Cost Management.ppt
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 

More from Imran Jamil

A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
Imran Jamil
 
6 project quality management (ij)
6  project quality management (ij)6  project quality management (ij)
6 project quality management (ij)
Imran Jamil
 
Project risk management
Project risk managementProject risk management
Project risk management
Imran Jamil
 
Project time management
Project time managementProject time management
Project time management
Imran Jamil
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
Imran Jamil
 
Project management a brief intro
Project management   a brief introProject management   a brief intro
Project management a brief intro
Imran Jamil
 
Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...
Imran Jamil
 
Copq benefits of correct measurement (for slideshare)
Copq   benefits of correct measurement (for slideshare)Copq   benefits of correct measurement (for slideshare)
Copq benefits of correct measurement (for slideshare)
Imran Jamil
 
Project Management - Basic Concepts
Project Management - Basic ConceptsProject Management - Basic Concepts
Project Management - Basic Concepts
Imran Jamil
 
PMI Project Risk Management
PMI Project Risk ManagementPMI Project Risk Management
PMI Project Risk Management
Imran Jamil
 
Quality Assurance and Quality Control - Areas of Improvement
Quality Assurance and Quality Control - Areas of ImprovementQuality Assurance and Quality Control - Areas of Improvement
Quality Assurance and Quality Control - Areas of Improvement
Imran Jamil
 
Project quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge AreaProject quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge Area
Imran Jamil
 
Quality assurance documentation
Quality assurance documentationQuality assurance documentation
Quality assurance documentation
Imran Jamil
 
Cost of quality concept and advantages
Cost of quality   concept and advantagesCost of quality   concept and advantages
Cost of quality concept and advantages
Imran Jamil
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wireImran Jamil
 
Role of qa&qc in manufacturing presentation
Role of qa&qc in manufacturing   presentationRole of qa&qc in manufacturing   presentation
Role of qa&qc in manufacturing presentationImran Jamil
 
Cost of poor quality presentation5
Cost of poor quality presentation5Cost of poor quality presentation5
Cost of poor quality presentation5Imran Jamil
 

More from Imran Jamil (18)

A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
6 project quality management (ij)
6  project quality management (ij)6  project quality management (ij)
6 project quality management (ij)
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project time management
Project time managementProject time management
Project time management
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Project management a brief intro
Project management   a brief introProject management   a brief intro
Project management a brief intro
 
Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...
 
Copq benefits of correct measurement (for slideshare)
Copq   benefits of correct measurement (for slideshare)Copq   benefits of correct measurement (for slideshare)
Copq benefits of correct measurement (for slideshare)
 
Project Management - Basic Concepts
Project Management - Basic ConceptsProject Management - Basic Concepts
Project Management - Basic Concepts
 
PMI Project Risk Management
PMI Project Risk ManagementPMI Project Risk Management
PMI Project Risk Management
 
Quality Assurance and Quality Control - Areas of Improvement
Quality Assurance and Quality Control - Areas of ImprovementQuality Assurance and Quality Control - Areas of Improvement
Quality Assurance and Quality Control - Areas of Improvement
 
Project quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge AreaProject quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge Area
 
Quality assurance documentation
Quality assurance documentationQuality assurance documentation
Quality assurance documentation
 
Cost of quality concept and advantages
Cost of quality   concept and advantagesCost of quality   concept and advantages
Cost of quality concept and advantages
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wire
 
Role of qa&qc in manufacturing presentation
Role of qa&qc in manufacturing   presentationRole of qa&qc in manufacturing   presentation
Role of qa&qc in manufacturing presentation
 
CSWIP Intro
CSWIP IntroCSWIP Intro
CSWIP Intro
 
Cost of poor quality presentation5
Cost of poor quality presentation5Cost of poor quality presentation5
Cost of poor quality presentation5
 

Recently uploaded

Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
khadija278284
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
Faculty of Medicine And Health Sciences
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
Sebastiano Panichella
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
OECD Directorate for Financial and Enterprise Affairs
 
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Orkestra
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
Vladimir Samoylov
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
Access Innovations, Inc.
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
Howard Spence
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
IP ServerOne
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Sebastiano Panichella
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
OWASP Beja
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Sebastiano Panichella
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Matjaž Lipuš
 

Recently uploaded (13)

Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
 
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
 

A brief on project cost management

  • 3. Types of Cost ▪ Direct Cost- Any cost that is identified specifically with a particular final cost objective. ▪ Indirect Cost- Any cost not directly identified with a single, final cost objective (more than one project) ▪ Fixed Cost - Periodic charge that does not vary with business volume ▪ Variable Cost - Cost that fluctuates based on the business volume ▪ Opportunity Cost: When there is a decision to be made between two opportunities, the opportunity cost is the value / money forgone for the not doing the project.
  • 4. Types of Cost • Lifecycle Costing: Takes into account cost of development of a project and also the cost of supporting during the lifecycle. • Sunk Cost - Cost already incurred which cannot be recovered regardless of future events
  • 5. Types of Cost 1. If you are constructing a road, the costs of excavators and bulldozers…? 2. Cost of Fuel, being used by equipment…? 3. Cost of Support Staff, providing services for project from Head office…? 4. Rent of Project Company Head office…? 5. Company has hired a freelancer to develop a website in .NET. After a month, you decide that the freelancer isn’t doing a good job and reach out to another freelancer. The second freelancer convinces you that .NET is not the way to go and that your website project would be better off based on the Java platform. The cost associated with the .NET freelancer would be treated as…?
  • 7. Project Cost Management Project Cost Management includes the processes involved in: • estimating, • budgeting, and • controlling costs so that the project can be completed within the approved budget Process Process Group Plan Cost Management Planning Estimate Costs Planning Determine Budget Planning Control Costs Monitoring and Controlling
  • 8. Plan Cost Management- Outputs Cost Management Plan – is a component of the project management plan and describes how the project costs will be planned, structured , and controlled. The cost management plan can establish the following.  Units of measure  Level of precision  Level of accuracy  Control threshold  Rules of performance measurement
  • 9. Estimate Cost Estimate cost is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of this process is that it determines the amount of cost required to complete project work.
  • 10. Estimate Costs -Tools and Techniques
  • 11. Estimate Costs -Tools and Techniques Analogous Estimating
  • 12. Estimate Costs -Tools and Techniques Parametric estimating
  • 13. Estimate Costs -Tools and Techniques Analogous vs Parametric estimating 1. It costed $7,100 to develop a website a few months ago and you are responsible for developing a new similar website, you estimate it to cost $7,100. 2. It took four days to excavate one acre of plant land last week and in order to excavate two acres this week, it will take eight days. 3. Sue is currently estimating the cost of a deliverable based on a project with a similar product 2 years ago. Sue puts down the estimate by copying directly from the actual cost of the product found from project documents. Which estimation technique does Sue make use of?
  • 14. Estimate Costs -Tools and Techniques • Three-point estimates concept originated with the program evaluation and review technique (PERT). PERT uses three estimates to define an approximate range for an activity’s cost: • Beta Distribution ESTIMATED COST = (Optimistic + 4*(Most Likely) + Pessimistic) / 6 • Bottom-up estimating produces a separate estimate for each scheduled activity. The detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting and tracking purposes. The cost and accuracy of bottom-up cost estimating is typically influenced by the size and complexity of the individual activity or work package. Bottom up estimating
  • 15. Determine Budget Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. This baseline includes all authorized budgets, but excludes management reserves.
  • 16. Determine Budget - Inputs • Once the project has been divided into the WBS work packages, a code or numbering system is assigned to every work package for cost monitoring, control, reports, and forecasting purposes. These codes are usually called “Code of accounts” or “Cost centers” • Cost Aggregation involves aggregating the costs of individual activities to work packages that are further aggregated to higher levels of WBS and finally into the project cost • Reserve Analysis include contingency reserve and management reserves for the project. Contingency reserves are allowances for response plan strategized for the identified risks. These are also known as “known unknowns”. Management reserves are allowance for unplanned changes to thee project scope and cost. The are also known as “unknown unknowns”. Reserves are not the part of the project cost baseline.
  • 17. Determine Budget – Tools and Techniques • Budget within the cost baseline that is allocated for identified & accepted risks • Viewed to address the “known-unknowns” • Provide for a specific activity/ whole project, or both • Percentage of the estimated cost, a fixed number, or may be developed by using quantitative analysis methods • As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated • Contingency should be clearly identified in cost documentation • Contingency reserves are part of the cost baseline and the overall funding requirements for the project • Amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project • To address the “unknown unknowns” that can affect a project • Not included in the cost baseline but is part of the overall project budget and funding requirements • When an amount of management reserves is used to fund unforeseen work, the amount of management reserve used is added to the cost baseline, thus requiring an approved change to the cost baseline
  • 20. Determine Budget – Outputs Cost performance baseline is an authorized time-phased budget at completion (BAC) used to measure, monitor, and control overall cost performance on the project. It is developed as a summation of the approved budgets by time period and is typically displayed in the form of an S-curve, as is illustrated in Figure below: Reference PMBOK 5th Edition
  • 21. Determine Budget – Outputs Reference PMBOK 5th Edition
  • 22. Exercise: Determine Budget Revise Tools to Determine Budget Monika reads a newspaper article that says there has been sharp increase in steel cost recently. She knows this was not in her contractor’s original plan and decidesto put a few hundred dollars aside to deal with the price hike if it should happen. The tool used by Monika is • Parametric estimating • Reserve analysis • Cost aggregation • Fund Limit Reconciliation
  • 23. Control Costs Control Costs is the process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.
  • 24. Control Costs – Tools and Techniques Earned value management is used to measure the performance of the project, It integrates project scope, cost and schedule measures to help the project management team assess and measure project performance and progress. 1. Planned Value (PV) is the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or work breakdown structure component. 2. Earned Value (EV) is the value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or a WBS component. 3. Actual Cost (AC) is the total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure component.
  • 25. Control Costs – Tools and Techniques • Variance Analysis helps in analyzing the performance of the project vis-à-vis cost and schedule baselines • Schedule Variance (SV) is a measure of schedule performance on a project. It is equal to the earned value (EV) minus the planned value (PV). SV= EV-PV. • Cost variance (CV) is a measure of cost performance on a project. It is equal to the earned value (EV) minus the actual costs (AC). CV = EV-AC • Schedule performance Index (SPI) in addition to project status is used to predict the completion date. SPI = EV/PV • Cost Performance Index (CPI) measures the cost efficiency for the work completed, it is the ration of EV to AC. CPI = EV/AC.
  • 26. Control Costs – Tools and Techniques Forecasting Techniques are used to calculate Estimate at completion (EAC) and Estimate to complete (ETC). EAC = AC + ETC To-complete performance index (TCPI) is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC. Performance reviews involves following three types of analysis 1.Variance Analysis compares actual project performance to planned or expected performance. Cost and schedule variances are the most frequently analyzed. 2.Trend Analysis examines project performance over time to determine if performance is improving or deteriorating. 3.Earned value management compares the baseline plan to actual schedule and cost performance.
  • 27. Control Costs – Outputs • Work Performance Information includes the calculated CV, SV, CPI, and SPI values for WBS components, in particular the work packages. • Cost Forecasts includes a calculated EAC value or a bottom-up EAC value. • Organizational Process Assets Updates include Causes of variances, Corrective action chosen and the reasons, and Other types of lessons learned from project cost control. • Change Requests include change request to the cost performance baseline or other components of the project management plan. Change requests can include preventive or corrective actions and are processed for review and disposition through the Perform Integrated Change Control process
  • 28.
  • 29. Exercise : EVM Your current project is an $800,000 software development effort, with two teams of programmers that will work for six months, at a total of 10,000 hours. According to the project schedule your team should be done with 38% of the work. You find that the project is currently 40% complete. You have spent 50% of the budget so far. Calculate the following 1. BAC 2. EV, PV 3. SV, CV 4. SPI, CPI