SlideShare a Scribd company logo
1 of 15
INTRODUCTION
• Client’s information
oWW (M) Sdn. Bhd. is a private property
developer.
oHas 6 years’ experience in the construction
industry.
oInvolved in the construction of offices,
warehouse, apartments and residential houses.
INTRODUCTION
• Project’s detail
oType: 3-storey shopping mall
oTotal area: 100,000m²
oProposed construction period: 24 months
oSustainable features are to be added to the building
oClient lack knowledge in constructing sustainable
building
BASIC PROCUREMENT METHODS
Traditional method Management Contracting
Principles -Involves client, consultant team,
main contractor and sub-cons.
-Consultant team prepares design;
main contractor responsible for whole
execution of work.
-Involves client, consultant team,
management contractor (MC) and
work packages contractors.
-MC appointed at early stage to
advice, plan, manage and oversee
construction activities.
Advantages -Scope of work is well defined at
early stage.
-Client knows total contract sum
before the work starts.
-Faster completion time as design
and construction can overlap.
-Experienced MC can provide
useful advice.
-Flexible to design changes.
Disadvantag
es
-Requires longer time to prepare
detailed design before tendering
process.
-Completion time is longer as
contactor can only start constructing
after design is prepared.
-Contract sum is uncertain until
design is completed.
-More Variations lead to more
works to be done (eg.
remeasurement).
TYPE OF CONTRACT FORMS
• Lump Sum Contracts
• Measurement Contracts
• Cost Reimbursement
Contracts
Cost Reimbursement Contracts
• Contractor is being paid the actual cost they incur in carrying out the works plus additional
payment to allow profit.
• Nature and scope of the work cannot be well defined at the beginning.
• Include some provision to allow profit which are :
- Cost plus percentage contract : additional amount of money is expressed as percentages
which pay to the contractor.
- Cost plus fixed fee contract : a negotiated fee that is fixed at the outset of contract forming
will be provided to the contractor.
- Cost plus fluctuating fee contract : client has to pay contractor actual construction cost plus
an additional variable fee which agreed by both parties at the outset.
Choice of Contract Form
CHOICE OF CONTRACT FORM
Cost Reimbursement Contracts
• Best choice for project which cannot be well defined.
• Advisable to use when time if of essence.
• Flexible to change designs and materials during construction.
Cost Plus Fluctuating Fee Contract
• Provide incentives to contractor.
• Good relationship between both parties.
• Allows flexible and efficient building experience.
VIABILITY OF DESIGNAND BUILD AS COMPARING
TO BASICPROCUREMENT METHODS
D&B
• Design and build is a generic term describing a procurement route in
which the main contractor is appointed to design and construct the
works, as opposed to a traditional contract, where
the client appoints consultants to design the development and then
a contractor is appointed to construct the works.
Management contracting
• Management contracting is a procurement method in which the works
are constructed by a number of different sub/works contractors who are
contracted to a management contractor.
Design and build Management contracting
• D&B reduced project duration by the
overlapping of the design and
construction phases.
• Allow the early involvement of the
management contractor.
• Client’s financial commitment is
capped. D&B contractor is required to
submit a Guarantee maximum price
(GMP) based on the approximate bills
of quantity by means of a percentage
addition on the price arrived.
• Lower the risk and challenges (in the
aspect of building technology) that
might encounter during the
construction phase.
• Client has lesser ability to control the
design of project
• Accommodates later design decisions.
• D&B method increase the difficulty in
comparison of tenders.
• Suitable for fast track project.
Construction work can start as soon as
sufficient work has been designed and
approved by the local authorities.
CRITICAL ANALYSIS OF ALTERNATIVE BASIC
PROCUREMENT METHODS TO THE PROPOSED
PROJECT
Not single procurement strategy is suitable for all projects and
all employers
CRITICAL ANALYSIS OF ALTERNATIVE BASIC
PROCUREMENT METHODS TO THE PROPOSED SUBJECT
1. Shopping malls are different from all other retail store construction
projects, it is large and complex.
a. The Management Contracting is suitable for large-scale and complex
project
b. The traditional procurement method is suitable for project which relies on
full design.
CRITICAL ANALYSIS OF ALTERNATIVE BASIC
PROCUREMENT METHODS TO THE PROPOSED SUBJECT
2. The shopping complex construction projects are scheduled quicker than
ordinary construction projects
a. The Management Contracting is suitable for fast track project
b. The traditional procurement method relies on full design information, it
result in long time pre-contract preparation
3. The building of a sustainable shopping mall requires knowledgeable
contractor or owner
> In construction management procurement, the client are require to have
experiences in the certain project
CRITICAL ANALYSIS OF ALTERNATIVE BASIC
PROCUREMENT METHODS TO THE PROPOSED SUBJECT
4. A great deal of variation appear when site conditions are difficult
> The Management Contracting allows flexibility where
programme and design are not final and can change.
CRITICAL ANALYSIS OF ALTERNATIVE BASIC
PROCUREMENT METHODS TO THE PROPOSED SUBJECT
CONCLUSION
Procurement method to be used:
Management contracting procurement
-Allows early access of management contractor
-Speed up or reduce construction period
-Employer has more time for new business
Contract form to be used:
Cost reimbursement contract
-Efficient when scope of works are not certainty
-More flexible in amendment of designs
-Allows provision profit for contractor

More Related Content

What's hot

Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract Venuri Lakshani
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Michael Audu
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingAditya Sanyal
 

What's hot (20)

Contracts
ContractsContracts
Contracts
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Type of Contracts.
Type of Contracts.Type of Contracts.
Type of Contracts.
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Contract management
Contract managementContract management
Contract management
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Claims
ClaimsClaims
Claims
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tendering
 

Viewers also liked

PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slidesDoreen Yeo
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentationKailyn Lee
 
PM Final Assignment Report
PM Final Assignment ReportPM Final Assignment Report
PM Final Assignment ReportMelvin Lim
 
Measurement 4 ooompa loompa
Measurement 4   ooompa loompaMeasurement 4   ooompa loompa
Measurement 4 ooompa loompaHasif Alias
 
Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group AssignmentHaziq1511
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Estimating letters
Estimating lettersEstimating letters
Estimating lettersZIyeeTan
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.lucaschinsheng
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment PresentationHaziq1511
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation seenyeeyong
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Kai Yun Pang
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareKai Yun Pang
 

Viewers also liked (20)

PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
PP1 report
PP1 reportPP1 report
PP1 report
 
PM Final Assignment Report
PM Final Assignment ReportPM Final Assignment Report
PM Final Assignment Report
 
Measurement 4 ooompa loompa
Measurement 4   ooompa loompaMeasurement 4   ooompa loompa
Measurement 4 ooompa loompa
 
Estimating
EstimatingEstimating
Estimating
 
Group Component
Group ComponentGroup Component
Group Component
 
Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group Assignment
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Estimating letters
Estimating lettersEstimating letters
Estimating letters
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment Presentation
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
 
M4 presentation slides
M4 presentation slidesM4 presentation slides
M4 presentation slides
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft Software
 

Similar to PP1 presentation slide.

Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management ContractingKai Yun Pang
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...Francis Ho
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project DeliverySHKLaw
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014SHKLaw
 

Similar to PP1 presentation slide. (20)

TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project Delivery
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014
 

More from lucaschinsheng

Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment reportlucaschinsheng
 
Glodon bim software presentation slide
Glodon bim software presentation slideGlodon bim software presentation slide
Glodon bim software presentation slidelucaschinsheng
 
Energy efficient ventilation system
Energy efficient ventilation systemEnergy efficient ventilation system
Energy efficient ventilation systemlucaschinsheng
 
Enbe final project process
Enbe final project processEnbe final project process
Enbe final project processlucaschinsheng
 
Enbe final project report efkairia
Enbe final project report efkairiaEnbe final project report efkairia
Enbe final project report efkairialucaschinsheng
 
Introduction to construction industy final project
Introduction to construction industy final projectIntroduction to construction industy final project
Introduction to construction industy final projectlucaschinsheng
 
Interior Architecture Drawing
Interior Architecture DrawingInterior Architecture Drawing
Interior Architecture Drawinglucaschinsheng
 
Cl project 2 individual part
Cl project 2 individual partCl project 2 individual part
Cl project 2 individual partlucaschinsheng
 
E portfolio enbe project 1
E portfolio enbe project 1E portfolio enbe project 1
E portfolio enbe project 1lucaschinsheng
 

More from lucaschinsheng (16)

Cl presentation
Cl presentationCl presentation
Cl presentation
 
Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment report
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Glodon bim software presentation slide
Glodon bim software presentation slideGlodon bim software presentation slide
Glodon bim software presentation slide
 
Energy efficient ventilation system
Energy efficient ventilation systemEnergy efficient ventilation system
Energy efficient ventilation system
 
Tj 3 5senses in kl
Tj 3 5senses in klTj 3 5senses in kl
Tj 3 5senses in kl
 
Enbe final project process
Enbe final project processEnbe final project process
Enbe final project process
 
Enbe final project report efkairia
Enbe final project report efkairiaEnbe final project report efkairia
Enbe final project report efkairia
 
Introduction to construction industy final project
Introduction to construction industy final projectIntroduction to construction industy final project
Introduction to construction industy final project
 
Ici magazine
Ici magazineIci magazine
Ici magazine
 
Interior Architecture Drawing
Interior Architecture DrawingInterior Architecture Drawing
Interior Architecture Drawing
 
Cl final project
Cl final projectCl final project
Cl final project
 
Cl project 2 individual part
Cl project 2 individual partCl project 2 individual part
Cl project 2 individual part
 
Tj 2 enbe
Tj 2 enbeTj 2 enbe
Tj 2 enbe
 
Tj 1 enbe
Tj 1 enbeTj 1 enbe
Tj 1 enbe
 
E portfolio enbe project 1
E portfolio enbe project 1E portfolio enbe project 1
E portfolio enbe project 1
 

Recently uploaded

Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 

Recently uploaded (20)

Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 

PP1 presentation slide.

  • 1. INTRODUCTION • Client’s information oWW (M) Sdn. Bhd. is a private property developer. oHas 6 years’ experience in the construction industry. oInvolved in the construction of offices, warehouse, apartments and residential houses.
  • 2. INTRODUCTION • Project’s detail oType: 3-storey shopping mall oTotal area: 100,000m² oProposed construction period: 24 months oSustainable features are to be added to the building oClient lack knowledge in constructing sustainable building
  • 3. BASIC PROCUREMENT METHODS Traditional method Management Contracting Principles -Involves client, consultant team, main contractor and sub-cons. -Consultant team prepares design; main contractor responsible for whole execution of work. -Involves client, consultant team, management contractor (MC) and work packages contractors. -MC appointed at early stage to advice, plan, manage and oversee construction activities. Advantages -Scope of work is well defined at early stage. -Client knows total contract sum before the work starts. -Faster completion time as design and construction can overlap. -Experienced MC can provide useful advice. -Flexible to design changes. Disadvantag es -Requires longer time to prepare detailed design before tendering process. -Completion time is longer as contactor can only start constructing after design is prepared. -Contract sum is uncertain until design is completed. -More Variations lead to more works to be done (eg. remeasurement).
  • 4. TYPE OF CONTRACT FORMS • Lump Sum Contracts • Measurement Contracts • Cost Reimbursement Contracts
  • 5. Cost Reimbursement Contracts • Contractor is being paid the actual cost they incur in carrying out the works plus additional payment to allow profit. • Nature and scope of the work cannot be well defined at the beginning. • Include some provision to allow profit which are : - Cost plus percentage contract : additional amount of money is expressed as percentages which pay to the contractor. - Cost plus fixed fee contract : a negotiated fee that is fixed at the outset of contract forming will be provided to the contractor. - Cost plus fluctuating fee contract : client has to pay contractor actual construction cost plus an additional variable fee which agreed by both parties at the outset. Choice of Contract Form
  • 6. CHOICE OF CONTRACT FORM Cost Reimbursement Contracts • Best choice for project which cannot be well defined. • Advisable to use when time if of essence. • Flexible to change designs and materials during construction. Cost Plus Fluctuating Fee Contract • Provide incentives to contractor. • Good relationship between both parties. • Allows flexible and efficient building experience.
  • 7. VIABILITY OF DESIGNAND BUILD AS COMPARING TO BASICPROCUREMENT METHODS D&B • Design and build is a generic term describing a procurement route in which the main contractor is appointed to design and construct the works, as opposed to a traditional contract, where the client appoints consultants to design the development and then a contractor is appointed to construct the works.
  • 8. Management contracting • Management contracting is a procurement method in which the works are constructed by a number of different sub/works contractors who are contracted to a management contractor.
  • 9. Design and build Management contracting • D&B reduced project duration by the overlapping of the design and construction phases. • Allow the early involvement of the management contractor. • Client’s financial commitment is capped. D&B contractor is required to submit a Guarantee maximum price (GMP) based on the approximate bills of quantity by means of a percentage addition on the price arrived. • Lower the risk and challenges (in the aspect of building technology) that might encounter during the construction phase. • Client has lesser ability to control the design of project • Accommodates later design decisions. • D&B method increase the difficulty in comparison of tenders. • Suitable for fast track project. Construction work can start as soon as sufficient work has been designed and approved by the local authorities.
  • 10. CRITICAL ANALYSIS OF ALTERNATIVE BASIC PROCUREMENT METHODS TO THE PROPOSED PROJECT Not single procurement strategy is suitable for all projects and all employers
  • 11. CRITICAL ANALYSIS OF ALTERNATIVE BASIC PROCUREMENT METHODS TO THE PROPOSED SUBJECT 1. Shopping malls are different from all other retail store construction projects, it is large and complex. a. The Management Contracting is suitable for large-scale and complex project b. The traditional procurement method is suitable for project which relies on full design.
  • 12. CRITICAL ANALYSIS OF ALTERNATIVE BASIC PROCUREMENT METHODS TO THE PROPOSED SUBJECT 2. The shopping complex construction projects are scheduled quicker than ordinary construction projects a. The Management Contracting is suitable for fast track project b. The traditional procurement method relies on full design information, it result in long time pre-contract preparation
  • 13. 3. The building of a sustainable shopping mall requires knowledgeable contractor or owner > In construction management procurement, the client are require to have experiences in the certain project CRITICAL ANALYSIS OF ALTERNATIVE BASIC PROCUREMENT METHODS TO THE PROPOSED SUBJECT
  • 14. 4. A great deal of variation appear when site conditions are difficult > The Management Contracting allows flexibility where programme and design are not final and can change. CRITICAL ANALYSIS OF ALTERNATIVE BASIC PROCUREMENT METHODS TO THE PROPOSED SUBJECT
  • 15. CONCLUSION Procurement method to be used: Management contracting procurement -Allows early access of management contractor -Speed up or reduce construction period -Employer has more time for new business Contract form to be used: Cost reimbursement contract -Efficient when scope of works are not certainty -More flexible in amendment of designs -Allows provision profit for contractor

Editor's Notes

  1. The selection process should therefore provide a best-fit solution based upon good judgement, which is acceptable in terms of the identified criteria and acceptable distribution of risk
  2. Construction can start before design work is completed. Its design, preparation of tender documents and construction is overlapping. Shopping mall is basically big. It’s complex because it’s sustainable. Because traditional procurement relies on full design. Shopping mall is large and complex. If full design, project duration may be too long.
  3. The developer of a shopping mall wants a prompt payback from the development project by completing the project as soon as possible. a. Overlapping of design and construction. b. Long time preparation., slow to start on site No or little overlap between design and construction
  4. As our client has no experience on sustainable building, they need an experienced contractor to participate early in planning stage of project.
  5. Changes can be accommodated provided packages affected have not been let and there is little or no impact on those already let. Client can modify or develop design requirements during construction.