This document discusses and compares different construction project procurement methods for a proposed 20-story condominium development. It analyzes traditional procurement, management contracting, lump sum contracting, and design-build approaches. The document recommends the traditional procurement method for this project, noting it provides price certainty, allows for client control over design quality, and secures the project budget and completion timeline. Traditional procurement is seen as most suitable given the project characteristics and client needs and risks. Design-build is not recommended due to reduced client control and potential cost-cutting affecting quality for a large-scale development like a 20-story condominium.