SlideShare a Scribd company logo
1 of 76
Construction Supervising Site Engineer
Duties and Responsibilities
© www.asia-masters.com
- Traditionally from time immemorial, the architect has been saddled with the dual
responsibility of providing technical (design) and administrative roles in the construction
process.
- The challenges posed by modern construction coupled with the dynamism of modern
society had imposed more responsibility on the architect as a project manager hence;
there is the need to separate these dual functions so that an architect can concentrate
well on one (technical) while another architect / professional takes over the other role
(administrative).
- The acceptance of project management as a separate profession indicates that the
application of knowledge, processes, skills, tools and techniques can have a significant
impact on the success of a project and requires someone who possesses the qualities of
a project manager.
-However the project manager must ensure that project management knowledge, skills
and tools be applied to projects so as to improve the chances of success over many
project.
© www.asia-masters.com
However this paper is being written with the aim of addressing the following
issues
•The meaning and concept of project management.
-Project.
-Program
-Relationship between project and program
-Meaning and concept of project management
-What is project management?
•The Role of the Project Manager.
-Characteristics of a project manager.
Skill required of a project manager
•The Architect as a Construction Project Manager.
-Role / function.
© www.asia-masters.com
LET US EXAMINE THE FOLLOWING:
PROJEC T: This can be defined as follows.
A Project is the use or application of one or more scarce resources of the 3M’s (Man Material and Money). Within a
specific time frame with the hope of achieving an investment return (result). It could further be defined as an
intervention tool designed to influence the direction and speed of development.
A project is a temporary endeavor undertaken to create a unique deliverable (product, service or result). The
temporary nature of a project is that a project has a definite beginning and the end. The end of a project is reached
when the project objectives have been achieved or the project is terminated because its objective cannot be met, when
the need for the project is no more in existence.
A project may also be terminated if the client (customer, sponsor or champion) wishes to terminate the project.
FEATURES OF A PROJECT
-Must have a need
-Must have a beginning and end
-Must have limited resources of the 3M’s
-Must be unique on its own
-Must have potentials, risks and uncertainty
-Must be result oriented
Salient points
Temporary; A definite beginning and end . Also it does not necessarily mean that the duration of the project is short,
rather it refers to the project engagement and its longevity.
Unique; No two projects have exactly the same factors associated with it, although they might have the same repetitive
elements in their deliverables and activities but it does not change the fundamental unique characteristic of the project
work.
© www.asia-masters.com
However an ongoing work is generally a repetitive process that follows organizations existing procedures. In
contrast, because of the unique nature of projects there may be uncertainties or differences in the products,
services, or result that the project creates. Project activities can be new to a project team which might necessitate
more dedicated planning than other routine work. In addition a project is undertaken at all organizational levels. A
project may involve a single or multiple individuals, as well as single organizations or multiple organizations.
A Project can be;
A finished product or component of another item
A capability to perform a service e.g., a business function
A result e.g., an outcome of a research work
An improvement in the existing product or service lines.
Examples of projects include, but not limited to;
Developing a new product , service or result;
Effecting a change in the structure, processes, staffing, or style of an organization:
Developing or acquiring a new or modified information systems ( hardware or software);
Conducting a research effort whose outcome will aptly recorded;
Constructing a building, industrial plant, or infrastructure;
Implementing, improving, or enhancing existing business processes and procedures.
PROGRAM: Can be defined in the following ways.
 It is the use or application of one or more scarce resources of the 3m’s (Man Material and Money) in a continuous
manner (No time limit) without any cost benefits.
A program is defined as a group of related projects, subprograms, and program activities managed in a coordinated
way to obtain benefits and control not available from managing them individually.
© www.asia-masters.com
The relationship among portfolio and projects is such that a portfolio refers to a collection of projects, programs,
sub-portfolios, and operations managed as a group to achieve strategic objectives. Programs are grouped within
a portfolio and are comprised of subprograms, projects, or other work that are managed in a coordinated fashion
in support of the portfolio. Individual projects that are either within or outside of a program are still considered
part of a portfolio. Although the projects or programs within the portfolio may not necessarily be interdependent
or directly related, they are linked to the organizations strategic plan by means of the organizations portfolio.
ITEMS PROJECTS PROGRAMS
SCOPE Projects have defined objectives. Scope is
progressively elaborated throughout the project life
cycle.
Programs have a large scope and provide more
significant benefits.
CHANGE Project managers expect change and implement
processes to keep change managed and controlled.
Program managers expect change from both inside
and outside the program and are prepared to
manage it.
PLANNING Project managers progressively elaborate high-level
information into detailed plans throughout the
project life cycles.
Program managers develop the overall program
plan and create high-level plans to guide detailed
planning at the component level.
MANAGEMENT Project managers manage the project team to meet
the project objectives.
Program managers manage the program staff and
the project managers; they provide vision and
overall leadership.
COMPARATIVE OVERVIEW OF PROJECT AND PROGRAMME MANAGEMENT.
© www.asia-masters.com
SUCCESS Success is measured by product and
project quality, timelines, budget
compliance and degree of customer
satisfaction.
Success is measured by the
degree to which the
program satisfies the needs
and benefits for which it
was undertaken.
MONITORING Project managers monitor and control
the work of producing the product,
services or results that the project was
undertaken to produce
Program managers monitor
the progress of program
components to ensure the
overall goals, schedules,
budget and benefits of the
program will be met.
© www.asia-masters.com
MEANING:
Definition:
Project management is about creating an environment for achievement of defined goals in a controlled manner by
a team of people. In order to compete in a fast paced and high technical world, you need to master the best
practice in project management.
According to (PMBOK) Project Management Body of Knowledge 5th
edition, project management is the application
of knowledge, skills, tools, and techniques to project activities to meet project requirement & objectives. Project
Management is however accomplished through the appropriate application & integration of the 47 logically
grouped project management processes, which are categorized into 5 process groups namely;
oInitiating: Develop project charter, identify stake holders
oPlanning : Requirement, Scope, WBS, Sequence, Estimate, Budget, Quality, Communication, Risk, Procurement.
oExecuting: Quality Assurance, Develop and Manage Project Team, Conduct Procurement,
Manage Stake holder engagement.
oMonitoring & control : Validate Scope, Control Scope, Control Schedule, Perform Quality control, Control
Risk, Control Procurement, Control Stake holder.
oClosing out: Close Project and Close Procurement, Lessons learnt.
 The Chartered Institute of Building (CIOB) (1998) defined project management as:
“The planning control and co-ordination of a project from conception (including commissioning) on behalf of a
client is concerned with the identification of the client’s objectives in terms of utility, function, quality, time and
cost and the establishment of relationships between resources. The integration, monitoring and control of the
contributors to the project and their output and the evaluation and satisfaction with the project outcome are
fundamental aspects of construction project management”.
© www.asia-masters.com
A third variant sees project management as encompassing construction management, hence it means acting for the client
in applying professional expertise and experience to do for the client what he would wish to do for himself had he the
time, knowledge, skill and experience to do so. A project manager provides a coordinated service to the client.
A fourth approach in terms of meaning is that project management in the building construction industry is the application
of management functions of planning, organizing, directing and controlling in the combination of resources (human,
plants, materials, capital etc) for the realization of a building or construction project at budget within specified quality and
time frame and in consonance with clients requirements.
Therefore, the scope of project management services is limited to the requirements of the clients or the circumstances of
the employer’s organization. In the construction industry, the scope may be in any of the following;
Managements of pre-contract operations.
Management of post-contract operations.
Management of both pre-contract and post contract operation.
CONCEPT (THE NEED FOR PROJECT MANAGEMENT SERVICES)
Since the beginning of the 21st
century, there has been a new challenge to every current and potential employee or
practice in the job market of ‘’what they have to offer” The only way out is to have a marketable strategy or edge.
The concept of project management however originated because of some or all of the following needs:
•Decreasing quality of professional’s work.
•Increasing complexity of projects.
•Greater degree of financial planning.
•Reduction in design and completion time.
•Increasing burden or demands of project administration at both pre and post contract stages.
•Poor coordination by design professionals who also carryout management functions.
© www.asia-masters.com
New technology or initiative creates projects that must be
managed.
Project management however benefits organization and
individuals by
•Ensuring utilization of limited resources in the right direction.
•Ensuring utilization of human resources in achieving desired
goal.
•Ensuring management of complex changes in an organized
way.
Assessing and managing risk index.
© www.asia-masters.com
According to the Project Management Body of Knowledge, PMBOK 5th
Edition, Project Management is the
application of knowledge, skills, tools and techniques to project activities to meet the project requirements.
Project management is accomplished through the appropriate application and integration of the 47 logically
grouped project management processes, which are categorized into five Process Groups.
These five Process Groups are:
 Initiating
 Planning
 Executing
 Monitoring and controlling, and
 Closing
Managing a project typically includes, but is not limited to:
• Identifying requirements;
• Addressing the various needs, concern and expectations of the stakeholders in
• Planning and executing the project;
• Setting up, maintaining, and carrying out communication among stakeholders that is active, effective,
and collaborative in nature;
• Managing stakeholders towards meeting projects requirements an d creating project deliverables;
• Balancing the competing projects constraints, which include, but are not limited to:
 Scope
 Quality
 Schedule
 Budget
 Resources and
 Risks.
The specific project characteristics and circumstances can influence the constraints on which the project
management team needs to focus.
© www.asia-masters.com
The project manager is the person assigned by the performing organization to achieve project
objectives. A project manager must have people- managing and inter-personal skills and general
management skills such as negotiation, leadership and mentoring.
Effective project management requires that the project manager possess the following
characteristics:
Knowledge- what project manager knows about project management?
Performance- what the project manager is able to accomplish.
Personal- how a project manager behaves when performing the project.
Some of the skills that must be possessed by the project manager to deliver organization projects
include:
 Communication skills
 Organizational skills
 Budgeting skills
 Problem solving skills
 Negotiating skills
 Leadership skills
 Team building and human resources.
© www.asia-masters.com
Part 2 - Project Managers 13
Functional Manager
 Expert in functional area
 Full authority over
employees
 Competes for resources
with other functional dept.
 Knows subordinates very
well
 Functional environment is
fairly stable & people are
comfortable in their jobs
Project Manager
 May not be expert in any
area
 May have limited authority
over employees
 Competes for resources
with other projects
 May not have known
subordinates very long
 Project environment is
temporary & people expect
changes
© www.asia-masters.com
Part 2 - Project Managers 14
 Manager
◦ oversees and manages the work and the employees
 Facilitator
◦ ensures that all resources and work are available
when needed and that any problems are resolved
 Communicator
◦ must effectively communicate with senior
management, client, project team, and other
participants (vendors, dept. managers, etc.) as needed
(which is frequently)
© www.asia-masters.com
Part 2 - Project Managers 15
 Politician
◦ knows how to “get things done”, how to “work the
system”, how to get people to cooperate, how to
influence others
 Negotiator
◦ skilled at getting what is needed for the project to
succeed: negotiate with senior mgmt. for more
resources, negotiate with functional manager to get a
particular project team member or to use a functional
resource, negotiate with vendor for shorter lead time,
negotiate with client about project goal changes
© www.asia-masters.com
Part 2 - Project Managers 16
 Doing whatever it takes to get the job done
 Acquiring resources
◦ Funds, personnel, other resources
 Fighting fires and obstacles
 Providing leadership
 Making tradeoffs between project goals
 Negotiating and persuading
 Resolving conflicts
© www.asia-masters.com
17
1. Understand the problems, opportunities, and
expectations of a project manager.
2. Recognize that project teams will have conflicts,
but this is a natural part of group development.
3. Understand who the stakeholders are and their
agendas.
4. Realize that organizations are very political and
use politics to your advantage.
5. Realize that project management is “leader
intensive” but that you must be flexible.
© www.asia-masters.com
Part 2 - Project Managers 18
6. Understand that project success is defined by four
components: budget, schedule, performance
criteria, and customer satisfaction.
7. Realize that you must build a cohesive team by
being a motivator, coach, cheerleader,
peacemaker, and conflict resolver.
8. Notice that your team will develop attitudes based
on the emotions you exhibit—both positive and
negative.
© www.asia-masters.com
Part 2 - Project Managers 19
9. Always ask “what-if” questions and avoid
becoming comfortable with the status of the
project.
10. Don’t get bogged down in minutiae and lose sight
of the purpose of the project.
11. Manage your time efficiently.
12. Above all, plan, plan, plan.
© www.asia-masters.com
Part 2 - Project Managers 20
 Leadership ability
 Communication skills
 Ability to develop
people
 Team-building skills
 Interpersonal skills
 Ability to handle
stress
 Planning skills
 Organizational skills
 Problem-solving skills
 Administrative skills
 Conflict resolution skills
 Time management
skills
© www.asia-masters.com
Part 2 - Project Managers 21
 Strong focus on “finishing the job”
 Good at flexibility and adaptability
 Willing to make decisions
 Credibility is critical (technical & administrative)
 Strong sense of ethics
 Political and personal sensitivity
 Effective leadership skills (can motivate)
 Participative style of management
 Ability to handle stress
© www.asia-masters.com
COMMUNICATI
ON SKILL
COMMUNICATI
ON SKILL
ACTION
MANAGEMENT
ACTION
MANAGEMENT
ORGANIZATIO
NAL
AWARENESS
ORGANIZATIO
NAL
AWARENESS
KNOWLEDGEKNOWLEDGE
INTER
PERSONAL
SKILL
INTER
PERSONAL
SKILL
PROJECT
MANAGER
PROJECT
MANAGER
LEADERSHIPLEADERSHIP
JUDGEMENT,
INTEGRITY.
JUDGEMENT,
INTEGRITY.
THINKING
SKILL
THINKING
SKILL
NEGOTIATION
SKILL
NEGOTIATION
SKILL
© www.asia-masters.com
HOWEVER, EXAMINE THE FOLLOWING ISSUES:
i. Project success: a project is successful if it delivers the expected result on time within budget limit.
ii. Why projects succeed:
—Manage and control scope changes.
—Create a detailed plan and track progress against it using progress chart.
—Assign correct resources to the specific task.
—Manage risk and uncertainty effectively.
—Involve stakeholder’s participation.
—Maintain good communication channel.
iii. Successful project:
―End-users apparently involved throughout the development.
―The project manager had the full backing of the executives.
―Specifications were clear cut. There was close ranking between the project team and end-users.
―Project expectations were realistic. All project’s constraint were adequately taken care of.
iv. Challenged project:
― Users input were inadequate or thoroughly lacking. Passive users got chance to comment after project
was neatly handed over to them
― Project specifications were incomplete in the light of the global technological changes.
― Hence, specification will keep on changing over period of execution. The project team keeps on
incorporating the changes to satisfy the client or stakeholders.
― Executive management showed little or no interest in putting out fires that flared up during project
execution. No proper resolution of issues, approval for payment not prompt. In-house experts pose threat
rather than being an asset.
― The technical (project) team was less than competent.
© www.asia-masters.com
v. Failed project:
― Users failed to provide complete requirement.
― Users were not involved in the development process.
― The project had no resource/ or inadequate resource for its
completion
•Executive management did not have any interest.
•Planning was a casualty
•Specifications were coming due to changes in business environment.
•The project was technically incompetent.
•Scope management and base lining was absent.
© www.asia-masters.com
The project manager in the executive status provides only management
functions: he is not concerned with technical responsibilities but coordinates
and integrates the contributions of the respective professional consultants.
He merely welds the consultants and contractors (if appointed) and all
selecting consultants and contractors, arranging project briefing and user
requirements, organizing the ultimate project operation and arranging
commissioning.
The executive project manager is involved where the project scope is wide
and complex to ensure operational efficiency.
In performing his functions, the project manager may assume either:
•An executive role
•A non-executive role.
© www.asia-masters.com
AN EXECUTIVE PROJECT MANAGEMENT ROLE
This status is also referred to as total project management.
The figure below shows this status.
The project manager here is given a free hand by the
employer/ client to deliver the completed project in
accordance with the agreed objectives. The project manager
would therefore have direct contractual relationship with the
contractor and consultants.
© www.asia-masters.com
A NON-EXECUTIVE PROJECT MANAGEMENT STATUS (INDEPENDENT FUNCTION)
The project manager here provides management services and operates like one of the consultants. In fact he may be
called a management contractor who performs a management function under a professional services contract with the
employer.
THE STRUCTURE OF NON-EXECUTIVE PROJECT MANAGEMENT ROLE
All the structure consultants have contractual relationship with the employer/ client. In Nigeria, it is
suggested that the non-executive role be carried out by any of the professional members of the design
team. That is, The Architect, Engineer and The Quantity Surveyor.
Under the non-executive structure, the project manager is expected to perform the following roles:
1.Technical supervision:
To earn the respect of clients and co-professionals, the projects manager must be technically competent.
This will also enable him to respond to problems more efficiently.
2. Planning:
© www.asia-masters.com
The project requirements are divided into elements for effective management. This eliminates unnecessary cases
and anticipating solution to them when they occur.
3. Organizing:
He should be involved where practicable in the selection of the project tam and allocation and management of
responsibilities.
4. Directing:
The project manager must coordinate the activities of the project team and motivate them to achieve results.
5. Controlling: this involves:
• Technical quality
• Budget
• Schedule
• Client satisfaction
The project must ensure that the final product is as planned
6. Financial management:
The project manager is most familiar with the project and the client and hence would ensure strict accountability.
7. Marketing assistance:
The project manager is also a firm’s public relations personnel. He must be able to sell ideas very easily. The
success of the project at hand may attract future projects.
ROLE OF THE PROJECT MANAGER IN SUMMARY:
• Responsible for all phases of projects: direction, planning, admin.
• Assist in land acquisition.
• Obtain planning approval.
• Hire labor, plants, machineries, and fund.
• Central point of contact for all stakeholders.
• Coordinate activities.
• Track project schedule.
© www.asia-masters.com
Significance
Ensure that task is completed on time.
Monitoring
Value for money.
Benefits
Job satisfaction on the path of project despite stress undertaken.
Positive working relations with stakeholders.
Relevance of Project Management to an Architect
Project goal is defined.
Appropriate utilization of limited fund is ensured.
Appropriate utilization of limited time is ensured.
Appropriate utilization of human resource is ensured.
Uniqueness is the sense that every project is a new thing.
© www.asia-masters.com
 To carry out the project management service, the practitioner is
expected to have a project management training so to be at home
with the management, financial and accounting aspects of the
project. The training is better as a mid carrier course after some
years of practice.
• Therefore, any of the construction professional with the required
attributes and training can confidently carry-out the function of
project management. Some of the requirement include knowledge
of design and construction, contract law, programming and
progressing, budgetary control, power of communications,
administration, power of persuasion, diplomacy, energy and drive.
Must have a team skill which includes being able to work with other
stakeholders as a single team
© www.asia-masters.com
 Project manager
 Designer
 Engineer-of-Record/Permit reviewer
 Construction Manager
 Inspector
 Subdivision Plan Checker
 Emergency Responder
 Technical Expert
◦ Traffic, structural, civil, hydraulic, etc.
© www.asia-masters.com
 Design Team Leader
 Technical Manager
 Construction Manager
 Project Manager
 City Engineer
 Director of Public Works
© www.asia-masters.com
THE ARCHITECT AS A PROJECT MANAGER IN THE TRADITIONAL STRUCTURE
(COMBINED FUNCTION)
The architect traditionally provides both design and management
responsibilities in building projects. As earlier stated, the new fee scale has
recognized and provided a separate fee for the management function originally
provided (free of charge) by the architect.
SHORT COMINGS OF THE TRADITIONAL STRUCTURE
The standard form of building contract has not separated the management
responsibilities from the architects design functions. This by implementation
means that the architect will for a very long time be saddled with the dual role
of a manager and a designer, but they have not done anything to ensure that
this structure is separated.
Many projects are still poorly managed by architect thereby giving room for
criticism by the allied professionals. Architects should improve their knowledge,
general competence in the area of project management to ensure that their
leadership in the industry will not be questioned. Some of the architect’s
responsibilities under these structures are:
© www.asia-masters.com
 Coordinating and incorporating the work of specialist consultants and
nominated sub-contractors.
 Assisting the employer in pre-qualification of contractors and sub-contractors
and advising on suitable prospective tenderers.
 Obtaining, analyzing and reporting on open tenders and preparing and advising
on the appointment of works contractors .
 Arrange for possessions of site and examination of contractors program
including cash flows.
 Arranging insurances and obtaining any other consent required for effective
coordination and execution of the project.
 Coordinating site supervision by specialist consultants.
 Arranging site meetings and producing and circulating site meeting reports
(minutes of the site meetings).
 Issuing interim payment certificates.
© www.asia-masters.com
Senior LeadershipSenior Leadership
Project LeadershipProject Leadership
Project Work TeamsProject Work Teams
SponsorSponsor
Advisory or Steering
Team
Advisory or Steering
Team
Project
Leader
Project
Leader
Project
Manager
Project
Manager
Core TeamCore Team
Functional
Team
Functional
Team
Serve as champions for the project and
provide high-level direction, authority,
decision-making and resources for the
project.
Supports the sponsor(s) and project leader.
Provides high-level direction, input, and
decision making.
Provides the subject matter expertise and day-to-day planning and
implementation for the respective functional area(s). Resolves issues
and escalates when required.
Provides project management,
process improvement, and change
management process expertise,
tracking, and reporting.
Provides subject matter
expertise and functional
ownership and
accountability for project
results.
Provides day-to-day
leadership for the
planning,
implementation, and
closing of the project.
Resolves issues and
escalates when required.
Assesses change
management needs and
develop strategies.
Implements
communication plan.
Leads the individual
functional teams.
Functional
Team
Functional
Team
Functional
Team
Functional
Team
Project ResourcesProject Resources Critical resources that can be brought in
as subject matter experts as needed.
Executive
Sponsor
Executive
Sponsor
© www.asia-masters.com
Executive Sponsor
Project Sponsor
Has ultimate authority and responsibility
for the project
• Include the most important responsibilities for each of the roles.
Advisory or Steering
Team
Supports the Sponsor & Project Leader
Project/Functional
Leader
Provides subject matter expertise and
functional ownership and accountability
for project results.
Project Manager
Responsible for planning, organizing,
managing, controlling and
communicating on all phases of a project
© www.asia-masters.com
Core Team
Provides day-to-day leadership for the
planning, implementation, and closing of
a project
Functional Team
Leader
Manages the sub team and pursues the
team’s given objectives (i.e. project
tasks)
Team Member
Responsible for contributing to overall
project objectives and specific team
deliverables
Project Resource
Responsible for providing subject matter
expertise as needed
© www.asia-masters.com
Project Sponsor
<Insert Name>
Project Leader
<Insert Name>
Project Core Team
<Insert Names>
<Name>
Functional Team
<Insert Team Member Names>
<Name>
Functional Team
<Insert Team Member Names>
<Name>
Functional Team
<Insert Team Member Names>
Advisory/Steering Team
<Insert Names>
Project Resources
<Insert Names>
Executive Sponsor
<Insert Name>
Project Manager
<Insert Name>
<Name>
Functional Team
<Insert Team Member Names>
<Name>
Functional Team
<Insert Team Member Names>
<Name>
Functional Team
<Insert Team Member Names>
<Name>
Functional Team
1.List responsibilities of this
team
2.Include specific deliverables
that this team should deliver
<Name>
Functional Team
1.List responsibilities of this
team
2.Include specific deliverables
that this team should deliver
<Name>
Functional Team
1.List responsibilities of this
team
2.Include specific deliverables
that this team should deliver
Resources Resources Resources
© www.asia-masters.com
NATURE OF THE
CONSTRUCTION INDUSTRY
Like Manufacturing industry – Involves the production of a
physical product
Like Service industry – Does not accumulate large amount of
capital
– Many small businesses
Success or failure is highly dependent on the qualities of the people
rather than
Technologies protected by patent
or
Availability of capital facilities
© www.asia-masters.com
PROJECT INTEREST GROUPS
Owner wants to achieve best value for their
investment
Contractors desire to bid low enough to win but
high enough to realize profit on investment
Workers hope to achieve better living standards
and working conditions
© www.asia-masters.com
INTEREST GROUPS
Owner wants to achieve best value for their
investment
Contractors desire to bid low enough to win but
high enough to realize profit on investment
Workers hope to achieve better living standards
and working conditions
Architect and Engineers are not directly
associated with the above groups
Professional achievement more attractive
© www.asia-masters.com
Forecast Future Demand
Location
Availability of Resources
Accessibility to transportation
 
Political and Institutional Factors
Sociological and Economic Impact on Community
Environmental Impact
Overall Technical and Economic
Feasibility
© www.asia-masters.com
Architectural concepts
Evaluation of technological process alternatives
Size and capacity of facility
Comparative economic studies
Reviews by regulatory bodies for compliance
Zoning regulations
Building codes
Licensing procedures
Safety standards
Environmental impact
 
Public Hearing
 
Funding cycles in Legislative and Executive Bodies
© www.asia-masters.com
3. Detailed Engineering and Design
Design of Architectural Elements
Design of Structural Elements
Site Investigation
Foundation Design
Electrical and Mechanical Design
Preparation of Specifications and Drawings
Preparation of Contract Documents
 
© www.asia-masters.com
3. Detailed Engineering and Design
Design of Architectural Elements
Design of Structural Elements
Site Investigation
Foundation Design
Electrical and Mechanical Design
Preparation of Specifications and Drawings
Preparation of Contract Documents
 
Field Construction Methods
Cost Knowledge
© www.asia-masters.com
• Services
• Equipment
• Materials
•  
© www.asia-masters.com
• Services
• Equipment
• Materials
•  
• Lump Sum Contract
• Cost Plus Fee Contract
• Negotiated Contract
© www.asia-masters.com
Process whereby the Designer’s Plans and Specifications are converted into
Physical Structures and Facilities
Co-ordination of all resources to complete the project
On Schedule
Within Budget
According to Specified Standard of Quality and Performance
© www.asia-masters.com
Testing of Components
Warranty Period
 
 
© www.asia-masters.com
Regular Maintenance of Facilities
© www.asia-masters.com
Architect
Interior Designer
Landscape Architect
Civil Engineer
Environmental Engineer
Electrical Engineer
Mechanical Engineer
Chemical Engineer
Geologist
Environmental Scientist
Economist
© www.asia-masters.com
General Contractor
Land Surveyor
Formwork Carpenters
Steel Fabricators
Concreters
Bricklayers
Plant and Equipment Operators
Specialist subcontractors
Suppliers
© www.asia-masters.com
American Institute of Architects
Documents
A101 Standard Form of Agreement between Owner
and Contractor – Stipulated Sum
A111 Standard Form of Agreement between Owner
and Contractor – Cost of the Work Plus a Fee
A201 General Conditions of the Contract for Construction
B141 Standard form of Agreement between Owner
and Architect
A132 Performance Bond and Payment Bond
© www.asia-masters.com
ARTICLES
Contract Documents
Architect
Owner
Contractor
Subcontractors
Work by Owner or by Separate Contractors
Time of Completion and Extension of Time
Progress and Final Payments
Substantial Completion
Insurance
Changes in the Work
Uncovering and Correction of Work
Termination of Contract
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Architech/Engineer Owner
General Contractor
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Architech/Engineer Owner
General Contractor
Subcontractor Subcontractor Subcontractor
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Architech/Engineer Owner
General Contractor
Subcontractor Subcontractor Subcontractor
2nd Tier Subcontractor
3rd Tier Subcontractor
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Architech/Engineer Owner
General Contractor
Subcontractor Subcontractor Subcontractor
2nd Tier Subcontractor
3rd Tier Subcontractor
Supplier
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Architech/Engineer Owner
Specialists General Contractor
Subcontractor Subcontractor Subcontractor
2nd Tier Subcontractor
3rd Tier Subcontractor
Supplier
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Architech/Engineer Owner
Specialists Construction Manager
Subcontractor Subcontractor Subcontractor
2nd Tier Subcontractor
3rd Tier Subcontractor
Supplier
ORGANIZATIONAL RELATIONSHIPS
Architech/Engineer Owner
Specialists Construction Manager
General Contractor
Subcontractor Subcontractor Subcontractor
2nd Tier Subcontractor
3rd Tier Subcontractor
Supplier
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Owner
Architech/Engineer Design Builder
Specialists
Subcontractor Subcontractor Subcontractor
2nd Tier Subcontractor
3rd Tier Subcontractor
Supplier
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Architech/Engineer Owner
Specialists
Subcontractor Subcontractor Subcontractor
2nd Tier Subcontractor
3rd Tier Subcontractor
Supplier
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Beneficiary Owner Performance Bond
Principal General Contractor Surety
Subcontractor Subcontractor Subcontractor
2nd Tier Subcontractor
3rd Tier Subcontractor
Supplier
© www.asia-masters.com
ORGANIZATIONAL RELATIONSHIPS
Beneficiary Owner Payment Bond
Principal General Contractor Surety
Subcontractor Subcontractor Subcontractor
Beneficiary
2nd Tier Subcontractor
3rd Tier Subcontractor
Supplier
© www.asia-masters.com
Requirements under AIA A201Contract Documents
Contractor’s Liability Insurance
Owner’s Liability Insurance
Property Insurance
Loss of Use Insurance
Workmen Compensation
Disability Benefits
© www.asia-masters.com
Make Financial Arrangements to fulfill his obligations
Furnish Accurate Contract Specifications and Drawings for the Contractor’s work
Right to Stop Work
Right to Change Work
Right to Terminate Contract if Contractor Defaults
© www.asia-masters.com
Architect is the Owner’s Representative
Architect is the Administrator of the Contract
Visit site at appropriate stages of construction to familiarize
himself generally with the progress and quality of the Work
and to determine whether Work is proceeding in accordance
with Contract Documents.
Advice the Owner on Work Progress
Guard the Owner against Defects and Deficiencies in the
Work of the Contractor
Reviews Contractor’s Claims and Approves Amount to be
paid to the Contractor
Architect is not responsible for Methods of Construction or Site
Safety
© www.asia-masters.com
Review Contract documents for Errors and Inconsistencies
Supervise and Co-ordinate all Construction Work
Provide full time Superintendent on Site
Responsible for Site Safety
Indemnify the Owner against any Claims by third parties
© www.asia-masters.com
Contract is signed between Owner and Contractor
Architect acts as Interpreter of the Contract between Owner
and Contractor
Architect acts as Judge of the Performance of the Owner
and Contractor
All disputes between Owner and Contractor shall be decided
by Architect
Architect shall not show Partiality
Architect’s Decision on Artistic Effects is Final
Arbitration
© www.asia-masters.com
Scoping
Planning
Organizing
Controlling
© www.asia-masters.com
SCOPING
Establishing Realistic and Specific Objectives which states in advance
the Desired Results
PLANNING
Programming
Costing
Scheduling
© www.asia-masters.com
ORGANIZING
Design of the Organization Structure
Delegation of Responsibilities
Working Relationships between Individuals and Groups
System of Communication to keep everyone informed
Provide Leadership
Feedback Loop
© www.asia-masters.com
CONTROLLING
Awareness of Current Status of Cost, Schedule and Quality
Performance compared to Project Goals
Regular Inspection and Supervision
Formulate Procedures to Identify Errors in time for
Remedial Works to be made
Manage Disputes
© www.asia-masters.com
Thank You
© www.asia-masters.com

More Related Content

What's hot

THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYSSudhaVelan
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfMeleseMengistu
 
Construction technology presentation
Construction technology presentationConstruction technology presentation
Construction technology presentationSze Ting Kuek
 
Construction phases
Construction phasesConstruction phases
Construction phasesMeesum Zaidi
 
Safety management for construction machines & equipments
 Safety management for construction machines & equipments Safety management for construction machines & equipments
Safety management for construction machines & equipmentsSelva Prakash
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In ConstructionIsidro Sid Calayag
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptTouqeer1
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projectsakashpadole
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryAkshika Mahanama
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & EquipmentsGAURAV. H .TANDON
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality controlSOURAV4798
 
Planning of materials in Construction Project management
Planning of materials in Construction Project managementPlanning of materials in Construction Project management
Planning of materials in Construction Project managementAravind Samala
 

What's hot (20)

THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Tekla BIM Basics
Tekla BIM BasicsTekla BIM Basics
Tekla BIM Basics
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdf
 
Construction technology presentation
Construction technology presentationConstruction technology presentation
Construction technology presentation
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
Safety management for construction machines & equipments
 Safety management for construction machines & equipments Safety management for construction machines & equipments
Safety management for construction machines & equipments
 
Construction Equipment Management
Construction Equipment ManagementConstruction Equipment Management
Construction Equipment Management
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In Construction
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.ppt
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality control
 
Planning of materials in Construction Project management
Planning of materials in Construction Project managementPlanning of materials in Construction Project management
Planning of materials in Construction Project management
 

Viewers also liked

Site-Manager & Site-Engineer (Civil Engineer)
Site-Manager & Site-Engineer (Civil Engineer)Site-Manager & Site-Engineer (Civil Engineer)
Site-Manager & Site-Engineer (Civil Engineer)PT. IRAWAN PRIMA UTAMA
 
The role of an Architect
The role of an ArchitectThe role of an Architect
The role of an ArchitectClara Lee
 
The Role Of An Architect
The Role Of An ArchitectThe Role Of An Architect
The Role Of An Architectllangit
 
Alfresco Share - Recycle Bin Ideas
Alfresco Share - Recycle Bin IdeasAlfresco Share - Recycle Bin Ideas
Alfresco Share - Recycle Bin IdeasAlfrescoUE
 
Internal control services
Internal control servicesInternal control services
Internal control servicessandesh mundra
 
Ici and itd project 1
Ici and itd project 1Ici and itd project 1
Ici and itd project 1xennechau
 
Construction business training
Construction business   trainingConstruction business   training
Construction business trainingveritama
 
What we learned building Campaign Monitor
What we learned building Campaign MonitorWhat we learned building Campaign Monitor
What we learned building Campaign MonitorWeb Directions
 
A challenging job you
A challenging job youA challenging job you
A challenging job youDon Bury
 
7-point checklist that every Project Manager needs to look at
7-point checklist that every Project Manager needs to look at 7-point checklist that every Project Manager needs to look at
7-point checklist that every Project Manager needs to look at ProofHub
 
Quality supervisor job description
Quality supervisor job descriptionQuality supervisor job description
Quality supervisor job descriptionqualitymanagement246
 
Webinar:Building an Agile Enterprise with Business Activity Monitor
Webinar:Building an Agile Enterprise with Business Activity Monitor Webinar:Building an Agile Enterprise with Business Activity Monitor
Webinar:Building an Agile Enterprise with Business Activity Monitor WSO2
 
Building Skills to Monitor & Evaluate Performance & Outcomes
Building Skills to Monitor & Evaluate Performance & Outcomes Building Skills to Monitor & Evaluate Performance & Outcomes
Building Skills to Monitor & Evaluate Performance & Outcomes Lauren-Glenn Davitian
 
一位B肝帶原、惡性腫瘤、肝硬化、肝癌病患的抗癌歷程
一位B肝帶原、惡性腫瘤、肝硬化、肝癌病患的抗癌歷程一位B肝帶原、惡性腫瘤、肝硬化、肝癌病患的抗癌歷程
一位B肝帶原、惡性腫瘤、肝硬化、肝癌病患的抗癌歷程annagirlqq
 
Amway gi summary 2015
Amway gi summary 2015Amway gi summary 2015
Amway gi summary 2015Cory Franek
 

Viewers also liked (20)

Site-Manager & Site-Engineer (Civil Engineer)
Site-Manager & Site-Engineer (Civil Engineer)Site-Manager & Site-Engineer (Civil Engineer)
Site-Manager & Site-Engineer (Civil Engineer)
 
The role of an Architect
The role of an ArchitectThe role of an Architect
The role of an Architect
 
The Role Of An Architect
The Role Of An ArchitectThe Role Of An Architect
The Role Of An Architect
 
Alfresco Share - Recycle Bin Ideas
Alfresco Share - Recycle Bin IdeasAlfresco Share - Recycle Bin Ideas
Alfresco Share - Recycle Bin Ideas
 
Internal control services
Internal control servicesInternal control services
Internal control services
 
The Consultants Role
The Consultants RoleThe Consultants Role
The Consultants Role
 
PILINH RIG OPERATOR
PILINH RIG OPERATORPILINH RIG OPERATOR
PILINH RIG OPERATOR
 
Manohar New Resume
Manohar New ResumeManohar New Resume
Manohar New Resume
 
Ici and itd project 1
Ici and itd project 1Ici and itd project 1
Ici and itd project 1
 
Construction business training
Construction business   trainingConstruction business   training
Construction business training
 
What we learned building Campaign Monitor
What we learned building Campaign MonitorWhat we learned building Campaign Monitor
What we learned building Campaign Monitor
 
A challenging job you
A challenging job youA challenging job you
A challenging job you
 
Amera Engineering Services Presentations
Amera Engineering Services PresentationsAmera Engineering Services Presentations
Amera Engineering Services Presentations
 
7-point checklist that every Project Manager needs to look at
7-point checklist that every Project Manager needs to look at 7-point checklist that every Project Manager needs to look at
7-point checklist that every Project Manager needs to look at
 
Quality supervisor job description
Quality supervisor job descriptionQuality supervisor job description
Quality supervisor job description
 
Webinar:Building an Agile Enterprise with Business Activity Monitor
Webinar:Building an Agile Enterprise with Business Activity Monitor Webinar:Building an Agile Enterprise with Business Activity Monitor
Webinar:Building an Agile Enterprise with Business Activity Monitor
 
Building Skills to Monitor & Evaluate Performance & Outcomes
Building Skills to Monitor & Evaluate Performance & Outcomes Building Skills to Monitor & Evaluate Performance & Outcomes
Building Skills to Monitor & Evaluate Performance & Outcomes
 
Role of an architect
Role of an architectRole of an architect
Role of an architect
 
一位B肝帶原、惡性腫瘤、肝硬化、肝癌病患的抗癌歷程
一位B肝帶原、惡性腫瘤、肝硬化、肝癌病患的抗癌歷程一位B肝帶原、惡性腫瘤、肝硬化、肝癌病患的抗癌歷程
一位B肝帶原、惡性腫瘤、肝硬化、肝癌病患的抗癌歷程
 
Amway gi summary 2015
Amway gi summary 2015Amway gi summary 2015
Amway gi summary 2015
 

Similar to Construction Supervising Site Engineer - Duties & Responsibilities

Project Management Course & Tutorial by eAcademy.lk
Project Management Course & Tutorial by eAcademy.lkProject Management Course & Tutorial by eAcademy.lk
Project Management Course & Tutorial by eAcademy.lkUdara Sandaruwan
 
1. Construction Methods and Project Management Introduction.pdf
1. Construction Methods and Project Management Introduction.pdf1. Construction Methods and Project Management Introduction.pdf
1. Construction Methods and Project Management Introduction.pdfAikaterineSmith
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
Project Management
Project ManagementProject Management
Project Managementirfan ali
 
PMP preparation course
PMP preparation coursePMP preparation course
PMP preparation coursemohamed fawzy
 
Project management lecture 1
Project management lecture 1Project management lecture 1
Project management lecture 1Abeera Malik
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021Sprintzeal
 
Project management professional
Project management professionalProject management professional
Project management professionalReema
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410Saqib Imran
 
Presentation of project management (905, scm. rajib ahashan rashel)
Presentation of project management (905, scm. rajib ahashan rashel)Presentation of project management (905, scm. rajib ahashan rashel)
Presentation of project management (905, scm. rajib ahashan rashel)ferozpatowary
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 
ACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estateACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estatehando2845
 
Project Management
Project ManagementProject Management
Project ManagementPrarthan P
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 

Similar to Construction Supervising Site Engineer - Duties & Responsibilities (20)

Project Management Course & Tutorial by eAcademy.lk
Project Management Course & Tutorial by eAcademy.lkProject Management Course & Tutorial by eAcademy.lk
Project Management Course & Tutorial by eAcademy.lk
 
1. Construction Methods and Project Management Introduction.pdf
1. Construction Methods and Project Management Introduction.pdf1. Construction Methods and Project Management Introduction.pdf
1. Construction Methods and Project Management Introduction.pdf
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Project management – standard for today´s modern company
Project management – standard for today´s modern companyProject management – standard for today´s modern company
Project management – standard for today´s modern company
 
Project Management
Project ManagementProject Management
Project Management
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
PMP preparation course
PMP preparation coursePMP preparation course
PMP preparation course
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Project management lecture 1
Project management lecture 1Project management lecture 1
Project management lecture 1
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021
 
Project management professional
Project management professionalProject management professional
Project management professional
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410
 
Presentation of project management (905, scm. rajib ahashan rashel)
Presentation of project management (905, scm. rajib ahashan rashel)Presentation of project management (905, scm. rajib ahashan rashel)
Presentation of project management (905, scm. rajib ahashan rashel)
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
ACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estateACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estate
 
Project Management
Project ManagementProject Management
Project Management
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 

More from Asia Master Training آسيا ماسترز للتدريب والتطوير

More from Asia Master Training آسيا ماسترز للتدريب والتطوير (20)

Annual training plan 2018 2018
Annual training plan 2018 2018Annual training plan 2018 2018
Annual training plan 2018 2018
 
Human Resource Management : The Importance of Effective Strategy and Planning
Human Resource Management : The Importance of Effective Strategy and PlanningHuman Resource Management : The Importance of Effective Strategy and Planning
Human Resource Management : The Importance of Effective Strategy and Planning
 
Purpose of Contract CloseOuts - Overview Landscape
Purpose of Contract CloseOuts - Overview LandscapePurpose of Contract CloseOuts - Overview Landscape
Purpose of Contract CloseOuts - Overview Landscape
 
Public Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground RulesPublic Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground Rules
 
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACTNATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
OPTICAL INDUSTRY - Design Engineering Fabrication TestingOPTICAL INDUSTRY - Design Engineering Fabrication Testing
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
 
Microsoft Word 2010 - Technical Skills Training
Microsoft Word 2010 - Technical Skills TrainingMicrosoft Word 2010 - Technical Skills Training
Microsoft Word 2010 - Technical Skills Training
 
Microsoft® Office Word 2007 Skills & Compentencies Training
Microsoft® Office Word 2007 Skills & Compentencies Training Microsoft® Office Word 2007 Skills & Compentencies Training
Microsoft® Office Word 2007 Skills & Compentencies Training
 
Competency Modeling v. Job Analysis
Competency Modeling v. Job AnalysisCompetency Modeling v. Job Analysis
Competency Modeling v. Job Analysis
 
Competency gaps for Professional Development
Competency gaps for Professional DevelopmentCompetency gaps for Professional Development
Competency gaps for Professional Development
 
Competency Approach to Human Resource Management
Competency Approach to Human Resource ManagementCompetency Approach to Human Resource Management
Competency Approach to Human Resource Management
 
Developing a University-Wide Integrated Employee Core Competency Framework
Developing a University-Wide Integrated Employee Core Competency FrameworkDeveloping a University-Wide Integrated Employee Core Competency Framework
Developing a University-Wide Integrated Employee Core Competency Framework
 
Organizational Change and Development
Organizational Change and DevelopmentOrganizational Change and Development
Organizational Change and Development
 
Competency-based Management for the DoD-wide Contracting Community
Competency-based Management for the   DoD-wide Contracting CommunityCompetency-based Management for the   DoD-wide Contracting Community
Competency-based Management for the DoD-wide Contracting Community
 
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & TeachingCOMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
 
The Counseling Interview - Principles & Practices
The Counseling Interview - Principles & PracticesThe Counseling Interview - Principles & Practices
The Counseling Interview - Principles & Practices
 
Behavioral Interview - Selecting Quality Employees for a Quality Organization
Behavioral Interview - Selecting Quality Employees for a Quality OrganizationBehavioral Interview - Selecting Quality Employees for a Quality Organization
Behavioral Interview - Selecting Quality Employees for a Quality Organization
 
Effective Hiring Practices - Recruiting the Best Person
Effective Hiring Practices - Recruiting the Best PersonEffective Hiring Practices - Recruiting the Best Person
Effective Hiring Practices - Recruiting the Best Person
 
Industrial & Organisational Psychology Selecting Employees
Industrial & Organisational Psychology Selecting EmployeesIndustrial & Organisational Psychology Selecting Employees
Industrial & Organisational Psychology Selecting Employees
 

Recently uploaded

Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 

Recently uploaded (20)

Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 

Construction Supervising Site Engineer - Duties & Responsibilities

  • 1. Construction Supervising Site Engineer Duties and Responsibilities © www.asia-masters.com
  • 2. - Traditionally from time immemorial, the architect has been saddled with the dual responsibility of providing technical (design) and administrative roles in the construction process. - The challenges posed by modern construction coupled with the dynamism of modern society had imposed more responsibility on the architect as a project manager hence; there is the need to separate these dual functions so that an architect can concentrate well on one (technical) while another architect / professional takes over the other role (administrative). - The acceptance of project management as a separate profession indicates that the application of knowledge, processes, skills, tools and techniques can have a significant impact on the success of a project and requires someone who possesses the qualities of a project manager. -However the project manager must ensure that project management knowledge, skills and tools be applied to projects so as to improve the chances of success over many project. © www.asia-masters.com
  • 3. However this paper is being written with the aim of addressing the following issues •The meaning and concept of project management. -Project. -Program -Relationship between project and program -Meaning and concept of project management -What is project management? •The Role of the Project Manager. -Characteristics of a project manager. Skill required of a project manager •The Architect as a Construction Project Manager. -Role / function. © www.asia-masters.com
  • 4. LET US EXAMINE THE FOLLOWING: PROJEC T: This can be defined as follows. A Project is the use or application of one or more scarce resources of the 3M’s (Man Material and Money). Within a specific time frame with the hope of achieving an investment return (result). It could further be defined as an intervention tool designed to influence the direction and speed of development. A project is a temporary endeavor undertaken to create a unique deliverable (product, service or result). The temporary nature of a project is that a project has a definite beginning and the end. The end of a project is reached when the project objectives have been achieved or the project is terminated because its objective cannot be met, when the need for the project is no more in existence. A project may also be terminated if the client (customer, sponsor or champion) wishes to terminate the project. FEATURES OF A PROJECT -Must have a need -Must have a beginning and end -Must have limited resources of the 3M’s -Must be unique on its own -Must have potentials, risks and uncertainty -Must be result oriented Salient points Temporary; A definite beginning and end . Also it does not necessarily mean that the duration of the project is short, rather it refers to the project engagement and its longevity. Unique; No two projects have exactly the same factors associated with it, although they might have the same repetitive elements in their deliverables and activities but it does not change the fundamental unique characteristic of the project work. © www.asia-masters.com
  • 5. However an ongoing work is generally a repetitive process that follows organizations existing procedures. In contrast, because of the unique nature of projects there may be uncertainties or differences in the products, services, or result that the project creates. Project activities can be new to a project team which might necessitate more dedicated planning than other routine work. In addition a project is undertaken at all organizational levels. A project may involve a single or multiple individuals, as well as single organizations or multiple organizations. A Project can be; A finished product or component of another item A capability to perform a service e.g., a business function A result e.g., an outcome of a research work An improvement in the existing product or service lines. Examples of projects include, but not limited to; Developing a new product , service or result; Effecting a change in the structure, processes, staffing, or style of an organization: Developing or acquiring a new or modified information systems ( hardware or software); Conducting a research effort whose outcome will aptly recorded; Constructing a building, industrial plant, or infrastructure; Implementing, improving, or enhancing existing business processes and procedures. PROGRAM: Can be defined in the following ways.  It is the use or application of one or more scarce resources of the 3m’s (Man Material and Money) in a continuous manner (No time limit) without any cost benefits. A program is defined as a group of related projects, subprograms, and program activities managed in a coordinated way to obtain benefits and control not available from managing them individually. © www.asia-masters.com
  • 6. The relationship among portfolio and projects is such that a portfolio refers to a collection of projects, programs, sub-portfolios, and operations managed as a group to achieve strategic objectives. Programs are grouped within a portfolio and are comprised of subprograms, projects, or other work that are managed in a coordinated fashion in support of the portfolio. Individual projects that are either within or outside of a program are still considered part of a portfolio. Although the projects or programs within the portfolio may not necessarily be interdependent or directly related, they are linked to the organizations strategic plan by means of the organizations portfolio. ITEMS PROJECTS PROGRAMS SCOPE Projects have defined objectives. Scope is progressively elaborated throughout the project life cycle. Programs have a large scope and provide more significant benefits. CHANGE Project managers expect change and implement processes to keep change managed and controlled. Program managers expect change from both inside and outside the program and are prepared to manage it. PLANNING Project managers progressively elaborate high-level information into detailed plans throughout the project life cycles. Program managers develop the overall program plan and create high-level plans to guide detailed planning at the component level. MANAGEMENT Project managers manage the project team to meet the project objectives. Program managers manage the program staff and the project managers; they provide vision and overall leadership. COMPARATIVE OVERVIEW OF PROJECT AND PROGRAMME MANAGEMENT. © www.asia-masters.com
  • 7. SUCCESS Success is measured by product and project quality, timelines, budget compliance and degree of customer satisfaction. Success is measured by the degree to which the program satisfies the needs and benefits for which it was undertaken. MONITORING Project managers monitor and control the work of producing the product, services or results that the project was undertaken to produce Program managers monitor the progress of program components to ensure the overall goals, schedules, budget and benefits of the program will be met. © www.asia-masters.com
  • 8. MEANING: Definition: Project management is about creating an environment for achievement of defined goals in a controlled manner by a team of people. In order to compete in a fast paced and high technical world, you need to master the best practice in project management. According to (PMBOK) Project Management Body of Knowledge 5th edition, project management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirement & objectives. Project Management is however accomplished through the appropriate application & integration of the 47 logically grouped project management processes, which are categorized into 5 process groups namely; oInitiating: Develop project charter, identify stake holders oPlanning : Requirement, Scope, WBS, Sequence, Estimate, Budget, Quality, Communication, Risk, Procurement. oExecuting: Quality Assurance, Develop and Manage Project Team, Conduct Procurement, Manage Stake holder engagement. oMonitoring & control : Validate Scope, Control Scope, Control Schedule, Perform Quality control, Control Risk, Control Procurement, Control Stake holder. oClosing out: Close Project and Close Procurement, Lessons learnt.  The Chartered Institute of Building (CIOB) (1998) defined project management as: “The planning control and co-ordination of a project from conception (including commissioning) on behalf of a client is concerned with the identification of the client’s objectives in terms of utility, function, quality, time and cost and the establishment of relationships between resources. The integration, monitoring and control of the contributors to the project and their output and the evaluation and satisfaction with the project outcome are fundamental aspects of construction project management”. © www.asia-masters.com
  • 9. A third variant sees project management as encompassing construction management, hence it means acting for the client in applying professional expertise and experience to do for the client what he would wish to do for himself had he the time, knowledge, skill and experience to do so. A project manager provides a coordinated service to the client. A fourth approach in terms of meaning is that project management in the building construction industry is the application of management functions of planning, organizing, directing and controlling in the combination of resources (human, plants, materials, capital etc) for the realization of a building or construction project at budget within specified quality and time frame and in consonance with clients requirements. Therefore, the scope of project management services is limited to the requirements of the clients or the circumstances of the employer’s organization. In the construction industry, the scope may be in any of the following; Managements of pre-contract operations. Management of post-contract operations. Management of both pre-contract and post contract operation. CONCEPT (THE NEED FOR PROJECT MANAGEMENT SERVICES) Since the beginning of the 21st century, there has been a new challenge to every current and potential employee or practice in the job market of ‘’what they have to offer” The only way out is to have a marketable strategy or edge. The concept of project management however originated because of some or all of the following needs: •Decreasing quality of professional’s work. •Increasing complexity of projects. •Greater degree of financial planning. •Reduction in design and completion time. •Increasing burden or demands of project administration at both pre and post contract stages. •Poor coordination by design professionals who also carryout management functions. © www.asia-masters.com
  • 10. New technology or initiative creates projects that must be managed. Project management however benefits organization and individuals by •Ensuring utilization of limited resources in the right direction. •Ensuring utilization of human resources in achieving desired goal. •Ensuring management of complex changes in an organized way. Assessing and managing risk index. © www.asia-masters.com
  • 11. According to the Project Management Body of Knowledge, PMBOK 5th Edition, Project Management is the application of knowledge, skills, tools and techniques to project activities to meet the project requirements. Project management is accomplished through the appropriate application and integration of the 47 logically grouped project management processes, which are categorized into five Process Groups. These five Process Groups are:  Initiating  Planning  Executing  Monitoring and controlling, and  Closing Managing a project typically includes, but is not limited to: • Identifying requirements; • Addressing the various needs, concern and expectations of the stakeholders in • Planning and executing the project; • Setting up, maintaining, and carrying out communication among stakeholders that is active, effective, and collaborative in nature; • Managing stakeholders towards meeting projects requirements an d creating project deliverables; • Balancing the competing projects constraints, which include, but are not limited to:  Scope  Quality  Schedule  Budget  Resources and  Risks. The specific project characteristics and circumstances can influence the constraints on which the project management team needs to focus. © www.asia-masters.com
  • 12. The project manager is the person assigned by the performing organization to achieve project objectives. A project manager must have people- managing and inter-personal skills and general management skills such as negotiation, leadership and mentoring. Effective project management requires that the project manager possess the following characteristics: Knowledge- what project manager knows about project management? Performance- what the project manager is able to accomplish. Personal- how a project manager behaves when performing the project. Some of the skills that must be possessed by the project manager to deliver organization projects include:  Communication skills  Organizational skills  Budgeting skills  Problem solving skills  Negotiating skills  Leadership skills  Team building and human resources. © www.asia-masters.com
  • 13. Part 2 - Project Managers 13 Functional Manager  Expert in functional area  Full authority over employees  Competes for resources with other functional dept.  Knows subordinates very well  Functional environment is fairly stable & people are comfortable in their jobs Project Manager  May not be expert in any area  May have limited authority over employees  Competes for resources with other projects  May not have known subordinates very long  Project environment is temporary & people expect changes © www.asia-masters.com
  • 14. Part 2 - Project Managers 14  Manager ◦ oversees and manages the work and the employees  Facilitator ◦ ensures that all resources and work are available when needed and that any problems are resolved  Communicator ◦ must effectively communicate with senior management, client, project team, and other participants (vendors, dept. managers, etc.) as needed (which is frequently) © www.asia-masters.com
  • 15. Part 2 - Project Managers 15  Politician ◦ knows how to “get things done”, how to “work the system”, how to get people to cooperate, how to influence others  Negotiator ◦ skilled at getting what is needed for the project to succeed: negotiate with senior mgmt. for more resources, negotiate with functional manager to get a particular project team member or to use a functional resource, negotiate with vendor for shorter lead time, negotiate with client about project goal changes © www.asia-masters.com
  • 16. Part 2 - Project Managers 16  Doing whatever it takes to get the job done  Acquiring resources ◦ Funds, personnel, other resources  Fighting fires and obstacles  Providing leadership  Making tradeoffs between project goals  Negotiating and persuading  Resolving conflicts © www.asia-masters.com
  • 17. 17 1. Understand the problems, opportunities, and expectations of a project manager. 2. Recognize that project teams will have conflicts, but this is a natural part of group development. 3. Understand who the stakeholders are and their agendas. 4. Realize that organizations are very political and use politics to your advantage. 5. Realize that project management is “leader intensive” but that you must be flexible. © www.asia-masters.com
  • 18. Part 2 - Project Managers 18 6. Understand that project success is defined by four components: budget, schedule, performance criteria, and customer satisfaction. 7. Realize that you must build a cohesive team by being a motivator, coach, cheerleader, peacemaker, and conflict resolver. 8. Notice that your team will develop attitudes based on the emotions you exhibit—both positive and negative. © www.asia-masters.com
  • 19. Part 2 - Project Managers 19 9. Always ask “what-if” questions and avoid becoming comfortable with the status of the project. 10. Don’t get bogged down in minutiae and lose sight of the purpose of the project. 11. Manage your time efficiently. 12. Above all, plan, plan, plan. © www.asia-masters.com
  • 20. Part 2 - Project Managers 20  Leadership ability  Communication skills  Ability to develop people  Team-building skills  Interpersonal skills  Ability to handle stress  Planning skills  Organizational skills  Problem-solving skills  Administrative skills  Conflict resolution skills  Time management skills © www.asia-masters.com
  • 21. Part 2 - Project Managers 21  Strong focus on “finishing the job”  Good at flexibility and adaptability  Willing to make decisions  Credibility is critical (technical & administrative)  Strong sense of ethics  Political and personal sensitivity  Effective leadership skills (can motivate)  Participative style of management  Ability to handle stress © www.asia-masters.com
  • 23. HOWEVER, EXAMINE THE FOLLOWING ISSUES: i. Project success: a project is successful if it delivers the expected result on time within budget limit. ii. Why projects succeed: —Manage and control scope changes. —Create a detailed plan and track progress against it using progress chart. —Assign correct resources to the specific task. —Manage risk and uncertainty effectively. —Involve stakeholder’s participation. —Maintain good communication channel. iii. Successful project: ―End-users apparently involved throughout the development. ―The project manager had the full backing of the executives. ―Specifications were clear cut. There was close ranking between the project team and end-users. ―Project expectations were realistic. All project’s constraint were adequately taken care of. iv. Challenged project: ― Users input were inadequate or thoroughly lacking. Passive users got chance to comment after project was neatly handed over to them ― Project specifications were incomplete in the light of the global technological changes. ― Hence, specification will keep on changing over period of execution. The project team keeps on incorporating the changes to satisfy the client or stakeholders. ― Executive management showed little or no interest in putting out fires that flared up during project execution. No proper resolution of issues, approval for payment not prompt. In-house experts pose threat rather than being an asset. ― The technical (project) team was less than competent. © www.asia-masters.com
  • 24. v. Failed project: ― Users failed to provide complete requirement. ― Users were not involved in the development process. ― The project had no resource/ or inadequate resource for its completion •Executive management did not have any interest. •Planning was a casualty •Specifications were coming due to changes in business environment. •The project was technically incompetent. •Scope management and base lining was absent. © www.asia-masters.com
  • 25. The project manager in the executive status provides only management functions: he is not concerned with technical responsibilities but coordinates and integrates the contributions of the respective professional consultants. He merely welds the consultants and contractors (if appointed) and all selecting consultants and contractors, arranging project briefing and user requirements, organizing the ultimate project operation and arranging commissioning. The executive project manager is involved where the project scope is wide and complex to ensure operational efficiency. In performing his functions, the project manager may assume either: •An executive role •A non-executive role. © www.asia-masters.com
  • 26. AN EXECUTIVE PROJECT MANAGEMENT ROLE This status is also referred to as total project management. The figure below shows this status. The project manager here is given a free hand by the employer/ client to deliver the completed project in accordance with the agreed objectives. The project manager would therefore have direct contractual relationship with the contractor and consultants. © www.asia-masters.com
  • 27. A NON-EXECUTIVE PROJECT MANAGEMENT STATUS (INDEPENDENT FUNCTION) The project manager here provides management services and operates like one of the consultants. In fact he may be called a management contractor who performs a management function under a professional services contract with the employer. THE STRUCTURE OF NON-EXECUTIVE PROJECT MANAGEMENT ROLE All the structure consultants have contractual relationship with the employer/ client. In Nigeria, it is suggested that the non-executive role be carried out by any of the professional members of the design team. That is, The Architect, Engineer and The Quantity Surveyor. Under the non-executive structure, the project manager is expected to perform the following roles: 1.Technical supervision: To earn the respect of clients and co-professionals, the projects manager must be technically competent. This will also enable him to respond to problems more efficiently. 2. Planning: © www.asia-masters.com
  • 28. The project requirements are divided into elements for effective management. This eliminates unnecessary cases and anticipating solution to them when they occur. 3. Organizing: He should be involved where practicable in the selection of the project tam and allocation and management of responsibilities. 4. Directing: The project manager must coordinate the activities of the project team and motivate them to achieve results. 5. Controlling: this involves: • Technical quality • Budget • Schedule • Client satisfaction The project must ensure that the final product is as planned 6. Financial management: The project manager is most familiar with the project and the client and hence would ensure strict accountability. 7. Marketing assistance: The project manager is also a firm’s public relations personnel. He must be able to sell ideas very easily. The success of the project at hand may attract future projects. ROLE OF THE PROJECT MANAGER IN SUMMARY: • Responsible for all phases of projects: direction, planning, admin. • Assist in land acquisition. • Obtain planning approval. • Hire labor, plants, machineries, and fund. • Central point of contact for all stakeholders. • Coordinate activities. • Track project schedule. © www.asia-masters.com
  • 29. Significance Ensure that task is completed on time. Monitoring Value for money. Benefits Job satisfaction on the path of project despite stress undertaken. Positive working relations with stakeholders. Relevance of Project Management to an Architect Project goal is defined. Appropriate utilization of limited fund is ensured. Appropriate utilization of limited time is ensured. Appropriate utilization of human resource is ensured. Uniqueness is the sense that every project is a new thing. © www.asia-masters.com
  • 30.  To carry out the project management service, the practitioner is expected to have a project management training so to be at home with the management, financial and accounting aspects of the project. The training is better as a mid carrier course after some years of practice. • Therefore, any of the construction professional with the required attributes and training can confidently carry-out the function of project management. Some of the requirement include knowledge of design and construction, contract law, programming and progressing, budgetary control, power of communications, administration, power of persuasion, diplomacy, energy and drive. Must have a team skill which includes being able to work with other stakeholders as a single team © www.asia-masters.com
  • 31.  Project manager  Designer  Engineer-of-Record/Permit reviewer  Construction Manager  Inspector  Subdivision Plan Checker  Emergency Responder  Technical Expert ◦ Traffic, structural, civil, hydraulic, etc. © www.asia-masters.com
  • 32.  Design Team Leader  Technical Manager  Construction Manager  Project Manager  City Engineer  Director of Public Works © www.asia-masters.com
  • 33. THE ARCHITECT AS A PROJECT MANAGER IN THE TRADITIONAL STRUCTURE (COMBINED FUNCTION) The architect traditionally provides both design and management responsibilities in building projects. As earlier stated, the new fee scale has recognized and provided a separate fee for the management function originally provided (free of charge) by the architect. SHORT COMINGS OF THE TRADITIONAL STRUCTURE The standard form of building contract has not separated the management responsibilities from the architects design functions. This by implementation means that the architect will for a very long time be saddled with the dual role of a manager and a designer, but they have not done anything to ensure that this structure is separated. Many projects are still poorly managed by architect thereby giving room for criticism by the allied professionals. Architects should improve their knowledge, general competence in the area of project management to ensure that their leadership in the industry will not be questioned. Some of the architect’s responsibilities under these structures are: © www.asia-masters.com
  • 34.  Coordinating and incorporating the work of specialist consultants and nominated sub-contractors.  Assisting the employer in pre-qualification of contractors and sub-contractors and advising on suitable prospective tenderers.  Obtaining, analyzing and reporting on open tenders and preparing and advising on the appointment of works contractors .  Arrange for possessions of site and examination of contractors program including cash flows.  Arranging insurances and obtaining any other consent required for effective coordination and execution of the project.  Coordinating site supervision by specialist consultants.  Arranging site meetings and producing and circulating site meeting reports (minutes of the site meetings).  Issuing interim payment certificates. © www.asia-masters.com
  • 35. Senior LeadershipSenior Leadership Project LeadershipProject Leadership Project Work TeamsProject Work Teams SponsorSponsor Advisory or Steering Team Advisory or Steering Team Project Leader Project Leader Project Manager Project Manager Core TeamCore Team Functional Team Functional Team Serve as champions for the project and provide high-level direction, authority, decision-making and resources for the project. Supports the sponsor(s) and project leader. Provides high-level direction, input, and decision making. Provides the subject matter expertise and day-to-day planning and implementation for the respective functional area(s). Resolves issues and escalates when required. Provides project management, process improvement, and change management process expertise, tracking, and reporting. Provides subject matter expertise and functional ownership and accountability for project results. Provides day-to-day leadership for the planning, implementation, and closing of the project. Resolves issues and escalates when required. Assesses change management needs and develop strategies. Implements communication plan. Leads the individual functional teams. Functional Team Functional Team Functional Team Functional Team Project ResourcesProject Resources Critical resources that can be brought in as subject matter experts as needed. Executive Sponsor Executive Sponsor © www.asia-masters.com
  • 36. Executive Sponsor Project Sponsor Has ultimate authority and responsibility for the project • Include the most important responsibilities for each of the roles. Advisory or Steering Team Supports the Sponsor & Project Leader Project/Functional Leader Provides subject matter expertise and functional ownership and accountability for project results. Project Manager Responsible for planning, organizing, managing, controlling and communicating on all phases of a project © www.asia-masters.com
  • 37. Core Team Provides day-to-day leadership for the planning, implementation, and closing of a project Functional Team Leader Manages the sub team and pursues the team’s given objectives (i.e. project tasks) Team Member Responsible for contributing to overall project objectives and specific team deliverables Project Resource Responsible for providing subject matter expertise as needed © www.asia-masters.com
  • 38. Project Sponsor <Insert Name> Project Leader <Insert Name> Project Core Team <Insert Names> <Name> Functional Team <Insert Team Member Names> <Name> Functional Team <Insert Team Member Names> <Name> Functional Team <Insert Team Member Names> Advisory/Steering Team <Insert Names> Project Resources <Insert Names> Executive Sponsor <Insert Name> Project Manager <Insert Name>
  • 39. <Name> Functional Team <Insert Team Member Names> <Name> Functional Team <Insert Team Member Names> <Name> Functional Team <Insert Team Member Names> <Name> Functional Team 1.List responsibilities of this team 2.Include specific deliverables that this team should deliver <Name> Functional Team 1.List responsibilities of this team 2.Include specific deliverables that this team should deliver <Name> Functional Team 1.List responsibilities of this team 2.Include specific deliverables that this team should deliver Resources Resources Resources © www.asia-masters.com
  • 40. NATURE OF THE CONSTRUCTION INDUSTRY Like Manufacturing industry – Involves the production of a physical product Like Service industry – Does not accumulate large amount of capital – Many small businesses Success or failure is highly dependent on the qualities of the people rather than Technologies protected by patent or Availability of capital facilities © www.asia-masters.com
  • 41. PROJECT INTEREST GROUPS Owner wants to achieve best value for their investment Contractors desire to bid low enough to win but high enough to realize profit on investment Workers hope to achieve better living standards and working conditions © www.asia-masters.com
  • 42. INTEREST GROUPS Owner wants to achieve best value for their investment Contractors desire to bid low enough to win but high enough to realize profit on investment Workers hope to achieve better living standards and working conditions Architect and Engineers are not directly associated with the above groups Professional achievement more attractive © www.asia-masters.com
  • 43. Forecast Future Demand Location Availability of Resources Accessibility to transportation   Political and Institutional Factors Sociological and Economic Impact on Community Environmental Impact Overall Technical and Economic Feasibility © www.asia-masters.com
  • 44. Architectural concepts Evaluation of technological process alternatives Size and capacity of facility Comparative economic studies Reviews by regulatory bodies for compliance Zoning regulations Building codes Licensing procedures Safety standards Environmental impact   Public Hearing   Funding cycles in Legislative and Executive Bodies © www.asia-masters.com
  • 45. 3. Detailed Engineering and Design Design of Architectural Elements Design of Structural Elements Site Investigation Foundation Design Electrical and Mechanical Design Preparation of Specifications and Drawings Preparation of Contract Documents   © www.asia-masters.com
  • 46. 3. Detailed Engineering and Design Design of Architectural Elements Design of Structural Elements Site Investigation Foundation Design Electrical and Mechanical Design Preparation of Specifications and Drawings Preparation of Contract Documents   Field Construction Methods Cost Knowledge © www.asia-masters.com
  • 47. • Services • Equipment • Materials •   © www.asia-masters.com
  • 48. • Services • Equipment • Materials •   • Lump Sum Contract • Cost Plus Fee Contract • Negotiated Contract © www.asia-masters.com
  • 49. Process whereby the Designer’s Plans and Specifications are converted into Physical Structures and Facilities Co-ordination of all resources to complete the project On Schedule Within Budget According to Specified Standard of Quality and Performance © www.asia-masters.com
  • 50. Testing of Components Warranty Period     © www.asia-masters.com
  • 51. Regular Maintenance of Facilities © www.asia-masters.com
  • 52. Architect Interior Designer Landscape Architect Civil Engineer Environmental Engineer Electrical Engineer Mechanical Engineer Chemical Engineer Geologist Environmental Scientist Economist © www.asia-masters.com
  • 53. General Contractor Land Surveyor Formwork Carpenters Steel Fabricators Concreters Bricklayers Plant and Equipment Operators Specialist subcontractors Suppliers © www.asia-masters.com
  • 54. American Institute of Architects Documents A101 Standard Form of Agreement between Owner and Contractor – Stipulated Sum A111 Standard Form of Agreement between Owner and Contractor – Cost of the Work Plus a Fee A201 General Conditions of the Contract for Construction B141 Standard form of Agreement between Owner and Architect A132 Performance Bond and Payment Bond © www.asia-masters.com
  • 55. ARTICLES Contract Documents Architect Owner Contractor Subcontractors Work by Owner or by Separate Contractors Time of Completion and Extension of Time Progress and Final Payments Substantial Completion Insurance Changes in the Work Uncovering and Correction of Work Termination of Contract © www.asia-masters.com
  • 57. ORGANIZATIONAL RELATIONSHIPS Architech/Engineer Owner General Contractor Subcontractor Subcontractor Subcontractor © www.asia-masters.com
  • 58. ORGANIZATIONAL RELATIONSHIPS Architech/Engineer Owner General Contractor Subcontractor Subcontractor Subcontractor 2nd Tier Subcontractor 3rd Tier Subcontractor © www.asia-masters.com
  • 59. ORGANIZATIONAL RELATIONSHIPS Architech/Engineer Owner General Contractor Subcontractor Subcontractor Subcontractor 2nd Tier Subcontractor 3rd Tier Subcontractor Supplier © www.asia-masters.com
  • 60. ORGANIZATIONAL RELATIONSHIPS Architech/Engineer Owner Specialists General Contractor Subcontractor Subcontractor Subcontractor 2nd Tier Subcontractor 3rd Tier Subcontractor Supplier © www.asia-masters.com
  • 61. ORGANIZATIONAL RELATIONSHIPS Architech/Engineer Owner Specialists Construction Manager Subcontractor Subcontractor Subcontractor 2nd Tier Subcontractor 3rd Tier Subcontractor Supplier
  • 62. ORGANIZATIONAL RELATIONSHIPS Architech/Engineer Owner Specialists Construction Manager General Contractor Subcontractor Subcontractor Subcontractor 2nd Tier Subcontractor 3rd Tier Subcontractor Supplier © www.asia-masters.com
  • 63. ORGANIZATIONAL RELATIONSHIPS Owner Architech/Engineer Design Builder Specialists Subcontractor Subcontractor Subcontractor 2nd Tier Subcontractor 3rd Tier Subcontractor Supplier © www.asia-masters.com
  • 64. ORGANIZATIONAL RELATIONSHIPS Architech/Engineer Owner Specialists Subcontractor Subcontractor Subcontractor 2nd Tier Subcontractor 3rd Tier Subcontractor Supplier © www.asia-masters.com
  • 65. ORGANIZATIONAL RELATIONSHIPS Beneficiary Owner Performance Bond Principal General Contractor Surety Subcontractor Subcontractor Subcontractor 2nd Tier Subcontractor 3rd Tier Subcontractor Supplier © www.asia-masters.com
  • 66. ORGANIZATIONAL RELATIONSHIPS Beneficiary Owner Payment Bond Principal General Contractor Surety Subcontractor Subcontractor Subcontractor Beneficiary 2nd Tier Subcontractor 3rd Tier Subcontractor Supplier © www.asia-masters.com
  • 67. Requirements under AIA A201Contract Documents Contractor’s Liability Insurance Owner’s Liability Insurance Property Insurance Loss of Use Insurance Workmen Compensation Disability Benefits © www.asia-masters.com
  • 68. Make Financial Arrangements to fulfill his obligations Furnish Accurate Contract Specifications and Drawings for the Contractor’s work Right to Stop Work Right to Change Work Right to Terminate Contract if Contractor Defaults © www.asia-masters.com
  • 69. Architect is the Owner’s Representative Architect is the Administrator of the Contract Visit site at appropriate stages of construction to familiarize himself generally with the progress and quality of the Work and to determine whether Work is proceeding in accordance with Contract Documents. Advice the Owner on Work Progress Guard the Owner against Defects and Deficiencies in the Work of the Contractor Reviews Contractor’s Claims and Approves Amount to be paid to the Contractor Architect is not responsible for Methods of Construction or Site Safety © www.asia-masters.com
  • 70. Review Contract documents for Errors and Inconsistencies Supervise and Co-ordinate all Construction Work Provide full time Superintendent on Site Responsible for Site Safety Indemnify the Owner against any Claims by third parties © www.asia-masters.com
  • 71. Contract is signed between Owner and Contractor Architect acts as Interpreter of the Contract between Owner and Contractor Architect acts as Judge of the Performance of the Owner and Contractor All disputes between Owner and Contractor shall be decided by Architect Architect shall not show Partiality Architect’s Decision on Artistic Effects is Final Arbitration © www.asia-masters.com
  • 73. SCOPING Establishing Realistic and Specific Objectives which states in advance the Desired Results PLANNING Programming Costing Scheduling © www.asia-masters.com
  • 74. ORGANIZING Design of the Organization Structure Delegation of Responsibilities Working Relationships between Individuals and Groups System of Communication to keep everyone informed Provide Leadership Feedback Loop © www.asia-masters.com
  • 75. CONTROLLING Awareness of Current Status of Cost, Schedule and Quality Performance compared to Project Goals Regular Inspection and Supervision Formulate Procedures to Identify Errors in time for Remedial Works to be made Manage Disputes © www.asia-masters.com

Editor's Notes

  1. You’ll find engineers are very observant and practical... To the optimist, the glass is half full. To the pessimist, the glass is half empty. To the engineer, the glass is twice as big as it needs to be Engineers also can be stubborn and set in their ways. Did you hear whey the engineers crossed the road? Because they looked in the file, and that&amp;apos;s what they did last year.
  2. Q: How do you drive an engineer completely insane? A: Tie him or her to a chair, stand in front of him or her, and fold up a road map the wrong way.